GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
1Presentation 8 of 12Integration and Test
GLAST Large Area Telescope:GLAST Large Area Telescope:
Pre-Environmental Test Review
Integration and Test
Ken FoutsSLAC
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
2Presentation 8 of 12Integration and Test
OverviewOverview
• Review Current Status– LAT Instrument Configuration– Procedure Status
• Review Plan for Environmental Test– Organization– Pathfinding Summary– LAT I&T Operations at NRL– EGSE/MGSE Readiness– Test Configurations and flow
• Schedule Review
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
3Presentation 8 of 12Integration and Test
Current ConfigurationCurrent Configuration• As built configuration
– LAT-DS-1624 LAT Top Assembly– Radiators– ACD, Radiator & LAT MLI
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
4Presentation 8 of 12Integration and Test
DocumentDocument TitleTitle StatusStatus
LAT-PS-03263-01 Fastener Installation and Torqueing Procedure Released
LAT-PS-04727-01 Connector Mate and Demate Released
LAT-MD-04601-01 LAT I&T eLog Book Implementation Plan Released
LAT-PS-03291-01 Flight Hardware Bag and Purge Procedure Released
LAT-PS-04436-01 AeroGo Bearing Reference Guide Released
LAT-PS-04511-04 LAT Data Collection Procedure Released
LAT-MD-01533-01 LAT EGSE Plan Released
I&T Process ProceduresI&T Process Procedures
I&T Standard Processes will continue to be used at NRLI&T Standard Processes will continue to be used at NRL
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
5Presentation 8 of 12Integration and Test
DocumentDocument TitleTitle StatusStatus
LAT-PS-6898 LAT Environmental Test Implementation Plan In Signoff
LAT-PS-07929-01 LAT Shipping Container Procedure Released
LAT-PS-07728 LAT Environmental Test Handling Procedure In Signoff
LAT-MD-02717-01 LAT Environmental Test Sequence Released
LAT-MD-01196-03 LAT Dynamics Test Plan Released
LAT-MD-01600-03 LAT Thermal Vacuum Test Plan Released
LAT-MD-02726-01 LAT EMI/EMC Test Plan Released
LAT-DS-7411 LAT Environmental Test Wiring Diagram Released
Key Documents for Environmental TestKey Documents for Environmental Test
Key Environmental Test Planning has been completedKey Environmental Test Planning has been completed
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
6Presentation 8 of 12Integration and Test
Environmental Test Configuration DrawingsEnvironmental Test Configuration Drawings
DrawingDrawing TitleTitle StatusStatus
LAT-DS-06188 Acoustic Test Configuration Assembly Released
LAT-DS-06185 Thermal-Vacuum Test Configuration Assembly Draft
LAT-DS-06187 Horizontal Vibration Test Configuration Assembly Released
LAT-DS-06190 Vertical Vibration Test Configuration Assembly Released
LAT-DS-06186 Handling Configuration Assembly Released
LAT-DS-06184 Transport Configuration Assembly Released
LAT-DS-06189 EMI/EMC Test Configuration Assembly Released
LAT-DS-06191 Mass Properties Configuration Assembly Draft
LAT Instrument Configuration for Environmental Tests is documentedLAT Instrument Configuration for Environmental Tests is documented
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
7Presentation 8 of 12Integration and Test
I&T DocumentationI&T Documentation
Drawings(Mechanical Assembly, Cabling, EGSE/MGSE
interface, etc.)
Test SequenceLAT-MD-00676
Assembly Instruction Data Sheet (AIDS)
LAT Environmental Test Plans
Electronic Logbooks(Component installation,
Mate/Demate, Etc.)
