Cost Overruns in Transport Projects
- Experiences from Sweden
ANCHALEE JENPANITSUB
Master of Science Thesis
Stockholm, Sweden 2011
Cost Overruns in Transport Projects
- Experiences from Sweden
Master of Science Thesis
June 2011
Anchalee Jenpanitsub
Division of Transport and Location Analysis
Department of Transport Science
KTH Royal Institute of Technology, Stockholm
TSC-MT 11-018
1
Abstract
Cost overrun of transport projects is one of the most important problems in transport planning.
Apart from causing budget overruns, it also results in uncertain cost-benefit for decision making.
This thesis studies cost overruns in Sweden and internationally, factors affecting cost overruns
and possible improvements of cost calculations.
The literature study confirms that cost overrun problem is a global phenomenon. The average
cost overruns in rail projects are always higher than in road projects. We have compared cost
estimations and outcomes of 167 road and rail projects in Sweden during the period 1997-2009.
This reveals that average cost overruns are 11% (SD = 24.6%) and 21% (SD = 50.5%) for road
and rail projects, respectively. In Sweden, the average cost overrun in road projects is similar to
other countries, while the average cost overrun in rail projects is lower than in other countries.
However, the standard deviation of cost overruns in Swedish rail projects is very high. The cost
overruns in road and rail projects in Sweden have been constant for the 13-year period and cost
estimates have not improved over time. Furthermore, small Swedish transport projects (< 100
million SEK) have much higher percentage of cost overruns than large projects. To improve cost
estimates in Sweden, the Successive Calculation method has recently been applied. We have
collected data for 295 planned projects and find that the variance is significantly lower in these
than in actual outcomes, and that the difference is surprisingly small between projects in
different planning stages. Another method, Reference Class Forecasting, is demonstrated in
two case studies - Stockholm bypass and Västlänken. The two methods are also compared in
the thesis. For both case studies, the project costs by using the Reference Class Forecasting
method are higher than the project costs by using the Successive Calculation based on the
equal costs at 50% confident level of cost overrun.
2
This page is intentionally left blank.
3
Acknowledgements
It is pleasure to thank the many people who made this thesis possible. First and foremost, I am
heartily thankful to my supervisor, Mattias Lundberg, whose generosity, encouragement,
support and guidance from the initial to the final level enabled me to develop an understanding
of the subject. Without his assistance and patience, this thesis would never be as good as today.
I would like to thank Roger Pyddoke and Per Näsman for their valuable comments and
suggestions during thesis work.
I also would like to thank Pakpairin Uthairat, my good friend, for helping me out for with all kinds
of stuffs, including trying her best to do the proof reading of this thesis.
My special thanks go to my office – the Mass Rapid Transit Authority of Thailand, for
encouragement, and for giving me the opportunity of the study leave.
Lastly, and most importantly, I would like to thank my parents and my sister for their absolute
confidence in me, raising me in the loving environment, educating me well in arts and science,
and their unconditional endless love, support, understanding and encouragement throughout my
entire life. Without them, it would have been impossible for me to achieve all the success that
I have achieved throughout my life.
Anchalee Jenpanitsub
Stockholm, June 2011
4
This page is intentionally left blank.
