ISAS Liaison Report
October 25-26, 2007 MIC Meeting
2
ISAS Liaison Report
Discussion Topics: Tagging Under MRTU JISWG Update Interchange Authority Discussion ESWG Update
3
ISAS Liaison Report
Tagging Under MRTU Presentation by Kyle Hoffman, CAISO
Manager of Scheduling CA software – implemented Feb, 2007
Automates e-tag approval, validation and correlation to SI transmission market reservation and curtailments; and
Integrated Forward Market (IFM) power flow optimization reducing real-time congestion.
4
ISAS Liaison Report
Tagging Under MRTU CA software misc. data field info. –
Old system – manual, new – automated; Auto-validation e-Tags with CAISO SI
market reservations; Provide market notices to participants;
and Training P/S and RT – provided tagging
templates via website.
5
ISAS Liaison Report
JISWG Update e-Tag timing tables
Split (one for WECC and one for all other regions); and
Built-in definitions for time classification elements (e.g., on-time, late, etc).
e-Tag 1.8 changes Basic features of e-Tag 1.8 are much the same
as in the current version, 1.7097. Tag author uses agent service to create/submit Authority service validates requests and manages
approval process Approval services used to assess, approve and
submit changes
6
ISAS Liaison Report
JISWG Update Request State Changes:
1.7097 1.8
Pending Pending
Implemented Approved
Dead Withdrawn
Denied
Expired
7
ISAS Liaison Report
JISWG Update Individual Approval States:
1.7097 1.8
NA NA
Pending Pending
Approved Approved
Denied Denied
Study Study
Expired
8
ISAS Liaison Report
JISWG Update Composite State Changes:
1.7097 1.8
Pending Pending
Implemented Confirmed
Implemented
Dead Cancelled
Terminated
Withdrawn
Denied
Expired
9
ISAS Liaison Report
JISWG Update Composite State Changes
Indicates the overall state of the e-Tag Does not go to Implement until ramp is
started 1.8 formalizes the time classification
Authority service assigns based on the relative start and submittal times
On-Time Late After-the-fact
10
ISAS Liaison Report
JISWG Update Other new capabilities
Terminate ATF e-Tags if a mistake is made;
Dynamics and ATF e-Tags can be submitted for start times up to 168 hours in the past; and
Pseudo Tie transaction type – optional use, not mandatory – treatment determined by user and software vendor.
ftp://www.nerc.com/pub/sys/all_updl/oc/jiswg/e-Tag_1-8_tutorial_rev10.ppt#277,21,e-Tag 1.8
11
ISAS Liaison Report
Interchange Authority Discussion OC requested ISAS to discuss and make a
recommendation on identifying the IA for the WECC.
Discussion IA standards are vague White paper developed describe the IA in the
WECC. WECC banded together to create a common authority service - WIT
Who registers as IA in the WECC? What happens if the WIT fails to distribute
arranged interchange? Who pays penalties?
12
ISAS Liaison Report
Interchange Authority Discussion ISAS voted on the following motion:
“WECC provides its membership the IA functionality through the WIT and is the contract holder of the WIT. As a member driven organization, we recommend WECC register as the Interchange Authority.”
Motion passed: 34-0-3 Basis: NERC Functional Model, Version
3, technical document, page 39.
13
ISAS Liaison Report
ESWG Update Outstanding issue – some dynamic e-
Tags not updated after the hour. INT-BPS-008, WR4 – energy profile
updated within 60 minutes after the completion of the operating hour. 96 hour update for ATF to settle out.
e-Tag 1.8 will help resolve this issue – BAs can perform the update as well as the LSEs.
14
ISAS Liaison Report
2007 Next ISAS Meeting November 7-8, Scottsdale, AZ______________________________
Questions????