LBP-16-04
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
ATOMIC SAFETY AND LICENSING BOARD
Before Administrative Judges:
Paul S. Ryerson, Chairman
Dr. Gary S. Arnold Dr. Craig M. White
In the Matter of PSEG POWER, LLC AND PSEG NUCLEAR, LLC (Early Site Permit Application)
Docket No. 52-043-ESP ASLBP No. 15-943-01-ESP-BD01 April 26, 2016
INITIAL DECISION
I. BACKGROUND ........................................................................................................................ 4
II. LEGAL STANDARDS ............................................................................................................ 10
III. APPROACH TO EVIDENTARY HEARING .......................................................................... 14
IV. SUMMARY OF TESTIMONY ............................................................................................... 31
A. SER Topic 1 .................................................................................................................... 31
1. PSEG Witnesses .......................................................................................................... 32
2. NRC Staff Witnesses .................................................................................................... 35
B. SER Topic 2 .................................................................................................................... 39
1. PSEG Witnesses .......................................................................................................... 40
2. NRC Staff Witnesses .................................................................................................... 41
C. SER Topic 3 .................................................................................................................... 45
1. PSEG Witness .............................................................................................................. 45
2. NRC Staff Witnesses .................................................................................................... 47
D. SER Topic 4 .................................................................................................................... 50
E. SER Topic 5 .................................................................................................................... 54
F. SER Topic 6 .................................................................................................................... 60
1. PSEG Witness .............................................................................................................. 60
2. NRC Staff Witnesses .................................................................................................... 63
- 2 -
G. FEIS Topic 1 ................................................................................................................... 65
H. FEIS Topic 2 ................................................................................................................... 68
I. FEIS Topic 3 ................................................................................................................... 70
1. PSEG Witness .............................................................................................................. 70
2. NRC Staff Witnesses .................................................................................................... 73
J. FEIS Topic 4 ................................................................................................................... 76
K. FEIS Topic 5 ................................................................................................................... 79
L. FEIS Topic 6 ................................................................................................................... 81
1. PSEG Witness .............................................................................................................. 81
2. NRC Staff Witnesses .................................................................................................... 82
M. FEIS Topic 7 ................................................................................................................... 85
N. FEIS Topic 8 ................................................................................................................... 87
V. DISCUSSION ........................................................................................................................ 88
VI. FINDINGS ............................................................................................................................ 94
VII. ORDER ................................................................................................................................ 95
- 3 -
Before the Atomic Safety and Licensing Board (the Board) is an application from PSEG
Power, LLC and PSEG Nuclear, LLC (collectively PSEG) for a 10 C.F.R. Part 52, Subpart A
Early Site Permit (ESP).1 In its ESP application, PSEG proposes a site for a potential nuclear
power facility adjacent to two existing facilities in Salem County, New Jersey (the PSEG site).2
An ESP is a “partial construction permit.”3 However, “an ESP is not an authorization to
construct or operate a nuclear power plant. It relates only to site suitability.”4
Pursuant to Section 189a(1)(A) of the Atomic Energy Act (AEA), 42 U.S.C.
§ 2239(a)(1)(A), and 10 C.F.R. § 52.21, this Board was constituted to conduct a mandatory
(uncontested) hearing concerning PSEG’s ESP application.5 Licensing boards have an
“important but limited role” in such proceedings, in which the only parties are the applicant and
the NRC Staff.6 The Commission expects “licensing boards conducting mandatory hearings on
uncontested issues to take an independent ‘hard look’ at NRC Staff safety and environmental
1 See 75 Fed. Reg. 68,624, 68,624 (Nov. 8, 2010)
2 The existing nuclear power facilities are Salem Generating Station Units 1 and 2 and Hope Creek Generating Station Unit 1. Ex. NRC003, at 1-1 (Safety Evaluation of the Early Site Permit Application in the Matter of PSEG Power, LLC and PSEG Nuclear, LLC for the PSEG Early Site Permit Site at 1-1 (Sept. 2015)). 3 10 C.F.R. § 52.1(a); Exelon Generation Co., LLC (Early Site Permit for Clinton ESP Site), CLI-07-12, 65 NRC 203, 205 (2007).
4 See Clinton ESP Site, CLI-07-12, 65 NRC at 205. “If an applicant includes a satisfactory site redress plan, an ESP holder may conduct certain site preparation activities under a ‘limited work authorization’ granted under 10 C.F.R. § 50.10(e).” Va. Electric & Power Co. (N. Anna Power Station, Unit 3), LBP-08-15, 68 NRC 294, 307 n.58 (2008) (citing 10 C.F.R. § 52.27); see also 10 C.F.R. § 50.10(d)(3). PSEG’s ESP application did not request a limited work authorization.
5 Establishment of Atomic Safety and Licensing Board (Sept. 25, 2015); see also 80 Fed. Reg. 58,793 (Sept. 30, 2015).
6 Exelon Generation Co., LLC (Early Site Permit for Clinton ESP Site), CLI-05-17, 62 NRC 5, 41 (2005).
- 4 -
findings.”7 However, licensing boards are “not to replicate NRC Staff work.”8 The Commission
has directed that licensing boards “should conduct a simple ‘sufficiency’ review of uncontested
issues, not a de novo review.”9
After reviewing the Final Environmental Impact Statement (FEIS) and Safety Evaluation
Report (SER) prepared by the NRC Staff (including the license conditions imposed by the Staff),
the prefiled testimony and exhibits filed by the Staff and PSEG, the oral testimony heard over
the course of a one-day evidentiary hearing, and the complete record of this proceeding, the
Board finds that the application and record of this proceeding contain sufficient information to
support issuance of PSEG’s requested ESP and that the Staff’s review of the application has
been adequate to support its independent safety and environmental findings. We have also
independently considered the final balance among conflicting environmental and other factors
with a view to determining the appropriate action to be taken, and determined that an ESP
should be issued.
I. BACKGROUND
On May 25, 2010, PSEG submitted its initial ESP application to the NRC.10 PSEG’s
proposed site is located on the southern part of Artificial Island in Lower Alloways Creek
Township in New Jersey.11 “Artificial Island was formed from dredge spoils produced as a result
of maintenance dredging of the Delaware River navigation channel by the [U.S. Army Corps of
7 Clinton ESP Site, CLI-05-17, 62 NRC at 34.
8 Id.
9 Id. at 39; see also Nuclear Innovation N. Am. LLC (S. Texas Project Units 3 & 4), CLI-16-02, 82 NRC __, __ (slip op. at 7) (Feb. 9, 2016).
10 See Letter from David P. Lewis, PSEG Nuclear Development Project Director, & Paul J. Davison, Vice President, PSEG Operations Support to NRC (May 25, 2010) (ADAMS Accession No. ML101480484).
11 Ex. NRC004A, 1 Environmental Impact Statement for an Early Site Permit (ESP) at the PSEG Site at 2-1 (Nov. 2015) [hereinafter Ex. NRC004A].
- 5 -
Engineers (USACE)].”12 The proposed site is also adjacent to three existing nuclear power units
on Artificial Island—Salem Generating Station Units 1 and 2 and Hope Creek Generating
Station Unit 1.13
Pursuant to 10 C.F.R. Part 52, PSEG was not required to select a specific unit design at
the ESP stage.14 Rather, PSEG’s application referred to a plant parameter envelope (PPE) “as
a surrogate for a nuclear power plant and its associated facilities.”15 As stated in the FEIS, “[a]
PPE is a set of values of plant design parameters that an ESP applicant expects would bound
the design characteristics of the reactor or reactors that might be constructed at a given site.”16
Accordingly, the PPE approach allows PSEG to “defer the selection of a reactor design until the
construction permit (CP) or combined construction permit and operating license (combined
license or COL) stage.”17
The NRC Staff conducted a four-phase safety review of PSEG’s application.18 First, the
NRC Staff identified several areas of concern and submitted requests for additional information
12 Id.
13 Id.
14 See Ex. NRC004A, at 3-4 (“An applicant for an ESP need not provide a detailed design of a reactor or reactors and the associated facilities but should provide sufficient values for parameters for the reactor or reactors and the associated facilities so that an assessment of site suitability can be made.”); see also Exelon Generation Co., LLC (Early Site Permit for Clinton ESP Site), LBP-06-28, 64 NRC 460, 467-68 (2006), permit issuance authorized, CLI-07-12, 65 NRC 203 (2007). 15 Ex. NRC004A, at 1-2, 3-5.
16 Id. at 3-4 to 3-5.
17 Id. at 3-5. PSEG utilized information from the following reactor designs in developing the PPE for its proposed site: (1) Single Unit U.S. Evolutionary Power Reactor; (2) Single Unit Advanced Boiling Water Reactor; (3) Single Unit U.S. Advanced Pressurized Water Reactor; and (4) Dual Unit Advanced Passive 1000. Ex. NRC003, at 1-3.
18 Ex. NRC003, at xvii.
- 6 -
to PSEG.19 Second, the NRC Staff reviewed PSEG’s responses to these requests and issued
chapter-specific Advanced Safety Evaluations (ASEs).20 Having resolved any outstanding
concerns, there were no open items when the Staff completed the ASEs.21 Next, the NRC Staff
submitted the ASEs to the NRC Advisory Committee on Reactor Safeguards (ACRS).22 The
ACRS is an independent committee of technical experts who, pursuant to the Atomic Energy
Act, “advise the Commission with regard to the hazards of proposed or existing reactor facilities
and the adequacy of proposed reactor safety standards.”23 At the conclusion of its independent
review, the ACRS determined that the ESP should be issued.24 Finally, on September 29,
2015, the NRC Staff issued the final SER on PSEG’s application.
The SER concludes that “one or two reactors, having characteristics that fall within the
parameters for the site, and which meet the terms and conditions proposed by the staff in this
SER, can be constructed and operated without undue risk to the health and safety of the
public.”25 The SER also specifies nine permit conditions.26 For example, two of the permit
conditions address geology, seismology, and geotechnical engineering.27 One such condition
requires that:
[a]n applicant for a COL or CP referencing this early site permit shall perform detailed geologic mapping of excavations for safety-related structures; examine
19 Id.
20 Id.
21 Id.
22 Id.
23 42 U.S.C. § 2039; see also id. § 2232(b).
24 Ex. NRC003, App. E, at E-2.
25 Id. at 22-1.
26 Id., App. A, at A-2 to A-6.
27 Id. at A-3.
- 7 -
and evaluate geologic features discovered in those excavations; and notify the Director of the Office of New Reactors . . . once excavations for safety-related structures are open for examination by NRC staff.28
Another permit condition requires that “[a]n applicant for a COL or CP [r]eferencing this early
site permit shall remove and replace the soils directly above the Vincentown Formation for soils
under or adjacent to Seismic Category I structures to minimize any liquefaction potential.”29
Two other permit conditions address several issues with control over the proposed location’s
exclusion area30 and planning regarding possible explosions associated with gasoline storage
and delivery.31 The remaining five permit conditions address emergency planning.32
The NRC Staff also performed an environmental review. On October 15, 2010, in
accordance with 10 C.F.R. § 51.26, the NRC published a notice of intent to prepare an
environmental impact statement.33 Thereafter, the NRC Staff conducted two public meetings
near the proposed site and considered fifty-one written and oral public comments submitted in
response to these public meetings.34 In conducting its environmental review, the NRC Staff also
consulted with federal, state, and local authorities, including but not limited to the U.S. Fish and
Wildlife Service, the New Jersey Department of Environmental Protection (NJDEP), and the
28 Id.
29 Id.
30 10 C.F.R. § 100.3 defines exclusion area as the “area surrounding the reactor, in which the reactor licensee has the authority to determine all activities including exclusion or removal of personnel and property from the area.”
31 Id., App. A, at A-2 to A-3.
32 Id. at A-4 to A-6.
33 75 Fed. Reg. 63,521, 63,521 (Oct. 15, 2010).
34 See NRC Environmental Impact Statement Scoping Process Summary Report, PSEG [ESP] Application (Sept. 2011) at 3 (ADAMS Accession No. ML112150127).
- 8 -
State of Delaware Office of Historical and Cultural Affairs.35 Further, “in support of its proposed
action of issuing a Department of the Army permit, the U.S. Army Corps of Engineers . . .
participated in the preparation of the EIS as a cooperating agency and as a collaborative
member of the review team.”36
In August of 2014 the Staff published a Draft Environmental Impact Statement (DEIS).37
After the DEIS was published, the NRC Staff held two public meetings: one in Carneys Point,
New Jersey on October 1, 2014, and one in Middletown, Delaware on October 23, 2014.38
Approximately two hundred and fifteen people attended these public meetings.39 In addition to
oral comments at the two public meetings, the NRC received forty-five letters and e-mails
containing written comments.40 On November 13, 2015, the NRC Staff posted the Final
Environmental Impact Statement (FEIS) on the NRC public website.41
The Commission published a Notice of Hearing in the Federal Register on November 8,
2010.42 No petitions to intervene under 10 C.F.R. § 2.309 or petitions to participate as an
interested governmental entity under 10 C.F.R. § 2.315(c) were submitted.
35 Ex. NRC004A at xxiii.
36 Id.
37 [DEIS] for an [ESP] at the PSEG Site (Aug. 2014) (ADAMS Accession No. ML14219A304).
38 Ex. NRC004A, at xxiv.
39 See id.
40 Ex. NRC004C, 3 Environmental Impact Statement for an Early Site Permit (ESP) at the PSEG Site, App. E, at E-2 (Nov. 2015) [hereinafter Ex. NRC004C].
41 Licensing Board Order (Initial Scheduling Order) (Nov. 16, 2015) at 4 (unpublished) [hereinafter Initial Scheduling Order].
42 75 Fed. Reg. at 68,625.
- 9 -
This Board was established on September 25, 2015.43 On January 14, 2016, the parties
responded to the Board’s initial written questions regarding the SER.44 On January 28, 2016,
the parties responded to the Board’s second set of written questions primarily concerning the
FEIS.45
After reviewing the parties’ answers to the Board’s initial written questions, the Board
concluded that many of the parties’ answers resolved its concerns on a given issue and
established an adequate record.46 As contemplated by the Initial Scheduling Order,47 the Board
identified issues on which it still had questions and wished to review more detailed prefiled
testimony and exhibits.48 On February 25, 2016, the Staff and PSEG submitted their prefiled
written testimony and exhibits as directed by the Board’s orders.49
43 80 Fed. Reg. at 58,793. 44 PSEG Responses to Initial Board Questions (Jan. 14, 2016); NRC Staff Response to the Licensing Board’s Initial Questions Issued December 15, 2015 (Jan. 14, 2016); see also Licensing Board Memorandum and Order (Initial Board Questions and Associated Administrative Directives) (Dec. 15, 2015) (unpublished) [hereinafter December 15, 2015 Questions Order].
45 PSEG Responses to Second Set of Board Questions (Jan. 28, 2016); NRC Staff Response to the Licensing Board’s Second Set of Questions Issued January 6, 2016 and Other Matters (Jan. 28, 2016); see also Licensing Board Memorandum and Order (Second Set of Board Questions and Associated Administrative Directives) (Jan. 6, 2016) (unpublished) [hereinafter January 6, 2016 Questions Order].
46 Licensing Board Memorandum and Order (Identifying Areas for Prefiled Testimony) (Jan. 27, 2016) at 1-2 (unpublished) [hereinafter SER Prefiled Testimony Order]; Licensing Board Memorandum and Order (Identifying Additional Areas for Prefiled Testimony) (Feb. 8, 2016) at 1-2 (unpublished) [hereinafter FEIS Prefiled Testimony Order].
47 Initial Scheduling Order at 3-4.
48 SER Prefiled Testimony Order at 2-3; FEIS Prefiled Testimony Order at 2-3.
49 See SER Prefiled Testimony Order at 3; FEIS Prefiled Testimony Order at 4.
- 10 -
The Board conducted an evidentiary hearing on March 24, 2016.50 Except as
specifically excused prior to the hearing,51 all twenty-two witnesses who submitted prefiled
testimony were present and available to answer the Board’s questions. The Board admitted
without objection all prefiled exhibits submitted by either party.52 On April 11, 2016, the Board
accepted the parties’ proposed transcript corrections and closed the evidentiary record.53
II. LEGAL STANDARDS
Pursuant to 42 U.S.C. § 2239, “[t]he Commission shall hold a hearing . . . on each
application under section 2133 or 2134(b) of this title for a construction permit for a facility.”54
ESP applications, as partial construction permit applications, are subject to the AEA hearing
requirement, as well as “all procedural requirements in 10 C.F.R. part 2.”55
In a mandatory, uncontested hearing, this Board’s review is a limited one. The NRC
Staff and PSEG agree that this Board must determine whether seven requirements are
satisfied.56 Pursuant to 10 C.F.R. § 52.24(a), an ESP may issue if the Board finds, among other
things, that:
(1) An application for an early site permit meets the applicable standards and requirements of the Act and the Commission’s regulations;
50 Tr. at 62-185. On February 8, 2016, the Board issued a Notice of Hearing pursuant to 10 C.F.R. § 2.104. Licensing Board Order (Notice of Hearing) (Feb. 8, 2016). The Notice of Hearing was published in the Federal Register on February 16, 2016. 81 Fed. Reg. 7835, 7835 (Feb. 16, 2016).
51 Licensing Board Memorandum and Order (Identifying Resolved Topics) (Mar. 15, 2016) at 1 (unpublished).
52 Tr. at 70-72.
53 Licensing Board Order (Approving Joint Proposed Transcript Corrections) (Apr. 11, 2016) (unpublished).
54 42 U.S.C. § 2239(a)(1)(A).
55 10 C.F.R. § 52.21; see also Sys. Energy Res., Inc. (Early Site Permit for Grand Gulf ESP Site), LBP-07-1, 65 NRC 27, 35, permit issuance authorized, CLI-07-14, 65 NRC 216 (2007).
56 See Initial Scheduling Order at 2, Attach. A; Tr. at 14-15.
- 11 -
(2) Notifications, if any, to other agencies or bodies have been duly made; (3) There is reasonable assurance that the site is in conformity with the
provisions of the Act, and the Commission’s regulations; (4) The applicant is technically qualified to engage in any activities
authorized; (5) The proposed inspections, tests, analyses and acceptance criteria,
including any on emergency planning, are necessary and sufficient, within the scope of the early site permit, to provide reasonable assurance that the facility has been constructed and will be operated in conformity with the license, the provisions of the Act, and the Commission’s regulations;
(6) Issuance of the permit will not be inimical to the common defense and
security or to the health and safety of the public; [and] . . . (8) The findings required by subpart A of 10 CFR part 51 have been
made.57
Pursuant to § 52.24(a)(8), the provisions of 10 C.F.R. § 51.105(a) further require the
Board to:
(1) Determine whether the requirements of Sections 102(2) (A), (C), and (E) of [the National Environmental Policy Act (NEPA)] and the regulations in this subpart have been met;
(2) Independently consider the final balance among conflicting factors
contained in the record of the proceeding with a view to determining the appropriate action to be taken;
(3) Determine, after weighing the environmental, economic, technical, and
other benefits against environmental and other costs, and considering reasonable alternatives, whether the construction permit or early site permit
57 10 C.F.R. § 52.24(a)(1)-(6), (8). 10 C.F.R. § 52.24(a)(7) states that an ESP may issue if the Board finds that “[a]ny significant adverse environmental impact resulting from activities requested under § 52.17(c) can be redressed.” 10 C.F.R. § 52.17(c) allows an applicant to request a limited work authorization in conjunction with an ESP. Because PSEG has not requested a limited work authorization, this section does not apply. Additionally, 10 C.F.R. § 52.24(b) states that, if the Commission decides to authorize issuance of the ESP, the issued ESP “must specify the site characteristics, design parameters, and terms and conditions of the [ESP] the Commission deems appropriate.”
