LMS Harmonisation Phase 2 Study
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 1
AGENDA
LMS Harmonisation Background
Power Distribution System Thriving & Progress
LMS Harmonisation Phase 2 Road Map
Conclusion
History
Year 2005 - Founding Partners:Electricit Du Cambodge, Cambodia
Electricit Du Laos, Lao PDR
Hanoi Power Company, Vietnam
Ho Chi Minh Power Company, Vietnam
Metropolitan Electricity Authority, Thailand
International Copper Association Southeast Asia
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 2
Year 2009Danang Power Company, Vietnam
(subsidiary of CPC)
Hai Phong Power Company, Vietnam (subsidiary of NPC)
Year 2010Provincial Electricity Authority, ThailandCentral Power Corporation, Vietnam
Year 2012Northern Power Corporation, VietnamSouthern Power Corporation, Vietnam
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 3
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 4
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 5
Report Content
Power Distribution System
High Voltage Sub-transmission System
Medium Voltage Distribution System
Reliability Improvement
Customers Service and IT Support
Telecommunication Network and Application
Future Environment Countermeasure
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 6
Focus Areas
Loss Reduction
Power Quality
Undergrounding
Customer Service
Functional Training
External Funding
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 7
Stakeholders Commitment
Loss Reduction
Undergrounding Power Quality
Functional Training Customer
Service Delivery
Funding From Intl Agencies
Strategic Roadmap At A Glance
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 8
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 9
Loss Reduction: A Priority of LMS Utilities
Losses in Power Distribution System
Distribution System System Equipment
Underground Cables Distribution Transformers
Conversion
from overhead cabling
Adoption of
low loss transformers
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 10
Capacity Building
UG Cable
Training
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 11
Capacity Building
UG Cable
Seminar
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 12
Consultation Cooperation
Feasibility Study on OH to UG Conversion
Luang Prabang, Lao PDR
in 2009
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 13
Consultation Cooperation
Master Plan for OH to UG Conversion
Danang, Vietnam
in 2011
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 14
Handbook and Specifications Development
Cable TWG Meeting in 2009
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 15
Handbook and Specifications Development
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 16
Harmonisation Program Phase 2
Enhancing Harmonisation of Power Distribution Systems in the LMS:
The Technical Study for AEC 2015
and Beyond
PARTICIPATING UTILITIES
MEA
EVN HANOI
EVN NPC
EVN CPC
EVN SPC
EVN HCMC
EDL
EDC
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 17
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 18
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 19
Demand in MW
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 20
No. of Customers
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 21
No. of Employees
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 22
Consumption in GWh
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 23
Power Distribution System Reliability in LMS
SAIFI
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 24
SAIDI
Power Distribution System Reliability in LMS
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 25
Power Distribution System Loss in LMS
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 26
Smart Grid Implementation in LMS
SG Technology EDC EDL HANOI HCMC NPC CPC SPC MEA
SCADA mini SCADA
EMS x start
DMS x start start
CSCS
SA (IEC61850) IED supported
start
FA x study study
AMI x pilot start
GIS x start
OMS Start in 2012
start x
AMS x start study
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 27
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 28
POWER QUALITY
RELIABILITY
SMART GRIDLOSS
REDUCTION
UNDERGROUND CABLING Utilities
Consensus
STAFF CAPACITY BUILDING
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 29
1. Reliability
Stage 3Reliability Indices Calculation Methodology
Stage 4Reliability
Improvement
Stage 1Basic Knowledge Reinforcement
Stage 2Interruption Statistic Collection
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 30
2. Loss Reduction
Stage 3Implementation
Stage 4Self
Improvement
Stage 5 Benchmarking
Stage 1Basic Knowledge Reinforcement of
Related Equipment
Stage 2Analysis of Break-Even Point
for Investment
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 31
3. Power Quality
Stage 3Finding Solution
Stage 4 Standardisation
Stage 1Basic Knowledge Reinforcement
Stage 2Analysis and Identifying
Cause of Problem
4. Undergrounding
Stage 3Funding
Stage 4 Implementation
Stage 1Basic Knowledge Reinforcement
Stage 2Master Plan Development
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 32
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 33
5. Smart Grid
Stage 3Master Plan
Stage 4Funding
Pilot Project
Stage 5 Full Scheme
Stage 1Basic Knowledge Reinforcement
Stage 2Identifying Technology and
Practice
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 34
6. Staff Capacity Building
Stage 3Develop training material & resources by
Lead utilities
Stage 4Implement
training
Stage 1Identify training need
Stage 2Develop training module
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 35
UTILITYS GOAL
High quality
Superb performance & safety
Excellence efficiency
PQ RELIABILITYLOSS
REDUCTION
SMART GRID
UNDERGROUND CABLE
Staff Capacity Building
POWER DISTRIBUTION SYSTEM
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam 36
HARMONISATION
Interconnected
Interchangeability
Integrated market
Thank You
7th LMS Harmonisation Forum. 11-12 September 2013, Meeting Hall EVNHANOI, Hanoi, Vietnam
Top Related