Non-Conformance Report (NCR)
QA and Archive
Test Performance and Operation PlanLAT-MD-02730
I&T Operating Processes and
Procedures
CM processes for document control, release and completion will be maintained.CM processes for document control, release and completion will be maintained.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
8Presentation 8 of 12Integration and Test
LAT Environmental Test OrganizationLAT Environmental Test Organization
Ken FoutsI&T Manager
E. Grove, Deputy
Dynamics TestJ. Ku
EMI/EMCM. Lovellette
TVACJ. Armiger
NRL OperationsP. Dizon
B. RaynorNRL Resource
Manager
Rqmts & PlanningK. Fouts
N. Johnson
Environmental Test Management Team is in place work planning and scheduling Environmental Test Management Team is in place work planning and scheduling
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
9Presentation 8 of 12Integration and Test
LAT I&T TeamLAT I&T Team
Mark Molini, S&E Associate - Mechanical
Dave Kiehl, S&E Technician - Mechanical
Eliazar OrtizMechanical Lead Engineer
Leo Manger, S&E Associate - Mechanical
Tom Neiland, S&E Technician - Mechanical
Brian GristElectrical Lead Engineer
Phuc Hoang, S&E Technician - Electrical
John Canfield, S&E Associate - Electrical
Albert Nguyen, Electrical Engineer
Subsystem I&T Support ACD – Martin Kocian/Dave
Thompson CAL - Eric Grove
DAQ – Gregg ThayerElec - Dave NelsonFSW - Mike DeKlotz
SAS - Richard DuboisTKR -Hiro Tajima
Controls - Shannon LeoneQA - Doug Bartholomew
Science Verification,
Analysis, and Calibration
Anders Borgland, Manager (SU-SLAC)
WBS 4.1.9.9
Mechanical Design Support
Marc Campell, Manager (SU-SLAC)
WBS 4.1.9.4
Particle TestGary Godfrey,
Manager (SU-SLAC)WBS 4.1.9.7
Online SoftwareRic Claus,
Manager (SU-SLAC)WBS 4.1.9.5
Selim TuviSoftware Developer
Bill OlsonMechanical Engineer
Eric CharlesSoftware Developer
Warren FockeEngineering Physicist
Jim PanettaEngineering Physicist
Lester MillerEngineering Physicist
LAT Integration and Test Ken Fouts, Manager (SU-SLAC)
Eric Grove, Deputy Manager (NRL) WBS 4.1.9, 4.1.9.1
LAT Collaboration I&T CoordinationEduardo do couto e
silva (SU-SLAC)
Roger Williams, S&E Associate - Electrical
Jeff TiceMaterial Logistics Lead
Domi Celestino, Inventory Clerk
Arthur ScholzMechanical Engineer
Drew Roberts, Electrical Engineering Contractor Patrick Young, Electrical Engineer
Larry WaiLAT I&T Data Manager
LAT I&T Team has a proven track record for safe program executionLAT I&T Team has a proven track record for safe program execution
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
10Presentation 8 of 12Integration and Test
Pathfinding Summary (1 of 2)Pathfinding Summary (1 of 2)LAT Pathfinding Activity Documented in LAT-MD-07727Objective: Identify and mitigate mechanical operations/handling risk.• Pathfinder Lifting Operations
– Installation into and Removal from Shipping Container with the GPR.– Installation into and removal from the Test Stand with GPR– Onto and off of the Vibe Table with the GPR– Test Stand Turnover with Complete Mass Simulator and SLAC lift
slings– Installation of the rotated test stand and LAT onto the TVAC
table/Trolley• Pathfinder Move Operations
– Transport weighted shipping container– Move LAT in the test stand from clean tent to Sine Vibe.– Move LAT and test stand from clean tent to EMI test chamber. – Move LAT and test into Acoustic test chamber.– Move LAT and test stand TVAC staging area and into chamber.
LAT-PS-07728 LAT Handling Procedure was developed during PathfindingLAT-PS-07728 LAT Handling Procedure was developed during Pathfinding
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
11Presentation 8 of 12Integration and Test
Pathfinding Summary (2 of 2)Pathfinding Summary (2 of 2)• Pathfinding Miscellaneous Operations/Installations
– Radiator installation/removal procedures including timed trial runs (adhesive pot life)
– TVAC prep work – mount S/C simulator sink plate– TVAC configure – another rotation and install on Table/Cart
• Improved handling procedures for installation and use of test stand extensions
– Installation of TVAC STE – heater cages, ACD sink plates– Transport into TVAC chamber and working around LAT and STE inside
chamber.– TVAC cable installation and routing
Pathfinding activity mitigated potential risk for critical handling operationsPathfinding activity mitigated potential risk for critical handling operations
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
12Presentation 8 of 12Integration and Test
I&T Operating PlanI&T Operating Plan• The detailed LAT I&T schedule is maintained in MS Project by the I&T Scheduler.