- 12 -
should be issued, denied, or appropriately conditioned to protect environmental values;58 [and]
(4) Determine, in an uncontested proceeding, whether the NEPA review
conducted by the NRC staff has been adequate . . . .59
When addressing these questions, licensing boards are not expected to conduct a de
novo review of safety or environmental issues, but rather “a simple ‘sufficiency’ review of
uncontested issues.”60 Licensing boards must “take an independent ‘hard look’ at NRC Staff
safety and environmental findings, but not . . . replicate NRC Staff work. Giving appropriate
deference to NRC Staff technical expertise, boards are to probe the logic and evidence
58 Pursuant to 10 C.F.R. § 52.21, an applicant’s environmental report and the NRC Staff’s environmental impact statement for an ESP application are not required to address the benefits of constructing and operating the facility as distinct from the benefits of issuing an ESP. See 10 C.F.R. § 52.21 (“An early site permit is subject to all procedural requirements in 10 CFR part 2 . . . provided that the designated sections may not be construed to require that the environmental report, or draft or final environmental impact statement include an assessment of the benefits of construction and operation of the reactor or reactors, or an analysis of alternative energy sources.”); see also Licenses, Certifications, and Approvals for Nuclear Power Plants, 72 Fed. Reg. 49,352, 49,434 (Aug. 28, 2007). However, where, as here, the applicant’s environmental report and the NRC Staff’s FEIS do evaluate energy alternatives and the need for power, see FEIS at 8-1, the Board must consider these issues in weighing the costs and benefits of the application. See 72 Fed. Reg. at 49,434 (“If the applicant has addressed all of the costs and benefits associated with construction and operation of the facility in its environmental report, the final balancing between costs and benefits needs to occur at the early site permit stage.”). Prior to the most recent amendments to 10 C.F.R. § 52.21 in 2007, several Commission and Board decisions took a contrary view. See, e.g., Clinton ESP Site, CLI-05-17, 62 NRC at 47; Exelon Generation Co., LLC (Early Site Permit for Clinton ESP Site), LBP-06-28, 64 NRC 460, 487 (2006), permit issuance authorized, CLI-07-12, 65 NRC 203 (2007); Dominion Nuclear N. Anna, LLC (Early Site Permit for N. Anna ESP Site), LBP-07-9, 65 NRC 539, 615, permit issuance authorized, CLI-07-27, 66 NRC 215 (2007). 59 10 C.F.R. § 51.105(a)(1)-(4). Because this is an uncontested proceeding, 10 C.F.R. § 51.105(a)(5), which concerns only contested cases, does not apply.
60 Clinton ESP Site, CLI-05-17, 62 NRC at 39. The Commission has directed that:
[Licensing boards] should inquire whether the NRC Staff performed an adequate review and made findings with reasonable support in logic and fact. “An analogy is to the function of an appellate court, applying the ‘substantial evidence’ test, although it is imperfect because the ASLB looks not only to the information in the record, but also to the thoroughness of the review that the Staff . . . has given it.”
Id. (footnotes omitted).
- 13 -
supporting NRC Staff findings and decide whether those findings are sufficient to support
license issuance.”61
Regarding NEPA findings, however, licensing boards are instructed to make
independent environmental judgments,62 although they “need not rethink or redo every aspect of
the NRC Staff’s environmental findings or undertake their own fact-finding activities.”63 A
licensing board’s role is to “carefully probe [NRC Staff] findings by asking appropriate questions
and by requiring supplemental information when necessary,”64 but “the NRC Staff’s underlying
technical and factual findings are not open to board reconsideration unless, after a review of the
record, the board finds the NRC Staff review inadequate or its findings insufficient.”65 In
reaching our independent judgment regarding NEPA issues, licensing boards walk a fine line—
our role is not to “second-guess underlying technical or factual findings by the NRC Staff,”66 but
to ensure that the demands of NEPA and our regulations are met through “independent
environmental judgments by NRC licensing boards.”67 Even a licensing board’s NEPA review
61 Id. at 34 (footnote omitted).
62 After a licensing board in an uncontested proceeding determines the NRC Staff’s NEPA review is adequate, it must then “independently consider the final balance among conflicting factors that is struck in the staff’s recommendation.” Calvert Cliffs’ Coordinating Comm., Inc. v. AEC, 449 F.2d 1109, 1118 (D.C. Cir. 1971). The Commission has directed “boards to follow the approach spelled out in the D.C. Circuit’s seminal Calvert Cliffs decision.” Clinton ESP Site, CLI-05-17, 62 NRC at 44.
63 Clinton ESP Site, CLI-05-17, 62 NRC at 44; see also N. Anna ESP Site, LBP-07-9, 65 NRC at 559-60.
64 Clinton ESP Site, CLI-05-17, 62 NRC at 40.
65 Id.
66 Id. at 45.
67 Id. at 44 (quoting Consumers Power Co. (Midland Plant, Units 1 & 2), ALAB-123, 6 AEC 331, 335 (1973)).
- 14 -
“must not be so intrusive or detailed as to involve the board in ‘independent basic research’ or a
‘duplicat[ion of] the analysis previously performed by the staff.’”68
III. APPROACH TO EVIDENTARY HEARING
To summarize the posture of this proceeding as it comes before this Licensing Board:
1. PSEG seeks merely an early site permit. If granted, the permit will resolve some
important issues. However, PSEG has not yet even selected a reactor design or
manufacturer.69 To obtain permission to construct and operate a reactor on the site, PSEG
would have to come back to the NRC and address additional issues.70
2. PSEG’s proposal fundamentally requires the NRC merely to decide whether Artificial
Island—an uninhabited island created out of dredge spoils that is home to three existing nuclear
power reactors—might be an appropriate site for one or two additional nuclear power reactors.71
3. After reviewing both the safety aspects and environmental impact of PSEG’s
proposal, the NRC Staff recommended issuance of the permit subject to specified conditions.72
4. After being afforded the opportunity to seek a contested evidentiary hearing on
PSEG’s application, no member of the public or state or local government elected to do so.73
68 Id. at 45 (footnote omitted).
69 Ex. NRC004A, at 3-5.
70 Id.
71 See id. at 2-1.
72 See Ex. NRC003, at 22-1, App. A, at A-2 to A-6; Ex. NRC004B, 2 Environmental Impact Statement for an Early Site Permit (ESP) at the PSEG Site at 10-33 (Nov. 2015) [hereinafter Ex. NRC004B].
73 See Establishment of Atomic Safety and Licensing Board (Sept. 25, 2015); see also 80 Fed. Reg. 58,793 (Sept. 30, 2015).
- 15 -
5. After reviewing PSEG’s application, the NRC’s independent ACRS recommended
that the requested permit be issued.74
In these circumstances, some might suggest that a further independent hearing by this
Board is redundant and unnecessary. The Atomic Energy Act, as interpreted by the
Commission, provides otherwise. A hearing on an application for an early site permit is required
by statute regardless of whether the application is opposed.75 The Board’s challenge and
responsibility, therefore, has been to conduct this mandatory, uncontested proceeding so as to
make a meaningful but efficient contribution to what has already been a lengthy and thorough
review of PSEG’s application.
The Atomic Energy Act does not prescribe a specific structure for a mandatory hearing,
and the Commission has allowed licensing boards flexibility to select the most appropriate
approach in the circumstances of each individual case.76 As the Commission has explained:
As for the actual procedure to be followed at mandatory hearings, licensing boards have considerable flexibility. The AEA’s mandatory hearing requirements in sections 189a and 193(b)(1) are phrased generally. “[T]he Act itself nowhere prescribes the content of a hearing or prescribes the manner in which this ‘hearing’ is to be run.” The word “hearing” can refer to any of a number of events, including trial-type evidentiary hearings, “paper hearings,” paper hearings accompanied by oral arguments, hearings employing a mixture of procedural rules, and legislative hearings. The AEA’s hearing requirement does not demand a “one size fits all” approach. Thus, we do not dictate any particular procedure in the current cases, but we would expect the boards to select the most appropriate and expeditious approach given the specific circumstances of a case.77
In determining what structure may best serve the needs of this hearing, the Board heeded the
Commission’s advice to sharpen our focus by narrowing it:
74 Ex. NRC003, App. E, at E-2.
75 See Atomic Energy Act of 1954, §§ 185b, 189a, 42 U.S.C. §§ 2235(b), 2239(a); Clinton ESP Site, CLI-05-17, 62 NRC at 27-29 (explaining the history of the AEA’s mandatory hearing requirement and its applicability to early site permit applications).
76 See Clinton ESP Site, CLI-05-17, 62 NRC at 42-43.
77 Id. (footnotes omitted).
- 16 -
A “mandatory hearing” board must narrow its inquiry to those topics or sections in Staff documents that it deems most important and should concentrate on portions of the documents that do not on their face adequately explain the logic, underlying facts, and applicable regulations and guidance. It serves no purpose for the Staff to produce volumes of documents and information supporting facts and conclusions that are of small importance and are beyond dispute. It likewise serves no purpose for the Staff to produce copies of every document used in its review when the Board cannot possibly read through every one, let alone scrutinize them.78
Therefore, rather than undertake a comparatively shallow analysis of all possible issues, the
Board focused on a relatively thorough examination of selected issues of concern by instituting
a multi-step process that narrowed as the Staff and Applicant responded to the questions and
concerns of the Board.
First, the Board members reviewed the SER and the FEIS.
Second, on December 15, 2015, and January 6, 2016, the Board set forth a total of
ninety detailed written questions arising from the SER and the FEIS, to which it directed the
parties to respond.79 More specifically, we directed that “[t]he parties’ written answers shall, for
each question, identify the responding subject matter expert(s) or individuals(s), and shall be
submitted in exhibit form, under oath, so that they are suitable for receipt into evidence without
the necessity of the personal appearance of each expert or individual.”80 In other words, we
directed the parties to respond under oath to our initial written questions, so that the Board
could accord the responses as much weight as we would give sworn testimony presented in
person at an evidentiary hearing.
78 Exelon Generation Co., LLC (Early Site Permit for Clinton ESP Site), CLI-06-20, 64 NRC 15, 21-22 (2006).
79 January 6, 2016 Questions Order, Attach. A; December 15, 2015 Questions Order, Attach. A.
80 Initial Scheduling Order at 4; see also January 6, 2016 Questions Order at 1; December 15, 2015 Questions Order at 1.
- 17 -
The parties responded to the Board’s initial written questions on January 15 and 28,
2016.81 Collectively, the parties’ sworn responses totaled some 92 pages, exclusive of the
supporting affidavits and resumes of the 36 responding individuals.82 Because the parties
provided substantial and, for the most part, directly responsive answers to the Board’s initial
questions, the need for written or oral testimony at the evidentiary hearing was reduced to the
extent that the parties’ sworn answers resolved many of the Board’s concerns.
The following illustrate a few of the areas in which the Board’s preliminary concerns
were adequately addressed by the parties’ responses to the Board’s initial written questions:83
1. The Board was concerned about the extent to which the NRC Staff had
independently confirmed PSEG’s calculations.84 The Staff responded that independent
calculations were generally performed in significant safety areas and where there appeared to
be meaningful uncertainty.85 It specifically identified five areas in which significant verification
calculations were performed (including meteorology, radiation protection, hydrology, vibratory
81 PSEG Responses to Initial Board Questions (Jan. 14, 2016) [hereinafter PSEG Response to First Set of Board Questions]; NRC Staff Response to the Licensing Board’s Initial Questions Issued December 15, 2015 (Jan. 14, 2016) [hereinafter NRC Staff Response to First Set of Board Questions].
82 PSEG Response to First Set of Board Questions; NRC Staff Response to First Set of Board Questions; PSEG Response to Second Set of Board Questions (Jan. 28, 2016) [hereinafter PSEG Response to Second Set of Board Questions]; NRC Staff Response to the Licensing Board’s Second Set of Questions Issued January 6, 2016 and Other Matters (Jan. 28, 2016) [hereinafter NRC Staff Response to Second Set of Board Questions].
83 Additionally, as discussed in Section V infra, in other instances the parties’ initial responses—while not necessarily fully satisfactory by themselves—were adequate when considered together with subsequent written and oral testimony.
84 December 15, 2015 Questions Order, Attach. A, ¶ 2.
85 NRC Staff Response to First Set of Board Questions, Attach. A, at 1.
- 18 -
ground motion, and external manmade hazards)86 and established that responsible Staff
members were appropriately qualified,87 thereby satisfying our concerns.
2. Because the proposed PSEG site is adjacent to existing nuclear reactors, the Board
was interested both in whether the NRC Staff was able to conserve resources during its review
by relying on existing information regarding those facilities and in whether cumulative safety-
related effects were adequately considered.88 First, the NRC Staff clarified that it reviewed the
ESP application to determine whether it independently contained adequate information to
support the ultimate decision.89 Second, the NRC Staff described specific areas (including
meteorology, radiation protection, hydrology, external manmade hazards, and emergency
planning) where cumulative effects from existing units might arise, thus requiring that they be
considered.90 Based on the NRC Staff’s responses, the Board’s concerns regarding these
issues were resolved.
3. The Board identified other concerns—arising from the potential interplay between a
new power facility at the PSEG site and existing reactors—with respect to meteorology, flooding
hazards, geology, and emergency planning.91 The NRC Staff explained that its review of
meteorology at the PSEG site did not consider the meteorological descriptions in safety
documents for existing reactors, but that the Staff did review historical meteorological data
collected at an onsite tower associated with the existing reactors.92 Similarly, the NRC Staff
86 Id. at 2-4.
87 Id.
88 December 15, 2015 Questions Order, Attach. A, ¶¶ 4-5.
89 NRC Staff Response to First Set of Board Questions, Attach. A, at 4.
90 Id. at 4-5.
91 December 15, 2015 Questions Order, Attach. A, ¶¶ 13, 19, 42, 52.
92 NRC Staff Response to First Set of Board Questions, Attach. A, at 8.
- 19 -
explained that consideration of flooding hazards made use of related meteorological conditions
for all units.93 The NRC Staff stated that it also examined geologic information from the existing
reactors’ safety-related documents and confirmed that there are no significant differences
regarding the PSEG site.94 Likewise, the NRC Staff confirmed that the PSEG site emergency
plan does not significantly differ from the plans for the existing reactors, except as required to
incorporate the future selection of a reactor design.95 Based on the parties’ responses, the
Board was satisfied that the NRC Staff had adequately considered the relationship between the
PSEG site and the existing reactors on Artificial Island.
4. The Board was concerned about aspects of atmospheric stability and dispersion of
radioactive material if a release were to occur.96 The NRC Staff explained that, based on
design height release assumptions—for a flat terrain like the PSEG site—a ground level release
is generally conservative, which is consistent with NRC guidance.97 Because the atmosphere is
less dispersive at lower levels, and because less dispersion results in greater exposure to those
in the plume pathway, assuming a ground level release results in greater exposure and is
therefore conservative.98 Additionally, the Staff explained, it is conservative to disregard
building wakes because they are dispersive in nature.99 Regarding the possible rise of a hot
plume from above ground level, the NRC Staff acknowledged this possibility, but noted that the
93 Id. at 11.
94 Id. at 25.
95 Id. at 30.
96 December 15, 2015 Questions Order, Attach. A, ¶¶ 14-16.
97 NRC Staff Response to First Set of Board Questions, Attach. A, at 8-9.
98 See id. at 9.
99 See id.
- 20 -
higher altitude of the rise would result in greater dispersion and lower exposures.100 Hence, not
accounting for this possibility represented a conservative approach.101 Lastly, the NRC Staff
explained that assessing dispersion of airborne radioactive material in the reactor control room
was not a necessary future action item, because this issue will necessarily be reviewed if and
when PSEG applies for a COL.102 Based on these responses, the Board was satisfied that the
dispersion of radioactive material was adequately reviewed and subject to conservative
assumptions.
5. The Board identified several concerns regarding the NRC Staff’s review of PSEG’s
evaluation of the probable maximum surge and seiche flooding at the PSEG site.103 The Board
questioned the sensitivity of surface water elevation to the radius of maximum winds (radius
value) for a hurricane, and why the assumption of 28 nautical miles for that radius value is
conservative.104 The NRC Staff responded that “[i]n general, keeping all other storm surge
parameters constant, hurricane central pressure and resultant storm intensity decreases as
[radius value] (storm size) increases.”105 As a result, a lower radius value yields a higher storm
surge.106 Furthermore, the NRC Staff stated that the largest storm surge recorded in the United
States resulted from Hurricane Katrina, which had a radius value of 30 nautical miles.107
100 See id.
101 See id.; see also PSEG Response to First Set of Board Questions, Attach. A, at 9.
102 NRC Staff Response to First Set of Board Questions, Attach. A, at 10.
103 December 15, 2015 Questions Order, Attach. A, ¶¶ 21-25.
104 Id. ¶ 21.
105 NRC Staff Response to First Set of Board Questions, Attach. A, at 12.
106 See id.
107 Id.
- 21 -
Therefore, the NRC Staff considered a radius value of 28 nautical miles to be conservative.108
The Board also raised concerns regarding PSEG’s evaluation of the maximum surge and seiche
flooding using the SLOSH and ADCIRC+SWAN models.109 The NRC Staff explained that, in
one instance, PSEG had misapplied the SLOSH model in a context outside of its range of
applicability.110 After re-performing the analysis using the ADCIRC+SWAN model, the NRC
Staff relied on those figures in making its safety findings.111 Based on the NRC Staff’s
responses (together with the Board’s own analysis of information in the SER), the Board’s
concerns regarding maximum surge and seiche flooding were resolved.
6. The Board raised concerns regarding several aspects of the NRC Staff’s tsunami
evaluation.112 For example, the Board directed the Staff to support the conservatism of the
probable maximum tsunami by considering historical information regarding a landslide in the
Grand Banks resulting in a large tsunami along the coast of Newfoundland.113 The NRC Staff
replied that events similar to those in the Newfoundland example could occur; however, the
landslide used for the safety evaluation was larger than that in Newfoundland and resulted in a
tsunami of essentially the same height.114 Moreover, the modeled event would not pose a
hazard to the PSEG site because the height of the tsunami would be substantially reduced as it
traveled up the Delaware Bay—unlike conditions along the coast of Newfoundland.115
108 Id.
109 December 15, 2015 Questions Order, Attach. A, ¶ 22.
110 NRC Staff Response to First Set of Board Questions, Attach. A, at 13.
111 Id.
112 December 15, 2015 Questions Order, Attach. A, ¶¶ 26-33, 41.
113 Id. ¶ 27.
114 See NRC Staff Response to First Set of Board Questions, Attach. A, at 16.
115 See id.
- 22 -
The Board also directed the NRC Staff to consider an “earthquake located along a
northeast trending seismic zone off the eastern coast of the United States” as a tsunami
source.116 The Staff explained that, because of the small motion in the vertical direction, such a
source could not result in a large tsunami.117 The Board further inquired as to whether the
detailed geologic mapping to be performed in response to Permit Condition Number 3 would be
used for further identification of paleotsunami deposits.118 The NRC Staff replied that, due to
the location and depth of future geologic mapping, if such deposits are present “these deposits
would represent paleo-geologic and paleo-hydrologic conditions from so long ago they would
not be informative relative to the characteristics of potential future tsunamis at the PSEG site.”119
Lastly, the Board requested further information regarding inclusive boring logs;120 more recent
models for landslide-sourced tsunami waves along the east coast of the United States;121 the
conservatisms of the tsunami evaluation;122 and the large attenuation of tsunami wave height
within bays.123 In each instance, the NRC Staff responded by providing recent publications and
studies regarding these issues.124 Based on the NRC Staff’s responses and identification of
additional publications and studies, the Board’s concerns regarding tsunami issues were
resolved.
