Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Project Update
October 2019
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•Additional State Contract Purchases $ 176,223
•Approved Change Orders $ 432,812
•Remaining Construction Contingency $ 955,276
•Construction Project is 64% Complete
•Contingency Budget is 39% spent
•Contract allowance approved totals $0
•Project Team is following approximately $746,281 in pending issues
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Construction in Rooms 110, 108,
106, 117, The Art Room and the
Discovery Lab continue.
• Wall tile and ceiling grid has been
installed in Toilet Rooms 202 and 206.
• Casework is being installed in the Art
Room and Discovery Lab.
Transportation Building
• The Addition has been turned over to
the District and is being moved into.
• Once the move is complete
construction will begin in the existing
bays.
Senior High School
• Construction continues in the Flex Space and
Conference Room on the 2nd Floor.
• Construction is ongoing in the New Art Room,
Flexible Learning Lab and saw cutting has
begun in the New Cafeteria.
• Ceiling Tile has been installed in the New
Lobby and demo has begun in the Girls Pool
Locker Room.
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Lima Intermediate
• Block work for the elevator shaft and
the dividing wall between rooms 210
and 206 is nearly complete.
• Roofing work is complete
Middle School
• The Turf Field is substantially complete and a
punchlist is being created.
• The Projection Screen has been installed,
wired and the work for the proscenium is being
scheduled.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Construction is nearly complete in
the Art Room, Toilet rooms outside the
Art Room and the Discovery Lab.
• Rooms 110, 108 and 106 will
continue with the completion of
drywall; electrical is being roughed in
along with plumbing and the VRV
System is being piped.
• Construction in room 302 will be
nearly complete with the installation of
casework and flooring.
Senior High School
• Ceilings and lights in room 211 and the
corridor on the 2nd floor will be installed.
• Electrical work is being roughed in the
Art Room and will be followed by floor
mitigation, casework and flooring.
• Saw-cutting and under slab plumbing
and electrical work will be installed in the
Kitchen; framing drywall and electrical
rough-in will continue.
• Sidewalk in the Courtyard will be
installed.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Middle School
• The projection screen proscenium is
scheduled to be installed over
Christmas Break.
• DiFiore will punchout the Turf Field
and begin removing temporary fencing
and equipment.
Lima Elementary
• Masonry work for the elevator shaft will
continue along with work in room 210,
206 and 116.
• Ductwork will begin being installed in
rooms 210 and 206.
• The installation of the elevator is
scheduled to begin in November.
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
Main Entrance - High School
Main Entrance – High School
Main Entrance Vestibule – High School
High School Lobby
Girls Pool Locker Room – High School
2nd Floor Addition (201A) – High School
Courtyard – High School
Art Room – High School
Art Room – High School
Turf Field – Middle School
Repair Bays – Transportation Building
Parking Lot Addition - Transportation Center
Repair Bays – Transportation Building
Art Room – Manor
Art Room – Manor
Faculty Lounge – Manor
Screening Topsoil – Middle SchoolSensory Room – Manor
Work Room – Manor
Discovery Room – Manor
Projection Screen – Middle School Auditorium
Room 210 – Lima