CEDARSHED INSTRUCTIONS
BENTLEY - COLOURSTEEL ROOF
Base size: 3600mm x 2490mm deep
BENTLEY
• Battery Drill
• Riveter
• Hammer
• Tape Measure
• Ladder
• Skillsaw
• Level
• Screwdriver - Flat
• 3/8 Hex Drive bit
• 8mm Hex Drive bit
• Drill Bit 3.2mm
• Read all instructions carefully.
• Identify all parts and check quantities against checklist.
• Do not attempt to build your shed in high winds.
• Beware of sharp edges.
• Protect your eyes and ears.
• Use electric tools with care. Use a Safety Trip Switch.
• It is easier and quicker if this shed is erected by two people.
• Your shed must be level. Achieve this by either levelling the
ground or by using blocks.
Tools Required:
Select your site:
Safety:
Before you start:
PG 1
BENTLEY PARTS LIST Description Size Qty
PACK ONE - SHED
Standard Door 895 x 1780 1
Std Wall Panels 1200 x 1937 5
Front Wall Panel 300 x 1937 1
End Wall Panels (L/H) 1200 x 2460 2
End Wall Panels (R/H) 1200 x 2460 2
Door Lintel 167 x 900 1
Cedar Corner Clashings 65 x 17 x 1962 4
30 x 17 Std Cedarbead 30 x 17 x 1937 3
15 x 17 Std Cedarbead 15 x 17 x 1937 6
30 x 17 Gable Cedarbead 30 x 17 x 2465 2
Roof Truss w/ Brackets 535 x 2490 1
Bargeboards 90 x 17 x 1500 4
Door Stop 45 x 45 x 900 1
Diamonds 230 x 95 x 17 2
Building Paper 1370 x 7500 1
Roof Sheets 875 x 1450 8
1/2 Roof Sheets 370 x 1450 2
Ridge Flashing 240 x 2010 2
Purlins 70 x 45 x 1858 8
15mm Packer 15 x 45 x 1720 1
Clear Roof Panel 1 Replaces 1 Roof Sheet QTY
Hardware Pack
Tek Screws 14G x 75mm, CL4 50
Framing Nails 75 x 3.15mm 60
Bead Nails 50 x 2.5mm 100
Galv Clouts 30 x 2.5mm 120
Colour Rivets 3.2 x 8.2mm 70
Roofing Screws and Washers 50mm 50
Door Handle 1
Door Latch 1
Door Handle Screws 3/16 x 2.5" 2
Silicone Tubes 2
Truss Bracket Screws 40mm 4
Instructions 1
Plastic Weatherstrip 50mm x 20mtrs 1
PACK TWO - STIFFENERS (& FLOOR if required)
Spouting 3706mm 2
Stiffeners 45 x 45 x 3600 2
Floor Joists 70 x 45 x 3590 5
Floor Boards 150 x 19 x 2480 24
Floor Nails 50 x 2.5mm 240
Packed by: Date: / /
PG 2
BENTLEY CONCRETE FLOOR - OPTIONAL
Step 1: Establish size of shed and excavate sufficient area. Re-
member to allow for rear roof overhang up to 150mm, and
120mm on each end.
Step 2: Ensure that the base substrate is compacted firmly.
We suggest that the slab should be 80mm thick in the middle
and 100mm thick around the edges.
Step 3: Lay boxing to the required size, the raised slab
size should be 3585 x 2475mm and at least 30mm
above the ground line.
Step 4: Lay plastic sheeting if required. Plastic sheeting under slab
will prevent moisture coming through from underneath.
Step 5: Pour concrete and screed flush
Building a Raised Concrete Base
100mm
80mm
100mm
PG 3
BENTLEY FLOOR - OPTIONAL
Step 1: Lay out floor joists, spacing them evenly
as shown. Using 50mm flooring nails, nail a floor
board on each end, ensuring ends are flush with
joists. Make sure floor is level and joists are sup-
ported at 900mm centres.