116 December 15, 2015 Questions Order, Attach. A, ¶ 28.
117 NRC Staff Response to First Set of Board Questions, Attach. A, at 17.
118 December 15, 2015 Questions Order, Attach. A, ¶ 41.
119 NRC Staff Response to First Set of Board Questions, Attach. A, at 25.
120 December 15, 2015 Questions Order, Attach. A, ¶ 29.
121 Id. ¶ 31.
122 Id. ¶ 32.
123 Id. ¶ 33.
124 See NRC Staff Response to First Set of Board Questions, Attach. A, at 19-20.
- 23 -
7. The Board also identified various concerns associated with geology and seismology
in the PSEG site area.125 For example, the Board identified a situation in which PSEG defined
the region surrounding the proposed site by applying regulatory guidance rather than a specific
regulation addressing seismic requirements.126 In response, both the NRC Staff and PSEG
described why compliance with the regulatory guidance was an acceptable approach to
satisfying analogous regulatory requirements.127 In another example, the Board required the
NRC Staff to identify those portions of the seismic evaluation that would eventually become
design basis information should a COL or CP application be submitted.128 The NRC Staff
responded that, for a plant that does not have a design certification, the ground motion
response spectrum (GMRS) developed for the ESP would be used to develop the safe
shutdown earthquake spectra.129 By contrast, for a certified unit, the certified seismic design
response spectra (CSDRS) would be compared to the GMRS and either the CSDRS or a
modified form of it would be a part of the design basis.130 Lastly, the Board sought clarification
regarding the methods used to identify liquefaction features in the marshland around the PSEG
site.131 The NRC Staff responded that PSEG had performed aerial and field reconnaissance in
areas other than the tidal marsh area and identified no evidence of Quaternary seismic
125 December 15, 2015 Questions Order, Attach. A, ¶¶ 37-40.
126 Id. ¶ 37.
127 See NRC Staff Response to First Set of Board Questions, Attach. A, at 21-22; PSEG Response to First Set of Board Questions, Attach. A, at 18.
128 December 15, 2015 Questions Order, Attach. A, ¶ 38.
129 NRC Staff Response to First Set of Board Questions, Attach. A, at 22-23.
130 Id.
131 December 15, 2015 Questions Order, Attach. A, ¶ 40.
- 24 -
deformation.132 Because the NRC Staff found PSEG’s evaluation of surface tectonic
deformation adequate, the Staff did not find it necessary for PSEG to conduct any additional
tests in the tidal marsh area.133 Based in part on these responses, the Board was satisfied that
the geology and seismology of the PSEG site were adequately reviewed.
8. The Board questioned whether the risks from aircraft hazards should be considered
on an airport-by-airport basis or in the aggregate. 134 The NRC Staff responded that, for the
PSEG site, each nearby airport had been screened out for further consideration because each
posed a risk less than 10-7/yr of a crash at the site.135 However, even if the airports were
considered in the aggregate, the sum of risks for all airports in the area would be less than 10-
6/yr, which is the upper limit provided under NRC guidance.136 The NRC Staff’s response
resolved the Board’s concerns regarding this issue.
9. The Board questioned why the calculated radiation doses to the nearest resident
(due to normal operations) approached the allowable limit.137 The NRC Staff responded that it
conservatively disregarded the decay during radionuclide transport, which resulted in the
calculated dose being conservatively high.138 The NRC Staff’s response resolved the Board’s
concerns regarding this issue.
132 NRC Staff Response to First Set of Board Questions, Attach. A, at 24.
133 Id.
134 December 15, 2015 Questions Order, Attach. A, ¶ 45.
135 NRC Staff Response to First Set of Board Questions, Attach. A, at 26-27.
136 Id. at 27.
137 December 15, 2015 Questions Order, Attach. A, ¶ 50.
138 See NRC Staff Response to First Set of Board Questions, Attach. A, at 29.
- 25 -
10. To provide additional access road capacity to the site, PSEG proposes a three-lane,
elevated causeway through coastal wetlands.139 The Board therefore questioned whether the
parties had evaluated whether improvements to an existing access road might provide
additional capacity with fewer adverse environmental impacts.140 In response, PSEG and the
NRC Staff explained that, for operational and security reasons, two distinct traffic paths were
needed for existing operations and construction activities.141 Additionally, PSEG stated that
eight alternative routes were considered, including widening the existing access road.142
Because widening the access road would require wetland and floodplain fill, its adverse
environmental impacts were greater than the proposed causeway.143 On this basis, the Board
was satisfied that this issue had been adequately reviewed.
11. The most recent unemployment data evaluated in the FEIS were from 2011.144
Concerned that 2011 data might represent relatively depressed economic conditions, the Board
asked whether consideration was given to updating an FEIS table that relies on this
information.145 The NRC Staff stated that the most recent economic data available at the time
the FEIS was prepared were published by the Bureau of Labor Statistics in 2014, and
represented data from 2012—only a year after that referenced in the FEIS.146 The NRC Staff
139 Ex. NRC004A, at 2-18.
140 January 6, 2016 Questions Order, Attach. A, ¶ 6.
141 NRC Staff Response to Second Set of Board Questions, Attach. A, at 6; PSEG Response to Second Set of Board Questions, Attach. A, at 3.
142 PSEG Response to Second Set of Board Questions, Attach. A, at 3.
143 Id.
144 Ex. NRC004A, Tbl. 2-21, at 2-125.
145 January 6, 2016 Questions Order, Attach. A, ¶ 11.
146 NRC Staff Response to Second Set of Board Questions, Attach. A, at 8.
- 26 -
explained that it compared the 2011 and 2012 data and identified only marginal differences,
which did not affect the conclusions reached in the FEIS.147 The Staff also gave assurances
that, if a COL or construction permit application is later submitted, this issue will be reevaluated
when preparing a supplement to the FEIS.148 Therefore, the Board’s concerns in this area were
resolved.
12. Construction on the proposed site would occur mostly within areas dominated by
common reed (Phragmites australis), an invasive, non-native plant species.149 The Board
questioned whether construction activities in these areas could facilitate the spread of this
species to nearby wetlands, displacing more desirable plant species.150 PSEG explained that
many wetland impacts would occur within existing self-contained areas operated by the USACE
and PSEG, thereby eliminating any potential increase in the spread of this species, in part
because this species primarily depends on rhizome disruption and displacement for
expansion.151 PSEG stated that elevations within the route for the proposed causeway are
sufficient to counter invasion of this species through tidal flooding effects.152 Furthermore,
PSEG assured the Board that the spread of this species would be monitored during construction
and, if necessary, managed.153 On the basis of PSEG’s response, the Board was satisfied that
the spread of this species would not increase to any appreciable degree as a result of potential
construction activities.
147 Id. at 8.
148 Id. at 8-9.
149 Ex. NRC004A at 4-28.
150 January 6, 2016 Questions Order, Attach. A, ¶ 14.
151 PSEG Response to Second Set of Board Questions, Attach. A, at 7.
152 Id. at 8.
153 Id. at 8.
- 27 -
13. The Board had various other wetland resources concerns related to post-
construction recovery of these areas and the USACE’s role in permitting and identifying
mitigation requirements for activities impacting wetlands resources.154 Both the NRC Staff and
PSEG indicated that any construction activities in wetland areas would be subject to planning,
permitting, and mitigation requirements imposed by appropriate federal, state, and local
agencies, including the USACE and NJDEP.155 For example, PSEG will likely be subject to
mitigation requirements to address unavoidable impacts, and any failure to comply with permit
conditions could result in enforcement actions and/or suspension or revocation of any
permits.156 Furthermore, as noted by the NRC Staff, the NRC’s regulatory authority is limited to
NRC-regulated construction activities, thus limiting the NRC’s review to NEPA and verification of
the PSEG’s compliance with the requirements of other agencies.157 For these reasons, the
Board was satisfied that a regulatory framework exists to ensure that wetlands are restored to
pre-disturbance conditions or enhanced beyond existing conditions.158
14. The Board was concerned about elevated nighttime noise levels at two on-site
monitoring locations that were higher than daytime levels observed at the same locations.159
The NRC Staff responded that in one location higher noise levels were associated with an
154 January 6, 2016 Questions Order, Attach. A, ¶¶ 15, 17-19.
155 See NRC Staff Response to Second Set of Board Questions, Attach. A, at 10; PSEG Response to Second Set of Board Questions, Attach. A, at 8.
156 NRC Staff FEIS Responses, Attach. A, at 10-11.
157 See id. at 12.
158 See PSEG Response to Second Set of Board Questions, Attach. A, at 8 (“Any restoration of temporary fill areas will be monitored by regulatory agencies, including the USACE and the NJDEP. PSEG expects that permits issued by both agencies will have strict compliance and monitoring requirements for restoration of temporarily disturbed wetlands to assure they are restored to pre-disturbance conditions or enhanced beyond existing conditions.”).
159 January 6, 2016 Questions Order, Attach. A, ¶ 24.
- 28 -
employee shift change during pre-dawn hours.160 In the second location, the NRC Staff
concluded that any building or operation noise levels would dissipate to ambient levels within a
short distance.161 The NRC Staff’s response resolved the Board’s concern regarding this issue.
15. The Board was also concerned about an apparent inconsistency in dose rate
calculations regarding radiation exposure during the transport of new fuel.162 The NRC Staff
clarified that different computer codes, with different assumptions, were used to model doses for
two distinct groups: (1) populations and transportation workers, such as inspectors, during
routine operations; and (2) potentially maximally exposed individuals (e.g., persons stuck in
traffic) and to the population during routine transportation.163 The NRC Staff’s response
satisfied the Board’s concerns.
Third, after reviewing the parties’ responses to its initial questions, the Board
nonetheless determined that it still wished to receive more detailed and integrated sworn
prefiled testimony and exhibits concerning certain topics. Specifically, on January 27, 2016, the
Board requested prefiled written testimony and exhibits concerning six matters pertaining to the
SER,164 which are set forth in section IV infra. Thereafter, on February 8, 2016, the Board
requested prefiled written testimony and exhibits concerning eight matters pertaining to the
FEIS,165 which are set forth in section IV infra.
Again, we directed the parties to provide written testimony under oath, so that the Board
could accord sworn prefiled testimony as much weight as we would give sworn testimony
160 NRC Staff Response to Second Set of Board Questions, Attach. A, at 15.
161 Id.
162 January 6, 2016 Questions Order, Attach. A, ¶ 28.
163 NRC Staff Response to Second Set of Board Questions, Attach. A, at 17.
164 SER Prefiled Testimony Order at 2-3.
165 FEIS Prefiled Testimony Order at 2-3.
- 29 -
presented in person at the evidentiary hearing, without having to engage in the formality of
asking witnesses at the hearing to “adopt” their prior written testimony.166 In accordance with
the Board’s suggestion that the parties coordinate their testimony as to avoid repetition,167
PSEG did not submit prefiled testimony on every topic. Collectively, however, PSEG and the
NRC Staff submitted approximately two hundred pages of prefiled written testimony from
twenty-two witnesses, as well as associated exhibits.168
166 SER Prefiled Testimony Order at 3; FEIS Prefiled Testimony Order at 4.
167 See SER Prefiled Testimony Order at 3; FEIS Prefiled Testimony Order at 4.
168 Ex. PSEG001, Testimony of James Mallon and David Robillard on SER Topic 1 [hereinafter PSEG SER Topic 1 Testimony]; Ex. PSEG007, Testimony of James Mallon and David Robillard on SER Topic 2 [hereinafter PSEG SER Topic 2 Testimony]; Ex. PSEG011, Testimony of James Mallon on SER Topic 3 [hereinafter PSEG SER Topic 3 Testimony]; Ex. PSEG012, Testimony of James Mallon on SER Topic 6 [hereinafter PSEG SER Topic 6 Testimony]; Ex. PSEG013, Testimony of James Mallon on FEIS Topic 3 [hereinafter PSEG FEIS Topic 3 Testimony]; Ex. PSEG016, Testimony of James Mallon on FEIS Topic 6 [hereinafter PSEG FEIS Topic 6 Testimony]; Ex. NRC001-R, Testimony of Prosanta Chowdhury, Allen Fetter, and Bruce J. Musico on SER Topic 1 [hereinafter NRC SER Topic 1 Testimony]; Ex. NRC006-R, Testimony of Prosanta Chowdhury, Seshagiri Tammara, Gerry Lewis Stirewalt, Frankie G. Vega, and Bruce J. Musico on SER Topic 2 [hereinafter NRC SER Topic 2 Testimony]; Ex. NRC008-R, Testimony of Joseph F. Giacinto and Henry Jones on SER Topic 3 [hereinafter NRC SER Topic 3 Testimony]; Ex. NRC009, Testimony of Kevin R. Quinlan and Henry Jones on SER Topic 4 [hereinafter NRC SER Topic 4 Testimony]; Ex. NRC010-R, Testimony of Prosanta Chowdhury, Joseph F. Giacinto, Henry Jones, Dogan Seber, Stephanie Devlin-Gill, Donald Palmrose, and Bruce J. Musico on SER Topic 5 [hereinafter NRC SER Topic 5 Testimony]; Ex. NRC011, Testimony of Kevin R. Quinlan and Stephen E. Williams on SER Topic 6 [hereinafter NRC SER Topic 6 Testimony]; Ex. NRC012, Testimony of Michael Willingham and Neil Giffen on FEIS Topic 1 [hereinafter NRC FEIS Topic 1 Testimony]; Ex. NRC013, Testimony of Michael Willingham and Neil Giffen on FEIS Topic 2 [hereinafter NRC FEIS Topic 2 Testimony]; Ex. NRC014, Testimony of Philip Meyer and Mohammad Haque on FEIS Topic 3 [hereinafter NRC FEIS Topic 3 Testimony]; Ex. NRC015, Testimony of Michael Willingham and Neil Giffen on FEIS Topic 4 [hereinafter NRC FEIS Topic 4 Testimony]; Ex. NRC017, Testimony of Michael Willingham and Neil Giffen on FEIS Topic 5 [hereinafter NRC FEIS Topic 5 Testimony]; Ex. NRC018, Testimony of Allen Fetter, Jack Cushing, Jennifer Davis, and Andrew Kugler on FEIS Topic 6 [hereinafter NRC FEIS Topic 6 Testimony]; Ex. NRC019, Testimony of Allen Fetter, Jack Cushing, Jennifer Davis, and Andrew Kugler on FEIS Topic 7 [hereinafter NRC FEIS Topic 7 Testimony].
- 30 -
Fourth, at a one-day evidentiary hearing, the Board members had the opportunity to
question in person specific witnesses who submitted prefiled written testimony.169 All prefiled
testimony and exhibits were admitted into evidence without objection.170
In other words, the Board’s process was a continuing one, which allowed consideration
of various kinds of information at various times. The sworn oral testimony at the evidentiary
hearing constituted only a portion of the sworn testimony available to the Board—which included
both prefiled testimony and responses under oath to the Board’s initial written questions—and
addressed only a portion of all the information (including the application itself) that we began to
examine as soon as the Board was constituted. Also, absent objection in an uncontested case
such as this, the Board saw no reason to exclude opinion testimony or other evidence that might
be objectionable in a jury trial in a court of law.171 Rather, in addressing the issues before it, the
169 Mindful of the policies underlying Rule 615 of the Federal Rules of Evidence, the Board considered whether to exclude witnesses from the hearing room during the testimony of other witnesses testifying on the same issues, but ultimately determined that would not be necessary in this particular case. Rule 615 provides (subject to limited exceptions) that at the request of any party a court “must” order witnesses excluded so that they cannot hear other witnesses’ testimony. Fed. R. Evid. 615. Alternatively, Rule 615 provides, “the court may do so on its own.” Id. In contrast to the practice followed by many licensing boards, courts therefore routinely exclude witnesses prior to their testimony. They do so, as the Supreme Court has recognized, not only to discourage or expose outright fabrication, but also to exercise a restraint on the natural tendency of witnesses to “tailor” their testimony to that of earlier witnesses. Geders v. United States, 425 U.S. 80, 87 (1976); see also GE-Hitachi Global Laser Enrichment LLC (GLE Commercial Facility), LBP-12-21, 76 NRC 218, 249-50 (2012). 170 Tr. at 70-72.
171 NRC regulations provide that “strict rules of evidence do not apply to written submissions,” 10 C.F.R. § 2.319(d), and rarely is it productive for licensing boards to devote time and resources to trying to separate “inadmissible” evidence from the merely unpersuasive. The bedrock principle underlying much of the law of evidence is set forth in Fed. R. Evid. 403: “The court may exclude relevant evidence if its probative value is substantially outweighed by a danger of one or more of the following: unfair prejudice, confusing the issues, misleading the jury, undue delay, wasting time, or needlessly presenting cumulative evidence.” In NRC licensing cases, however, excluding evidence will seldom achieve these objectives. Written prefiled testimony and exhibits are typically submitted well in advance of the evidentiary hearing, and, in our most common types of hearings, the licensing boards themselves—not the parties—orally examine the witnesses. 10 C.F.R. § 2.1207. Therefore, rulings excluding evidence have, as a practical matter, little effect in eliminating delay, waste of time, or the needless presentation of cumulative evidence in the record. If a licensing board deems prefiled evidence to be of little
- 31 -
Board considered all available facts—recognizing that some sources of information may be
more reliable than others.172
IV. SUMMARY OF TESTIMONY
A. SER Topic 1
SER Topic 1 stated:
Pursuant to 10 C.F.R. § 52.24(a), in order to authorize issuance of an ESP the Licensing Board must make the following safety findings:
(1) An application for an early site permit meets the applicable standards and requirements of the [AEA] and the Commission’s regulations;
(2) Notifications, if any, to other agencies or bodies have been duly made;
(3) There is reasonable assurance that the site is in conformity with the provisions of the Act, and the Commission’s regulations;
(4) The applicant is technically qualified to engage in any activities authorized;
(5) The proposed inspections, tests, analyses and acceptance criteria, including any on emergency planning, are necessary and sufficient, within the scope of the early site permit, to provide reasonable assurance that the facility has been constructed and will be operated in conformity with the license, the provisions of the Act, and the Commission’s regulations; [and]
(6) Issuance of the permit will not be inimical to the common defense and security or to the health and safety of the public . . . .
or no value, it simply need not ask about it at the evidentiary hearing, and is free to accord such evidence little or no weight. Likewise, because the members of the licensing boards themselves must read challenged testimony to determine whether its probative value is substantially outweighed by the danger of unfair prejudice or confusion of the issues, excluding evidence on this ground also seems to have little practical effect. See GLE Commercial Facility, LBP-12-21, 76 NRC at 248 n.171. 172 The Board also received written limited appearance statements from interested members of the public. In accordance with 10 C.F.R. § 2.315(a), however, such statements were not considered as evidence.