5
Contents
Abstract ........................................................................................................................................................ 1
Acknowledgements ..................................................................................................................................... 3
List of Figures .............................................................................................................................................. 7
List of Tables ................................................................................................................................................ 9
List of Acronyms ........................................................................................................................................ 10
1 Introduction ........................................................................................................................................ 11
1.1 Purpose and scope of this thesis ........................................................................................... 11
1.2 Overview of state-of-the-art .................................................................................................... 12
1.3 Methodology .............................................................................................................................. 16
1.3.1 Research design ............................................................................................................... 16
1.3.2 Data .................................................................................................................................... 17
1.3.3 Disposition ......................................................................................................................... 17
2. Cost overrun problem ...................................................................................................................... 19
2.1 Previous studies ....................................................................................................................... 22
2.2 Cost overruns in Swedish transport projects ....................................................................... 31
2.2.1 Descriptive statistics ........................................................................................................ 31
2.2.2 Differences in cost calculations ...................................................................................... 34
2.3 Key findings and discussion ................................................................................................... 39
3. Factors contributing to cost overruns ............................................................................................ 41
3.1 Previous studies ....................................................................................................................... 41
3.2 Statistical methods ................................................................................................................... 48
3.3 Factors of cost overruns in Swedish transport projects ..................................................... 49
3.3.1 Types of projects .............................................................................................................. 49
3.3.2 Years of project completion ............................................................................................ 50
3.3.3 Sizes of projects ............................................................................................................... 55
3.3.4 Detailed project types ...................................................................................................... 58
3.3.5 Complexity ......................................................................................................................... 61
3.4 Key findings and discussion ................................................................................................... 64
6
4. Methods to improve cost estimations - Successive Calculation ............................................... 65
4.1 Successive Calculation method ............................................................................................. 65
4.1.1 General procedure ........................................................................................................... 65
4.1.2 Applications and limitations ............................................................................................ 71
4.2 Use in Swedish investment planning .................................................................................... 72
4.2.1 Successive Calculation in transport investment planning .......................................... 72
4.2.2 Cost variance analyses ................................................................................................... 75
4.2.3 Discussions ....................................................................................................................... 83
4.3 Key findings and discussion ................................................................................................... 84
5. Methods to improve cost estimations – Reference Class Forecasting ......................................... 85
5.1 Reference Class Forecasting method ................................................................................... 85
5.1.1 General procedure ........................................................................................................... 87
5.1.2 Applications and limitations ............................................................................................ 88
5.1.3 Probability distributions.................................................................................................. 100
5.2 Application in case studies ................................................................................................... 107
5.2.1 Case study projects........................................................................................................ 107
5.2.2 Results of road projects ................................................................................................. 110
5.2.3 Results of rail projects ................................................................................................... 114
5.3 Key findings and discussion ................................................................................................. 118
6. Conclusion and future research ..................................................................................................... 119
Appendix A: Data from VTI ................................................................................................................... 121
Appendix B: Statistical analyses .......................................................................................................... 122
Appendix C: Data from latest Transport Investment Plan ................................................................ 124
References .............................................................................................................................................. 125
7
List of Figures
Figure 1- 1 Flowchart of study. ............................................................................................................... 18
Figure 2- 1 Cost overrun study. .............................................................................................................. 21
Figure 2- 2 Inaccuracy of cost estimates in 167 road and rail projects. .......................................... 31
Figure 2- 3 Inaccuracy of cost estimates in road projects (a) and rail projects (b). ....................... 32
Figure 2- 4 Capital cost estimates – base estimate, inflation, and actual. ...................................... 37
Figure 2- 5 Price indexes for Swedish road projects (a) and rail projects (b). ................................ 38
Figure 3- 1 Inaccuracy of cost estimates in Swedish transport projects over time, 1997-2009. .. 51
Figure 3- 2 Inaccuracy of cost estimates in road and rail projects over time, 1997-2009. ........... 52
Figure 3- 3 Inaccuracy of cost estimates in road and rail projects over time with SD, 1997-2009.
.................................................................................................................................................................... 54
Figure 3- 4 Forecasted costs and inaccuracy of cost estimates. ...................................................... 56
Figure 3- 5 Distribution of inaccuracy of cost estimates by project sizes. ....................................... 56
Figure 3- 6 Distribution of inaccuracy of cost estimates in road projects (a) and rail projects (b)
by detailed project types. ........................................................................................................................ 59
Figure 3- 7 Complexity and inaccuracy of cost estimates. ................................................................ 62
Figure 3- 8 Complexity and inaccuracy of cost estimates by detailed project types. .................... 63
Figure 4- 1 Successive Calculation procedure. ................................................................................... 66
Figure 4- 2 Example of calculation details. .......................................................................................... 68
Figure 4- 3 Example of systematic and successive process. ............................................................ 69
Figure 4- 4 Example of S curve or cumulative distribution function related to the budget estimation. .. 71
Figure 4- 5 Example of the Successive Calculation result of the Stockholm bypass (Förbifart
Stockholm74 ................................................................................................................................................ .(
Figure 4- 6 Standard deviation of normal distribution. ........................................................................ 75
Figure 4- 7 Cost uncertainty during the project cycle. ........................................................................ 76
Figure 4- 8 Phases of transport planning. ............................................................................................ 77
Figure 4- 9 Comparison between road project variances and actual outcome. ................................. 78
Figure 4- 10 Comparison between rail project variances and actual outcome. .................................. 79
Figure 4- 11 Road project variances in different project sizes............................................................. 82
Figure 4- 12 Rail project variances in different project sizes. .............................................................. 82
Figure 5- 1 Explanatory power of optimism bias and strategic misrepresentation, respectively, in
accounting for forecasting inaccuracy as a function of political and organizational pressure. ..... 87
Figure 5- 2 Definition of Up-lifts within a certain class of transport scheme. ....................................... 88
Figure 5- 3 Probability distribution of cost overruns for road projects according to the UK study. .... 90
Figure 5- 4 Probability distribution of cost overruns for rail projects according to the UK study. ....... 91
8
Figure 5- 5 Probability distribution of cost overruns for fixed links projects according to the UK study.