– Schedules will be updated daily via the afternoon meeting with progress from that day. • NRL Operations
– Normal work time will be 7:00am-8:00pm. “Shifts” will run nominally 7:00am-4:00pm and 12:00am-8:00pm. Shifts will be adjusted to go around the clock as the need arises.
– Daily morning meeting at 7:00am and afternoon meeting at 3:00pm.– Daily phone tag-up to SLAC at 4:00pm.– Minimum staff when the instrument is under test is 2 LAT Electrical Test staff
members.– TVAC will be staffed 24/7– Extended shifts and/or Saturdays will be used to maintain schedule as required.
• LAT Instrument Handling– LAT will be configured in the portable clean tent whenever possible.– The LAT will be bagged to maintain cleanliness when outside of the controlled
environment.– Cleanroom and ESD protocol will be maintained during all LAT handling operations.
NRL Operating plan is similar to SLAC OperationsNRL Operating plan is similar to SLAC Operations
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
13Presentation 8 of 12Integration and Test
Troubleshooting in I&TTroubleshooting in I&T• No troubleshooting will be done without appropriate disposition on an NCR.• When an anomaly occurs:
– The test set-up is frozen– The instrument and test equipment is safed.– The test set-up and instrument configuration is reviewed and
documented by the Test Conductor.– Test conductor notifies the TD, Subsystem Engineer and QA.
• QA initiates an NCR with information from TC and convenes MRB.– At a minimum, MRB consists of the Test Director, Test Conductor,
Subsystem Engineer and QA.• MRB will provide detailed disposition for troubleshooting.• The test procedure will be redlined or a separate procedure will be written
(as defined by MRB) to document the troubleshooting activity defined in the disposition.
Troubleshooting will be done in accordance with the I&T Implementation PlanTroubleshooting will be done in accordance with the I&T Implementation Plan
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
14Presentation 8 of 12Integration and Test
Problem Resolution in I&TProblem Resolution in I&T
Test EquipmentProblem
Test Procedure/Set Up
Error
Test ConductorError
False Alarm!
PossibleFlight HW Failure
PossibleFlight SW
Failure
HW MRBTroubleshoot
HW
SW JIRATroubleshoot
SW
Flight HWFlight HWDamagedDamaged
IssueClosedProblem Observed
Inspection, Testing, Data Analysis
(HW, SW, Data)
Non Conformance Non Conformance Report (NCR)Report (NCR)
Categorizeby
Test Conductor and/or
Test Director
Yes
No
Root Cause IdentifiedCorrective Actions
CCB Action
Root Cause IdentifiedCorrective Actions
CorrectiveCorrectiveActionsActions
Problem Resolution will continue to use the NCR processProblem Resolution will continue to use the NCR process
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
15Presentation 8 of 12Integration and Test
Network Configuration for LAT Operations at NRLNetwork Configuration for LAT Operations at NRL
VSC and Power Rack will move with the LAT InstrumentVSC and Power Rack will move with the LAT Instrument
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
16Presentation 8 of 12Integration and Test
LAT I&T CCB Controls Test ConfigurationLAT I&T CCB Controls Test Configuration
• LAT-MD-03492 LAT I&T CM/CCB Procedure establishes the process for configuration control of flight and test software installed on the LAT and EGSE test stations.