- 32 -
Staff shall briefly summarize those portions of its review that support each of these findings.173
Five witnesses testified on SER Topic 1:
1. PSEG Witnesses
James Mallon. Mr. Mallon is the Nuclear Development Manager for the Nuclear
Development Department at PSEG.174 He has a B.A. in physics from Franklin and Marshall
College and has completed graduate business courses toward an M.B.A. at the University of
Southern Maine.175 He also holds a Senior Reactor Operator certification.176
Mr. Mallon has 34 years of experience in the nuclear industry.177 At PSEG, he was the
Early Site Permit Manager during the initial phases of the proposed project.178 In 2011, he
became the Manager of Nuclear Development, in which capacity he oversees both the ESP
project and other activities related to small modular reactors and advanced nuclear
technology.179
In his written testimony on SER Topic 1, Mr. Mallon testified as follows:
173 December 15, 2015 Questions Order, Attach. A, at 1. SER Topic 1 originated as SER Question No. 1 in the Board’s Order of December 15, 2015. As allowed by the Board, the NRC Staff elected to defer its response until it submitted prefiled written testimony. Although SER Question No. 1 was specifically addressed to the NRC Staff, PSEG also responded, both in its answers to our December 15, 2015 Order and in its prefiled written testimony and exhibits. PSEG Response to First Set of Board Questions, Attach. A, at 1-5; PSEG SER Topic 1 Testimony.
174 PSEG SER Topic 1 Testimony at 1.
175 Id.
176 Id.
177 Id.
178 Id. at 2.
179 Id.
- 33 -
Although SER Topic 1 was primarily addressed to the NRC Staff, PSEG has also
considered the findings that must be made to issue the ESP.180 PSEG concludes that its
application, the NRC’s review, and the NRC’s documentation all support making these
findings.181
PSEG has not yet selected a particular reactor design to be constructed at the site.182
However, to provide sufficient information to enable the NRC to determine whether the site is
suitable for a new plant, PSEG’s application sets forth a surrogate design with a set of bounding
parameters.183
PSEG’s application contains the information required by 10 C.F.R. § 52.17.184 The
structure and content of the application are based on relevant NRC guidance, including
NUREG-0800, Standard Review Plan for the Review of Safety Analysis Reports for Nuclear
Power Plants: LWR Edition; RS-002, Processing Applications for Early Site Permits; NRC
Regulatory Guide 1.70, Standard Format and Content of Safety Analysis Reports for Nuclear
Power Plants; NRC Regulatory Guide 1.206, Combined License Applications for Nuclear Power
Plants (LWR Edition); and NUREG-1555, Standard Review Plans for Environmental Reviews for
Nuclear Power Plants.185
The NRC Staff appropriately reviewed PSEG’s application, concluded all applicable
standards for issuance of the ESP had been met, and determined that an ESP should be
180 Id. at 4.
181 Id.
182 Id. at 5.
183 Id.
184 Id. at 6.
185 Id.
- 34 -
issued.186 The NRC’s independent ACRS reviewed both PSEG’s application and the Staff’s
analysis, determined that “[t]he staff has done a thorough review of the early site permit
application,” and likewise concluded that the early site permit should be issued.187
The Board did not require oral testimony from Mr. Mallon on SER Topic 1.
David Robillard. Mr. Robillard is the Licensing Lead and Quality Assurance Specialist
for the ESP project.188 In this role, he has been responsible for the quality and accuracy of all
submittals to the NRC.189 Mr. Robillard has both an A.S. degree in Nuclear Technology and a
B.S. degree in Business Administration from Excelsior College.190 He has 46 years of
experience working on a variety of nuclear activities.191
Mr. Robillard’s written testimony on SER Topic 1 was substantively identical to portions
of the written testimony of Mr. Mallon. In his oral testimony on SER Topic 1, Mr. Robillard
testified as follows:
PSEG considered all of the applicable safety and environmental standards in the NRC
regulations by reviewing the NRC’s standard review plans.192 PSEG considered the NRC
Staff’s environmental and safety reviews to be thorough given that the NRC Staff conducted a
number of site audits, reached out to local members of the surrounding community, conducted
186 Id. at 8
187 Id. (quoting Ex. NRC003, App. E, at E-2).
188 Id. at 2.
189 Id.
190 Id.
191 Id.
192 Tr. at 104-05.
- 35 -
an independent need-for-power analysis, and made several requests for additional information
regarding PSEG’s safety and environmental analyses.193
2. NRC Staff Witnesses
Prosanta Chowdhury. Mr. Chowdhury is a Project Manager in the NRC’s Division of
New Reactor Licensing.194 He has an M.S. in Nuclear Engineering from Louisiana State
University and an M.S. in Electrical Engineering from Moscow Power Engineering Institute.195
Mr. Chowdhury has about eight years of experience as a project manager at the NRC.196 He
coordinated all aspects of the NRC staff’s review of PSEG’s ESP application.197
In his written testimony on SER Topic 1, Mr. Chowdhury testified as follows:
The NRC Staff conducted the safety review of PSEG’s ESP application against the
applicable regulations in Title 10 of the Code of Federal Regulations, Parts 20, 50, 52, 73, and
100.198 The Staff performed its safety review and evaluation using applicable portions of the
Standard Review Plan (NUREG-0800), Interim Staff Guidance documents, Regulatory Guides,
bulletins, generic letters, and other applicable NUREGs.199 On the basis of its evaluation and its
193 Tr. at 106-07.
194 NRC SER Topic 1 Testimony at 1.
195 Ex. NRC002, Statements of Professional Qualifications for NRC Staff Witnesses, at 1 [hereinafter NRC Staff Statements of Professional Qualifications].
196 Id.
197 Id.
198 NRC SER Topic 1 Testimony at 2.
199 Id.
- 36 -
independent analyses as discussed in the SER,200 the NRC Staff concluded that PSEG’s ESP
application satisfies all applicable statutory and regulatory standards and requirements.201
No notifications to other agencies or bodies were required within the scope of the ESP
safety review.202 As described by other NRC Staff witnesses, the NRC did publish the required
availability, docketing, and hearing notices for the ESP application.203
When necessary after reviewing the application, the NRC Staff issued requests for
additional information, conducted audits of PSEG’s records, and performed its own confirmatory
calculations.204 The Staff also proposed certain permit conditions.205 On this basis, the Staff
was able to find reasonable assurance that the proposed PSEG site is in conformity with the
provisions of the Atomic Energy Act and NRC regulations.206
Because PSEG did not request a limited work authorization, no technical qualifications
to undertake construction activities had to be demonstrated at the ESP stage; rather, PSEG’s
technical qualifications to engage in NRC authorized activities would be evaluated at later
stages of the licensing process.207 PSEG has extensive experience as a nuclear plant owner
and operator, including the existing facilities on Artificial Island, and is technically qualified to
receive an ESP.208
200 See generally Ex. NRC003.
201 NRC SER Topic 1 Testimony at 2.
202 Id.
203 Id.
204 Id. at 3-4.
205 Id. at 4.
206 Id.
207 Id.
208 Id.
- 37 -
In the case of an ESP application that does not seek a limited work authorization, the
only inspections, tests, analyses, and acceptance criteria (ITAAC) are those that pertain to
emergency planning.209 PSEG submitted a complete and integrated emergency plan and
associated ITAAC,210 which the Staff found necessary and sufficient to provide reasonable
assurance that the facility that references the ESP will be constructed and operated in
conformity with the license, the Atomic Energy Act, and NRC regulations.211
Based on its overall review of PSEG’s application, the NRC Staff concluded that PSEG
complied with all applicable regulatory requirements and that issuance of an ESP for the PSEG
site will not be inimical to public health and safety or the common defense and security.212
In his oral testimony on SER Topic 1, Mr. Chowdhury testified as follows:
PSEG did not select a specific reactor design and instead utilized a PPE.213 If PSEG
selected a design outside these parameters at the COL stage, its application would be a
deviation from the ESP.214 However, in such circumstances, PSEG could request a variance,
whereupon the NRC Staff would evaluate the significance of the differences between the ESP
and the requested COL.215
209 Id.
210 See Ex. PSEG004AC, PSEG Site ESP Application, Part 5 Emergency Plan, Rev. 4 (Apr. 15, 2015).
211 NRC SER Topic 1 Testimony at 4-5.
212 Id. at 5.
213 Tr. at 93.
214 Id.
215 Tr. at 94.
- 38 -
The NRC Staff followed the NRC Standard Review Plan, NUREG-0800, to ensure that
PSEG met all the applicable regulatory requirements and standards.216 PSEG’s compliance
with these regulatory requirements allowed the NRC Staff to conclude that issuance of the ESP
would not be inimical to the common defense, as defined by the Atomic Energy Act.217
Allen Fetter. Dr. Fetter is a Senior Project Manager in the Environmental Projects
Branch of the NRC’s Division of New Reactor Licensing.218 He has a Ph.D. in Geology from the
University of Kansas, an M.S. in Geology from the University of North Carolina, and a B.A. in
Geology from Guilford College.219 Dr. Fetter has about seven years of experience as a project
manager at the NRC.220 He planned and coordinated most aspects of the NRC Staff’s
environmental review of PSEG’s ESP application.221
In his written testimony on SER Topic 1, Dr. Fetter testified that adequate
announcement, notification and distribution of the FEIS had occurred.222 In his oral testimony
on SER Topic 1, Dr. Fetter testified that the NRC Staff was able to ensure that all of the required
notifications were made to members of the public and other federal, state, and local regulatory
bodies through federal register notices, site audits, press releases regarding public meetings,
and meetings with local agencies.223
216 Tr. at 95, 98.
217 Tr. at 99-100.
218 NRC Staff Statements of Professional Qualifications at 3.
219 Id.
220 Id.
221 Id.
222 NRC SER Topic 1 Testimony at 3, 5-6.
223 Tr. at 96-97.
- 39 -
Bruce J. Musico. Mr. Musico is a Senior Emergency Preparedness Specialist in the New
Reactor Licensing Branch within the NRC’s Office of Nuclear Security and Incident
Response.224 He has a J.D. from Franklin Pierce Law Center and a B.S. in Nuclear Engineering
from the University of Michigan.225 He has over 30 years of experience in commercial nuclear
power and related industries, including approximately 25 years relating to nuclear reactor
emergency planning.226
Mr. Musico’s written testimony on SER Topic 1 was substantively identical to portions of
the written testimony of Mr. Chowdhury. The Board did not require oral testimony from Mr.
Musico on SER Topic 1.
B. SER Topic 2
SER Topic 2 stated:
The Staff’s response to SER Question No. 9 acknowledges that each of the nine permit conditions the Staff proposes in the SER (at pp. A-2 through A-6) must be “precisely drawn so that the verification of compliance becomes a largely ministerial . . . act.” Yet some of the proposed permit conditions arguably include subjective requirements, such as the direction that a future applicant must examine and adequately “evaluate” geologic features (No. 3) and develop emergency action plans that contain “few or no deviations or differences” from NRC-endorsed standards (No. 9). The Staff shall address in detail how verification of compliance with each proposed permit condition can be accomplished by “largely ministerial” action and, if and where appropriate, propose alternative language that might set forth a more objective standard.227
Seven witnesses testified on SER Topic 2:
224 NRC SER Topic 1 Testimony at 1.
225 NRC Staff Statements of Professional Qualifications at 5. 226 Id.
227 SER Prefiled Testimony Order at 2.
- 40 -
1. PSEG Witnesses
James Mallon. Mr. Mallon’s background and qualifications have been previously
summarized in relation to his testimony on SER Topic 1. In his written testimony on SER Topic
2, Mr. Mallon testified as follows:
The Commission has ruled that, when the NRC imposes license conditions, the
conditions must be precisely drawn so that verification becomes largely ministerial.228
Verification should not require overly complex judgments or be subject to meaningful debate.229
At the same time, the Commission has clarified, “[t]his is not to say that the Staff is
allowed no room to exercise professional judgment in conducting post-licensing verification
activities.”230 Verification of compliance need only be a “largely” ministerial act and possible
without having to make “overly” complex judgments.231
All nine proposed permit conditions meet this standard.232 Moreover, seven of the nine
proposed permit conditions are nearly identical to those that have been approved by the
Commission in other proceedings.233
The Board did not require oral testimony from Mr. Mallon on SER Topic 2.
David Robillard. Mr. Robillard’s background and qualifications have been previously
summarized in relation to his testimony on SER Topic 1.
228 PSEG SER Topic 2 Testimony at 6.
229 Id.
230 Id. at 5 (quoting Private Fuel Storage, L.L.C. (Indep. Spent Fuel Storage Installation), CLI-00-13, 52 NRC 23, 34 (2000)).
231 Id.
232 Id. at 3-4.
233 See id. at 9-21.
- 41 -
Mr. Robillard’s written testimony on SER Topic 2 was substantively identical to the
written testimony of Mr. Mallon. In his oral testimony on SER Topic 2, Mr. Robillard testified as
follows:
PSEG did not find analogous Commission decisions approving permit conditions similar
to PSEG Permit Conditions 1 and Permit Condition 2 because those conditions are very site
specific.234 For example, Permit Condition 1 requires PSEG to obtain a land exchange with the
USACE for approximately 85 acres north of the existing Hope Creek reactor site.235 By contrast,
other past ESP applicants had larger sites and already had control over their exclusionary
boundary.236 Thus, these past applications did not need a land exchange.237
2. NRC Staff Witnesses
Prosanta Chowdhury. Mr. Chowdhury’s background and qualifications have been
previously summarized in relation to his testimony on SER Topic 1.
In his written testimony on SER Topic 2, Mr. Chowdhury testified as follows:
The NRC Staff included sufficiently prescriptive detail in its proposed permit conditions to
ensure that its post-permitting compliance review will not require complex factual or legal
judgments going beyond ministerial verification that the required actions have been
completed.238 For example, the Staff used widely-accepted industry standards and terminology,
the interpretation of which would not be subject to reasonable dispute; incorporated as
requirements prescriptive methodologies and standards from particular guidance documents;
234 Tr. at 110.
235 Tr. at 109.
236 Id.
237 Id.
238 NRC SER Topic 2 Testimony at 2.
- 42 -
and established prescriptive compliance steps to the extent those steps were not already
incorporated from other sources referenced in the conditions.239
The Board did not require oral testimony from Mr. Chowdhury on SER Topic 2.
Seshagiri Tammara. Mr. Tammara is a Physical Scientist in the Radiation Protection
and Accident Branch of the NRC’s Division of Site Safety and Environmental Analysis.240 He
has an M.S. in Chemical Engineering from Osmania University, an M.S. in Chemical
Engineering and Nuclear Engineering from the University of Maryland, and an M.S. in
Environmental Engineering from the University of Maryland.241 He has over 40 years of
experience as a technical analyst and physical scientist.242
In his written testimony on SER Topic 2, Mr. Tammara addressed the process the NRC
Staff anticipates it will use to verify compliance with Permit Conditions 1 and 2.243 In his oral
testimony on SER Topic 2, Mr. Tammara testified as follows:
Permit Condition 2 requires PSEG to perform certain calculations to ensure that the
overpressure due to an explosion at a relocated gasoline storage tank will not exceed 1 psi.244
PSEG complies with this permit condition by performing the requisite calculations, as prescribed
in Regulatory Guide 1.19 and 1.78.245 Whether PSEG performed these calculations correctly
would be addressed in the NRC’s review of any COL application.246
239 Id.
240 Id. at 1
241 NRC Staff Statements of Professional Qualifications at 7.
242 Id.
243 NRC SER Topic 2 Testimony at 3-5.
244 See Tr. at 111-12; see also Ex. NRC003, App. A, at A-3.
245 Tr. at 113-114.
246 Tr. at 114.
- 43 -
Gerry Lewis Stirewalt. Dr. Stirewalt is a Senior Geologist in the Geoscience and
Geotechnical Engineering Branch of the NRC’s Division of Site Safety and Environmental
Analysis.247 He has a Ph.D. in Structural Geology from the University of North Carolina and a
B.A. in Geology and Mathematics from Catawba College.248 Dr. Stirewalt has more than 43
years of national and international experience in geoscience, including both practical experience
and university teaching.249
In his written testimony on SER Topic 2, Dr. Stirewalt addressed the process the NRC
Staff anticipates it will use to verify compliance with Permit Condition 3.250 In his oral testimony
on SER Topic 2, Dr. Stirewalt testified as follows:
Permit Condition 3 requires PSEG to perform detailed geologic mapping of its planned
excavation for safety-related structures.251 Although Dr. Stirewalt’s written testimony referenced
Regulatory Guide 1.132, Regulatory Guide 1.208 provides greater detail as to how the
excavations should be mapped.252 The NRC Staff did not explicitly reference these Regulatory
Guides in the permit condition in the event that the guidance documents change at a future
date.253
In addition, if PSEG were to find some kind of tectonic structure in the Vincentown
formation in conducting its excavations, such a discovery would trigger a more extensive NRC
247 NRC SER Topic 2 Testimony at 1.
248 NRC Staff Statements of Professional Qualifications at 8.
249 Id.
250 NRC SER Topic 2 Testimony, at 5-7.
251 See Tr. at 116-17; see also NRC003, App. A, at A-3.
252 Tr. at 116-17.
253 Tr. at 117-18.
- 44 -
Staff reevaluation of the PSEG site’s geologic structure.254 However, any review of PSEG’s
excavations would be undertaken as part of the NRC Staff’s construction inspections rather than
through satisfaction of Permit Condition 3.255 This distinction is to ensure that the requirements
of Permit Conditions 3 remain ministerial.256 Accordingly, Permit Condition 3 would be satisfied
when PSEG notifies the NRC Staff that the excavations are ready for the NRC Staff’s
examination.257
Frankie G. Vega. Mr. Vega is a Project Manager in the Hazard Management Branch of
the Japan Lessons Learned Division within the NRC’s Office of Nuclear Reactor Regulation.258
He has an M.E. in Civil Engineering from the University of Maryland and a B.S. in Civil
Engineering from the University of Puerto Rico, and possesses nine years of experience as an
engineer and project manager.259
In his written testimony on SER Topic 2, Mr. Vega addressed the process the NRC Staff
anticipates it will use to verify compliance with Permit Condition 4.260 The Board did not require
oral testimony from Mr. Vega on SER Topic 2.
Bruce J. Musico. Mr. Musico’s background and qualifications have been previously
summarized in relation to his testimony on SER Topic 1.
254 Tr. at 121-22.
255 Tr. at 122.
256 Id.; see also Private Fuel Storage, CLI-00-13, 52 NRC at 34 (“[W]e must insist that the condition be precisely drawn so that the verification of compliance becomes a largely ministerial rather than an adjudicatory act.”).
257 Tr. at 122.
258 NRC SER Topic 2 Testimony at 1.
259 NRC Staff Statements of Professional Qualifications at 10.
260 NRC SER Topic 2 Testimony at 7-8.
- 45 -
In his written testimony on SER Topic 2, Mr. Musico addressed the process the NRC
Staff anticipates it will use to verify compliance with Permit Conditions 5-9.261 The Board did not
require oral testimony from Mr. Musico on SER Topic 2.
C. SER Topic 3
SER Topic 3 stated:
In response to SER Question No. 20 the Staff stated as follows: While the Staff recognizes that increasing the resolution of the overall watershed basin model could improve the precision of the Applicant’s river flooding model results, the Staff determined on the basis of experience with hydraulic modeling that such improvements could not change the conclusion that storm surge is the bounding flood hazard for the PSEG ESP site and additional analyses were not necessary.
