Classification: Open 2016-11-30
Stavanger 30.11.2016
Gina Krog Frode Haldorsen – Topside Project Manager
Slide 2
Gina Krog – Field Development
Link: Video of Gina Krog Field Development
Classification: Open 2016-11-30
Slide 3
AGENDA
Classification: Open 2016-11-30
Video - Gina Krog Field Development (2,05 min)
Gina Krog Field Development
Gina Krog Sub-projects
Project Management Road Map
Video of Gina Krog Topside Sail Away from Korea (1,00 min)
Video of Gina Krog Topside Installation (1,00 min)
Slide 4
Gina Krog (1847 – 1916)
From Karmøy but born at Flakstad in Lofoten
Gina fought for women’s right in the
workplace, society and politics. She
believed that women should have the
same right-to-vote as men and her dream
was realised in 1913.
The Norwegian Ministry of Petroleum and
Energy decided to rename the Dagny
field to the Gina Krog field on 8 March
2013.
Classification: Open 2016-11-30
Slide 6
License owners: Statoil Petroleum AS: 58,7%
Total E&P Norge AS: 30,0%
PGNiG Upstream International AS: 8,0%
Aker BP ASA: 3,3%
Gina Krog Field Development
Classification: Open 2016-11-30
Slide 7
Gina Krog Field Development
Gina Krog
Floating Storage
Offloading (FSO)
14 Wells
Sleipner
Kårstø
Condensate pipeline to Kårstø
Gassled to Easington, Emden,
Dornum and Seebrugge
Gina Krog rich gas to Sleipner
Gassled from Kollsnes,
Zeepipe IIA
Import gas for Gina
Krog gas injection
Gina Krog stabilized
oil to FSO
Gina Krog oil, gas and
condensate reservoir
Shuttle tanker to
oil refinery
Jack-up
drilling rig
Classification: Open 2016-11-30
Gassled Area D
Gina Krog Value Chain
Gina Krog Sleipner Rich gas Sales gas
Kårstø
To market
To market
To UK and
Europe markets
NGL
Condensate
FSO
Oil
Unstable
condensate
Shuttle
tanker to
refineries
Future tie-ins to
Gina Krog Dry gas from
Zeepipe IIA
Wells
Well stream
Rich gas
Unstable condensate
Stabilized oil
Condensate
NGL
Sales gas/dry gas
Slide 8 Classification: Open 2016-11-30
Estimated oil and gas reserves: 225 million barrels
Oil production capacity: 10 kSm3/d
Gas production capacity: 9 MSm3/d
Number of wells: 14
8 horizontal for oil production, 3 for gas production and 3 for gas injection
Living quarters: 70 cabins
Normal manning: 20 persons
Oil export to Floating Storage and Offloading (FSO)
Gas export to Sleipner A
Gina Krog Field Development
Slide 9
Main characteristics
Gas discovery in 1974 and oil discovery in 2008-11
Plan for development and operation (PDO) approved May 2013
Total investment 31 BNOK
Drilling started July 2015 and production start is planned Q2 2017
Classification: Open 2016-11-30
Gina Krog Drilling & Well
• Contract with Maersk Drilling
• Maersk Integrator, CJ-70 jack-up drilling rig
• Drilling start July 2015
• 14 wells will be drilled
− 8 horizontal oil wells
− 3 gas producers
− 3 gas injector wells
• 4 wells are completed (no. 5 ongoing)
• Total well length approx. 74.000 m
Slide 11 Classification: Open 2016-11-30
Gina Krog SURF (Subsea, umbilical, riser, flowlines)
Slide 12 Classification: Open 2016-11-30
27,5 km 24,9 km
2,5 km
Gina Krog Floating Storage Offloading (FSO)
Slide 13 Classification: Open 2016-11-30
• Sembawang Shipyard (Singapore)
to convert the tanker Randgrid into
an FSO.
• The FSO will be used for Gina
Krog under a charter contract
between Teekay and Statoil.
• Major conversion works include
installation of a new helideck, hull
reinforcements, refurbishment of
submersible turret loading (STL),
compartment, installation of
offshore crane, loading hose reel
package and azimuth thruster.
N
C04
Riser ESV
Balcony
M24
Inlet heater and blow-
down valve
arrangement
C05/ C06
EV/HV and Pig Receiver
Balconies
M22
Tie-in's to exist.
process
Slide 14 Classification: Open 2016-11-30
Gina Krog Sleipner Modifications
Gina Krog Jacket
Slide 15 Classification: Open 2016-11-30
• Heerema Vlissingen (Netherlands): Engineering, procurement and construction
• Jacket (17.000 ton) - Launched in July 2015
• Pre- drilling module (155 ton) – Installed July 2015
• Jacked - Fixed to the sea bed with 18 piles (pile length approx. 90)
• Drilling of the first well commenced after installation of the pre-drilling module.