Step 2: Lay out remaining floor boards. Measure
diagonals to ensure measurements are equal (i.e.
floor is square). Rip down last floor board to suit
gap, and nail off floor with 50mm flooring nails
(10 nails per board).
Step 3: Nail plastic weather strip to edge of floor
on all four sides, with 30mm clouts, (approx 5
nails per side) ensuring top edge is flush with top
of floor. This isn't required if shed is on a concrete
base.
Step 4: Unpack panels and identify wall panels
and door positions as per plan on following page.
Select two panels that go either side of a corner
(gable and standard panel) and stand together.
PG 4
BENTLEY WALL PLAN
15 x 17mm Std Cedar bead
30 x 17mm Std Cedar bead
30 x 17mm Gable Cedar bead
Corner Clashing
45 x 20mm Packer
Tek Screws (To secure Walls to Floor)
Please note: The walls are not screwed down to the floor until all the walls
are erected, the roof is in place and the doors are about to be installed.
BENTLEY WALL PLAN
1200 1200 1200
1200R
1200R
1200L
1200L
1200 1200 300
PG 5
BENTLEY WALLS
Step 5: Screw wall panels together using 75mm
tek screws (3 per panel), ensuring gable wall pan-
els are inside the front and back walls as per the
wall plan.
Step 6: Silicone edge of weatherboards on
standing panel and nail on cedar beads with 5 x
bead nails. (Refer to wall plan for correct beads).
Make sure bead is properly sealed to avoid leaks.
Note: On standard panels only, top of bead is
bevelled to allow for slope of roof.
Step 7: Silicone and nail remaining beads on each
panel. Screw panels together using 3 tek screws
per join and 4 on the longer joins on gable end
panels.
PG 6
BENTLEY TOP STIFFENER
Step 9: Using 75mm framing nails, nail both top
plate stiffeners into standard wall panels studs, as
shown using 2 nails per stud. Ensure ends are
flush before nailing.
BENTLEY TOP LINTEL
Step 10: Using 30mm clouts nail top cedar boards
to stiffeners (2-3 nails per board). Predrill holes to
stop boards from splitting.
Step 8: Using 4 x 75mm tek screws screw
door lintel to studs. Ensure outside cedar
weatherboard on lintel is flush with weather-
boards each side.
Door Lintel shown from inside
Door Lintel shown from outside.
PG 7
BENTLEY CORNER CLASHINGS
Step 11: Silicone and nail 15 x 17mm beads on all
corners as shown using 5 x 50mm bead nails, per
bead.
Step 12: Silicone and nail corner clashings on all
corners as shown using 5 x beading nails per
clashing.
Silicone both edges of clashing to ensure this
doesn't leak.
BENTLEY ROOF
Step 13: Position roof truss in centre of front
and back walls. Using 8 x 40mm screws, screw
truss to top plate stiffeners, on front and back
walls.
Step 14: Position 8 purlins on roof. Top purlins
should be together and bottom purlins should
be against top plate. Using 75mm framing nails,
predrill then nail purlins into top of gable end
panels and truss (2 nails per join).
PG 8
BENTLEY ROOF
Step 15: Ensure shed is square, by measuring diagonals at top corner of wall panels.
Using 30mm clouts, nail building paper on to purlins.
Step 16: Position first full sheet with rib flush
with ends of purlins and top of sheet in the cen-
tre of roof. (So sheets touch in the middle).
Tack top of the sheet into the top purlin using a
30mm clout through the pan. Using a 50mm
Roofing Screw with Washer, screw through the
rib into the bottom purlin to a depth of approxi-
mately 10mm.
Note. Use 50mm Roofing screws with washers
for bottom purlin and 30mm clouts for top pur-
lin. Predrill holes for clear roof panels.
Step 17: Lay out remaining full roof sheets and
1/2 sheet. Rivet these sheets together, 2 rivets
per join, to make 1 large roof panel as shown in
photo. Tack remaining top corner and bottom
corner ensuring edge of sheet is flush with end of
purlins and height is correct.
