Page 1: Introduction to Agile Project Management and Scrum

Eric  Krock  Co-­‐Founder,  Voximate  

http://twitter.com/#!/voximate  http://www.voximate.com/blog/  

Page 2: Introduction to Agile Project Management and Scrum

Why  Waterfall  Usually  Sucks  Problem   Consequences  

Serialized  process:  MRD  –  PRD  –  Design  Document  –  Dev  -­‐  QA  

Longer  time  to  market;  developers  isolated  from  customer  needs  

Planning  far  in  advance   Plans  no  longer  match  reality  by  the  time  they’re  implemented  

Lack  of  visibility  into  rate  of  progress  

Teams  don’t  realize  they’re  behind  schedule  until  too  late  Features  slashed  very  late  to  compensate,  wasting  effort  and  leading  to  Swiss-­‐cheese  products  (e.g.  MS  Kin)  

Long  time  to  project  completion  

Customers  get  access  to  new  features  infrequently  and  after  long  delay  Customers  can  only  provide  feedback  “too  late”  Process  doesn’t  allow  for  rapid  incremental  learning  

Projects  fall  behind  schedule  

Projects  miss  market  window  or  are  killed  before  launch  

Page 3: Introduction to Agile Project Management and Scrum

Why  PRDs  Usually  Suck    Long   Monolithic   Unreadable  and  unread   Often  disconnected  from  actual  customer  needs    Lack  of  clarity  about  what  features  are  for  which  customers  

Page 4: Introduction to Agile Project Management and Scrum

User  Stories   Express  a  customer  need  as  a  story  about  a  real  or  composite  user  in  the  language  of  the  customer  

 As  a  [USER  ROLE],  I  [must  /  want  /  wish  to]  [need]  so  that  [user  goal]  

  Short:  can  fit  on  an  index  card   Example:  “As  a  project  manager,  I  must  track  each  task’s  delivery  deadline  so  that  I  can  make  sure  tasks  are  completed  on  team.”  

  Small  amount  of  work:  can  fit  within  a  day  or  a  sprint    Should  include  notes  for  needed  acceptance  test  Source: Mike Cohn, User Stories Applied

Page 5: Introduction to Agile Project Management and Scrum

Es7mate  Effort  for  Story  in  Points    “Story  point”  =  abstract,  RELATIVE  estimate  of  amount  of  work  to  complete  a  story  

 Optional:  Using  Fibbonacci  sequence  forces  clear  distinctions  in  difficulty:  1,  2,  3,  5,  8,  13,  21  …  

 Teams  must  agree  on  estimate  for  each  story   Tracking  velocity  (points  completed  per  sprint)  will  measure  team’s  true  capacity  

  Issues:  measure  with  points,  or  not?  

Source: Mike Cohn, Agile Estimating and Planning

Page 6: Introduction to Agile Project Management and Scrum

Release  Plan   Combines  multiple  sprints  to  achieve  larger  goal   Capacity  =  number  of  sprints  *  expected  velocity   Choose  list  of  stories  with  total  story  points  no  greater  than  capacity  

Source: Mike Cohn, Agile Estimating and Planning, Chapter 13, “Release Planning”

Page 7: Introduction to Agile Project Management and Scrum

Divide  Workload  Into  Short  Sprints    Sprint  =  short,  fixed-­‐length  interval  for  development   Usually  1-­‐2  weeks   Key:  Must  return  product  to  potentially  shippable  state  at  end  of  sprint!  

  Reduces  accumulation  of  technical  debt    Keeps  assessment  of  project  progress  realistic  

Page 8: Introduction to Agile Project Management and Scrum

Key  Concepts  in  Scrum   Product  Owner:  voice  of  the  customer,  facilitates  writing  of  user  stories  

  ScrumMaster:  manages  the  sprints   Team:  do  the  work!   Collective  ownership   Daily  standup:  did  yesterday,  doing  today,  stuck  on  …  

Source: Mike Cohn, User Stories Applied, Chapter 15

Page 9: Introduction to Agile Project Management and Scrum

Development  Concepts   Test  driven  design*   Depth-­‐first  development  

* Source: Kent Beck, XP Explained

Page 10: Introduction to Agile Project Management and Scrum

Sprint  Commit  Mee7ng   At  start  of  each  sprint,  team  meets  and  commits  which  stories  they  will  do  for  the  sprint.  

 Make  decision  based  on  tasks  for  each  story  and  estimated  hours  for  all  tasks,  not  based  on  points.  

 Key:  After  sprint  commit  meeting,  no  new  stories  can  be  added  to  that  sprint.      For  true  emergencies,  must  remove  equal  amount  of  work  if  add  something  in  after  sprint  commit.  