Gina Krog Topside
Slide 16 Classification: Open 2016-11-30
• Contract signed Feb. 2013
• Sail away from Korea 25 June 2016
• No serious HSE incident in Korea
• 5 Modules (MSF, PM, UM, FB, LQ)
• Some key numbers:
o Topside weight 18.000 tones
o 2,1 million engineering man hours
o 3,8 million construction man hours
o 110.000 commissioning man hours
• Living Quarter (Stord):
o 70 cabins (+20)
o 2100 tones
• Hook-up and completion offshore
ongoing
EPCH contract between Statoil and DSME (Daewoo Shipbuilding & Marine Engineering)
Sub-contractors to DSME: Aker Engineering International, Aker Solutions MMO, Apply Leirvik
DSME yard in Okpo, South-Korea
HSE Training Centre
Fire station
Trust hall
Daewoo Hospital
Outfitting area
Nue Tae
Production centre
Support Centre
DSME Engineering –
Harmony Centre
Heavy Zone G1 & G2
Main Gate
West Gate
East Gate
South Gate
Global Center
Slide 17 Classification: Open 2016-11-30
The Project Management Road Map
Main
Challenges
Cross Functional
Management &
Leadership
Success
Factors
Slide 18 Classification: Open 2016-11-30
HSE
No serious incident in the Gina Krog
project
Safety first
Expectation and confidence for all
project personnel to act as Statoil’s
Safety Ambassadors
Safety campaigns - management and
workers together
It’s all about us, it’s about people
and the environment
Slide 20 Classification: Open 2016-11-30
Openness and
trust are
essential in order
to deliver on time
and quality
Create common
arenas for
multidiscipline
and
multifunctional
collaboration
Respect each
other’s time –
fight bureaucracy
and lack of timely
feedback
Understand your
role and
contribution to
ensure Gina
Krog success
Collaboration
I am committed to deliver on the
Gina Krog project goals
Slide 21 Classification: Open 2016-11-30
Time is of the essence – respect
the project milestones
Search for simplifications and
standardisations in order to secure cost
reduction (Be a “change agent”)
Secure required quality and accept
good enough solutions
Schedule, cost and quality
Always time for safe behaviour
Slide 22 Classification: Open 2016-11-30
Challenges
HSE
Several large and complex building structures (new-build and modifications)
World wide activity
Integrated planning and communication/cooperation between contractors
Quality and timely delivery of engineering and critical equipment
Ensure minimum carry over work into offshore hook-up phase
Slide 23 Classification: Open 2016-11-30
Cross functional management
Project execution strategy and model
Follow-up strategy and methodology
Ensure reliable reporting and focus on risk mitigation
Take timely decisions
Hans-on and hands-in
Secure quality and delivery of engineering and procurement to construction
Slide 24 Classification: Open 2016-11-30
Leadership in action
Slide 25 Classification: Open 2016-11-30
Focus on the goal, your delivery and the success criteria
Develop your team and empower people
Secure collaboration and integration
Build trust and create willpower
Build relationships to selected stakeholders
Communication internally and externally
Cross functional leadership
Classification: Internal Slide 26 Classification: Open 2016-11-30
Key take away
HSE – It’s all about us, it’s about people
and the environment
Quality and delivery of engineering and
procurement to construction
Be hands-in, take timely decisions
Do not ignore leadership performance,
build trust and secure collaboration
Slide 29
Gina Krog Topside Sail Away
Heavy transport performed by TPI Megaline
Video of Gina Krog Topside - Sail Away from Korea Link: YouTube
Classification: Open 2016-11-30
Slide 30
Gina Krog Topside Installation
Heavy lifts performed by Saipem
Video of Gina Krog Topside Modules - Heavy Lifts August 2016 Link: YouTube
Classification: Open 2016-11-30
Five separate modules and lifts:
1.Main Support Frame (MSF)
2.Process Module (PM)
3.Utility Module (UM)
4.Living Quarter (LQ)
5.Flare Boom (FB)
Thank you Frode Haldorsen
Project Manager and Company Representative
Gina Krog Topside
Phone: +47 99 48 51 20
Slide 33 Classification: Open 2016-11-30