Download - Energy Audit Report-GCS-1 Duliajan · PDF file · 2013-05-29... IR(I) Compressor /NGEF Motor Capacity : ... GL = Gas Lift Compressor, GI = Gas Injection Compressor, ... Motor driven

Transcript

OF

Conducted By

(EASTERN REGION)

2, Gariahat Road South, Dhakuria

Kolkata – 700 068

Ph: 033 – 2414 5092, 2414 5088, 2414 5094;

Telefax: 033 – 2414 5091

e-mail: [email protected]

Website: http://www.pcra.org

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 2 of 21

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 3 of 21

ACKNOWLEDGEMENT

Petroleum Conservation Research Association, Eastern Region (PCRA, ER),

appreciates the interest, participation and collaboration by the management &

engineers of the Oil India Limited (OIL) in carrying out Energy Audit at “Gas

Compressor Station-1 (GCS –1), Duliajan”.

Our special thanks to the Installation Manager and his team of Engineers,

Supervisors and technicians attached to GCS-1, who have extended their proactive

co-operation and courtesy to the energy audit team during the audit.

T h e E n e r g y A u d i t T e a m :

Sl.

No.

From OIL From PCRA

1. Mr. David Zodingliana, Installation

Manager

Sri A. Chakraborti, CEA

2. Mr. R Mandal, CE (Tech. Audit) Sri D. Dutta,CEM

3 Mr. A.P. Goswami, Dy.SE(Elect.) Sri Dilip Mahapatra,CEA

4 Mr. K. Deka, Sr. Technical Auditor

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 4 of 21

INDEX

Chapter

No.

Title

Page

1.0 Executive Summary

5

2.0 Introduction

6

3.0 Existing Energy System

9

4.0 Study of Air Compressor

12

5.0 Study of Gas Compressor System 14

6.0 Study of Illumination 16

Annexure – I List of Energy Efficient Equip. Suppliers 18

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 5 of 21

1.0 EXECUTIVE SUMMARY

Table-1.1 Major Findings and Estimated Savings

Recommendations (Short /

Medium Term)

Savings per Annum Estimated

Investment

Simple

Payback

period

KWh Rs. Rs. Years

1. Maintain separate Air

Compressors with separate air

receivers at 11kg/cm2 and 6

kg/cm2 pressure level

30016 136,573

The cost of

exposing old

embedded lines

and replacement to

be estimated

To be

estimated.

2. Replace 36 watt FTL with 28

watt energy efficient T5 lamps 3504 15,943 16000 1 year

Total 33520 152,516

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 6 of 21

2.0 INTRODUCTION

2.1 IMPORTANCE OF ENERGY CONSERVATION & ITS BACKGROUND

Energy is one of the most coveted inputs in the development of any society. With the

accelerated growth of the economy the demand for energy is increasing exponentially. On the

supply side the stock of the conventional energy resources like fossil fuel are limited and

rapidly depleting. India gradually becoming dependent on external sources of energy thereby a

considerable part of the GDP is exhausted for procurement of energy.

One of the easier available options for survival is energy conservation through energy

efficiency improvement; thereby reduction of energy consumption and cost there of through

strategic energy management concept and mechanism.

Energy conservation is a worldwide objective. The energy policy of the Government of India

also calls for conservation of energy. With the enactment of ‘Energy Conservation Act-2001’,

amongst others has emphasized upon the power of the appropriate Govt. to enforce efficient

use of energy and its conservation.

The management of OIL has adopted the energy system study and implements solutions

thereof with the objective to optimal utilization and output of available energy consuming

systems and to conserve energy.

In view of energy efficiency improvement and cost reduction program for long-term business

solution the management of OIL sought the services of PCRA for energy system study on Gas

Compressors, air compressors and Lighting systems at their plant at Duliajan in Assam.

PCRA has studied the energy systems of the plants accordingly with the help of OIL

representatives. During the study, the energy audit team has mapped present status of

electrical power and energy systems at the plant premises, identified areas of weaknesses,

major energy loss areas etc. The study has identified potential scope for improvement and

energy efficiency improvement in major energy consuming systems. It also recommends cost

effective and fast pay back solutions for energy cost control.

