Page 1: James River Project Update for the James River Partnership XVII

US Army Corps of Engineers

BUILDING STRONG®

U.S. Army Corps of Engineers

Norfolk District James River Partnership XVIII

James River Project Update

Walter Trinkala

Project Manager

July 18, 2014

Page 2: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

James River Funding

2

FY 14 President's Budget:

FY 14 (work Plan)

FY 14 Sandy Funding

$3,801,000

$4,659,990

$750,000

FY 15 President’s Budget: $3,696,000

FY 15 Capability:

$7,600,000

Page 3: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Indefinite Delivery Indefinite Quantity

(IDIQ) Contract

W91236-13-D-0054 • IDIQ Contract Solicitation included a base year and two option years

(3 years total) $12M capacity

• Status:

• Base Contract Awarded August 19, 2013

• Task Order 0001 Awarded August 22, 2013

• Task Order 0002 Awarded December 6, 2013

• Task Order 0003

• YTD Contract Awarded: $8,697,340.61

Capacity Remaining: $3,302,659.39

3

Page 4: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Cottrell Contracting Corporation

The Lexington

4

Page 5: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Hydraulic Pipeline/CUTTERHEAD

5

Page 6: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

• Maintenance Dredging Completed:

• Dancing Point - Swann Point Shoal Channel (Task Order 0001)

• Dredged 1 Sept 2013 through 8 Nov 2013

• Tribell Shoal Channel (Task Order 0001)

• Dredged 3 Oct 2013 through 26 Oct 2013

• Goose Hill Shoal Channel (Task Order 0002)

• Dredged 10 Dec 2013 through 4 Feb 2014

• Dancing Point – Swann Point Channel (Task Order 0002)

• Dredged 5 February 2014 through 14 Feb 2014

• Total Volume of Dredged Material:

•1,063,926 Cubic Yards

FY 2013/2014

Accomplishments

6

Page 7: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

7

Page 8: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Status of Environmental

Permits

8

Upper James River:

( Hopewell to Richmond Harbor)

• Department of Environmental Quality (DEQ) Virginia Water Protection Permit (VWP)

• Expires 21 Dec 2014

• Corps will be renewing the DEQ VWP permit Aug 2014

Middle James River

(Goose Hill Shoal Channel to City Point Shoal Channel)

• DEQ VWP permit

• Issued 22 April 2014, Expires 21 April 2029

• Virginia Marine Resource Commission (VMRC)

• Permit Issued 19 March 2014, Expires 31 Jan 2017

Page 9: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Page 10: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

• Maintenance Dredging to be Performed:

(Starting early Aug 2014)

• Task Order 0003

• Dancing Point – Swann Point Shoal Channel

• Jordan Point – Windmill Point Shoal Channel

• Task Order 0004 (Subject to Availability of Funds)

• Shoal Channel TBD

• Contract Acquisition Strategy

• Condition Surveys:

•Richmond Deepwater Terminal to Hopewell.

FY 2014/2015 Activities

10

Page 11: James River Project Update for the James River Partnership XVII

BUILDING STRONG® 11

Page 12: James River Project Update for the James River Partnership XVII

BUILDING STRONG®

Questions/Comments?

Contact Information:

USACE, Norfolk District

Project Manager Walter Trinkala (757) 201-7715

Walter. A. [email protected]