• LAT I&T CCB is held on an as needed basis and requires the following minimum representation: I&T Manager (CCB Chair)
I&T Electrical Test Lead
Systems Engineering
Online Manager
Flight Software
Quality Assurance
DAQ Electronics
Software packages listed below are controlled by CCB in the locations listed
LAT I&T CCB has been successful in controlling software installation/changesLAT I&T CCB has been successful in controlling software installation/changes
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
17Presentation 8 of 12Integration and Test
Environmental Test MGSE/STEEnvironmental Test MGSE/STE• Transport Container
– Manufacture complete; Analyses complete– Proof test complete– Demo Road Test complete– Available at SLAC
• Test Interface Plate– Complete
• Test Stand/Spreader Bars– Complete, used in pathfinding
• TVAC Sink Plates – ACD & S/C Simulator– Complete, used in pathfinding 2
• TVAC Cal-Rod Cage– Complete, used in pathfinding 2
• Acoustic Simulator– Complete
• Mass Properties Plate– Load Cell Interface in manufacture – Complete
All MGSE has been used in dry run or pathfinding activityAll MGSE has been used in dry run or pathfinding activity
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
18Presentation 8 of 12Integration and Test
GPR, Lift Fixture Proof Test at SLACGPR, Lift Fixture Proof Test at SLAC
Rotation Stand w/ GPR Proof Test Proof Test of the 4x4 Lift Fixture and GPR
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
19Presentation 8 of 12Integration and Test
FacilitiesFacilities• Thermal Vacuum Test
– Cables and Port Plates – complete– Mechanical analyses complete– Trolley (cart) – complete, used in pathfinding– Chamber rails upgrade – complete and proof tested– Pathfinding 2 – complete– Chamber refurb, cleaning and recommissioning - complete– GSE bakeout and STE Validation – ECD: 5/16/06
• Acoustic Test– Ramp manufacture complete
• Vibration Test– Expander head load frame procurement - delivered– Load frame manufacture – complete– Installation and proof test - complete
• EMI/EMC Test– Ramp manufacture – complete, used in pathfinding
NRL Facility has been upgraded to meet LAT Operational RequirementsNRL Facility has been upgraded to meet LAT Operational Requirements
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
20Presentation 8 of 12Integration and Test
Environmental Test SequenceEnvironmental Test Sequence
FinalPre-TV
Sine VibeL
Mount Radiators
AcousticL
T-CycleT-Bal Remove Radiators
Weight CG
Ship to SpectrumCL L
Receive, Unpack T
L
Pack LATCSSC S
BaselineFC S
at SLAC
Ship to NRL
LLLPre Post-Axis
L Limited Performance TestComprehensive Performance TestSVAC Test
CS
F
T
E
TCS Functional TestEMI/EMC Emissions/Susceptibility Test
L Limited Performance TestComprehensive Performance TestSVAC Test
CS
F
T
E
LAT Functional and FSW TestTCS Functional TestEMI/EMC Emissions/Susceptibility Test
Rev date: 24 April 2006
F
NRLPost-Ship
CEMI/EMCL E L
TESTING IN THERMAL VAC CHAMBER
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
21Presentation 8 of 12Integration and Test
Sine Vibe ConfigurationSine Vibe Configuration
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
22Presentation 8 of 12Integration and Test
Vibration Facility LayouVibration Facility Layou
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
23Presentation 8 of 12Integration and Test
Radiator InstallationRadiator Installation
