Managerial Accounting: An Introduction To Concepts, Methods, And
Uses
Chapter 12Cost Center
Performance Evaluation
Maher, Stickney and Weil
C12 - 2
Learning Objectives (Slide 1 of 3)
Explain how variable production cost variances are calculated and why they occur.
Explain how fixed production cost variances are calculated and why they occur.
Explain the difference between price and efficiency variances.
Explain how to analyze variances using the variable cost variance model.
C12 - 3
Learning Objectives (Slide 2 of 3)
Analyze overhead variances using the variable cost variance model.
Identify the relation between actual, budgeted, and applied fixed manufacturing costs.
Explain how to apply activity-based costing to variance analysis.
C12 - 4
Learning Objectives (Slide 3 of 3)
Describe the impact of technology on variance analyses.
Identify tools managers use to decide when to investigate variances.
Explain how to calculate the mix variance portion of the efficiency variance.
C12 - 5
Responsibility For Production Variances (Slide 1
of 2)
Purchasing Department The materials price variance, used to
evaluate the purchasing dept.'s performance, is calculated as follows:
(Actual price - Standard Price) X Quantity Purchased
Measures the difference between actual and standard prices paid for materials
C12 - 6
Responsibility For Production Variances (Slide 2
of 2) The production dept. is responsible for the
following variances: Fixed manufacturing cost variance Remaining variable manufacturing cost
variance not assigned to purchasing including:
Direct materials Direct labor Variable manufacturing overhead Fixed manufacturing overhead
C12 - 7
Reasons for Variances Variances occur for a variety of
reasons: A variance is simply the difference
between a predetermined norm (an expected amount) and actual results so some differences should be expected
The standards may be biased Systematic reasons
C12 - 8
Reasons for Materials Variances
Generally, materials variances are attributable to two areas: Usage of materials Price paid for materials
Examples: Accounting may fail to take purchase
discounts on materials Employees may be poorly trained leading
to higher waste
C12 - 9
Reasons for Labor Variances
Generally, labor variances are attributable to two areas: Usage of labor hours Price (or wage) paid for labor
Examples: New employee is hired for less than
expected wage rate Union contract may call for wage rate
higher than forecast amount
C12 - 10
Reasons for Variable Manufacturing Overhead
Variances Generally, variable manufacturing
overhead variances are attributable to two areas: Usage of allocation base (e.g., machine
hours) Price of overhead items
Example: Utility company lowers rates for electricity resulting in a favorable variance
C12 - 11
Fixed Manufacturing Cost Variances
Difference between actual and budgeted fixed costs Fixed costs do not vary with the level of
activity Managers simply investigate what
caused the difference Example: Rent on production facility
was unexpectedly raised causing an unfavorable variance
C12 - 12
Variable Overhead in Service Organizations
Variable overhead is often significant for service firms, governmental agencies and nonprofit groups These types of organizations set
standards, perform variance analysis and establish flexible budgets
C12 - 13
Separating Variances into Price & Efficiency
Components Variable manufacturing cost variances
can be spit into two components Price variance - the difference between the
budgeted (or standard) price and the actual price paid
Efficiency variance - measures the difference between the actual quantity of inputs used and those allowed at standard to make a unit of output
C12 - 14
Variable Cost Variance Model (Slide 1 of 2)
Actual(AP X AQ)
(1)
Inputs at Standard(SP X AQ)
(2)
Flexible Production Budget
(SP X SQ)(3)
Price Variance(1) - (2)
(AP - SP) X AQ
Efficiency Variance(2) - (3)
SP X (AQ - SQ)Total Variance
(1) - (3)
C12 - 15
Variable Cost Variance Model (Slide 2 of 2)
General model can be used to calculate the following variances:
Input Price Variance Efficiency Variance
Direct Materials Price Variance Quantity Variance
Direct Labor Rate Variance Efficiency Variance
Variable Ovrhd Spending Variance Efficiency Variance
C12 - 16
Reasons for Materials Price & Efficiency
Variances Materials price variances may result
from: Failure to take purchase discounts Purchasing higher or lower quality material
Materials efficiency variances may result from: Purchasing inferior materials Using materials more or less efficiently
C12 - 17
Reasons for Labor Price & Efficiency
Variances Labor price variances may result from:
Failure to correctly anticipate changes in wage rates
Hiring new employees at wage rates different from standard
Labor efficiency variances may result from: Workers being poorly trained Faulty equipment Scheduling problems
C12 - 18
Variable Overhead Price and Efficiency Variances
Price and efficiency variances for variable overhead are computed using the same method as for other variable manufacturing costs Requires a measure of overhead input activity
such as machine hours or direct labor hours Care should be taken in interpreting these
variances since the input activity base may be chosen without regard for the true cause of variable overhead costs
C12 - 19
Fixed Manufacturing Cost Variances (Slide 1 of 3)
Manufacturing companies, using full absorption costing, use a predetermined overhead rate to apply fixed overhead to units produced, calculated as follows:
Estimated Fixed Manufacturing Cost per Period
Estimated ProductionVolume per Period
This rate is applied to units produced during the period
C12 - 20
Fixed Manufacturing Cost Variances (Slide 2 of 3)
The production volume variance equals budgeted fixed manufacturing costs minus applied fixed manufacturing costs Only arises when fixed costs are allocated to
units using a predetermined rate and estimated production volume is different from actual production volume achieved
The production volume variance appears to have little benefit for managerial purposes
C12 - 21
Fixed Manufacturing Cost Variances (Slide 3 of 3)
The price (spending) variance for fixed manufacturing costs equals the difference between actual and budgeted costs Used for management and control of
fixed manufacturing costs
C12 - 22
Quality Control and Variance Investigation Managers use a variety of methods to
determine which variances should be investigated, including: Rules of thumb such as investigate
variances > 10% of standard cost Tolerance limits - use predetermined limits
within which variances may fluctuate Variances outside these limits are investigated
Decisions models
C12 - 23
If you have any comments or suggestions concerning this PowerPoint Presentation for Managerial Accounting, An Introduction To Concepts, Methods, And Uses, please contact: