GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
1
GLAST Large Area TelescopeGLAST Large Area Telescope
WBS 4.1.BInstrument Science Operations Center Monthly Status Review1 September 2005
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
2
ISOC ManagementISOC Management
ISOC Operations Facility– Met with SLAC management to review plans for Ops facility in
Building 84, near existing Dataflow Lab– Preparing SLAC infrastructure proposal for construction of
operations facility– ISOC staff will be relocated to Building 84, coincident with
KIPAC move to new building– To be completed in 2006
Coordination activities– GLAST/SCCS meetings
• Managing ITAR-controlled data and computers• Offline processing – GLAST/BaBar resource sharing
– Increasing I&T coordination • Fastcopy data transport to SLAC during NRL, SASS tests• LAT Configuration tracking and control
– Operations Planning meetings• User review of FSW
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
3
ISOC Ground Test PreparationsISOC Ground Test Preparations
Continued Ground Readiness Test Team (GRTT) participation with GSFC and other ground elements
– Preliminary test objectives and procedures agreed to for GRT3 and GRT4
– Dates of GRT3 and GRT4 swapped to give more time to prepare for GRT3 (a much larger test for ground elements)
Next GRT - GRT4 on 25 Oct 05
– Regression test for ISOC - no new functionality
– New SW release (# 1.1) to be made ~ 4 wks before test
• No new functions to be tested, but incorporate several improvements since GRT2
• Will verify before test that functions needed for GRT4 still work in release 1.1
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
4
ISOC Ground Test Preparations –ISOC Ground Test Preparations –GRT 3 on 6 Dec 05GRT 3 on 6 Dec 05
New ISOC functions in GRT3– Ingest new data products from MOC into ISOC database
• New orbital data products• Integrated Science Timeline
– Trending data ingest and display/plot– Logging
• Log receipt/transmission of data products• Limit exceeded messages• Operator comments• Includes database and web interface
– Science Data Processing• Ingest L0 Process into L1 data
Package into ICD-compliant L1 product Send to GSSC• Provided small sample of L0 data to PSS• Still need to create large L0 sample to use in GRT3
– Cover typical pass size (~ 2GByte/pass)– With overlap between passes– Needed at least 1 month before test (by early Nov)
SW release 1.2 to be completed 9 Nov 05 (~4 weeks before GRT3)– New functions to be acceptance tested locally before release– Began acceptance test preparations for release 1.2
• Enhanced requirements database to support new tests• Identifying requirements to include in 1.2
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
5
ISOC Ground Test Preparations –ISOC Ground Test Preparations –Ground System Discrepancy Review BoardGround System Discrepancy Review Board
GSDRB began in August– Includes all ground elements– Primary focus is ground system problems identified in
GRTs, ETEs, Mission Sims– All problems addressed by GSDRB tracked via SOARS
(GSFC discrepancy reporting tool)– Met twice in August
• Agreed on roles and procedures of GSDRB• Dispositioned all pending SOARS reports
– Generally to meet once/month or more often as needed– Next meeting 12 Sept 05
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
6
Software DevelopmentSoftware Development
Next release planned for 22 September 2005– Interim release to bring production installation up to head
of development tree (release # 1.1)– Adds retrieval of CCSDS packet groups from raw archive –
required for science data processing in GRT3. Began integrating ISOC code modules into LICOS framework
for I&T support.– CCSDS packet archive file object used for recording
telemetry data from the VSC.– ISOC raw-archive implementation used for data-storage
organization and retrieval.– Flight-like packaging of data and use of FASTCopy for
transfers from I&T equipment to SLAC Central Unix.
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
7
Software Development (cont’d.)Software Development (cont’d.)
I&T support (cont’d)– Modified FASTCopy-automation software and database to
operate on non-Oracle RDBMS (PostgreSQL) for use on I&T mobile rack.
– Packaged ISOC software and required external packages for automated installation on mobile rack.
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
8
GOWG/GIMGOM ActivityGOWG/GIMGOM Activity
Ops Data Products ICD issues– Handling of priority and normal command requests by
GSSC– Change to project database delivery to ISOC - will be
delivered as a directory of “tarred” files, which is then “tarred” with a manifest
– Reviewed and approved new Science Timeline format– Deleted Spacecraft Timeline because information is
provided to ISOC through other means and the timeline itself is not used by the MOC
– Discussed revising As-Flown Timeline to ensure it contains useful information
Finalized agenda for the Sept Ops TIM
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
9
GOWG/GIMGOM Activity (cont.)GOWG/GIMGOM Activity (cont.)
