7/21/1710:34AM Page1of3
MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/18/17-8/1/17
WORK HOURS: 7:00 AM - 7:00 PM
FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]
FULL CONSTRUCTION BUILD OUT
ZONE LOCATION STATUS
1 95 and 101 State Street 95 State Interior fit out is underway along with interior demolition work/cleanup and floor leveling. Window delivery and installation has begun. Exterior façade work is underway. Sidewalk work inside fenced area anticipated to begin in coming weeks.
2 Hotel
The following activities are ongoing: Above ground storm piping, spray on fireproofing, mechanical, electrical and plumbing (MEP), exterior framing/backup wall, interior framing lay out, and interior framing.
Support steel for Union Chandler will be removed on Saturday July 29th & Saturday Aug 5th if needed. A police detail is anticipated. During this work a portion of Main Street will be closed to traffic. Access to Red Rose will be maintained.
3 Casino The following activities are ongoing: Above ground storm piping, exterior framing/backup wall, MEPs, roofing, interior framing/sheet rock, fire protection, dryfall paint, painting in telecommunications rooms, and escalator truss installation.
4 Da Vinci Park No work anticipated
5 Dave's Furniture No work anticipated
6 Armory No work anticipated
7 Plaza No work anticipated
8 Church No work anticipated
9 Entertainment The following activities are ongoing: spray on fireproofing, exterior framing/backup wall, roofing, and scaffold erection.
10 Parking Garage The following activities are ongoing: Above ground MEP installation, waterproofing and caulking, painting and line striping, installation of storefront, and elevator construction..
11 Support Area No work anticipated
12 MGM Way Receiving deliveries and staging of material/equipment.
7/21/1710:34AM Page2of3
STREET WORK
State Street Saturday Aug 12th, the city will be holding its Jazz & Roots Festival. On this day no work will occur on State or Main Street.
Main Street
Reflectorized drums will intermittently be placed in the south bound lane to shift traffic from 6am-6pm Monday through Friday to allow for the unloading of certain materials onto the construction site. The barrels will be moved out of the road at the end of each day to allow parking during non-working hours. Two way traffic will be maintained at all times and two police details will be present. This traffic shift is currently underway.
Support steel for the Union Chandler building will be removed on Saturday July 29th and, if needed, Aug 5th. A police detail is anticipated. During this work Main Street will be closed from State Street to Union Street. Vehicles will utilize Maple Street as a detour route. Access to local businesses will be maintained and signage will be in place to notify/direct patrons/drivers. Anticipated work hours are 6:00 AM until 6:00 PM.
Beginning on Monday July 24th, utility work will take place in the sidewalk and parking stalls on the east side of Main Street from Red Rose to Union Street. The sidewalk will be closed to pedestrian traffic at this time. This work is anticipated to take all week. The work area will be protected with barriers, construction barrels, and fencing at all times.
Saturday Aug 12th the city will be holding its Jazz & Roots Festival. On this day no work will occur on State or Main Street.
Union Street
Utility work is underway and will continue throughout the summer at the intersections of Union, Howard West, and Bliss Street with East Columbus Ave. During this work, Union Street will be closed to through traffic from Main Street to East Columbus Avenue. Access to Pride Gas Station, the Colvest Building, and 55 State Street will be maintained at all times. Signage will be in place to direct patrons to business’ on Main Street via State Street and to provide updates and direction for drivers in the area.
East Columbus Ave will be open to through traffic throughout the project. At times, lanes will need to be reduced to accommodate utility crossings at the intersections. Police details will be present throughout the summer to help traffic flow as efficiently as possible.
East Columbus Avenue Work is underway to repair/replace portions of water main piping. A police detail is anticipated.
Bliss Street Work is underway to repair/replace portions of water main piping. A police detail is anticipated.
Howard Street Turn Around No work anticipated
Howard Street Work is underway to repair/replace portions of water main piping. A police detail is anticipated.
UTILITY ACTIVITY
UTILITY PROVIDER WORK TO BE PERFORMED
Eversource No work anticipated
Verizon No work anticipated
Comcast No work anticipated
Columbia Gas No work anticipated
7/21/1710:34AM Page3of3
Springfield Water & Sewer No work anticipated
MISCELLANEOUS ACTIVITY
LOCATION WORK TO BE PERFORMED
York Street Lot Construction material staging is underway.
Zorzi Lot Established as parking for craft labor foreman and superintendents.
Offsite Parking Lots Craft labor parking has been established at the Mass Mutual Center parking garage and 1870 E. Columbus Ave.
MAIN STREET
EAST COLUMBUS AVENUE
HOW
ARD
TURN
ARO
UND
195/101 STATE
2HOTEL
3CASINO
12MGM WAY
7PLAZA
6ARMORY
8CHURCH
5DAVE’S
FURNITURE
4DA VINCI
PARK
9ENTERTAINMENT
10PARKING GARAGE
11SUPPORT
AREA
BLIS
S ST
REET
HOW
ARD
STRE
ET
STAT
E ST
REET
UNIO
N ST
REET
BEGINNING IN MID JUNE AND CONTINUING THROUGHOUT THE SUMMER, UTILITY WORK WILL BE TAKING PLACE AT THE INTERSECTIONS OF UNION, HOWARD WEST, AND BLISS STREET WITH EAST COLUMBUS AVE. DURING THIS WORK, UNION STREET WILL BE CLOSED TO THROUGH TRAFFIC FROM MAIN STREET TO EAST COLUMBUS AVENUE. ACCESS TO PRIDE GAS STATION, THE COLVEST BUILDING, AND 55 STATE STREET WILL BE MAINTAINED AT ALL TIMES. SIGNAGE WILL BE IN PLACE TO DIRECT PATRONS TO BUSINESSES ON MAIN STREET VIA STATE STREET AND TO PROVIDE UPDATES AND DIRECTION FOR DRIVERS IN THE AREA.
EAST COLUMBUS AVE WILL BE OPEN TO THROUGH TRAFFIC THROUGHOUT THE PROJECT. AT TIMES, LANES WILL NEED TO BE REDUCED TO ACCOMMODATE UTILITY CROSSINGS AT THE INTERSECTIONS. POLICE DETAILS WILL BE PRESENT THROUGHOUT THE SUMMER TO HELP TRAFFIC FLOW AS EFFICIENTLY AS POSSIBLE.
SUPPORT STEEL FOR THE UNION CHANDLER BUILDING WILL BE REMOVED ON SATURDAY JULY 29TH AND, IF NEEDED, AUG 5TH. A POLICE DETAIL IS ANTICIPATED. DURING THIS WORK MAIN STREET WILL BE CLOSED FROM STATE STREET TO UNION STREET. VEHICLES WILL UTILIZE MAPLE STREET AS A DETOUR ROUTE. ACCESS TO LOCAL BUSINESSES WILL BE MAINTAINED AND SIGNAGE WILL BE IN PLACE TO NOTIFY/DIRECT PATRONS/DRIVERS. ANTICIPATED WORK HOURS ARE 6:00 AM UNTIL 6:00 PM.
BEGINNING ON MONDAY JULY 24TH, UTILITY WORK WILL TAKE PLACE IN THE SIDEWALK AND PARKING STALLS ON THE EAST SIDE OF MAIN STREET FROM RED ROSE TO UNION STREET. THE SIDEWALK WILL BE CLOSED TO PEDESTRIAN TRAFFIC AT THIS TIME. THIS WORK IS ANTICIPATED TO TAKE ALL WEEK. THE WORK AREA WILL BE PROTECTED WITH BARRIERS, CONSTRUCTION BARRELS, AND FENCING AT ALL TIMES.
Top Related