Page 1: Directly Funded Housing Programme Highlight …moderngov.southwark.gov.uk/documents/s47491/Appendix 3...Crossways Church (a.ka. Castle Resource Centre) Hampton Street, SE1 9 Phase

� 169 Long Lane, SE1

� Willow Walk, SE1

� Sumner Workshops, North Peckham Estate, SE15

� Masterman House Garages, Elmington Estate, SE5

� Cator Street, SE15

� Clifton Garages, Clifton Estate, SE15

� Nunhead Green Site B, SE15

� Southdown House and Gatebeck House, East Dulwich Estate, SE22

Crossways Church (a.ka. Castle Resource Centre) Hampton Street, SE1

9

Phase 1 Site Locations

Directly Funded Housing Programme Highlight Report Appendix 3

Page 1 As of June 2014

Page 2: Directly Funded Housing Programme Highlight …moderngov.southwark.gov.uk/documents/s47491/Appendix 3...Crossways Church (a.ka. Castle Resource Centre) Hampton Street, SE1 9 Phase

���� 169 Long Lane, SE1 21 Social Rent flats - 5 storey with lift - Ground floor commercial unit - To be managed by Leathermarket JMB - Ringfenced allocations to Kipling Estate

• Start on site (enabling works) - April 14

• Start on site due - Oct 2014

• Completion - Feb 2016

���� Willow Walk, SE1 21 Social Rent flats in a 4 storey block with lift 54 Short Stay accommodation in 3 storey block and amenity/office space. - Play area shared with Alscot Estate - Blocks divided by new road - General Needs ring fenced to Alscot Estate

• Start on site (construction) - 10 Apr 2014

• Completion due - Mar 2015

���� Sumner Workshops, North Peckham Estate, SE15 50 Social Rented Units 20 Shared Ownership 41 Private housing - In blocks max 6 storey divided by new road. - New T&RA facility - New playground to be shared with North Peckham Estate - Ring fenced allocations to North Peckham Estate

• Planning Application submitted June 2014

• Start on site due - May 2015

• Completion due - Dec 2016

Direct Delivery Housing Programme Appendix 3

Phase 1 Progress Report

Page 2 As of June 2014

Page 3: Directly Funded Housing Programme Highlight …moderngov.southwark.gov.uk/documents/s47491/Appendix 3...Crossways Church (a.ka. Castle Resource Centre) Hampton Street, SE1 9 Phase

���� Masterman House Garages, Elmington Estate, SE5 15 Social Rent units 10 Private Housing units - 2 blocks max - 5 storey with lift - ringfenced allocations to Elmington Estate

• Planning consent obtained April 2014

• Enabling works complete

• Start on site due - Apr 2014

• Completion due - Feb 2016

���� Cator Street, SE15 Extra Care - 42 General Needs Housing Units - 4 storey block with common parts and office/amenity space

• Start on site (enabling works incl Centre of Excellence) - Mar 2014

• Start on site (construction) due –Nov 2014

• Completion due - Mar 2016

���� Clifton Garages, Clifton Estate, SE15 8 Social Rent Units - in 4 storey block with lift - ringfenced allocations to Clifton Estate

• Enabling works completed

• Start on site due - Mar 2014

• Completion due - Dec 2015

Direct Delivery Housing Programme Appendix 3

Phase 1 Progress Report

Page 3 As of June 2014

Page 4: Directly Funded Housing Programme Highlight …moderngov.southwark.gov.uk/documents/s47491/Appendix 3...Crossways Church (a.ka. Castle Resource Centre) Hampton Street, SE1 9 Phase

���� Nunhead Green Site B, SE15 8 Social Rent Houses - 2 x 4 bed/4p - 5 x 3 bed/5p - 1 x 4 bed/6p

• Planning consent obtained

• Demolition of Community Centre complete

• Window renewal programme at Crofton/Basswood imminent

• Start on site due Sept 2014

• Completion due Oct 2015

���� Southdown House and Gatebeck House, East Dulwich Estate, SE22 19 Social Rented Units and 8 Shared Ownership Units - ringfenced allocations to East Dulwich Estate

• Start on site due –Nov 2014

• Completion due - Nov 2015

Crossways Church (a.k.a. Castle Resource Centre) Hampton Street, SE1 6 flats, 4 for social rent and 2 for church

• Planning application submitted -May 2014

• Start on site due - Jan 2015

• Completion due - Apr 2016

Direct Delivery Housing Programme Appendix 3

Page 4 As of June 2014

Phase 1 Progress Report