Method Statement - PILINGContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Precast reinforced concrete piles (6m length)
Sequence of Operations:(include sketchesif required)
1. Setting out for exact piling points in accordance to Drawing. Pile locations shall be marked with suitable identifiable pegs.
2. The piling rig shall be set up to the required rake.3. Each pile shall be driven until set or the required length in accordance to Drawing.4. During driving and until the pile has set, all exposed piles shall be supported and restrained with
temporary support.5. While piling, a detailed piling log shall be kept to record number of blows for every 0.5meters.6. For the final set of a pile shall be recorded as the penetration in millimeters (mm) per 10 blows.
Temporary Supports and Props needed to facilitate the works:
Timber Props
Method of Access and Egress to the work area:
Working on flat platform
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Exclusion zone
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
Method Statement - PILING
First Aid Facilities:
Name of On-Site First Aider:
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – RC WORKSContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Ready mixed concrete Reinforcement bars Timber planks
Sequence of Operations:(include sketchesif required)
1. Excavation shall be carried out until desired level.2. Dimensions of structures to be verified in accordance to Drawing.3. Shuttering shall be carried out using timber planks and runners following verified dimensions.4. Installation of reinforcement bars after completion of shuttering works in accordance to Drawing.5. Placement of ready mixed concrete with appropriate methods.6. While concreting, concrete vibrators shall be used to ensure concrete pour is even and free of air
bubbles so that the concrete is strong and have smooth finish.
Temporary Supports and Props needed to facilitate the works:
Method of Access and Egress to the work area:
Ladders Scaffoldings Step ladders
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Guard rails Safety harness
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
Method Statement – RC WORKS
First Aid Facilities:
Name of On-Site First Aider:
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – ROOF WATERPROOFINGContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Water repellant
Sequence of Operations:(include sketchesif required)
1. Surface of concrete surface shall be cleaned and free from debris.2. Prime water repellant onto the concrete surface where waterproofing work is required.3.
Temporary Supports and Props needed to facilitate the works:
Method of Access and Egress to the work area:
Ladders Scaffoldings
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Safety harness
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
First Aid Facilities: Name of On-Site First
Aider:
Method Statement – ROOF WATERPROOFING
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – BRICKWORKSContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Mortar Bricks
Sequence of Operations:(include sketchesif required)
1. Preparation of wall layout, marking the brick line parallel to horizontal and vertical axis.2. Bricks shall be laid with the ‘frog’ up to ensure the ‘frog’ is filled with mortar to prevent voids
within the wall.3. Bricks shall be laid in a course to check if the work fits in given space. Joints shall be adjusted
slightly rather than cutting off bricks.4. The four elements that shall be checked while work progress are: levels, height, verticality and
straightness.5.
Temporary Supports and Props needed to facilitate the works:
Method of Access and Egress to the work area:
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
Method Statement – BRICKWORKS
First Aid Facilities:
Name of On-Site First Aider:
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – Contractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Mortar Bricks
Sequence of Operations:(include sketchesif required)
Temporary Supports and Props needed to facilitate the works:
Timber Props
Method of Access and Egress to the work area:
Working on flat platform
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Exclusion zone
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
First Aid Facilities: Name of On-Site First
Aider:
Method Statement –
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – ALUMINIUM WALL CLADDINGContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Aluminium wall cladding (to Manufacturer’s details)
Sequence of Operations:(include sketchesif required)
1. Installation works shall be carried out by the Contractor after receiving clear understanding from the Manufacturer of the product.
2. Selected building wrap, flexible sill and jamb tape system must be installed by the Contractor prior installation of aluminium wall cladding.
3. The cladding shall start from the corner, and cut to length allowing a 1mm gap per meter for expansion.
4. Fixing brackets shall be ensured that it engages correctly with fixing fin of the board to avoid distortion or cupping.
5. Subsequent claddings must be locked into the channel of the board beside it, and shall be secured at the side of the board with universal fixing brackets.
Temporary Supports and Props needed to facilitate the works:
Method of Access and Egress to the work area:
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Method Statement – ALUMINIUM WALL CLADDINGEmergency Procedures:
First Aid Facilities:
Name of On-Site First Aider:
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – PAINTING WORKSContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials Color Paints
Sequence of Operations:(include sketchesif required)
1. Surfaces shall be thoroughly cleaned down; all loose and flaking paint removed and dusted off.
2. All holes, cracks, broken and crazed plaster shall be filled with suitable patching material.
3. All bare surfaces shall be sealed with a suitable pigmented penetrating oil sealer.4. All surfaces where previously painted with oil sealer shall be given a coat of
undercoat.5. After undercoating, all surfaces shall be given the finishing coat of paint.
Temporary Supports and Props needed to facilitate the works:
Method of Access and Egress to the work area:
Scaffoldings Ladders
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Safety harness
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
Method Statement – PAINTING WORKS
First Aid Facilities:
Name of On-Site First Aider:
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Method Statement – ALUMINIUM FRAMED GLASS PANELContractor Name:
UNITED ENGINEERS (B)SDN BHD
Address: Tel:
E-mail:
Project Name DESIGN AND BUILD FOR THE PROPOSED SIMULATION TRAINING CENTERAT PENANJONG GARRISON, NEGARA BRUNEI DARUSSALAM
Site Supervisor: Tel:
Safety Officer Tel:
Key Materials
Sequence of Operations:(include sketchesif required)
1. Aluminium frame shall be prefabricated in accordance to Drawing2.
Temporary Supports and Props needed to facilitate the works:
Method of Access and Egress to the work area:
Fall Protection Measures: (Where work at height cannot be eliminated – consider both Personnel & Materials)
Hazardous Substances:(Attach MSDS if required)
Applicable:
Very Toxic Harmful/ Irritant Corrosive DangerousFor the
environment
Oxidising Highly flammable
Explosives
No No No No No No No
Required Personnel Protective Equipment:
Safety Boots Hard Hats Safety Gloves Hearing Protection
Eye Protection Respiratory Protection
Other:
1. Hi-Viz
2. Coveralls
3.
Emergency Procedures:
First Aid Facilities: Name of On-Site First
Aider:
Method Statement – ALUMINIUM FRAMED GLASS PANEL
First Aid Box Location:
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the companies’ health and safety Policy.
Prepared by: xxx
Position: xxx Date: xxx
Reviewed by: xxx
Position: xxx Date: xxx
Items Attached: Yes NoSketches
Certification of Plant etc. Programme of Work
Risk Assessments
Top Related