2.2 COMPANY PROFILE

The story of Oil India Limited (OIL) traces and symbolizes the development and growth of the

Indian petroleum industry. From the discovery of crude oil in the far east of India at Digboi,

Assam in 1889 to its present status as a fully integrated upstream petroleum company, OIL has

come far, crossing many milestones.

On February 18, 1959, Oil India Private Limited was incorporated to expand and develop the

newly discovered oil fields of Naharkatiya and Moran in the Indian North East. In 1961, it

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 7 of 21

became a joint venture company between the Indian Government and Burmah Oil Company

Limited, UK.

In 1981, OIL became a wholly-owned Government of India enterprise. Today, OIL is a premier

Indian National Oil Company engaged in the business of exploration, development and

production of crude oil and natural gas, transportation of crude oil and production of LPG. OIL

also provides various E&P related services and holds 26% equity in Numaligarh Refinery

Limited.

The Authorized share capital of the Company is Rs. 2000 Crores. The Issued, Subscribed and

Paid share capital of the company is Rs. 601.14 Crores. At present, The Government of India,

the Promoter of the Company is holding 78.43% of the total Issued & Paid-up Capital of the

Company. The balance 21.57% of the Equity capital is held by others.

OIL has over 1 lakh sq km of PEL/ML areas for its exploration and production activities; most of

it is in the Indian North East, which accounts for its entire crude oil production and majority of

gas production. Rajasthan is the other producing area of OIL, contributing 10 per cent of its

total gas production.

Additionally, OIL’s exploration activities are spread over onshore areas of KG Basin, Mahanadi

Basin, Cauvery Basin, Andaman Basin and Gujarat-Kutch Basin etc. OIL also has participating

interest in NELP exploration blocks in Mahanadi Offshore, Mumbai Deepwater, Krishna

Godavari Deepwater, etc. as well as various overseas projects in Libya, Gabon, Iran, Yemen,

Nigeria, Sudan and Venezuela.

In a recent CRISIL-India Today survey, OIL was adjudged as one of the five best major PSUs and

one of three best energy sector PSUs in the country.

Objective of Energy Audit

With the advent of energy crisis and exponential hikes in the costs of different forms of

energy, Energy Audit is manifesting its due importance in Industrial Establishments. Energy

Audit helps to understand more about the ways energy and fuels are used in any

Establishment and helps in identifying areas where waste may occur and scope for

improvement exists.

Energy Audit is the key to a systematic approach for decision-making in the area of energy

management as it attempts to balance the total energy inputs with its use and serves to

identify all the energy streams in a facility/ Establishment.

It was with this objective that Petroleum Conservation Research Association (PCRA) was

entrusted by OIL, the Energy Audit of Gas Collecting Station#1, Duliajan.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 8 of 21

Table-2.1 GENERAL DETAILS OF THE COMPLEX

2.3 ENERGY AUDIT STUDY:

a) SCOPE OF THE STUDY

• To study Electrical system and transformers

• To study Electrical Motors

• To study Gas Compressors.

• To study air compressor system.

• To study lighting system & illumination level at various work places & suggest for

improvement.

b) METHODOLOGY

The study was concentrated on the above areas to find out energy conservation options.

Discussion was held with the concerned personnel regarding the system familiarization and the

operation of the specific equipment. Trial and field measurement by portable instrument were

conducted in selective areas. Related data also collected from estate department for further

analysis. Cost benefit analysis was carried out in some energy conservation options.

c) INSTRUMENTS USED:

1. Three phase power analyzer,

2. Single phase power analyzer,

3. Anemometer,

4. Non-contact thermometer,

5. Lux meter,

Name of the Complex GCS -1, OIL, Duliajan

Address Duliajan, Assam

Contact Person Mr. David Zodingliana

Tel 0374-2806404 / 94350 38903

Type of Ownership Central PSU

Contract Demand Self-Generation

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 9 of 21

3.0 EXISTING ENERGY SYSTEM:

The source of Energy for GCS-1 are as follows:

1) Electrical energy for GCS – 1 from Gas based Captive Power Plant at Duliajan

2) Fuel gas for engine driven gas compressor - fuel gas taken from the main

suction line through MP header coming from OCS.