To what extent is the “experience with hydraulic modeling” upon which this decision was based documented? If experience based knowledge is used in the Staff’s decision-making process generally, how is this experience documented?262
Three witnesses testified on SER Topic 3:
1. PSEG Witness
James Mallon. Mr. Mallon’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 1.
In his written testimony on SER Topic 3, Mr. Mallon testified as follows:
The SER correctly concluded that the probable maximum hurricane is the bounding
flood hazard for the PSEG site.263 The potential causes of flooding at the PSEG site include: (1)
the probable maximum flood (PMF) on rivers and streams, (2) dam failures, (3) a storm surge
261 Id. at 8-13.
262 SER Prefiled Testimony Order at 2.
263 PSEG SER Topic 3 Testimony at 2.
- 46 -
due to the probable maximum hurricane (PMH), (4) tsunamis, and (5) ice effects.264 Each is
summarized in the following chart:265
Because the PMH event resulted in the highest total water surface elevation (WSEL), it
represents PSEG’s design basis flood.266
Although increasing the resolution of the overall watershed basin model could affect the
primary flood causing mechanism for the PMF event, “increasing the resolution would not
necessarily increase the resulting WSEL, but could result in a decrease in water level.”267
Moreover, an increased resolution for the overall watershed basin model would only potentially
impact the primary flood-cause mechanism for the PMF event, and “[a]side from the PMH event,
the primary flood-causing mechanism associated with each flood hazard represents a small
portion of the associated WSEL.”268 Thus, even if the increased resolution did slightly increase
the resulting WSEL for the PMF event, there was such a significant margin between the total
264 Id. at 4. 265 Id. at 7. 266 Id. at 7-10. 267 Id. at 8. 268 Id. at 9.
- 47 -
WSEL for the PMF event (21 feet North American Vertical Datum (NAVD)) and the PMH event
(32.1 feet NAVD) that the PMH event would still serve as the design basis flood event.269
In his oral testimony on SER Topic 3, Mr. Mallon testified as follows:
Regulatory Guide 1.59 and American National Standards Institute Standard 2.8 set forth
standards for performing a PMH analysis.270 These standards require an applicant to conduct
its analysis to approximate the roughly one in a million flood risk.271 Both PSEG and the NRC
Staff determined that Run No. 2 in Table 2.4.5-4 of PSEG’s Site Safety Analysis Report, which
represents PSEG’s design basis flood of 32.1 feet NAVD,272 also represents the water level
expected in the requisite one in a million flood risk.273
2. NRC Staff Witnesses
Henry Jones. Dr. Jones is a Hydrologist in the Office of New Reactors, Division of Site
and Environmental Analysis, Hydrology and Meteorology Branch.274 He has a diploma in
Strategic Studies from the Naval War College, a B.S. in Oceanography from the United States
Naval Academy, an M.A. in International Relations from Salve Regina University, an M.S. in
Systems Management (Information Systems) from the University of Southern California, an
M.S. in Meteorology and Physical Oceanography from the Naval Postgraduate School, and a
Ph.D., in Physical Oceanography from the Naval Postgraduate School.275 Upon retiring from
269 Id. at 7, 9. 270 Tr. at 124.
271 Tr. at 125.
272 See PSEG SER Topic 3 Testimony at 6; Ex. PSEG004B, PSEG Site ESP Application Part 2, Site Safety Analysis Report, Tbl. 2.4.5-4, at 2.4-93.
273 Tr. at 125.
274 NRC Staff Statements of Professional Qualifications at 12. 275 Id.
- 48 -
the United States Navy in 2007, Dr. Jones joined the NRC, where he serves as the surge,
seiche and tsunami hazard technical reviewer for all COL and ESP applications.276
In his written testimony on SER Topic 3, Dr. Jones testified as follows:
The NRC Staff has experience with the river flood model used by PSEG to calculate the
probable maximum flood (PMF) event.277 The following chart provides a summary of the
component contributions to the maximum water level for the PMF event:278
Thus, as stated in PSEG’s written testimony, the total PMF maximum water level is 21 feet.279
The river flood model used by PSEG employs a one-dimensional numerical method that
results in river flood level estimates that are conservatively high.280 The model’s estimates are
conservative because it includes limited lateral dispersal of energy when, “[i]n reality, river
channels are rarely straight and flow energy disperses laterally traveling downstream which
would tend to reduce the water level height resulting from [one-dimensional] model
calculations.”281 Further, although the riverine flooding component is most likely conservatively
high based on the one-dimensional model calculations, it remains a small portion of the PMF
276 Id. at 12-13. 277 NRC SER Topic 3 Testimony at 1.
278 Id. at 3. 279 Id.; see also PSEG SER Topic 3 Testimony at 4. 280 Id. at 3. 281 Id.
- 49 -
maximum water level since it contributes only about 2.1 feet to the total maximum water level of
21 feet.282
As a general matter, the NRC Staff documents its experience based decision-making in
NRC Staff guidance. 283 However, the NRC Staff’s experience based knowledge as to the
relevant river model is documented in SER Section 2.4 as well as in the NRC Staff’s numerous
requests for additional information.284
The Board did not require oral testimony from Dr. Jones on SER Topic 3.
Joseph F. Giacinto. Mr. Giacinto is a Hydrologist in the NRC’s Office of New Reactors,
Division of Site and Environmental Analysis, Hydrology Branch.285 He received his B.S. in
Geology (Geophysics) from San Diego State University, and his M.S. in Hydrology from the
University of Arizona.286 Mr. Giacinto has eight years of experience working as a hydrologist at
the NRC.287 During his time at the NRC, Mr. Giacinto has provided technical support in the
areas of hydrology and geology for the NRC Staff’s review of multiple COL and ESP
applications.288
Mr. Giacinto’s written testimony on SER Topic 3 was substantively identical to Dr. Jones’
written testimony on this topic. In his oral testimony on SER Topic 3, Mr. Giacinto testified as
follows:
282 Id. 283 Id. 284 Id. at 4. 285 NRC Staff Statements of Professional Qualifications at 11. 286 Id. 287 Id.
288 Id.
- 50 -
The Delaware River Basin is very large at approximately 14,000 square miles.289 Due to
the basin’s size, the river basin model’s “coarse” resolution was still sufficient.290 A professional
who routinely evaluates these types of river basin models would recognize that the nodalization
was adequate.291
D. SER Topic 4
SER Topic 4 stated:
The [U.S. Global Change Research Program (USGCRP)] report cited in the FSER section 2.3.1.4.10 noted that the power and frequency of tropical storms has “increased substantially in recent decades,” and many reports, including the USGCRP report, have predicted that this trend will continue in the coming decades. Expanding on their discussion in section 2.3.1.4.10, Staff shall explain how they addressed the issue of climate change induced increases in the power and frequency of hurricanes. In particular, Staff will explain how the models used to establish the PMH at the PSEG ESP site accommodate predicted increases in the power and frequency of storms.292
Two NRC Staff witnesses testified on SER Topic 4:
Kevin R. Quinlan. Mr. Quinlan is a Physical Scientist (Meteorologist) in the NRC’s Office
of New Reactors, Division of Site and Environmental Analysis, Hydrology and Meteorology
Branch.293 Mr. Quinlan has a B.S. in Meteorology from Millersville University of Pennsylvania
and an M.S. in Atmospheric Science from the University of Alabama in Huntsville.294 He has
been employed with the Office of New Reactors since July 2008.295 His work primarily includes
289 Tr. at 128.
290 Tr. at 129-30.
291 Tr. at 131.
292 SER Prefiled Testimony Order at 2-3.
293 NRC SER Topic 4 Testimony at 1.
294 NRC Statements of Professional Qualifications at 14.
295 Id.
- 51 -
the analysis of regional and local climatology to determine the most severe weather that may
impact a potential reactor site or design.296
In his written testimony on SER Topic 4, Mr. Quinlan testified as follows:
The hurricane site characteristic wind speed at the PSEG site was reviewed pursuant to
NRC Regulatory Guide 1.221, which provides the design-basis hurricane wind speeds with an
exceedance frequency of 10-7 per year.297 This is a conservative exceedance frequency that
represents a hurricane wind speed that is expected to occur once every 10 million years.298
Regulatory Guide 1.221 derived Design-Basis Hurricane Wind Speed values from
NUREG/CR-7005, which uses a sensitivity analysis to assess the possible effects of increased
hurricane frequency in the future.299 NUREG/CR-7005 addresses a potential doubling in
hurricane frequency on the exceedance frequency of 10-7 per year.300 The sensitivity analysis
suggested that a factor of two increase in hurricane frequency would result in less than a two
percent increase in wind speed.301 A two percent increase in a wind speed of 159 mph (3-
second gust), which Regulatory Guide 1.221 indicates is applicable to the PSEG site, results in
a 3 mph increase to the site characteristic.302 The NRC Staff found this to be appropriately
conservative to account for potential climate change related increases in hurricane power and
frequency, particularly given that climate change increases are still uncertain.303 Moreover, if
296 Id.
297 NRC SER Topic 4 Testimony at 2.
298 Id.
299 Id.
300 Id.
301 Id.
302 Id. at 2-3.
303 Id. at 3.
- 52 -
long-term climatic change becomes an issue, a COL holder has a continuing obligation to
ensure that the plant stays within the licensing basis.304
In his oral testimony on SER Topic 4, Mr. Quinlan testified as follows:
To account for the variability associated with climate change, the NRC Staff analyzed
hurricane wind speeds based on a doubling of the frequency of hurricanes in the Atlantic and
Gulf Coasts.305 The result was a two percent increase in maximum hurricane wind speeds.306
At the ESP site this resulted in an approximately three mile per hour increase in wind speed.307
Prospectively, the NRC Staff would be obligated to update regulatory guidance to address
evolving site conditions associated with climate change and a license holder would be obligated
to ensure that their site remained safe to operate.308
Henry Jones. Dr. Jones’ background and qualifications were previously summarized
with regard to his testimony on SER Topic 3. In his written testimony on SER Topic 4, Dr.
Jones testified as follows:
The Probable Maximum Hurricane (PMH) models used to establish the PMH for the
PSEG site are conservative in view of climate change predications.309 The PMH includes
meteorological factors such as radius of maximum winds, central pressure, latitude, forward
speed, track direction, peripheral pressure, inflow angle, location of landfall, among others.310
304 Id. 305 Tr. at 135.
306 Id.
307 Id.
308 See Tr. at 144-45. Legal counsel for the NRC Staff stated at the hearing that regulations exist, including 10 C.F.R. § 50.54(f), to ensure that licensees maintain adequate protection as a condition of licensing. See Tr. at 145.
309 NRC SER Topic 4 Testimony at 1.
310 Id. at 3.
- 53 -
Hurricane intensity is influenced by all of these factors, but is mostly determined by the
oceanographic parameter of sea surface temperature.311 The PMH is used to calculate the
probable maximum storm surge (PMSS).312
Basic climate change theory indicates that atmospheric warming will lead to warmer sea
surface temperatures, which will fuel stronger storms.313 However, studies exist that show that
warming can lead to more El Nino events, which hinder hurricane development along the
northern Atlantic seaboard.314 Additional factors, including the divergence of the Gulfstream
offshore north of Cape Hatteras, result in hurricanes losing energy as they approach the mid-
Atlantic Coast, which includes the PSEG site location.315 This feature of the Gulfstream is likely
to be present irrespective of near-term climate change.316
Only three Category 3 storms have made landfall along the northern Atlantic seaboard
since 1869, with no storms stronger than Category 3.317 In the PMSS calculation, margin for
climate change was provided at the PSEG site by using a Category 4 PMH.318 Additional
conservatism was built into the analysis by assuming steady-state winds, no decay in intensity
prior to landfall, and no deviation in track speed or direction.319 More generally, the influence of
311 Id.
312 Id. at 3-4.
313 Id. at 4.
314 Id.
315 Id.
316 Id.
317 Id.
318 Id.
319 Id.
- 54 -
land and associated frontal systems results in the environment near the PSEG site not being
optimal for intense hurricanes.320
In his oral testimony on SER Topic 4, Dr. Jones testified as follows:
Sea level rise is the only factor that the NRC Staff requires to account for climate
change, because the analysis contains so many conservatisms that the climate change factor is
“swamp[ed]” after analyzing storm surge with a ten percent exceedance high tide.321 More
generally, if the intensity of a tropical storm increases, then central pressure lowers.322 This
results in an increased pressure gradient and higher wind velocities, which drive storm surge.323
At the ESP site, however, an approaching tropical storm would be confronted with the
ameliorating effect of traveling over colder water above Cape Hatteras and exposure to dry
continental air.324 The result would be a decrease in storm intensity and relatively lower storm
surge.325
E. SER Topic 5
SER Topic 5 stated:
In what ways has the PSEG ESP application and review differed from previous ESPs due to events at Fukushima and subsequent evaluations and recommendations?326
Seven NRC Staff witnesses testified on SER Topic 5:
320 Id. at 5.
321 Tr. at 134. Dr. Jones also stated that storm surge is subject to deterministic modeling; whereas, wind speed is subject to probabilistic modeling. Tr. at 133-34, 136.
322 Tr. at 137.
323 Id.
324 Tr. at 139-141.
325 See Tr. at 140-42.
326 SER Prefiled Testimony Order at 3.
- 55 -
Prosanta Chowdhury. Mr. Chowdhury’s background and qualifications have been
previously summarized with regard to his testimony on SER Topic 1.
In his written testimony on SER Topic 5, Mr. Chowdhury testified as follows:
Following the events at Fukushima resulting from the March 11, 2011 Great Tohoku
earthquake and tsunami in Japan, the NRC established the Fukushima Near-Term Task Force
(NTTF) to review NRC regulations and make recommendations.327 The NRC Staff then adopted
specific actions to address NTTF’s Recommendations as modified by input from the
Commission.328
As part of its review of PSEG’s ESP application, the NRC Staff considered whether the
following Tier 1 recommendations from the NTTF were applicable:
Recommendation 2.1: Seismic and Flood Hazard Reevaluations
Recommendation 2.3: Seismic and Flood Walkdowns
Recommendation 4.1: Station Blackout Regulatory Actions
Recommendation 4.2: Equipment Covered under 10 C.F.R. 50.54(hh)(2)
Recommendation 5.1: Reliable Hardened Vents for Mark I and Mark II Containments
Recommendation 7.1: Spent Fuel Pool Instrumentation
Recommendation 8: Strengthening and Integration of Emergency Operating Procedures, Severe Accidents Management Guidelines, and Extensive Damage Mitigation Guidelines
327 NRC SER Topic 5 Testimony at 2.
328 Id. at 2-3; see SECY-12-0025, Proposed Orders and Requests for Information in Response to Lessons Learned from Japan’s March 11, 2011, Great Tohoku Earthquake and Tsunami, (Feb. 17, 2012 ) (ADAMS Accession No. ML12039A103); SECY-11-0137, Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned (Oct. 3, 2011) (ADAMS Accession No. ML11269A204); SECY-11-0124, Recommended Actions to Be Taken Without Delay from the [NTTF] Report (Sept. 9, 2011) (ADAMS Accession No. ML11245A144); SECY-11-0093, Near-Term Report and Recommendations for Agency Actions Following the Events in Japan (July 12, 2011) (ADAMS Accession No. ML11186A950).
- 56 -
Recommendation 9.3: Emergency Preparedness Regulatory Actions (staffing and communications)329
The NRC Staff ultimately determined that only Recommendations 2.1 and 9.3 are applicable to
PSEG’s ESP application.330 The other recommendations are applicable to design certification
and COL applications.331 Although the NRC Staff applied these two NTTF Recommendations to
the PSEG review, the NRC Staff’s underlying review methodologies and guidance did not differ
from previous ESP application reviews.332
In his oral testimony on SER Topic 5, Mr. Chowdhury testified as follows:
The NRC Staff considered NTTF Recommendation 9.3 to be applicable because PSEG
submitted a complete and integrated emergency plan with its ESP application.333 This
integrated emergency plan is equivalent to what would be submitted with a COL application.334
However, because PSEG did not select a reactor technology, PSEG could not submit all the
required information for Recommendation 9.3.335 Accordingly, the NRC Staff identified two
permit conditions to ensure that the entirety of Recommendation 9.3 is addressed at the COL
stage.336
Dogan Seber. Dr. Seber is a senior Geophysicist in the Office of Nuclear Reactor’s
Division of Site Safety & Environmental Analysis, Geosciences and Geotechnical Engineering
329 NRC SER Topic 5 Testimony at 3. 330 Id. 331 Id. at 4. 332 Id. at 5-6. 333 Tr. at 151.
334 Id.
335 Id.
336 See id.
- 57 -
Branch.337 He has a B.S. in Geophysical Engineering from Istanbul Technical University, an
M.Sc. in Geophysics from St. Louis University, and a Ph.D. in Seismology from Cornell
University.338 Dr. Seber has 30 years of professional work experience in geophysics.339 As a
senior geophysicist at the NRC, Dr. Seber has worked on the re-assessment of seismic hazards
of the operating nuclear power plants following the NTTF Fukushima recommendations.340
In his written testimony on SER Topic 5, Dr. Seber testified that, with respect to
Recommendation 2.1, “[t]he Staff determined that [PSEG’s] use of the most recent seismic
source model, i.e., CEUS-SSC, for its site specific seismic hazard calculations fully and
adequately addressed the reevaluation of seismic hazards aspect of NTTF Recommendation
2.1.”341 The Board did not require oral testimony from Dr. Seber on SER Topic 5.
Stephanie Devlin-Gill. Dr. Devlin-Gill is a Project Scientist in the Office of New Reactor’s
Division of Site Safety & Environmental Analysis.342 She received her B.A. in Physics with a
Computer Science minor from Rutgers University, and her Ph.D. in Geophysics from Cornell
University.343 During her seven years at the NRC, Dr. Devlin-Gill has reviewed numerous
existing reactor site seismic hazard reevaluations associated with the NTTF seismic
337 NRC Staff Statements of Professional Qualifications at 15. 338 Id. 339 Id. 340 Id. 341 NRC SER Topic 5 Testimony at 4. 342 NRC Staff Statements of Professional Qualifications at 17. 343 Id.
- 58 -
Recommendation 2.1.344 In addition, Dr. Devlin-Gill was the lead geophysicist on the 2014
update of two sections of the Standard Review Plans.345
Dr. Devlin-Gill’s written testimony on SER Topic 5 was substantively similar to Dr.
Seber’s. The Board did not require oral testimony from Dr. Devlin-Gill on SER Topic 5.
Henry Jones. Dr. Jones’ background and qualifications have been previously
summarized with regard to his testimony on SER Topic 3.
In his written testimony on SER Topic 5, Dr. Jones testified as follows:
Another aspect of Recommendation 2.1 included a flooding hazard reevaluation and the
NRC Staff determined that PSEG’s use of Regulatory Guide 1.56 “fully and adequately
addressed” this aspect of Recommendation 2.1.346 The NRC Staff then concluded that there
were “no additional requirements left to be addressed in Recommendation 2.1 for flooding
reevaluations applicable to the PSEG Site ESP application review.”347 The Board did not
require oral testimony from Dr. Jones on SER Topic 5.
Joseph F. Giacinto. Mr. Giacinto’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 3. His written testimony on SER Topic 5
was substantively identical to Dr. Jones’ written testimony. The Board did not require oral
testimony from Mr. Giacinto on SER Topic 5.
Bruce J. Musico. Mr. Musico’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 1.