.................................................................................................................................................................... 91
Figure 5- 6 Probability distribution of cost escalation for rail projects in the Netherlands.
Based on reference class of 68 projects. ................................................................................................ 94
Figure 5- 7 Road projects in Thailand. .................................................................................................. 95
Figure 5- 8 Road projects in the Philippines. ....................................................................................... 96
Figure 5- 9 COR histograms for highway and bridge projects in Vancouver Island. ..................... 98
Figure 5- 10 Inaccuracies of cost estimates of 167 road projects by the Erlang distribution.
(database from Flyvbjerg et al., p.17 [28]) ............................................................................................ 103
Figure 5- 11 Inaccuracies of cost estimates of 58 rail projects by the Erlang distribution.
(database from Flyvbjerg et al., p.17 [28]) ............................................................................................ 104
Figure 5- 12 Inaccuracies of cost estimations of the hybrid, RBE and convention methods
by Lognormal distribution. ..................................................................................................................... 104
Figure 5- 13 Examples of distributions in the thesis. ........................................................................ 106
Figure 5- 14 Stockholm bypass (Förbifart Stockholm). .................................................................... 108
Figure 5- 15 Västlänken. ....................................................................................................................... 109
Figure 5- 16 Probability curves of road projects. ................................................................................. 111
Figure 5- 17 Distribution of cost overruns of road projects. ............................................................. 111
Figure 5- 18 Required uplift of road projects...................................................................................... 112
Figure 5- 19 Cost estimations for road projects. ............................................................................... 113
Figure 5- 20 Probability curves of rail projects. ................................................................................. 115
Figure 5- 21 Distribution of cost overruns of rail projects. ................................................................ 116
Figure 5- 22 Required uplift of rail projects. ....................................................................................... 116
Figure 5- 23 Cost estimations for rail projects. .................................................................................. 117
9
List of Tables
Table 2- 1 Summary of reviewed studies. ............................................................................................ 29
Table 2- 2 Inaccuracy of transport project cost estimates by types of projects. ............................ 33
Table 2- 3 Comparison of cost overruns between Swedish transport projects and results of
Flyvbjerg studies. ..................................................................................................................................... 34
Table 2- 4 Comparison of cost overruns between Swedish transport projects and result of other
studies. ....................................................................................................................................................... 34
Table 2- 5 Cost of major rail projects (2005-2009). ........................................................................... 39
Table 3- 1 Summary of factors contributing to cost overruns. ........................................................... 47
Table 3- 2 Independent samples test by types of projects. .............................................................. 50
Table 3- 3 F-statistic of average cost overruns in road and rail projects over time, 1997-2009. 52
Table 3- 4 F-statistic of average cost overruns in road and rail projects, before and after 2005.
.................................................................................................................................................................... 53
Table 3- 5 Distribution of cost overruns in percent and in million SEK by project sizes............... 57
Table 3- 6 Distribution of cost overruns in percent and in million SEK by detailed project types.