3.1 MAJOR EQUIPMENT LIST:

a) LPB 4 Make: IR(I) Compressor /NGEF Motor

Capacity : 5400 Standard Cubic mtrs/hr

b) LPB 5 Make : Worthington Compressor /Caterpillar CAT G399(Engine)

Capacity : 2700 Standard Cubic mtrs/hr

c) LPB 6 Make : Atlas Copco (Compressor) / Waukesha L7042 (Engine)

Capacity : 5400 Standard Cubic mtrs/hr

d) GL 3 Make : BPCL Compressor / Waukesha L3711 (Engine)

Capacity : 3167 Standard Cubic mtrs /hr

e) GL 5 Make : BPCL Compressor / BHEL Motor driven

Capacity : 3167 Standard Cubic mtrs /hr

f) GI 4 Make : AC Compressor / Waukesha engineL5790

Capacity : 3917 Standard Cubic mtrs /hr

g) GDU Make: ABAX, Capacity : 15 MMSCFD

h) Air Compr # 2 Make: Ingersoll Rand (IR 15T2), Capacity : 2.8 Cu.M/min

i) Air Compr # 4 Make: KGK Khosla, Capacity : 2.83 Cu.M/min

( LPB = Low Pressure Booster, GL = Gas Lift Compressor,

GI = Gas Injection Compressor, GDU = Glycol Dehydration Unit)

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 10 of 21

3.2 ELECTRICAL MOTOR DETAILS:

SL. NO L.T. LOADS K.W.

1 AIR COMPRESSOR MOTOR NO -2 15

3 AIR COMPRESSOR MOTOR NO -4 30

4 COOLING WATER PUMP MOTOR 2

5 COOLING WATER PUMP MOTOR 2

6 AUX. LUBE OIL PUMP MOTOR OF G.B. -4 2.4

7 AUX. WATER PUMP MOTOR OF G.B. -4 0.75

8 AUX. COOLING FAN MOTOR OF G.B. -4 18

9 AUX. LUBE OIL PUMP MOTOR OF G.L. 5 1.5

10 AUX. WATER PUMP MOTOR OF G.L. 5 1.5

11 AUX. COOLING FAN MOTOR OF G.L. -5 7.5

12 METHANOL PUMP MOTOR 0.37

13 PIT PUMP MOTOR NO -1 0.37

14 PIT PUMP MOTOR NO -2 7.5

15 GLYCOL PUMP MOTOR NO -1 2.23

16 GLYCOL PUMP MOTOR NO -2 2.23

17 LIGHTING LOAD 8.2

18 HIGH MAST (FUTURE) 14

19 WATER TREATMENT PLANT (FUTURE) 5

LOAD IN K.W. 120.55

SL. NO H.T. LOADS K.W.

1 GAS BOOSTER NO -4 (MAIN MOTOR) 550

2 GAS LIFTER NO -5 (MAIN MOTOR) 330

LOAD IN K.W. 880

TOTAL LOAD = 135.55+880= 1015.55 K.W

3.3 THE POWER SYSTEM:

The source of power supply for GCS-1 is from CPP at 3.3 kV for HT supply to the 2 nos. of

Motor driven Gas Compressors (1 no. Gas Lifter & 1 no. Low Pressure Booster). Another

transformer is present (3300 volt / 415 volt of 400 KVA) for LT supply to lighting & Air

Compressors and smaller motors.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 11 of 21

Fig.1, shows percentage share of electrical power consumption by major equipment at the OIL-

GCS plant:

Observation :

� It is observed that the major portion of the electrical power is consumed by the HT

motors (LPB-4 and GL-5).

� Monitoring of electrical power consumed by the plant is not practiced at present.

Energy monitoring and targeting is primarily a management technique that uses energy

information as the basis to eliminate wastage, reduce and control current level of

energy usage and improve the existing operating procedures.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 12 of 21

4.0 STUDY OF AIR COMPRESSOR

4.1 AIR COMPRESSOR DETAILS

The compressed air system of GCS-1, Duliajan has two reciprocating type air compressors. One

is of 15 kW and the other one is of 30 kW capacities.

Table-4.1 Specification of Air Compressors

Air Comp. No. 2 Air Comp. No. 4

MAKE Ingersoll Rand KG Khosla

MODEL IR 15T2

CAPACITY

(in m3/min)

2.8 2.83

Motor Rating, kW 15 30

Discharge pressure in

kg/cm2

14 14

Air compressors are connected to common receivers. Air is supplied at 14 kg/ cm2 for cranking

operation of the gas engines of gas compressors during start-up. Air @ 6 kg/cm2 is required for

the pneumatic control of the gas engine valves & circuit.