Radiator installation test
Radiator flange access
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
24Presentation 8 of 12Integration and Test
EMI/EMC Test ConfigurationEMI/EMC Test Configuration
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
25Presentation 8 of 12Integration and Test
EMI Chamber LayoutEMI Chamber Layout
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
26Presentation 8 of 12Integration and Test
Acoustic Test ConfigurationAcoustic Test Configuration
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
27Presentation 8 of 12Integration and Test
Acoustic Test LayoutAcoustic Test Layout
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
28Presentation 8 of 12Integration and Test
TVAC ConfigurationTVAC Configuration
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
29Presentation 8 of 12Integration and Test
Thermal STEThermal STE
S/C Sink Plate Configuration
Heater Cage Configuration
Installation of ACD Sink Plate Panels (5)
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
30Presentation 8 of 12Integration and Test
TVAC LayoutTVAC Layout
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
31Presentation 8 of 12Integration and Test
Environmental Test Schedule (1 of 3)Environmental Test Schedule (1 of 3)ID Task Name Start Finish
1 Environmental Test 5/15/06 9/7/062 Deliver LAT/Offload/Set-up 5/15/06 5/16/063 CPT 5/17/06 5/22/064 Install FSW B0-6-9 5/22/06 5/24/065 Pre Environmental Test Review (PER) 5/25/06 5/25/066 Sine Vibe Test 5/24/06 6/7/067 Sine Vibe Test Readiness Review (TRR) 5/24/06 5/24/068 Pre-test Activities 5/25/06 5/25/069 Z-Axis Vibration Test 5/26/06 5/31/0610 Low Level Signiture Sine Sweep to 150 Hz 5/26/06 5/26/0611 Half-level run to 50 Hz 5/26/06 5/26/0612 Full-level run to 50 Hz 5/30/06 5/30/0613 Low-level signature sine sweep to 150 Hz 5/30/06 5/30/0614 Run LPT 5/30/06 5/31/0615 Post Z-Test/ Pre X-Test Activities 5/31/06 5/31/0616 X-Axis Vibration Test 6/1/06 6/2/0617 Low Level Signiture Sine Sweep to 150 Hz 6/1/06 6/1/0618 Half-level run to 50 Hz 6/1/06 6/1/0619 Full-level run to 50 Hz 6/1/06 6/1/0620 Low-level signature sine sweep to 150 Hz 6/1/06 6/1/0621 Run LPT 6/2/06 6/2/0622 Post X-Test / Pre Y-Test Activities 6/5/06 6/5/0623 Y-Axis Vibration Test 6/5/06 6/7/0624 Low Level Signiture Sine Sweep to 150 Hz 6/5/06 6/5/0625 Half-level run to 50 Hz 6/5/06 6/5/0626 Full-level run to 50 Hz 6/6/06 6/6/0627 Low-level signature sine sweep to 150 Hz 6/6/06 6/6/0628 Run LPT 6/6/06 6/7/0629 Post Y-test activities 6/7/06 6/7/0630 Radiator Installation 6/8/06 6/12/0631 Install Radiators 6/8/06 6/9/0632 Radiator Pull Test 6/12/06 6/12/0633 LAT16x Survival Heater Test 6/12/06 6/12/0634 EMI/EMC Test Readiness Review (TRR) 6/9/06 6/9/06
5/25
5/24
6/9
5/14 5/21 5/28 6/4 6/11 6/18May June
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
32Presentation 8 of 12Integration and Test
Environmental Test Schedule (2 of 3)Environmental Test Schedule (2 of 3)ID Task Name Start Finish