Source: Mike Cohn, User Stories Applied

Page 11: Introduction to Agile Project Management and Scrum

User  Stories    Conversa7ons   User  story  is  basis  for  a  conversation  with  developer   Conversation  (not  the  user  story)  is  basis  for  actual  development  

 Goals:    Get  engineering  talking  to  product  owner,  customers,  etc.  

  Get  deeper  mutual  understanding  of  the  story  by  talking  about  it  

  Increase  odds  that  features  developed  will  actually  satisfy  customer’s  needs  

Source: Mike Cohn, User Stories Applied

Page 12: Introduction to Agile Project Management and Scrum

Sprint  Burndown  Chart  

0  

10  

20  

30  

40  

50  

60  

70  

3/27/11   3/28/11   3/29/11   3/30/11   3/31/11   4/1/11  

Sprint  Hours  of  Work  Remaining  

Page 13: Introduction to Agile Project Management and Scrum

Sprint  Review  Mee7ng   At  end  of  sprint,  review  what  work  actually  got  done.   Velocity  =  total  points  for  all  user  stories  completed  during  sprint.  

 No  partial  credit  for  partially-­‐complete  stories!   Estimated  time  to  project  completion  =    total  story  points  for  all  stories  in  project  /    moving  average  of  velocity  

 Moving  average  =  average  velocity  of  last  three  sprints   Team’s  accuracy  estimating  doable  work  per  sprint  should  improve  over  time  

Source: Mike Cohn, Agile Estimating and Planning

Page 14: Introduction to Agile Project Management and Scrum

Project  Burndown  Chart  

0  

50  

100  

150  

200  

250  

300  

350  

400  

1/7/11   1/14/11   1/21/11   1/28/11   2/4/11   2/11/11   2/18/11   2/25/11   3/4/11  

Points  Closed  Points  Added  Points  Remaining  

Page 15: Introduction to Agile Project Management and Scrum

Backlog:  Per-­‐Project,  or  Per-­‐Release?   Backlog  is  list  of  all  stories  not  yet  assigned  to  a  sprint    Simple  project,  single  release:  single  backlog  

  Benefit:  simplicity    Long-­‐lived  project  with  multiple  releases:  may  have  one  backlog  per  release    Benefit:  do  initial  division  of  work  by  release,  then  divide  each  release’s  work  into  sprints  during  development;  product  owner  needn’t  review  ALL  stories  at  every  sprint  

Page 16: Introduction to Agile Project Management and Scrum

Agile  Best  Prac7ces  Best  Practice   Benefit  

Don’t  write  stories  too  far  in  advance  of  development.*  

Avoid  wasted  effort  on  stories  that  are  not  implemented.  Use  best,  most-­‐current  information  when  writing  story.  

Don’t  event  tentatively  schedule  stories  more  than  2-­‐3  sprints  in  advance.  

Avoid  wasted  effort  of  moving  stories  when  priorities  change.  

Have  customers  write  and  prioritize  user  stories.*  

Let  customers  express  their  needs.  Avoid  “telephone  game”  problem.  Force  customers  to  make  tradeoffs.  

* Source: Mike Cohn, User Stories Applied

Page 17: Introduction to Agile Project Management and Scrum

Key  Agile  Values   Communication   Transparency   Honesty    Incremental  effort    Incremental  learning  feedback  

For fuller list of Agile / XP values, see Kent Beck, XP Explained, Chapters 3-5

Page 18: Introduction to Agile Project Management and Scrum

Agile  Versus  Tradi7onal  Waterfall  Metric   Waterfall   Agile  

Planning  scale   Long-­‐term   Short-­‐term  

Distance  between  customer  and  developer  

Long   Short  

Time  between  specification  and  implementation  

Long   Short  

Time  to  discover  problems  

Long   Short  

Project  schedule  risk   High   Low  

Ability  to  respond  quickly  to  change  

Low   High  

Page 19: Introduction to Agile Project Management and Scrum

Addi7onal  Reading  Book   Author   Notes  

User  Stories  Applied   Mike  Cohn   Intro  to  Agile  and  use  of  user  stories  for  expressing  requirements.  

Agile  Estimating  and  Planning  

Mike  Cohn   Deep  dive  on  Agile  metrics,  estimating,  and  project  planning.  

Succeeding  with  Agile   Mike  Cohn   Tips  on  rolling  out  Agile  in  a  larger  organization.  

Extreme  Programming  Explained  

Kent  Beck  &  Cynthia  Andres  

Introduction  to  XP  

Page 20: Introduction to Agile Project Management and Scrum

Addi7onal  Resources   http://www.mountaingoatsoftware.com/  Mike  Cohn’s  site  with  blog,  presentations,  more  

 http://agilemanifesto.org/   http://www.agilealliance.org/   http://www.scrumalliance.org/