Pneumatic air taken from the air receiver passes through a pressure reducing device and air

dryer and supplied to various pneumatic systems @ 6 kg/cm2.

Air Pressure of 14 kg/cm2 is only required at the time of start-up of the gas engines and once

the engines are started then 14 kg/cm2 pressure is not required. Continuous air pressure is

only required for the pneumatic control valves & circuit of the gas engines and that too at 6

kg/cm2 pressure.

In present condition the air is maintained from 10 kg/cm2 to around 14 kg/cm

2 at any point of

time. The unloading of the air compressor is done at around 14kg/cm2 and the loading is done

at 10 kg/cm2.

Hence in the above condition it is clear that although the air pressure requirement of 14

kg/cm2 is only required during starting of the Gas engines but still the pressure is maintained

from 10 to 14 kg/cm2 throughout the day in order to start any engine when sudden

requirement is there.

The performance of the Air Compressors could not be checked as the compressors could not

be isolated due to operational inconvenience.

It should be noted that more power is required to compress air at higher pressure compared

to lower pressure i.e, energy required to compress air from 10 to 14 kg/cm2 is much higher

compared to pressurizing air from 3 to 6 kg/cm2.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 13 of 21

RECOMMENDATIONS :

At GCS-1, compressed air is used for two purposes:

1. To start Gas compressor engines (pressure requirement 14 kg/cm2).

2. To drive pneumatic instruments (pressure requirement 6 kg/cm2).

Pressure requirement for both the works are different as mentioned above.

It is recommended to maintain different air receivers for 14 kg/cm2 and 6 kg/cm2 line pressure.

Also one of the compressors should be dedicated to 14 kg/cm2 and the other one for 6 kg/cm2

line so that total running time of both the air compressors would reduce in a day.

To have redundancy in operation of the air compressors, one bypass line can be connected

from both the air receivers with a valve in-between so that whenever one compressor is under

shutdown then the other compressor can be compensated.

With an estimated min. of 25% of energy can be saved with this kind of arrangement.

Power

Consumption,

Kw

Running

Hour per

day

Energy

Consumption

per day, kWh

Energy

Consumption

per year,

kWh

Total Energy

Consumption

per year, kWh

25% Energy

Saving, kWh

AIR COMP.

2 14.18 8 113.44 39704

120064 30,016 AIR COMP.

4 28.7 8 229.6 80360

Since the Station is going for a new air compressor house hence it would be easy to carry out the

recommendation.

Investment for this recommendation = The buried old air lines need to be replaced which need

investment. The need of investment is to be estimated.

Monetary value of energy saved per annum @ Rs. 4.55 per kWh = 30016 x 4.55 = Rs. 1.36 Lacs

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 14 of 21

5.0 STUDY OF GAS COMPRESSORS

5.1 FUEL CONSUMPTION BY INDIVIDUAL EQUIPMENT:

Compressor

No

Gas

Compressed

(SCMD)

Power

Consumption

(KwH)

Equivalent Natural

Gas Consumption

(SCUM/HR)

1 LPB 4 4050 275.6 143.3

2 LPB 5 1890

129.2

3 LPB 6 3780 204.2

8 GL 3 1900 118.8

9 GL 5 2937 177.9 92.51

10 GL 4 2741 164.6

Note: The equivalent gas consumption for motor is based on the gas consumed to generate power

at Duliajan Gas based Power Plant.

5.2 REPLACEMENT OF MOTOR DRIVEN COMPRESSORS WITH GAS ENGINE DRIVEN TO

CONSERVE POWER

It was informed to us by OIL personnel that power consumption by existing motor driven

compressors are much higher, replacement of the same with gas engine driven

compressor unit to be assesed for effective utilisation of power.

Therefore, following calculation is given to assesss the cost of replacement of Compressor

Motors with New Gas engines.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 15 of 21

By matching the RPM of the Gas compressors and BHP of the present Electric Motors, it is

found that Waukesha Dresser F 3521GL is suitable for replacing motors of GL-5 and LPB-4.

As per the data sheet the compressor is having Compression Ration of 10.5:1, RPM of 1000

and BHP of 615.