35 EMI/EMC Test 6/13/06 6/27/0636 Preliminary setup 6/13/06 6/13/0637 Pre-EMI Functional Test 6/14/06 6/14/0638 CE102 Conduct Emissions, Power Leads 10kHz to 10MHz DAQ Interface 6/15/06 6/15/0639 CE102 Conduct Emissions, Power Leads 10kHz to 10MHz SIU Interface 6/15/06 6/16/0640 Conduct Emission , Time Domain, 150MHz bandwidth, DAQ Interface 6/16/06 6/19/0641 Conduct Emission , Time Domain, 150MHz bandwidth, SIU Interface 6/19/06 6/19/0642 CS102 Conduct Susceptability, Pwr Leads 10 kHz to 10 MHz, DAQ Interface 6/20/06 6/20/0643 CS102 Conduct Susceptability, Pwr Leads 10 kHz to 10 MHz,SIU Interface 6/20/06 6/21/0644 CSCM Conducted Susceptibility, Common Mode, 10 kHz to 150 MHz at LAT-DAQ Interface6/21/06 6/22/0645 CS06 Conducted Susceptibility, Spike, Power Leads at LAT-DAQ Interface 6/22/06 6/22/0646 CS06 Conducted Susceptibility, Spike, Power Leads at LAT-SIU Interface 6/23/06 6/23/0647 RE101 Radiated Emissions, Magnetic Field, 20 Hz to 50 kHz 6/23/06 6/26/0648 RE102 Radiated Emissions, Electric Field, 10 kHz to 18 GHz 6/26/06 6/26/0649 RS101 Radiated Susceptibility, Magnetic Field, 20 Hz to 50 kHz 6/27/06 6/27/0650 RS103 Radiated Susceptibility, Electric Field, 30 MHz to 18 GHz 6/27/06 6/27/0651 Acoustic Test Readiness Review (TRR) 6/23/06 6/23/0652 Acoustic Test 6/28/06 7/7/0653 Acoustic Test Prep/Checkout 6/28/06 6/28/0654 Run LPT 6/29/06 6/29/0655 Low Level run at -6db for 30 sec (establish pre-test signature, review data) 6/30/06 6/30/0656 Full Level run at -0dB for 60 seconds 7/3/06 7/3/0657 Low Level run at -6dB for 30 sec ( signature check, review data, complete axis) 7/5/06 7/5/0658 Run LPT 7/6/06 7/6/0659 Post Acoustic Test activities 7/7/06 7/7/0660 TVAC Test Readiness Review (TRR) 7/5/06 7/5/06
6/23
7/5
6/11 6/18 6/25 7/2 7/9 7/16June July
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
33Presentation 8 of 12Integration and Test
Environmental Test Schedule (3 of 3)Environmental Test Schedule (3 of 3)ID Task Name Start Finish
61 TVAC 7/8/06 8/24/0662 TVAC Prep/Check-out 7/8/06 7/12/0663 TVAC Open Door Test 7/13/06 7/15/0664 Chamber pump down 7/16/06 7/16/0665 Pre-bake 7/17/06 7/17/0666 Bake-out 7/18/06 7/18/0667 Hot Operational thermal balance 7/19/06 7/20/0668 Hot Operational TCS Testing 7/21/06 7/29/0669 RIT Control with Primary reservoir heaters & Symmetric Orbit Average Load 7/21/06 7/23/0670 Peak Power Testin 7/24/06 7/25/0671 RIT Control with Redundant Reservoir Heaters & Transient Loadin 7/26/06 7/27/0672 Hot performance Testing (PFQ) and Hot Turn On/Off/On 7/28/06 7/29/0673 Cold Operational TCS testing 7/30/06 8/7/0674 Cold survival thermal balanvce and radiator/grid heater functioning 7/30/06 7/31/0675 Cold performance Testing (PFQ) and Cold Turn On 8/1/06 8/2/0676 Cold Operational Thermal balance 8/3/06 8/4/0677 RIT Control with Primary reservoir Heaters and Symmetric Orbit Average Load 8/5/06 8/5/0678 RIT Control with Redundant reservoir Heaters and Symmetric Orbit Average Load8/6/06 8/6/0679 TCS Parameter Uploads 8/7/06 8/7/0680 Thermal Cycling 8/8/06 8/13/0681 Final Hot CPT 8/14/06 8/18/0682 Final Cold CPT 8/19/06 8/23/0683 Transition to Ambient 8/24/06 8/24/0684 Final CPT 8/25/06 8/29/0685 Remove Radiators 8/30/06 8/31/0686 Weight & CG 9/1/06 9/4/0687 Instrument Check 9/1/06 9/1/0688 Align LAT on Test Platform 9/1/06 9/1/0689 Measure overall Mass & cg 9/1/06 9/4/0690 Rotate LAT 180 degrees and align to test platform 9/4/06 9/4/0691 Measure overall mass & cg 9/4/06 9/4/0692 Pack and Ship 9/5/06 9/7/06
7/2 7/9 7/16 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 9/17July August September
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
34Presentation 8 of 12Integration and Test
Staffing PlanStaffing Plan• Current staffing plan for NRL:
– Single long shift 5-6 days per week for Sine Vibe, Acoustic, EMI/EMC tests.