In his written testimony on SER Topic 5, Mr. Musico testified as follows:
344 Id. 345 Id. 346 NRC SER Topic 5 Testimony at 4. 347 Id.
- 59 -
Recommendation 9.3 “identifies the need for: (i) determining and implementing the
required staffing for responding to a multi-unit event, and (ii) providing means to power
communications equipment needed to communicate onsite and offsite during a prolonged
station blackout.”348 Because PSEG had not selected a reactor design, “detailed designs on
onsite and offsite communication systems and emergency staffing plan are not yet complete.”349
Consequently, the NRC Staff included Permit Conditions 5 and 6, which require PSEG to
address the communication and staffing aspects of Recommendation 9.3 at the COL stage.350
The Board did not require oral testimony from Mr. Musico on SER Topic 5.
Donald Palmrose. Dr. Palmrose is a Senior Reactor Engineer in the Office of New
Reactor’s Division of Site Safety and Environmental Analysis, Radiation Protection and Accident
Consequences Branch.351 He received his B.S. in Nuclear Engineering from Oregon State
University, his M.S. in Nuclear Engineering from Texas A&M University, and his Ph.D. in
Nuclear Engineering from Texas A&M University.352 He has over 30 years of experience in the
nuclear engineering profession.353 As a Senior Reactor Engineer for the NRC, Dr. Palmrose
performs and coordinates the environmental reviews for standard design certifications, COL,
and ESP applications in the areas of environmental radiological dose analyses, nuclear power
plant severe accident risks, and the evaluations of the transportation of radioactive materials.354
In his written testimony on SER Topic 5, Dr. Palmrose testified as follows:
348 Id. 349 Id. 350 Id. 351 NRC Staff Statements of Professional Qualifications at 19. 352 Id. 353 Id. 354 Id.
- 60 -
The NTTF Recommendations applicable to PSEG’s application were addressed in the
NRC Staff’s safety review.355 Therefore, although all previous ESPs were issued prior to the
events at Fukushima, the NRC Staff determined that the PSEG environmental review “did not
require application of different review methodologies, or guidance compared to those applied in
previous ESP application reviews.”356
The Board did not require oral testimony from Dr. Palmrose on SER Topic 5.
F. SER Topic 6
SER Topic 6 stated:
Explain, for the non-expert, how the Applicant calculated the long-term atmospheric dispersion for routine releases. What was the extent of Staff’s review? Details of the calculations of the GASPAR code are not required.357
Three witnesses testified on SER Topic 6:
1. PSEG Witness
James Mallon. Mr. Mallon’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 1.
In his written testimony on SER Topic 6, Mr. Mallon testified as follows concerning the
first portion of Topic 6, namely how PSEG calculated the long-term atmospheric dispersion for
routine releases:358
To confirm that a proposed nuclear power plant meets NRC’s regulatory standards for
radiation dose limits, applicants evaluate the short-term release of radionuclides following a
design basis accident and the long-term release of radionuclides as part of routine releases.359
355 NRC SER Topic 5 Testimony at 5. 356 Id. 357 SER Prefiled Testimony Order at 3.
358 PSEG SER Topic 6 Testimony at 3-6.
359 Id.
- 61 -
Because the radionuclides that may be in the gaseous effluents at a plant are dispersed by wind
after being released, applicants use atmospheric dispersion modeling to predict the extent of a
release.360
The concentration of radionuclides in the air is represented by the long-term diffusion
estimates expressed in χ/Q values.361 These values are determined at “receptors of interest,”
such as a nearby residence, and at locations where an individual may receive the maximum
allowable individual exposure outside of the plant site boundary.362 These points of maximum
individual exposure “are evaluated using a radial grid of sixteen 22½ degree sectors extending
to 50 miles (mi.) from the new plant.”363
PSEG estimated the applicable χ/Q values using NRC-sponsored XOQDOQ computer
program.364 This computer program incorporates assumptions outlined in Regulatory Guide
1.111, including that the effluents will travel in a straight-line trajectory from the release point to
all receptors.365 To calculate the χ/Q values, the primary inputs in the XOQDOQ computer
program are wind speed and wind direction.366 For its calculations, PSEG used wind speed and
wind direction inputs based on on-site meteorological data from January 1, 2006 through
December 31, 2008.367
360 See id. 361 Id. at 4. 362 Id. 363 Id. 364 Id. at 5. 365 Id. 366 Id. 367 Id.
- 62 -
The results of the XOQDOQ modeling are summarized in PSEG’s Site Safety Analysis
Report Table 2.3-24,368 and the complete set of χ/Q values for routine releases is provided in
Table 2.3-37.369 Ultimately, PSEG determined that the largest χ/Q values for the site boundary
is 1.6E-01 sec/m3 in the South direction.370 However, PSEG disregarded the limiting values for
sectors SE to NW (clockwise direction) because in those sectors the site boundary borders the
Delaware River.371 “Therefore, the only sectors that are used to obtain the limiting χ/Q value for
the site boundary are between the NNW and ESE directions (clockwise direction).”372
In his oral testimony on SER Topic 6, Mr. Mallon testified as follows:
Differential heating rates of land versus water affect wind direction.373 Thus the
XOQDOQ computer model accounts for the different heating rates by using a joint frequency
distribution of meteorological data.374 In addition, PSEG’s maximum χ/Q values for routine
releases adequately account for the range of half-lives of the nuclides in a release for purposes
of calculating long-term, chronic exposure.375 By contrast, “a short-lived code and accident-type
analysis where you might have short-lived noble gases or iodine-131 would be different.”376
368 Id.; see Ex. PSEG004B, Tbl. 2.3-34, at 2.3-96. 369 PSEG SER Topic 6 Testimony at 6; see Ex. PSEG004B, Tbl. 2.3-34, at 2.3-109. 370 PSEG SER Topic 6 Testimony at 6. 371 Id. at 6-7. 372 Id. at 7. 373 Tr. at 159.
374 Id.
375 Tr. at 161; see also PSEG SER Topic 6 Testimony at 6.
376 Tr. at 161.
- 63 -
2. NRC Staff Witnesses
Kevin R. Quinlan. Mr. Quinlan’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 4.
In his written testimony on SER Topic 6, Mr. Quinlan testified as follows:
Mr. Quinlan’s testimony as to how PSEG calculated the long term atmospheric
dispersion for routine releases was substantially similar to Mr. Mallon’s testimony.377 However,
Mr. Quinlan added that, because PSEG disregarded the limiting values for sector SE to NW
(clockwise direction), the NRC Staff included COL Action Item 2.3-1.378 This action item
requires an applicant at the COL stage to verify “receptors of interest” to ensure that the
applicant identifies any receptor changes in sector SE to NW (clockwise direction) and, if
necessary, to consider the χ/Q values for that previously disregarded sector.379
As to the extent of the NRC Staff’s review of the PSEG’s calculations, the NRC Staff
completed a quality assurance review of the three-year onsite meteorological data that PSEG
used as the basis for its primary inputs in the XOQDOQ computer model.380 The NRC Staff also
independently created its own inputs of wind speed, wind direction, and atmospheric stability
based on the same dataset.381 After running this confirmatory analysis, the NRC Staff obtained
results that were within approximately one percent of PSEG’s values.382 Thus, the NRC Staff
concluded that PSEG’s long-term atmospheric dispersion estimates were acceptable.383
377 See NRC SER Topic 6 Testimony at 2-3; see also PSEG SER Topic 6 Testimony at 3-6. 378 NRC SER Topic 6 Testimony at 3. 379 Id. 380 Id. at 4. 381 Id. 382 Id. 383 Id.
- 64 -
In his oral testimony on SER Topic 6, Mr. Quinlan testified as follows:
PSEG used a joint frequency distribution of wind speed, wind direction, and atmospheric
stability as an input to the XOQDOQ computer model.384 “A joint frequency distribution is a way
of summarizing multiple years of meteorological data.”385 PSEG’s data set for the joint
frequency distribution was for a three-year period.386 The NRC Staff conducted a rigorous
quality assurance review of PSEG’s data set to ensure that each year within the three-year
period was a reasonable representation of metrological conditions.387 Further, while certain
topographical features such as a nearby mountain range or large body of water could preclude
the use of the XOQDOQ model, the PSEG site has no such topographical features.388 More
specifically, although some bodies of water are near the PSEG site, these are not large enough
to preclude the use of the XOQDOQ model.389
Stephen E. Williams. Mr. Williams is a Health Physicist in the Office of New Reactors’
Division of Site and Environmental Analysis, Radiation Protection Accident Consequences
Branch.390 He received his B.S. in Radiological Health from Duquesne University and his M.S.
in Environmental Pollution Control from Penn State University.391 Mr. Williams has 40 years of
experience in various disciplines in Health Physics, including eight years of experience at the
384 See Tr. at 153; see also NRC SER Topic 6 Testimony at 3.
385 Tr. at 153.
386 Id.
387 Tr. at 154-55.
388 Tr. at 155-56.
389 Tr. at 156.
390 NRC Staff Statements of Professional Qualifications at 20. 391 Id.
- 65 -
NRC.392 As a Health Physicist within the Office of New Reactors, Mr. Williams has participated
in the technical review of three COL applications, four design certification documents, and three
ESP applications.393
In his written testimony on SER Topic 6, Mr. Williams testified as follows:
To estimate the gaseous effluent doses and effluent concentrations to the public, PSEG
combined its long-term atmospheric dispersion estimates with “routine gaseous effluent release
parameters.”394 These parameters “include volumes, flow rates, filtration factors, radiation
monitor estimated readings, estimated duration of each release, and radiological sample
results.”395 PSEG’s methodology conformed to the NRC guidance in Regulatory Guide 1.112
and Regulatory Guide 1.109.396 The NRC Staff also evaluated PSEG’s methodology by
independently calculating the applicable doses and effluent concentrations.397 The NRC Staff’s
confirmatory calculations were within regulatory limits and similar to the values obtained by
PSEG.398
The Board did not require oral testimony from Mr. Williams on SER Topic 6.
G. FEIS Topic 1
FEIS Topic 1 stated:
In its response to FEIS Question 8, PSEG implies that there was never evidence of the Bog Turtle on Artificial Island. Does the NRC Staff agree? If so, should FEIS subsection 2.4.1.3, which states that the Bog Turtle was recorded
392 Id. 393 Id. 394 NRC SER Topic 6 Testimony at 4. 395 Id. 396 Id. 397 Id. at 5. 398 Id.
- 66 -
historically “for Artificial Island and vicinity,” be revised to assert merely that there is historical evidence of the Bog Turtle in the “vicinity” of Artificial Island?399
Two NRC Staff witnesses submitted prefiled written testimony on FEIS Topic
1:400
Michael Willingham. Mr. Willingham is a Project Manager in the NRC’s Office of New
Reactors, Division of Site Safety and Environmental Reviews, Hydrology and Meteorology
Branch 2.401 Mr. Willingham has a B.S. in Environmental Science from Texas A&M University
Corpus Christi and an M.S. in Environmental Engineering and Science from Johns Hopkins
University.402 He has over nine years of experience managing and participating in
multidisciplinary environmental and safety related projects for the NRC, including NEPA
reviews, preparation of environmental impact statements, and pre-application activities related
to environmental reviews of new reactors.403
In his written testimony on FEIS Topic 1, Mr. Willingham testified as follows:
Mr. Willingham is the technical reviewer for terrestrial ecology and land use for the
environmental review associated with the ESP application submitted by PSEG.404 As the ESP
application reviewer for terrestrial ecology and land use, he was responsible for preparing the
terrestrial and wetlands ecology portions of Sections 2.4, 4.3, 5.3, 7.3, and 9.3 of the FEIS.405
399 FEIS Prefiled Testimony Order at 2.
400 The Board did not require oral testimony concerning FEIS Topic 1. See Licensing Board Order (Identifying Resolved Topics) (Mar. 15, 2016) at 1 (unpublished) [hereinafter Resolved Topics Order].
401 NRC FEIS Topic 1 Testimony at 1.
402 NRC Staff Statements of Professional Qualifications at 21. 403 Id.
404 NRC FEIS Topic 1 Testimony at 1.
405 Id.
- 67 -
A 1980 study of the terrestrial ecology of Artificial Island and vicinity identified that the
Bog Turtle was present within the study area, including Delaware.406 The Bog Turtle, however,
was not observed during a 2009-10 survey of the proposed ESP site and its vicinity.407 The
preferred habitat for the Bog Turtle does not exist in the quantity needed to support the species
on Artificial Island.408
Furthermore, the FEIS was intended to reflect that the 1980 study merely
“encompassed” both the Artificial Island and vicinity.409 “[T]he historical evidence does not
indicate direct observations of the bog turtle on Artificial Island.”410 That the Bog Turtle was not
historically present on the Artificial Island is a conclusion that is implicit in the FEIS.411 A formal
revision of the FEIS that “[t]he bog turtle was recorded historically for Artificial Island and
vicinity” is therefore not required.412
Neil Giffen. Mr. Giffen is a Natural Resources Manager of the Facilities and Operations
Directorate at the Oak Ridge National Laboratory (ORNL).413 He is employed by UT-Battelle,
LLC, a not-for-profit organization that manages and operates the ORNL for the U.S. Department
of Energy.414 Mr. Giffen has a B.A. in Environmental Science from State University of New York
406 Id. at 2.
407 Id.
408 Id. at 2-3.
409 Id. at 3.
410 Id.
411 Id.
412 See id.; see also Ex. NRC004A, at 2-6B.
413 NRC FEIS Topic 1 Testimony at 1.
414 Id.
- 68 -
and an M.S. in Wildlife Science from the University of Maryland.415 He has over 25 years of
experience conducting environmental assessments, including environmental impact analysis for
proposed development projects and reviews of numerous environmental assessments and
impact statements.416
Mr. Giffen assisted the NRC Staff in its environmental review of PSEG’s ESP application
associated with the areas of terrestrial and wetlands ecology.417 In his written testimony on
FEIS Topic 1, Mr. Giffen concurred with Mr. Willingham’s statements regarding this issue.418
H. FEIS Topic 2
FEIS Topic 2 stated:
In its response to FEIS Question 9, PSEG implies that there was never evidence of the Eastern Tiger Salamander on Artificial Island. Does the NRC Staff agree? If so, should FEIS subsection 2.4.1.3, which asserts that the Eastern Tiger Salamander was recorded “during an ecological survey conducted on Artificial Island from 1972 through 1978,” be revised to assert that the cited survey examined a study area within a 16 kilometer radius of southern Artificial Island and concluded merely that the Eastern Tiger Salamander was found in southern New Castle County, Delaware “just outside the study area and may occur within it”?419
Two NRC Staff witnesses submitted prefiled written testimony on FEIS Topic
2:420
415 NRC Staff Statements of Professional Qualifications at 23.
416 Id.
417 NRC FEIS Topic 1 Testimony at 1.
418 Id. at 1-3.
419 FEIS Prefiled Testimony Order at 2.
420 The Board did not require oral testimony concerning FEIS Topic 2. Resolved Topics Order at 1.
- 69 -
Michael Willingham. Mr. Willingham’s background and qualifications were previously
summarized with regard to his testimony on FEIS Topic 1. In his written testimony on FEIS
Topic 2, Mr. Willingham testified as follows:
A 1980 study of the terrestrial ecology of Artificial Island found that the Eastern Tiger
Salamander was present just outside the study area, including a portion of Delaware, and may
occur within the study area.421 The Eastern Tiger Salamander was not observed during a 2009-
10 survey of the proposed ESP site and its vicinity.422 Artificial Island does not contain the
habitat resources needed to support the Eastern Tiger Salamander.423
The Eastern Tiger Salamander was not recorded on Artificial Island during the 1972 to
1978 survey, but was reported in Salem County, New Jersey in the 1980 study.424 The FEIS
need not be revised to clarify that the 1980 study examined an area within a 16 kilometer radius
of Artificial Island and concluded that the Eastern Tiger Salamander was found just outside of
the study area and may occur within that area.425 The FEIS was merely intended to reflect that
the 1980 survey “encompassed” Artificial Island, but that the Eastern Tiger Salamander was not
recorded on Artificial Island in that survey.426
Neil Giffen. Mr. Giffen’s background and qualifications were previously summarized with
regard to his testimony on FEIS Topic 1. In his written testimony on FEIS Topic 2, Mr. Giffen
concurred with Mr. Willingham’s statements regarding this issue.427
421 NRC FEIS Topic 2 Testimony at 2.
422 Id.
423 Id.
424 Id. at 3.
425 Id.
426 Id.
427 Id. at 1-3.
- 70 -
I. FEIS Topic 3
FEIS Topic 3 stated:
In its response to FEIS Question 21, PSEG clarifies that flow augmentation from Merrill Creek is not for the purposes of safety or non-safety cooling system operability. PSEG acknowledges, however, that such flow augmentation may be necessary to allow power generation to continue, in certain conditions, so as to avoid impacting the salt line in the Delaware River. Should PSEG apply for a construction permit or COL, will the NRC Staff examine at that time PSEG’s ability to obtain adequate water supplies from the Merrill Creek Reservoir?428
Three witnesses testified on FEIS Topic 3:
1. PSEG Witness
James Mallon. Mr. Mallon’s background and qualifications were previously summarized
with regard to his testimony on SER Topic 1. In his written testimony on FEIS Topic 3, Mr.