The fuel consumption at full load is 110.6 m3/hr. as the load curve the fuel consuption at

60% load as per design will be 98 m3/hr

Cost of purchasing the Gas Engine is $1,65000 = 1,65000 X 55= Rs. 90075000/-

The cost of running one Gas engine is 98 X 24X365 = 858480 X Rs.8.83 (Cost of NG) = Rs.

7580383.00

Present average power consumption of running motor is 226.75 Kwh

Cost of running of one motor is 226.75 X Rs.4.55 X24 X365 = Rs. 9037801/-

Saving for Gas Engine per year = 9037801-7580383= Rs. 1457418/-

Payback = 90075000/ 1457418 = 61 Years

Therefore, it is economically not feasible to replace a motor with a gas engine. But, in case

of non-availability of power gas engine can be procured.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 16 of 21

6.0 ILLUMINATION SYSTEM

6.1 SUMMARY OF LUMINAIRES

The illumination level in the GCS – 1 is on the lower side. Average lux level maintained in the

roads, pathways etc. are in the range of 1 – 10.

The lighting at the main entrance and also in the pipeline manifold area is very poor which

needs to be improved.

The street lights are fitted with HPSV and the shed are fitted with MLL& HPMV fittings. There

are some 36 watt FTL present in air compressor house & other office areas as well.

The average lux level in different areas are shown below:

Area LUX Level Recommended Lux

Gate Entry 0 - 5 30 – 50

Pathway 0 -10 30 – 50

Pipeline Manifold 0 - 5 30 – 50

Small Shed 2 - 25 50 – 100

Large Shed 5 - 15 50 - 100

Air Compressor Shed 30 - 150 100 - 150

6.2 RECOMMENDATIONS AND PAYBACK ANALYSIS:

1. Replace all the conventional 40 watt and 36 watt tube light (Fluorescent Tube Light)

with energy efficient T5 (28 watt).

2. Use reflector in FTL systems and other present lighting system to get better lux level at

working height.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 17 of 21

Table- 6.3 ANNUAL ENERGY SAVING OPTIONS

Present System Proposed

System

Total

No. of

Item

Daily

Working

Hours

Annual

Working

Day

Present

Annual

Consumption

(kWh)

Expected

Annual

Consumption

(kWh)

Annual

Savings

(kWh)

FTL of 36 watt

with choke of

12 watt

T5 light of

28 watt 40 12 365 8409.6 4905.6 3504

Investment for T5 lights = 40 Nos. x Rs. 400/- = Rs.16,000/-

Annual Monetary Savings = 3504 x 4.55 = Rs. 15,943/-

Simple Payback Period = 16000 / 15953= 1 year

Energy conservation opportunity in lighting :

� Installation of electronic ballast for fluorescent lamps

� Switching off lighting whenever not needed

� Installation of automatic lighting controls

� Installation of lighting voltage controllers

� Regular maintenance and cleaning of lamps

� Use of localized lighting close to working areas where appropriate

List of References :

1) BEE guide book on Energy Efficiency on Electrical Utilities

2) Handbook on energy conservation -by PCRA

.

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 18 of 21

Annexure-I

Energy Efficient Equipment Suppliers

Product/ Equipment Contact Details

AC Drives Rockers Control System,

SCO 819, 2nd

Floor, NAC, Manimajra, Chandigarh 160101

Ph: 0172 – 2730900, 5071627

AC Drives Allen Bradley India Ltd

C-11, Industrial Area, Site-IV, Sahibabad, Ghaziabad 201 010

AC Drives Asea Brown Boveri Ltd.

Guru Nanak Foundation Building, 15-16, Qutab Institutional Area,

Saheed Jeet Singh Sansanwal Marg, New Delhi - 110 067

AC Drives Crompton Greaves Ltd.

Machine 3 Division, A-6/2, MIDC Area, Ahmednagar 414 111.

Automation, Panel Meters Conzerv System

44P Electronic City Phase –II, East Hosur Road, Bangalore – 560100

Ph: 080-51189700 www.conzerv.com

Automation, Panel Meters Selec controls Pvt Ltd

E – 121, Ansa Industrial Estate, Saki Vihar Road, Mumbai 400072

Ph: 022-28471882, 28476443 www.selecindia.com

Building Automation, sensors, twilight

switches

Electro Art

Plot No K-11, MIDC Area, Ambad, Nashik –422010,

Ph: 0253-5603954, 2380918 www.electronicswitchesindia.com

Burners WESMAN ENGINEERING (P) LTD.