Aura Mission Planning tool (used on Aura project) – MOC evaluating use of tool (with modifications) during
L&EO and on-orbit ops– Pass plan used for routine operations with ISOC
command requests handled through change requests – would still have GSSC approval of requests
Relative Time Sequence (RTS) allocation - 35 slots with 29 for S/C and 6 allocated for use by LAT and GBM
Operation Agreements - interface information between the ground elements that does not belong in ICD
Confirmation of PROC requests by GSSC– GSSC confirms PROC requests (real time command
requests) from ISOC are valid but does not validate PROC contents
– List of PROC requests to be added to ICD – Use of rejection messages will be described in MOA
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
10
ISOC Database ActivitiesISOC Database Activities
LAT Command and Telemetry database– Updating LAT T&C DB for housekeeping trending, as
updates occur in conjunction with FSW releases– Working with I&T on control of telemetry limits and cal
curves to be shared between LICOS for (SLAC and NRL testing) and dbx files (for SASS testing and flight ops).
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
11
LAT Configuration Control and TrackingLAT Configuration Control and Tracking
Second TIM held on 15 August
– Operations concept review
– LAT configuration data flow through existing and proposed tools
– MOOT/MOOD (config management tools and database) design progress
– LICOS interfaces
– Instrument turn-on sequence
– Agenda: http://confluence.slac.stanford.edu/display/ISOC/TIM%2C+15+Aug+2005
First draft of all MOOD database tables nearing completion
– Next: make test database to operate with FSW tools
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
12
Issues and ConcernsIssues and Concerns
Handling ITAR-restricted data– Spacecraft telemetry (which contains 96 LAT analog
telemetry points + bilevel telemetry)– Optional approaches
• ITAR-compliant restricted network for GLAST data, firewalled from SCCS servers, filesystems and databases
• Use ITOS capabilities at MOC to extract and deliver LAT-specific telemetry as sequential prints. ICD change required.
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
13
Future ActivitiesFuture Activities
Ops TIM – 14-15 September 2005 GRT4 – 25 October 2005 GRT3 – 6 December 2005 MOR – 15-16 March 2006
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
14
Level 3 Milestone CountLevel 3 Milestone Count
0
1
2
DE
C05
JAN
05
FE
B05
MA
R05
AP
R05
JUN
05
JUL0
5
Plan
Actual
Forecast
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
15
Level 3 Milestone ListLevel 3 Milestone List
WPNO ActivityDescription
BaselineFinish
-2mVar
-1mVar
DeltaBslnVar
EarlyFinish
4.1.B ISOC
Ground System Interface Test start 06/15/05* -9 -9 -9 06/28/05A
Mission Operations Review 01/17/06* 0 0 0 01/17/06*
2005 2006FEBMARAPRMAYJUNJULAUGSEPOCTNOVDECJANFEBMARAPRMAYJUNJUL
© Primavera Systems, Inc.
Run Date 08/19/05 08:47
Data Date 08/01/05
GLAST LAT PROJECTLevel 3 Milestones
Baseline Variance (Organized by Subsystem)
LT-DZ: Baseline VarianceFL-D4: AV: Level 3 Milestones
Report #10Sheet 12
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
16
Milestone Variance ExplanationMilestone Variance Explanation
Schedule Impact Cost Impact Corrective Action
– None Required
GLAST LAT Project Monthly Status Review - ISOC, 1 September 2005
17
Cost ReportCost Report
Reporting Cost Incurred Estimated Cost Estimated Final UnfilledCategory Cost Orders
During Month Cum. to Date Detail Balance of Contractor Contract OutstandingActual Planned Actual Planned AUG05 SEP05 Contract Estimate Value
4.1.B LAT INSTRUMENT SCIENCE OPERATIONS CENTER4.1.B.1 PROJECT MANAGEMENT 2 5 171 181 5 2 9 188 188 04.1.B.2 PERFORMANCE ASSURANCE 0 0 0 6 0 0 6 6 6 04.1.B.3 MISSION & OPERATIONS PLANNING 0 0 101 101 0 0 0 101 101 04.1.B.4 LAT OPERATIONS FACILITY 0 0 16 16 0 0 0 16 16 04.1.B.5 IOC TEST 0 0 0 0 0 0 0 0 04.1.B.6 LAT PERFORMANCE VERIFICATION 0 0 24 24 0 0 0 24 24 0CAPW[3]Totals: 2 5 312 327 5 2 15 334 334 0