– 24/7 staffing for TVAC duration.– SLAC will average 14 people including
• I&T Management• I&T Electrical • I&T Mechanical • Mechanical Design• Online• SVAC• QA• DAQ
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
35Presentation 8 of 12Integration and Test
Staffing Plan (1 of 2)Staffing Plan (1 of 2)5/1/2006 5/29/2006 6/5/2006 6/12/2006 6/19/2006 6/26/2006 7/3/2006 7/10/2006 7/17/2006 7/24/2006 7/31/2006 8/7/2006 8/14/2006 8/21/2006 8/28/2006 9/4/2006
Sine Vibe TestInstall RadiatorsEMI Test Acoustic Test TVAC Prep TVAC Open Door Remove RadiatorsWt & CG Ship
I&T ElectricalB. Grist 1 1 1 1 1 1 1 1 1 1J. Canfield 1 1 1 1 1 1 1 1 1 1D. Roberts 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1P. Hoang 1 1 1 1 1 1 1 1 1P. Young 1 1 1 1 1 1 1 1 1 1R. Williams 1 1 1 1 1 1 1 1 1A. Nguyen 1 1 1 1 1 1 1 1 1 1
Sub-Total 5 5 5 5 4 4 5 5 5 5 5 5 5 5 5
I&T MechanicalE. Ortiz 1 1 1 1 1 1 1 1L. Manger 1 1 1 1 1 1 1 1T. Neiland 1 1 1 1 1 1 1 1 1 1 1 1D. Kiehl 1 1 1 1 1 1 1 1M. Molini 1 1 1 1 1 1 1 1 1
Sub-Total 3 4 4 3 3 4 3 4 0 0 0 4 4 4 5
QAJ. Cullinan 1 1 1D. Bartholomew 1 1 1YC Liew 1 1 1E. Rodriguez 1 1 1J. Marshall 1 1 1
Sub-Total 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
I&T OnlineR. Claus 1 1 1 1J. Panetta 1 1 1 1S. Tuvi 1 1L. Miller 1 1 1
Sub-Total 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
TVAC Test
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
36Presentation 8 of 12Integration and Test
I&T SVACA. Borgland 1E. Charles 1 1 1W. Focke 1 1
Sub-Total 1 1 1 0 0 0 0 0 2 1 0 0 0 0 0
Mech/ThermalM. Campell 1 1 1 1 1 1B. Olson 1 1 1 1 1 1 1 1 1 1 1J. Ku 1 1 1 1 1J. Goodman 1 1 1 1 1 1 1J. Wang 1 1 1 1 1 1 1
Sub-Total 3 3 1 3 2 4 3 3 2 2 2 2 2 3 1
DAQJ. ThayerG. Thayer
Sub-Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
System EngineeringP. Hascall 1 1 1 1R. Baun 1 1 1R. Bright 1 1 1 1R. Bielawski 1 1 1 1
Sub-Total 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
ManagementK. Fouts 1 1 1 1 1 1L. KlaisnerD. Horn
Sub-Total 0 1 0 0 0 0 1 1 0 1 0 1 0 1 0
As Required
5/1/2006 5/29/2006 6/5/2006 6/12/2006 6/19/2006 6/26/2006 7/3/2006 7/10/2006 7/17/2006 7/24/2006 7/31/2006 8/7/2006 8/14/2006 8/21/2006 8/28/2006 9/4/2006Sine Vibe TestInstall RadiatorsEMI Test Acoustic Test TVAC Prep TVAC Open Door Remove RadiatorsWt & CG ShipTVAC Test
Staffing Plan (2 of 2)Staffing Plan (2 of 2)
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
37Presentation 8 of 12Integration and Test
Environmental Test Staffing SummaryEnvironmental Test Staffing SummarySLAC Staffing at NRL
0
2
4
6
8
10
12
14
16
18
5/29/2
006
6/5/20
06
6/12/2
006
6/19/2
006
6/26/2
006
7/3/20
06
7/10/2
006
7/17/2
006
7/24/2
006
7/31/2
006
8/7/20
06
8/14/2
006
8/21/2
006
8/28/2
006
9/4/20
06
Tota
l FTE
at N
RL
EMI Test TVAC TestAcoustic TestVibe Test WT/CG Ship
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review
38Presentation 8 of 12Integration and Test
SummarySummary• The LAT baseline performance has been demonstrated post
shipment to NRL.• The LAT instrument as-built configuration is in accordance with
current engineering.• Documentation, preparation and pathfinding for handling and
configuring the LAT for Environmental Test have been completed.• All EGSE and MGSE has been identified and its use has been
demonstrated.• LAT I&T has completed the necessary preparation to begin the LAT
Instrument Environmental Test.