503-504 Eros Apartments, 56 Nehru Place, New Delhi 110019

Tel: +91 (11) 26431723 Fax: +91 (11) 26434577

Burners, Furnace Recuperators, Hot air

generators, Heating & Pumping unit,

Laddle preheating

ENCON

12/3, Mathura Road, Faridabad-121003

Phone: 0129 -25275454 Fax: 0129 –25279070

www.encon.co.in

Capacitors Asian Electronics Ltd.

Plot 68, MIDC, Satpur, Nasik, Nashik - 422 007

Capacitors Shreem Capacitors Pvt. Ltd.

7/39, Vikram Vihar, Lajpat Nagar-IV, New Delhi - 110 024

Capacitors and APFC Panels Matrix Controls & Engineers Pvt Ltd

Rajeev Batra 9811624440, [email protected]

E- 725 DSIDC, Industrial Complex, Narela, GT Road, Delhi – 110040

Ph: 01127786945 / 46 / 47

www.matrixcapacitor.com

Capacitors and APFC Panels Standard Capacitors

B-70/43, DSIDC Complex, Lawrence road Industrial Area, Delhi –110035

Ph: 011 –27181490, 27151027

www.standardcapacitors.com

Capacitors and APFC Panels Saif Electronics

174, Hira Building, 1st

Floor, Carnac Road,

Opposite Police Commissioner office , Mumbai – 400002

Ph : 022 – 22064626 , 22086613

www.saifel.com

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 19 of 21

Product/ Equipment Contact Details

Compressed Air Piping Legris India Pvt Ltd.

Legris House, 99 Pace city –1, sector 37, Gurgaon- 122001

Ph : 9958297093 , 9811054826

www.transair.legris.com

DG Synchronization, Automation and

Capacitors

SGS Industrial Controls & Solutions Pvt Ltd

Floor-II, Madanpur Khadar, Sarita Vihar, New Delhi.

Ph 011 – 29942516, 41402992

Eco-ventilators Nu Plast pipes & profiles

SCF – 124, sector 17 Market, Faridabad – 121002

Ph : 0129 – 6546217 , 4070023

Electrical measurement Instruments Riken Instrumentation Ltd

369, Industrial Area, Phase –II, Panchkula, Haryana

Ph : 0172 – 2591651, 2592028 ,

www.rikeninstrumenatation.com

Energy Management & Control

Systems

Manaco Energy Solutions (P) Ltd.

A-6, Shanti Apts.,21 & 22, 1st Cross St, TTK Road, Alwarpet, Chennai-18 ,

044-42316164,

www.mesco.co.in

Energy Saving Products Gautam Enterprises

205, Vinay Indl. Est., Chicholi Bunder Link Road, Malad (West),

Mumbai - 64, India

Tel: (91-22) 2875 04 22, Fax: (91-22) 2873 6985

www.gautament.com

Energy Saving products Techmark Engineers & Consultants.

K-1/28 Ground Floor, Chittaranjan Park New Delhi-110019

Telephone: 91-011-26238349

Fax : 91-011-51603925

Flue Gas Analyzers / Oxygen Analyzer Nevco Engineers Pvt. Ltd.,

90A (2nd Floor), Amritpuri B, Main Road, East of Kailash,

Opp. Iskcon Temple, New Delhi – 110 065

Telephone No 26226328, 26213009; Fax: 26285202

www.nevco.co.in

Flue Gas Analyzers / Oxygen Analyzer ACE Instruments & Controls

1, Biradari, Above Kashi Dairy, M.G. Road,

Ghatkopar (W), Bombay – 400 086

Tel.: 5125153, 5122762

Flue Gas Analyzers / Oxygen Analyzer Testo India Pvt Ltd

Pune 020 – 25665085,

www.testo.com

FRP Blades and cooling tower

accessories

Eneertech Engineers

SCO 144 – 145, Sector 34A, Chandigarh

Ph : 0172 – 5018077, 9876022225

HVAC related instruments

Thermocouples, pipe fittings, pressure

gauges

Waaree , 36 Damji shamji Industrial Complex

Off Mahakali caves road, Andheri East Mumbai 400093

022 –66963030 26874778

www.waaree.com

Infrared Temperature Meters (600 °C

to 1800 °C)

Toshniwal Industries Pvt. Ltd.