Mallon testified as follows:
The Merrill Creek Reservoir (MCR) would not be required for safety-related cooling in
connection with a potential new plant at the PSEG site.429 Furthermore, if additional water rights
are required in the future, then PSEG considers it likely that it could transfer water rights from
another PSEG-owned facility or it could obtain the water rights from a third party.430 Finally, if
PSEG proceeds with a COL application that references this ESP, then the MCR water rights
issue would be subject to NRC Staff review.431
The MCR is used for low flow augmentation of the Delaware River during times of
drought.432 Specifically, the MCR allows certain power plants to continue to withdraw water
from the Delaware River for power generation during declared drought warnings or
428 FEIS Prefiled Testimony Order at 2.
429 PSEG FEIS Topic 3 Testimony at 3.
430 Id.
431 Id.
432 Id. at 4.
- 71 -
emergencies.433 The MCR is not required for any safety cooling purposes because the tidal flow
in the Delaware River at the PSEG site is much greater than the flow required by an intake
structure for a potential new plant.434
Flow augmentation from the MCR is initiated when flows in the Delaware River fall below
3,000 cubic feet per second at Trenton, New Jersey, which is 80 miles north of the PSEG
site.435 Flow augmentation occurs during declared drought conditions to protect the salt line in
the Delaware River, so that Philadelphia-area freshwater intakes are not adversely effected.436
Since the MCR was placed into service in 1988, it has been used for drought-related flow
augmentation only four times.437
Storage allocation for the MCR is determined for each power plant or “designated unit”
with ownership rights in the MCR.438 Currently, thirty six generating stations are listed as
designated units for purposes of the MCR.439 Storage allocation in the MCR is based on the
geographic location of a power plant along the Delaware River.440 Power plants further north
along the Delaware River have the highest allocations due to their higher freshwater
consumptive uses relative to existing plants at the PSEG site that are located along a portion of
the Delaware River that is considered brackish.441
433 Id.
434 Id. at 5.
435 Id. at 6.
436 Id.
437 Id. at 7.
438 Id. at 4, 7.
439 Id. at 8.
440 Id. at 7.
441 Id.
- 72 -
If PSEG required additional water allocation rights in the MCR at the PSEG site, then it
could potentially transfer rights from other PSEG-owned facilities, like Mercer Generating
Station, or enter into negotiations with a third-party designated unit.442 If allocation rights were
obtained from a third-party, then any agreement would be submitted to the Delaware River
Basin Commission (DRBC) for approval.443 Based on the existence of designated units with
lengthy operation histories, it is likely that allocation rights would be available for acquisition as
those plants ceased operations.444
Any new power plant at the PSEG site would require PSEG to submit an application to the
DRBC, with specific plant values for water use.445 The DRBC would then review the application,
hold a public hearing, and issue a docket for surface water withdrawal with appropriate
conditions.446 As a part of this process, PSEG would be required to either hold the specific
required MCR water allocation, or would be required to commit to an operating plan that would
be in effect during declared droughts.447 Regarding the latter, PSEG could commit to an
operating plan that included power generation limits at the PSEG site or other PSEG-owned
facilities.448
Finally, pursuant to 10 C.F.R. § 51.50(c)(1)(iii), an applicant for a COL that references an
ESP must provide “[a]ny new and significant information for issues related to the impacts of
construction and operation of the facility that were resolved in the early site permit
442 Id. at 8-9.
443 Id. at 9.
444 Id.
445 Id.
446 Id.
447 Id.
448 Id. at 9-10.
- 73 -
proceeding.”449 Any identification and evaluation of new and significant information would
include consideration of adequate water supplies from the MCR.450 For this reason, PSEG
anticipated that the NRC Staff will review the water allocation associated with any potential COL
application associated with the PSEG site as a part of the process of preparing any supplement
to the FEIS.451
In his oral testimony on FEIS Topic 3, Mr. Mallon testified as follows:
The purpose of the Merrill Creek Reservoir is to control the salt line of the Delaware River
during a period of drought.452 The PSEG site is south of the salt line and, therefore, any
proposed plant at that site would be cooling with brackish water.453 Nonetheless, the DRBC
wanted PSEG to have a fresh water allocation so they assumed that eighteen percent of
PSEG’s cooling water would be freshwater.454 Downpowering the proposed new plant at the
PSEG site would not have an impact on the salt line.455 However, PSEG would downpower the
plant if ordered to do so by the DRBC.456
2. NRC Staff Witnesses
Philip Meyer. Dr. Meyer is a Senior Research Engineer in the Hydrology Group of the
Energy and Environment Directorate at the Pacific Northwest National Laboratory.457 He has
449 Id. at 11; see also 10 C.F.R. § 51.50(c)(1)(iii).
450 PSEG FEIS Topic 3 Testimony at 11.
451 Id.
452 Tr. at 163.
453 Tr. at 167.
454 Tr. at 164.
455 Tr. at 166.
456 Tr. at 164-65.
457 NRC FEIS Topic 3 Testimony at 1.
- 74 -
supported the NRC Office of New Reactors since 2007, including serving as principal author
and technical analyst for the groundwater sections of safety evaluations for the North Anna Unit
3 COL, Calvert Cliffs Unit 3 COL, and Vogtle Units 3 and 4 COL.458 Dr. Meyer has a B.A. in
Physics from Cornell University and an M.S. and a Ph.D in Civil Engineering from the University
of Illinois.459
In his written testimony on FEIS Topic 3, Dr. Meyer testified as follows:
Dr. Meyer, along with Mohammad Haque, served as the NRC Staff technical reviewers
for the water-related aspects of the ESP application.460 They were responsible for the
hydrology, water use, and water quality technical content of the FEIS, and for the preparation of
Sections 2.3, 4.2, 5.2, and 7.2 of the FEIS.461
The NRC Staff would necessarily evaluate the adequacy of the MCR for low flow
augmentation to the Delaware River as part of the environmental review of any CP or COL
application that references an ESP for the proposed site.462 In preparing a supplemental EIS for
a CP or COL application that references the PSEG ESP, the NRC Staff would determine
whether there is new and significant information related to the plant’s water use.463 More
specifically, any supplemental ESP review would be in accordance with the NRC’s regulations
under 10 C.F.R. Part 51.464
458 NRC Staff Statements of Professional Qualifications at 27.
459 Id.
460 NRC FEIS Topic 3 Testimony at 1.
461 Id.
462 Id.
463 Id. at 2
464 Id.
- 75 -
The NRC Staff would look at changes to the list of designated units and changes in the
allocation of MCR storage.465 Additionally, the NRC Staff would consider, as appropriate, other
related information including changes in the DRBC’s requirements, new development that
increases consumptive water use in the Delaware River basin, and changes in the climate of the
region that could impact water resources.466 In performing a review of any new or significant
information associated with a CP or COL application, the NRC Staff would re-examine the
potential environmental impacts associated with the MCR, which would inform the NRC’s
ultimate licensing decision.467
The Board did not require oral testimony from Dr. Meyer on FEIS Topic 3.
Mohammad Haque. Mr. Haque is a Senior Hydrologist in the NRC’s Office of New
Reactors, Division of Site Safety and Environmental Analysis, Environmental Technical Support
Branch.468 Mr. Haque has a B.S. in Civil Engineering and an M.S. in Civil Engineering from the
University of Texas at Arlington.469 He has over 40 years of experience in environmental and
water resources engineering in the private and public sectors, including approximately 18 years
at the NRC.470 Mr. Haque’s NRC experience includes approximately seven years in the Division
of Site Safety and Environmental Analysis, including serving as a project manager and as a
technical expert reviewing hydrologic aspects of safety analysis and environmental reports for
various ESP and COL applications.471
465 Id.
466 Id.
467 Id.
468 NRC FEIS Topic 3 Testimony at 1.
469 NRC Staff Statements of Professional Qualifications at 26.
470 Id.
471 Id.
- 76 -
In his written testimony on FEIS Topic 3, Mr. Haque concurred with Dr. Meyer’s
statements regarding this issue.472 In his oral testimony on FEIS Topic 3, Mr. Haque testified as
follows:
In evaluating the potential environmental impacts that would be associated with release
of the MCR water for low-flow augmentation, the NRC Staff would consider the equivalent
freshwater consumptive water use of a new plant at the PSEG site.473 Specifically, “[t]he DRBC
requires that the consumptive use by a utility should be compensated for low flow augmentation
and . . . they have an equivalent factor of 0.18 that has been established . . . to compute [the]
equivalent amount for the brackish water.”474 This equivalency factor is the same for the Salem
and Hope Creek power plants.475
J. FEIS Topic 4
FEIS Topic 4 stated:
Following the discussion in FEIS subsection 5.3.1.1 and the NRC Staff responses to FEIS Questions 22 and 23, the Staff shall provide additional detail about the potential impact of salt drift on freshwater wetlands in the vicinity of the ESP site. Specifically, the Staff noted in their response that “vegetation in the area has already adapted to naturally occurring levels of salt deposition” and that “cumulative impacts of salt deposition on the site and the vicinity would be minimal”; however, does this generalization apply to all of the potentially affected wetlands and could an incremental increase in salt drift adversely affect threatened or endangered plant or animal species?476
Two NRC Staff witnesses submitted prefiled written testimony on FEIS Topic 4:477
472 NRC FEIS Topic 3 Testimony at 1-2.
473 See Tr. at 169; see also NRC FEIS Topic 3 Testimony at 2.
474 Tr. at 169.
475 Tr. at 170.
476 FEIS Prefiled Testimony Order at 2-3.
477 The Board did not require oral testimony concerning FEIS Topic 4. See Resolved Topics Order at 1.
- 77 -
Michael Willingham. Mr. Willingham’s background and qualifications were previously
summarized with regard to his testimony on FEIS Topic 1. In his written testimony on FEIS
Topic 4, Mr. Willingham testified as follows:
Cumulative maximum salt deposition from the Hope Creek Generating Station natural
draft cooling tower (NDCT), proposed linear mechanical draft cooling towers (LMDCTs), and
natural salt deposition would result in a cumulative salt deposition rate of 3.74 kg/ha/mo.478 The
salt deposition rate for the proposed LMDCTs is 1.31 kg/ha/mo, and the rate for the existing
NDCT is 1.13 kg/ha/mo.479 The natural salt deposition rate for the area is 1.3 kg/ha/mo.480 The
salt deposition rates do not entirely overlap; therefore, the numerical values from the cooling
towers are not directly additive.481 Rather, the maximum salt drift deposition from the proposed
LMDCTs would occur within 700 meters to the east, while the deposition from the existing
NDCT occurs within 400 meters to the southeast.482 As a result, the cumulative salt deposition
rate of 3.74 kg/ha/mo is a conservative maximum bounding limit and actual rates are expected
to be lower.483
Additionally, the dominant habitat type 700 meters to the east and southeast of the
proposed location of the LMDCTs is Phragmites-dominated coastal wetlands.484 Existing land
use types that could potentially be affected by salt drift deposition from the proposed LMDCTs
include disturbed wetlands, Phragmites-dominated interior wetlands, and developed land
478 NRC FEIS Topic 4 Testimony at 2.
479 Id.
480 Id.
481 Id.
482 Id.
483 Id.
484 Id.
- 78 -
uses.485 Furthermore, all of the land uses and habitats within 400 meters of the east and
northeast of the existing NDCT are urban/developed land uses and Phragmites-dominated
coastal wetlands.486
155.6 acres of the existing PSEG site are Phragmites-dominated coastal wetlands,
which is tidally influenced and can have salinity ranges from 1 to 9 ppt.487 Therefore, the
vegetation species in this habitat would be expected to have a higher level of salinity tolerance,
resulting in minimal cumulative impacts of salt deposition on the site and vicinity.488
The extent of vegetation damaged by salt drift is related to the climatic conditions, stage
of life cycle, and tolerance to salt.489 For example, salt drift is more likely to damage (1)
vegetation in more arid environments, (2) less salt tolerant species, and (3) plants during their
growing season.490 At the PSEG site, mean annual rainfall would be expected to prevent soil
salinization that could damage vegetation, relative to more arid environments.491 Additionally,
the cumulative maximum salt deposition rate of 3.74 kg/ha/mo would occur during the winter.492
This cumulative rate is less than that expected to cause acute injury to the most sensitive
species list in NUREG-1437 and would not occur during the growing season of plants on and in
the vicinity of the PSEG site.493 Moreover, the coastal location of the site results in vegetation
485 Id.
486 Id.
487 Id.
488 Id.
489 See id. at 3
490 Id.
491 Id.
492 Id.
493 Id.
- 79 -
that is generally expected to have a high level of salinity tolerance; therefore, salt deposition is
expected to have a minimal impact on plant species.494
Lastly, there are no known Federally-listed endangered or threatened vegetation or
animal species that occur within the areas affected by salt drift.495 In addition, although various
state-listed species occur within wetlands affected by salt drift, including various wading birds
and the northern harrier, these species commonly frequent coastal wetland habitats and are
acclimated to saline environments.496 As a result, the incremental increase in salt deposition
rates resulting from a new cooling tower would not be expected to impact these bird species.497
Neil Giffen. Mr. Giffen’s background and qualifications were previously summarized with
regard to his testimony on FEIS Topic 1. In his written testimony on FEIS Topic 4, Mr. Giffen
concurred with Mr. Willingham’s statements regarding this issue.498
K. FEIS Topic 5
FEIS Topic 5 stated:
In its response to FEIS Question 29, the NRC Staff asserts that it does not expect that the potential new nuclear units “and associated infrastructure” would adversely affect either the Bog Turtle or the Eastern Tiger Salamander. Has the Staff confirmed that, in the most recent surveys, neither the Bog Turtle nor the Eastern Tiger Salamander were identified in the areas proposed for a new causeway, transmission lines, or related infrastructure?499
494 Id.
495 Id.
496 Id.
497 Id.
498 Id. at 1-4
499 FEIS Prefiled Testimony Order at 3.
- 80 -
Two NRC Staff witnesses submitted prefiled written testimony on FEIS Topic
5:500
Michael Willingham. Mr. Willingham’s background and qualifications were previously
summarized with regard to his testimony on FEIS Topic 1. In his written testimony on FEIS
Topic 5, Mr. Willingham testified as follows:
In preparing the FEIS, the NRC Staff reviewed relevant information and conducted site
visits regarding the presence of the Bog Turtle and the Eastern Tiger Salamander in the areas
proposed for a new causeway, transmission lines, or related infrastructure.501 The 2009-10
survey—referenced in his testimony regarding FEIS Topics 1 and 2—included the proposed
causeway, transmission lines, and related infrastructure.502 As previously noted, the Bog Turtle
and Eastern Tiger Salamander were not observed during the 2009-10 survey.503 Reports by the
Conserve Wildlife Foundation of New Jersey and the NJDEP indicate that Bog Turtles are
primarily restricted to several counties in New Jersey, including northeastern portions of Salem
County.504 Eastern Tiger Salamanders are limited to the far eastern portions of Salem County,
and Cumberland and Atlantic Counties in New Jersey.505
The NRC Staff also conducted several site visits to the proposed ESP site and vicinity
and confirmed that the habitat observed was consistent with the information provided to the
500 The Board did not require oral testimony concerning FEIS Topic 5. See Resolved Topics Order at 1.
501 NRC FEIS Topic 5 Testimony at 2.
502 Id. at 3.
503 Id.
504 Id.
505 Id.
- 81 -
NRC, which did not indicate the presence of the preferred habitat for either species.506 Neither
species was observed during NRC Staff site visits.507
Neil Giffen. Mr. Giffen’s background and qualifications were previously summarized with
regard to his testimony on FEIS Topic 1. In his written testimony on FEIS Topic 5, Mr. Giffen
concurred with Mr. Willingham’s statements regarding this issue.508
L. FEIS Topic 6
FEIS Topic 6 stated:
In its response to FEIS Question 33, the NRC Staff states that, “[w]ith the exception of the mitigation activities associated with the PSEG traffic study, all of the activities listed in Table 10-1 in the FEIS are associated with expected permit requirements of other Federal, State, and local agencies.” For each of these expected permit requirements, the Staff shall either confirm that the expected permit requirement is essentially certain, or if not essentially certain, provide an estimate of the unavoidable impact if the respective requirement is not made. Likewise, in Table 10-2 of the FEIS, listing unavoidable impacts of operation, the Staff makes use of similar mitigation acts based upon expected permit requirements. The Staff shall make similar confirmations for this table as well.509
Five witnesses submitted prefiled written testimony on FEIS Topic 6:510
1. PSEG Witness
James Mallon. Mr. Mallon’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 1.
In his written testimony on FEIS Topic 6, Mr. Mallon testified as follows:
506 Id.
507 Id.
508 Id. at 2-4.
509 FEIS Prefiled Testimony Order at 3.
510 The Board did not require oral testimony concerning FEIS Topic 6. Tr. at 72-73.
- 82 -
The mitigation activities listed in Table 10-1 of the FEIS will likely be included in the
various permit requirements of other federal, state, and local agencies.511 Specifically,
Appendix H of the FEIS identifies the numerous authorizations, permits and certifications that
may be required for the operation of a new nuclear power plant at the PSEG site.512 Although
PSEG has not yet received or applied for many of the necessary approvals, based on PSEG’s
40 years of site experience and knowledge of the relevant agencies, it is likely that the required
mitigation measures will be “comprehensive and complete.”513 Further, at the COL state, PSEG
will be required to identify any new and significant information, including changes to the
mitigation actions.514
For example, with respect to construction mitigation measures, the required land use
approvals include, but are not limited to, a Federal USACE Section 10 and Section 404 Permit,
a NJDEP Coastal Area Facility Review Act/Waterfront Development permit, as well as various
zoning and construction approvals from the local Lower Alloways Creek Township.515 “Based
on PSEG’s experience with other large construction projects, combined with the anticipated
conditions of the NJDEP and USACE land use construction approvals, specific monitoring
conditions and mitigation activities will be included.”516
2. NRC Staff Witnesses
Allen Fetter. Mr. Fetter’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 1.
511 PSEG FEIS Topic 6 Testimony at 2-3.
512 Id. at 4; see Ex. NRC004C, App. H, at H-1 to H-7. 513 PSEG FEIS Topic 6 Testimony at 8-9. 514 Id. at 7. 515 Id. at 9. 516 Id.
- 83 -
In his written testimony on FEIS Topic 6, Mr. Fetter testified as follows:
Under NEPA, the NRC Staff is required to consider mitigation measures that are
reasonably foreseeable.517 NRC Staff guidance regarding mitigation measures states that a
mitigation measure is reasonably foreseeable if (1) it is required by the NRC as a license
condition, (2) the mitigation measure is required or likely to be required by another regulatory
agency or (3) the applicant stated in its communications with the NRC that it will perform the
mitigation measure.518 Mr. Fetter and the other NRC Staff witnesses on this topic included a
chart in their written testimony that describes the NRC Staff’s bases for concluding that the
mitigation measures identified in Tables 10-1 and 10-2 of the FEIS are reasonably
foreseeable.519
For example, in terms of impacts to aquatic resources, the NRC Staff concluded that its
identified migration measures are reasonably foreseeable because PSEG will be required to
acquire a Department of Army permit under Section 10 of the Rivers and Harbors Act of 1899
and Section 404 of the Clean Water Act.520 PSEG will also be required to obtain a Clean Water
Act Section 401 water quality certification from NJDEP.521 According to the NRC Staff, these
permits will contain “special conditions, including [best management practices], to minimize
impacts to aquatic resources and habitats.”522 In addition, prior to the issuance of the
517 NRC FEIS Topic 6 Testimony at 2. 518 Id.; see Environmental Issues Associated with New Reactors, Interim Staff Guidance, (Aug. 2014) at 4 (ADAMS Accession No. ML14092A402). 519 NRC FEIS Topic 6 Testimony, Tbl. 10-1, at 4-28. 520 Id. at 8. 521 Id. 522 Id.
- 84 -
Department of Army permit, PSEG will be required to develop “a detailed compensatory
mitigation plan to address unavoidable impacts to aquatic resources.”523
Jack Cushing. Mr. Cushing is a Senior Project Manager, in the Office of New Reactor’s
Division of Site Safety & Environmental Analysis, Environmental Technical Support Branch.524
He received his B.S. in Marine Engineering from the Massachusetts Maritime Academy.525 Mr.
Cushing has 33 years of experience in the nuclear power field, including 17 years with the
NRC.526 As part the NRC Staff’s review of PSEG’s ESP application, Mr. Cushing provided
technical oversight for the historic and cultural resource review.527
Mr. Cushing’s written testimony on FEIS Topic 6 was substantively identical to Mr.
Fetter’s written testimony on this topic.
Jennifer Davis. Ms. Davis is a Senior Project Manager, in the Office of New Reactor’s
Division of Site Safety & Environmental Analysis, Environmental Technical Support Branch.528
She received a B.A. in Historic Preservation/Classical Civilization from Mary Washington
College.529 Ms. Davis has approximately 14 years of experience managing environmental
projects at the NRC.530 During the PSEG review, Ms. Davis was the NRC’s technical lead for
the NEPA evaluation of impacts to cultural and historic resources.531
523 Id. 524 NRC Staff Statements of Professional Qualifications at 24. 525 Id. 526 Id. 527 Id. 528 Id. at 29. 529 Id. 530 Id. 531 Id. at 30.
- 85 -
Ms. Davis’ written testimony on FEIS Topic 6 was substantively identical to Mr. Fetter’s
written testimony on that topic.