Ensure purlins are straight, Nail through the pan
using 30mm clouts into the top purlin, using
50mm roofing screws with washers screw
through the rib into the bottom purlin.
Step 18: Rivet ridge flashing to roof on every
second rib, as shown.
PG 9
BENTLEY DOOR
Step 19: Fit door stop in doorway. Check all wall
panels are straight and panels either side of
doorway are tight against door stop. Screw pan-
els to floor using 1 x 75mm tek screw per panel.
Screw near the panel joins, where possible.
Nail door stop to floor using 75mm framing nails.
Step 20: Fit door in position as shown.
Step 21: Using 3 x 75mm tek screws, screw
door stud to panel ensuring height is correct.
Check that door opens and closes correctly and
height is correct.
Fit handle as shown. Attach with 2 x handle
screws. Attach and tighten latch to square shaft.
Using 5 x 50mm beading nails, nail 20mm pack-
er onto side of door opening as shown in Wall
plan on pg. 5.
PG 10
BENTLEY BARGE
PG 11
Step 22: Attach barges with 2 x 50mm
bead nails into each purlin. Nail diamond
to barges with 2 x 50mm bead nails.
Remember to remove all drill filings from your colour steel roof.
Your shed is now complete. You may protect Cedar by staining cedar weatherboards if
required.
Step 23: Attach spouting channels to
roof, leaving approximately 5mm at
each end for water to run off. One
rivet through both end ribs, then
every second rib between.
CEDAR SHED WARRANTY GUARANTEE TO CUSTOMER
Congratulations on purchasing a quality New Zealand made Cedar Shed manufactured by Riverlea Group Limited. With proper care and attention this
product will offer you many years of use.
WARRANTY ON METAL CLADDING
Your new shed is guaranteed for the benefit of the original purchaser, against defective material or faulty workmanship for fifteen years from date of
purchase. Riverlea Group Limited will, at its discretion, replace or repair any faulty or defective materials within this time on condition that due care
and maintenance has been carried out as detailed below.
TERMS AND CONDITIONS
This warranty does not cover Cedar sheds with steel roofing if it is installed outside the inland corrosion zone or areas where the
corrosion rate is more than 200g/m2 (as published by BRANZ)
1. The warranty does not cover damage or failure due to improper assembly.
2. This warranty does not cover damage through force majeure or other cause beyond the control of Riverlea Group Limited.
3. This warranty is void if maintenance as detailed below and in the assembly manual has not been adhered to.
4. This warranty does not cover natural variations, expansion, contractions as can be reasonably expected from a timber product.
Painting or coating of your Cedar Shed with a dark colour will cause increased timber temperature and movement which will render this warranty
null and void.
Beyond the exclusions above, Riverlea Group Limited will repair or replace the damaged or faulty product. The balance of the original warranty will
cover any repaired or replaced material. Riverlea Group Limited will not be liable for any consequential loss or damage, labour or transport costs.
All claims must be made within 21 days of discovery.
MAINTENANCE
The following are the minimum maintenance requirements for Cedar Sheds manufactured by Riverlea Group Limited. Please refer to your assembly
manual for more details.
Immediately coat all cedar walling cladding with “Endurance Cedar Wall Protector”. Cedar walls are to be regularly recoated according to application
instructions on the product packaging.
Immediately coat all cedar shingle roofing with “Endurance Cedar Shingle Protector” Cedar shingles are to be regularly recoated
according to application instructions on the product packaging.
All steel roofing is to be kept clean and free of debris and washed annually with a hose and soft brush.
Timber floors, where supplied are to be kept out of direct water contact or runoff
The above guidelines will guarantee you a superior Cedar Shed that will offer you many years of outstanding usefulness.
Please visit http://www.riverleagroup.co.nz/warranty-garden-sheds to validate the Warranty on your shed.
Click on the Warranty Registration Link and complete all details.
If you are unable to access the computer, please phone us on 0800 438 274 and one of the customer services team will help you to activate the
warranty on your garden shed.
Many thanks, from the Team at Riverlea Group.
WARRANTY REGISTRATION
Top Related