.................................................................................................................................................................... 60
Table 3- 7 Test of homogeneity of variance of detailed project types. ........................................... 60
Table 4- 1 Two examples of applications and results in cost estimation by the Successive
Calculation. ................................................................................................................................................ 72
Table 4- 2 Descriptive statistics of road projects.................................................................................... 78
Table 4- 3 Descriptive statistics of rail projects. ..................................................................................... 79
Table 4- 4 Variances by project sizes. .................................................................................................. 81
Table 5- 1 Categories and types of projects used as basis for Reference Class Forecasting. ... 89
Table 5- 2 Required uplifts by the Reference Class Forecasting according to the UK study. ..... 92
Table 5- 3 Descriptive statistics of estimation errors in the three samples in Australia. ............... 97
Table 5- 4 COR probabilities of highway projects in Vancouver Island. .......................................... 99
Table 5- 5 Cost overruns probability estimation comparison between Monte Carlo method
and Beta Distribution Fitting method. .................................................................................................. 101
Table 5- 6 Goodness-of-fit Statistics of distributions of road and highway projects in VIHP. .... 102
Table 5- 7 Types of projects used as basis for Reference Class Forecasting of road projects. 110
Table 5- 8 Cost uplifts for selected percentiles of road projects. .................................................... 112
Table 5- 9 Types of projects used as basis for Reference Class Forecasting of rail projects. .. 114
Table 5- 10 Cost uplifts for selected percentiles of rail projects. .................................................... 117
10
List of Acronyms
Acronym Name
ADB Asian Development Bank
ANOVA Analysis of Variance
BART San Francisco Bay Area Rapid Transit
CBA Cost-Benefit Analysis
COR Cost Overrun Ratio
CPI Consumer Price Index
CV Critical Value
FDOT Florida Department of Transportation
FTA Federal Transit Administration
HEATCO Harmonised European Approaches for Transport Costing
and Project Assessment
INDOT Indiana Department of Transportation
JBIC Japan Bank for International Cooperation
MLE Maximum Likelihood Estimation
NPI Net Price Index
PASW Predictive Analytics Software
PPP Public Private Partnership
RBE Risk-Based estimating
RCF Reference Class Forecasting
RRV Riksrevisionsverket (Swedish National Audit Bureau)
SIKA Swedish Institute for Transport and Communications Analysis
SD Standard Deviation
SOC Social Overhead Capital
SPSS Statistical Package for the Social Sciences
SvD Swedish newspaper Svenska Dagbladet
TIE Transport Initiatives Edinburgh
UMTA Urban Mass Transportation Administration
VIHP Vancouver Island Highway Project
VTI Swedish National Road and Transport Research Institute
WBS Work Breakdown Structure
Introduction 11
1 Introduction
1.1 Purpose and scope of this thesis
The purpose of this thesis is to study cost overruns in Sweden and internationally, factors
affecting cost overruns and possible improvements of cost calculations.
The following topics are analysed in this thesis;
The situation and trend for cost overruns in transport projects in Sweden and internationally.
General descriptive statistics for transport projects in Sweden.
Factors that affect cost overruns in transport projects.
How cost calculations are currently carried out in Sweden, particularly how the Successive
Calculation method is applied.
A probability distribution of cost overruns for transport projects in Sweden. This is used to
test the Reference Class Forecasting method for two case studies.
Transport projects contribute to the development of societies. The countries that provide
efficient transport investments with good management have develop in social, economic and
environment dimensions. Unfortunately, transport investments are plagued by cost overrun and
benefit shortfall problems. The implementations of transport projects with such problems will
lead to risks for the wrong prioritization and costly delay. These problems are found not only in
transport projects but occur in other kind of projects such as water projects, power plants, ICT
systems and urban and regional development projects [1] [2].
The desire of decision makers is to improve the returns from the limited budget. In this process,
Cost-Benefit Analysis (CBA) has been an important tool for evaluating and ranking transport
investments for several decades [3]. The cost overrun and benefit shortfall problems lead to
incorrect CBAs because CBA depends on cost and benefit forecasts. However, this thesis only
concentrates on cost estimates.