Andrew Kugler. Mr. Kugler is a Senior Environmental Project Manager, in the Office of
New Reactor’s Division of Site Safety & Environmental Analysis, Environmental Technical
Support Branch.532 He received a B.S. in Mechanical Engineering from Cooper Union, and an
M.S. in Technical Management from Johns Hopkins University.533 Mr. Kugler has 15 years of
experience managing environmental projects for the NRC.534 During his time at the NRC, Mr.
Kugler has managed or participated in review of over ten license renewal applications and
several ESP applications.535
Mr. Kugler’s written testimony on FEIS Topic 6 was substantively identical to Mr. Fetter’s
written testimony on this topic.
M. FEIS Topic 7
FEIS Topic 7 stated:
Related to the NRC Staff’s response to FEIS Question 34, on page 10-5 of the FEIS, Table 10-1 lists the unavoidable adverse environmental impacts of construction on the PSEG site. The third column of this table lists the actions that can be taken to mitigate the impacts. However, FEIS section 10.2, Unavoidable Adverse Environmental Impacts, defines unavoidable adverse impacts as: “Unavoidable adverse environmental impacts are those potential impacts of the NRC action and the USACE action that cannot be avoided and for which no practical means of mitigation are available.” The Staff shall confirm that the mitigation actions listed will not reduce impacts to less than the impacts listed in the second column of Table 10-1, but rather are actions required to limit impacts to those listed in the second column.536
532 Id. at 31. 533 Id. 534 Id. 535 Id. 536 FEIS Prefiled Testimony Order at 3.
- 86 -
Four NRC Staff witnesses submitted prefiled written testimony on FEIS Topic 7:537
Allen Fetter. Dr. Fetter’s background and qualifications have been previously
summarized with regard to his testimony on SER Topic 1. In his written testimony on FEIS
Topic 7, Dr. Fetter testified as follows:
The NRC Staff classified unavoidable adverse impacts and mitigation actions in Table
10-1 of the FEIS.538 Specifically, Table 10-1 lists the potential mitigation measures for various
impacts in the third column.539 In the fourth column, the table lists any remaining unavoidable
adverse impacts after the mitigation measures are applied.540 Thus, the mitigation measures
identified in the third column of Table 10-1 will not alter the impact level on each resource area
(i.e., whether the adverse impact will be small, moderate, or large).541
Jack Cushing. Mr. Cushing’s background and qualifications have been previously
summarized with regard to his testimony on FEIS Topic 6. Mr. Cushing’s written testimony on
FEIS Topic 7 was substantively identical to Mr. Fetter’s testimony on this topic.
Jennifer Davis. Ms. Davis’ background and qualifications have been previously
summarized with regard to her testimony on FEIS Topic 6. Ms. Davis’ written testimony on
FEIS Topic 7 was substantively identical to Mr. Fetter’s testimony on this topic.
Andrew Kugler. Mr. Kugler’s background and qualifications have been previously
summarized with regard to his testimony on FEIS Topic 6. Mr. Kugler’s written testimony on
FEIS Topic 7 was substantively identical to Mr. Fetter’s testimony on this topic.
537 The Board did not require oral testimony concerning FEIS Topic 7. See Resolved Topics Order at 1.
538 NRC FEIS Topic 7 Testimony at 2.
539 Id.; see Ex. NRC004B, Tbl. 10-1, at 10-5 to 10-9.
540 NRC FEIS Topic 7 Testimony at 2; see Ex. NRC004B, Tbl. 10-1, at 10-5 to 10-9.
541 NRC FEIS Topic 7 Testimony at 2.
- 87 -
N. FEIS Topic 8
FEIS Topic 8 stated:
The NRC Staff shall ensure the presence at the evidentiary hearing of one or more witnesses capable of making brief presentations identifying the most significant parts of the cumulative impact assessment and assessment of alternative sites, and responding to the Board’s questions thereon.542
Although the parties were not required to submit prefiled written testimony on FEIS
Topic 8, two witnesses testified orally:
Andrew Kugler. Mr. Kugler’s background and qualifications have been previously
summarized with regard to his testimony on FEIS Topic 6. At the hearing, Mr. Kugler testified
regarding the value of the alternative site analysis generally.543 Although none of the alternative
sites considered in the NRC Staff’s environmental review of PSEG’s application were obviously
superior to the PSEG site, “there have been other application[s] in which a nearby existing
nuclear power plant site has not been chosen over a different site that had other advantages.”544
Jack Cushing. Mr. Cushing’s background and qualifications have been previously
summarized with regard to his testimony on FEIS Topic 6. At the hearing, Mr. Cushing testified
that the cumulative impact assessment ensures that NRC Staff considers the full impact of
action that may be minor in isolation, but collectively significant.545 Therefore, the cumulative
impact analysis examines the “tipping point on the resource” to analyze whether an individually
minor action becomes the “straw [that] breaks the camel’s back.”546
542 FEIS Prefiled Testimony Order at 3.
543 Tr. at 174-75.
544 Tr. at 174.
545 Tr. at 180.
546 Id.
- 88 -
V. DISCUSSION
In SER Topic 1, the Board asked the NRC Staff to summarize those portions of its
review that supported each of the six safety-related findings necessary for issuance of an
ESP.547 The Staff confirmed that, based on its review of PSEG’s application, PSEG complied
with all applicable regulatory requirements.548 The Staff also proposed certain permit
conditions.549
Because PSEG did not request a limited work authorization, the scope of the Staff’s
review was limited. The Board is satisfied that the NRC will review PSEG’s qualifications to
engage in NRC authorized activities at later stages in the licensing process.550 For example,
even though PSEG has extensive experience as a nuclear power plant owner and operator, it
was not actually required to demonstrate its technical qualifications to undertake construction
activities at this stage.551 For the same reason, the only applicable ITAAC at this stage are
those that pertain to emergency planning, and the Staff correctly determined that PSEG had
submitted a satisfactory emergency plan and associated ITAAC.552
Similarly, although PSEG has not yet selected a specific reactor design, its application
utilized a plant parameter envelope.553 The Board is satisfied that, if PSEG were to select a
design outside these parameters at the COL stage, the NRC would have an appropriate
547 In fact, both the Staff and PSEG responded, and each went beyond the Board’s request and addressed environmental findings as well. NRC SER Topic 1 Testimony at 5-7; PSEG SER Topic 1 Testimony at 18-29.
548 NRC SER Topic 1 Testimony at 5.
549 Id. at 4.
550 Id.
551 See id.
552 Id. at 4-5.
553 Tr. at 93.
- 89 -
opportunity to evaluate the significance of the differences in the context of the variance request
that would be required in such circumstances.554
In SER Topic 2, the Board sought to determine whether each of the NRC Staff’s nine
proposed permit conditions was drawn with sufficient precision, such that verification of
compliance would be largely a ministerial act. The NRC Staff explained how each permit
condition included sufficiently prescriptive detail and used widely-accepted industry standards
and terminology.555 The Board also finds persuasive the fact that seven of the nine conditions
are nearly identical to conditions the Commission has approved in other proceedings,556 and
that the other two are very site specific.557
In SER Topic 3, the Board specifically asked about the extent of the Staff’s experience in
hydraulic modeling and how it is documented. Both PSEG and the Staff provided considerably
more detail concerning PSEG’s flooding model and the Staff’s review of it.558 The Board is
satisfied that the NRC Staff possesses appropriate experience, and that it is documented in
SER Section 2.4.
In SER Topic 4, the Board asked the NRC Staff to explain how it had addressed the
possible influence of climate change on the power and frequency of hurricanes. As the Staff
explained, design-basis wind speeds were based on a doubling of the frequency of hurricanes
in the Atlantic and Gulf Coasts and the PMH used to calculate maximum water elevation was
sufficiently conservative to account for potential increases in power.559 Overall, the Board
554 Tr. at 93-94.
555 NRC SER Topic 2 Testimony at 3-13.
556 PSEG SER Topic 2 Testimony at 9-21.
557 Tr. at 110.
558 See NRC SER Topic 3 Testimony at 2-3; PSEG SER Topic 3 Testimony at 4-7.
559 NRC SER Topic 4 Testimony at 2-3.
- 90 -
agrees with the Staff’s conclusion that its analysis is appropriately conservative, especially given
uncertainties related to the ameliorating effect of colder water on tropical storms approaching
the mid-Atlantic coast.560 Additionally, the NRC Staff would be required to update regulatory
guidance as necessary to address evolving site conditions, and PSEG would be obligated to
ensure that its site remains safe to operate.561
In SER Topic 5, the Board asked what, if any, impact the Fukushima events in Japan
had on the NRC Staff’s review of PSEG’s application. The Board is satisfied that, while the
Staff considered numerous recommendations that arose out of the Fukushima incident,562 the
Staff properly concluded that only a few recommendations applied to the PSEG site at the ESP
stage, and that none substantively altered the scope or nature of the Staff’s review of PSEG’s
application.563
In SER Topic 6, the Board asked about PSEG’s calculations of the long-term
atmospheric dispersion of routine releases of radionuclides, and about the extent of the NRC
Staff’s review. The Board agrees with the Staff’s conclusion that PSEG’s long-term atmospheric
dispersion estimates are acceptable.564 Among other things, the NRC Staff undertook a quality
assurance review of the onsite meteorological data that PSEG used as the basis for its primary
inputs to the atmospheric dispersion model.565 The Staff then created its own inputs, based on
the same dataset, and ran a confirmatory analysis that produced results very similar to PSEG’s
560 Id. at 3.
561 See NRC SER Topic 5 Testimony at 4-5; Tr. at 144-45.
562 NRC SER Topic 5 Testimony at 3.
563 See id. at 4-5; Tr. at 151-52.
564 NRC SER Topic 6 Testimony at 4.
565 Id.
- 91 -
values.566 Further, the Staff created COL Action Item 2.3-1, which will require PSEG at the COL
stage to verify and, if necessary, adjust receptors of interest.567
In FEIS Topic 1, the Board sought and received confirmation that the preferred habitat
for the Bog Turtle does not exist in the quantity needed to support the species on Artificial
Island,568 and that the historical evidence does not indicate direct observations of the Bog Turtle
on Artificial Island at any time.569
In FEIS Topic 2, the Board sought and received confirmation that Artificial Island does
not contain the habitat resources needed to support the Easter Tiger Salamander,570 and that
the Eastern Tiger Salamander was not observed during a 2009-10 survey of the ESP Site and
its vicinity.571
In FEIS Topic 3, the Board was concerned about PSEG’s ability to obtain flow
augmentation from the MCR if and when necessary. The Board is satisfied that (1) the MCR
would not be required for safety-related cooling of a potential new plant at the PSEG site;572 (2)
if additional water rights are required in the future, PSEG considers it likely that it could transfer
water rights from another PSEG-owned facility or could obtain them from a third party;573 and (3)
566 Id.
567 Id.
568 NRC FEIS Topic 1 Testimony at 2-3.
569 Id. at 3.
570 NRC FEIS Topic 2 Testimony at 2.
571 Id.
572 PSEG FEIS Topic 3 Testimony at 3.
573 Id.
- 92 -
if PSEG proceeds with a COL application, the MCR water rights issue would be subject to NRC
Staff review at that time.574
In FEIS Topic 4, the Board was concerned whether an incremental increase in salt drift
on freshwater wetlands in the vicinity of the ESP site could adversely affect threatened plant or
animal species. The Board is persuaded that any such impact would be minimal, in part
because (1) the coastal location of the site results in vegetation that is generally expected to
have a high salinity tolerance;575 and (2) no known federally-listed endangered or threatened
vegetation or animal species occur within the areas affected by salt drift.576 Additionally,
although various wading birds and other state-listed species occur within wetlands affected by
salt drift, these species commonly frequent coastal wetland habitats and are acclimated to
saline environments.577
In FEIS Topic 5, the Board requested and received confirmation that neither the Bog
Turtle nor the Eastern Tiger Salamander is present in the areas proposed for a new causeway,
transmission lines, or related infrastructure.578
In FEIS Topic 6, the Board was concerned about the extent to which environmental
mitigation activities over which the NRC does not exercise direct control will actually take place.
The NRC Staff explained that, under NEPA, the NRC is required to consider mitigation
measures that are reasonably foreseeable, even if some such measures arise from expected
permits from other state and federal agencies that may not yet exist at the ESP stage.579 NRC
574 Id.
575 NRC FEIS Topic 4 Testimony at 3.
576 Id.
577 Id.
578 NRC FEIS Topic 5 Testimony at 2-3.
579 NRC FEIS Topic 6 Testimony at 2.
- 93 -
Staff guidance provides that a mitigation measure is reasonably foreseeable if (1) it is required
by the NRC as a license condition, (2) it is required or likely to be required by another regulatory
agency, or (3) an applicant has stated in communications with the NRC that it will perform the
measure.580 Several NRC Staff witnesses included a chart in their written testimony describing
the Staff’s grounds for concluding the mitigation measures identified in the FEIS are reasonably
foreseeable.581 On this basis, the Board’s concerns are satisfied.
In FEIS Topic 7, the Board expressed concern about the relationship between mitigation
measures and the Staff’s characterization in the FEIS of the size of the anticipated impact level
on each resource. The Board’s concern has been addressed by the Staff’s explanation that the
mitigation measures would not alter the impact levels as set forth in the FEIS.582
In FEIS Topic 8, the Board did not express a specific concern, but directed the presence
at the evidentiary hearing of NRC Staff witnesses capable of responding to the Board’s
questions regarding the cumulative impact assessment and assessment of alternative sites in
the FEIS. The testimony of the Staff’s witnesses583 adequately addressed the Board’s
questions in these areas.
Based on the written and oral testimony, the Board’s concerns regarding all fourteen
issues identified for the evidentiary hearing were resolved. The Board sees no reason to
impose permit conditions beyond the nine already proposed by the NRC Staff.584
580 Id.
581 Id. at 4-28 Tbls.10-1 & 10-2.
582 NRC FEIS Topic 7 Testimony at 2.
583 Tr. at 173-81.
584 Ex. NRC003, App. A, at A-2 to A-6.
- 94 -
VI. FINDINGS
For the foregoing reasons, the Board makes the following determinations as required by
10 C.F.R. § 52.24(a) and 10 C.F.R. § 51.105(a):
1. In accordance with 10 C.F.R. § 52.24(a)(1), the applicable standards and
requirements of the AEA and the NRC regulations have been met.
2. In accordance with 10 C.F.R. § 52.24(a)(2), all required notifications to other
agencies or bodies have been made.
3. In accordance with 10 C.F.R. § 52.24(a)(3), there is reasonable assurance that the
facility will be constructed and operated in conformity with the licenses, the provisions of the
AEA, and the NRC’s regulations.
4. In accordance with 10 C.F.R. § 52.24(a)(4), PSEG is technically qualified to engage
in the activities authorized.
5. In accordance with 10 C.F.R. § 52.24(a)(5), the proposed inspections, tests, analyses
and acceptance criteria, including any on emergency planning, are necessary and sufficient,
within the scope of the ESP, to provide reasonable assurance that the facility will be constructed
and will be operated in conformity with the license, the provisions of the Act, and the
Commission’s regulations.
6. In accordance with 10 C.F.R. § 52.24(a)(6), issuance of the licenses will not be
inimical to the common defense and security or to the health and safety of the public.
7. In accordance with Subpart A of 10 C.F.R. Part 51, the requirements of Sections
102(2)(A), (C), and (E) of NEPA and Subpart A of 10 C.F.R. Part 51 have been complied with in
the proceeding.
8. The Board determines, without conducting a de novo evaluation of the application,
that the review conducted by the NRC Staff pursuant to 10 C.F.R. Part 51 has been adequate.
- 95 -
9. In accordance with Subpart A of 10 C.F.R. Part 51, the Board has independently
considered the final balance among conflicting factors contained in the record of the proceeding
with a view to determining the appropriate action to be taken.
10. In accordance with Subpart A of 10 C.F.R. Part 51, the Board determines, after
weighing the environmental, economic, technical, and other benefits against the environmental
and other costs, and considering reasonable alternatives, that an ESP should be issued.
VII. ORDER
The Director of the Office of New Reactors is authorized to issue to PSEG an ESP for
the PSEG site for a duration of not more than twenty (20) years, consistent with the AEA, the
Commission’s regulations, and this Initial Decision. The ESP shall be subject to the nine permit
conditions set forth in the SER.585
585 Ex. NRC003, App. A, at A-2 to A-6.
- 96 -
Pursuant to 10 C.F.R. § 2.341(a)(2), this Initial Decision will constitute a final decision of
the Commission 120 days from the date of issuance, unless a petition for review is filed in
accordance with 10 C.F.R. § 2.341(b) or the Commission directs otherwise. Any party wishing
to file a petition for review on the grounds specified in § 2.341(b) must do so within twenty-five
days after service of this Initial Decision.
It is so ORDERED.
THE ATOMIC SAFETY AND LICENSING BOARD /RA/
___________________________ Paul S. Ryerson, Chairman ADMINISTRATIVE JUDGE /RA/ ___________________________ Dr. Gary S. Arnold ADMINISTRATIVE JUDGE /RA/ ___________________________ Dr. Craig M. White ADMINISTRATIVE JUDGE
Rockville, Maryland April 26, 2016
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
In the Matter of ) ) PSEG POWER, LLC ) Docket No. 52-043-ESP AND PSEG NUCLEAR, LLC ) (Early Site Permit Application) )
CERTIFICATE OF SERVICE
I hereby certify that copies of the foregoing INITIAL DECISION (LBP-16-04) have been served upon the following persons by Electronic Information Exchange. Office of Commission Appellate Adjudication Mail Stop: O-7H4 Washington, DC 20555-0001 [email protected]
Office of the Secretary of the Commission Mail Stop: O-16G4 Washington, DC 20555-0001 [email protected]
Paul S. Ryerson, Chairman Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop: T-3F23 Washington, DC, 20555-0001 [email protected]
Dr. Craig M. White Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop: T-3F23 Washington, DC, 20555-0001 [email protected]
Dr. Gary S. Arnold Administrative Judge Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop: T-3F23 Washington, DC, 20555-0001 [email protected]
Jennifer E. Scro Law Clerk Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop: T-3F23 Washington, DC, 20555-0001 [email protected]
Cooper J Strickland Law Clerk Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Mail Stop: T-3F23 Washington, DC, 20555-0001 [email protected]
OGC Mail Center U.S. Nuclear Regulatory Commission Mail Stop: O-15D-21 Washington, DC, 20555-0001 [email protected]
PSEG POWER, LLC AND PSEG NUCLEAR, LLC - Docket No. 52-043-ESP INITIAL DECISION (LBP-16-04)
2
Patrick A. Moulding, Esq. Office of the General Counsel Mail Stop O-15D-21 Washington, DC 20555-0001 [email protected]
Susan H. Vrahoretis, Esq. Office of the General Counsel Mail Stop O-15D-21 Washington, DC 20555-0001 [email protected]
Ann N. Hove, Esq. Office of the General Counsel Mail Stop O-15D-21 Washington, DC 20555-0001 [email protected]
Kevin C. Roach, Esq. Office of the General Counsel Mail Stop O-15D-21 Washington, DC 20555-0001 [email protected]
Jeffrie Keenan, Esq. PSEG Nuclear LLC P.O. Box 236, N-21 Hancocks Bridge, NJ 08036 [email protected]
Stephen J. Burdick, Esq. Morgan, Lewis & Bockius LLP 1111 Pennsylvania Ave., N.W. Washington, DC 20004 [email protected]
[Original signed by Herald M. Speiser ] Office of the Secretary of the Commission Dated at Rockville, Maryland, this 26th day of April, 2016
Top Related