Industrial Area, Mahukupura, AJMER - 305 002,

Ph 91145 269 5171, 91145 269 5205

[email protected] www.tipl.com

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 20 of 21

Product/ Equipment Contact Details

Infrared Temperature Meters (upto

1500 °C)

KUSAM MECO, G-17 , Bharat Industrial Area ,

T.J. Road, Sewree Mumbai 400015,

Ph : 022 – 24156638, 24124540

www.kusam-meco.co.in

Insulations Lloyd Insulation (India) Ltd.

P.B. No. 4321, Kalkaji Industrial Area,

Punj Sons Premises, New Delhi – 110 019

Ph: 26430746-7 Fax: 26478601/26467259

Insulations Himal Supply (India) Ltd

168 , Rajagarden, New Delhi – 110015

Ph : 011-25438602 , 25448602

www.himalsupply.com

LED lighting Synergy Solar (P) ltd

SCO 133, sector 28D, Chandigarh

Ph 0172-6451133

www.synergysolars.com

Lighting Systems Philips India Ltd

Regional office-North, 9th floor Ashoka Estate, 24,

Barakhamba Road New Delhi – 110 001

Telephone No.: 3353280, 3317442, Fax No.: 3314332

Lighting Systems Crompton Greaves Ltd.

Lighting Business Group, 405, Concorde, RC Dutt Road,

Baroda – 390 007

Lighting Systems OSRAM India Ltd. Signature Towers,

11th Floor, Tower B, South City-I, Gurgaon 122001, Haryana

Tel: 0124- 6526175, 6526178, 6526185

Fax: 0124- 6526184

Lighting Systems Asian Electronics

Surya Place, First Floor, K-185/1, Sarai Julena,

New Friends Colony, New Delhi – 110 025

Lighting Systems Asian Electronics

Surya Place, First Floor, K-185/1, Sarai Julena,

New Friends Colony, New Delhi – 110 025

Lighting Systems Philips India Limited , Technopolis Knowledge Park,

Nelco Complex, Mahakali Caves Road, Chakala,

Andheri (East), Mumbai 400 093.

Tel : 022 56912000

Lighting Systems Surya Roshni Ltd.

Padma Tower-I, Rajendra Palace, New Delhi 110 006.

Lighting Systems Wipro Limited

Sco 196-197, Sector 34-A, Chandigarh - 160 022

Lighting Systems OSRAM India Ltd. Signature Towers,

11th Floor, Tower B, South City-I, Gurgaon 122001, Haryana

Tel: 0124- 6526175, 6526178, 6526185

Fax: 0124- 6526184

Lighting Voltage Control Systems Jindal Electric & Machinery Corporation

C-57, Focal Point, Ludhiana – 141010

Ph : 2670250 , 2676890 ,

www.jindalelectric.com

Report on Energy Audit of OIL installation at GCS-1, Duliajan, Assam, India

---------------------------------------------------------------------------------------------------------------

Energy Audit by PCRA, Eastern Region Page 21 of 21

Product/ Equipment Contact Details

Lighting Voltage Control Systems ES Electronics (India) Pvt. Ltd.

Plot No.82, KIADB Industrial Area,

Bommasandra – Jigani Link Road, Jigani Hobli,

Anekal Taluk, Bangalore District – 562 106

Telefax: +91 - 8110 – 414547 / 414548,

414549 / 414550

E-mail ID: [email protected]

Website: www.energysaversindia.com

Soft starters Amtech Electronics (India) Ltd

E-6, GIDC Electronics Zone, Ghandinagar – 382028 , Gujarat

Ph : 079 –23289101-3,

www.amtechelectronics.com

Thermocouples and Heaters Beeco Electronics

450 –A, Industrial Area, Phase-II, Chandigarh 160002,

Ph : 0172 – 5083350, 5073750 ,

www.beecoelectronics.com

Thermocouples and temperature

gauges & sensors

Radix Microsystem , 1005, Hemkunt House, 6, Rajendra Place

New Delhi,

Ph : 011-25786350, 09312600075 ,

www.radix.co.in

Note: - The suppliers mentioned above are not the only ones or the best in the market. The

plant may contact other suppliers for competitive rates/ specifications.