In recent years there has been an increased interest in cost overruns in transport projects in
Sweden and elsewhere e.g. in Norway, Australia, England and Canada. New methods, such as
Successive Calculation and Reference Class Forecasting, have been developed to improve the
cost calculations. These methods are intended to lead to better cost estimates and thus better
CBAs as well as a better control over public investment budgets. However strong emphasis on
decreasing cost overruns, may induce incentives to adapt in both desirable and undesirable
ways. Examples of undesirable consequences could be;
Introduction 12
Adding reserve funds to projects may lead to heterogeneous assessments and deceptive
representations of relative merits of projects. Such reserves may in turn induce lead risks for
inefficient designs and overspending [4]. Good incentives in the planning phase are therefore
important.
Undesired reductions of quality: With too much emphasis on reaching cost targets projects
are likely to be constructed below at the intended standard levels. Some items for
implementing on projects such as environmental and safety aspects risk being compromised
or even being removed. In such cases the real costs can become higher as the deficiencies
have to be corrected later.
Incentives to postpone the construction of dimensions representing secondary objectives
like environment and safety.
These potential consequences will also be addressed in this thesis. How to deal with cost
overrun problem is the motivation to do this research. Lessons learnt from Swedish transport
projects are studied in order to find the better methods and/or practical applications of cost
calculation. Our hope is that this will consequently contribute to more efficient transport planning
in the future. Moreover, the thesis can be a part of an evaluation of the first use of Successive
Calculation in transport planning in Sweden.
1.2 Overview of state-of-the-art
This section gives an overview of the cost overrun problems and the methods to handle them.
More about different aspects of this are found in each chapter of the thesis.
The definition of the cost overruns or inaccuracy in cost forecasts is measured as actual cost
minus forecasted cost as a percentage of forecasted cost [5]. An inaccuracy of zero shows that
the forecasted cost for the project is correct and thus equals actual cost. Forecasted cost is the
estimate made at the time of decision to build, or as close to this as possible. Actual cost is the
output of construction cost measured after the project is completed. All costs are calculated in
constant prices or inflation-adjusted currencies.
From the studies of Bent Flyvbjerg and others [1] [2] [5] [6], key observations about the cost
overruns in transport projects (based on a sample of 258 transport projects in 20 countries on 5
continents) are:
9 out of 10 projects have cost overruns;
Overrun is found across the 20 nations and 5 continents;
Introduction 13
The average cost overruns are 45%, 34% and 20% for rail projects, bridges and tunnels,
and road projects, respectively;
Overrun is constant for the 70-year period and cost estimates have not improved over time.
Many transport projects have experienced cost overruns. To mention only a few:
One is the Channel tunnel, the longest underwater rail tunnel in Europe, connecting France
and the UK [2]. It opened in 1994. The construction cost was 80% over budget and revenues
were half of those forecasted. As a consequence, the internal rate of return was
negative, at -14.5%. An economic and financial ex post evaluation of the project concluded
that “the British Economy would have been better off had the Tunnel never been
constructed” [2].
The next example is the Danish Great Belt rail tunnel, the second-longest underwater rail
tunnel in Europe. It opened in 1998. The construction cost was 120% over budget and the
project proved nonviable even before it opened [2]. Only by cross-subsidizing the tunnel with
revenues from a nearby motorway bridge was it possible to pay for the tunnel [2].
Another example is the Ōedo Line, Tokyo's first linear motor metro line which allows it to use
smaller cars and smaller tunnels [7]. It opened in 2000. The original budget was ¥682.6 billion
and the final cost of this construction ranged from ¥988.6 billion to over ¥1,400 billion or
105% of cost escalation [7].
The next example is the Central Artery/Tunnel project (CA/T), known unofficially as the Big
Dig. It is a megaproject in Boston that rerouted the Central Artery (Interstate 93) into a 5.6-
km tunnel [8]. Although the CA/T project cost was estimated in 1985 at US$6.0 billion
(adjusted for inflation as of 2006), over US$14.6 billion had been spent as of 2006 or a
143% cost escalation [8].
The last example is Edinburgh Trams. It is a tramway system which is currently under
construction (2011) in Edinburgh, Scotland [9]. With an original budget at a cost of £375
million in 2003, the cost of this tram system is now uncertain, and it is anticipated to be over
£600 million [9]. It was originally scheduled to enter service in February 2011 but had to
postpone the opening to 2014 because of the budget problem. In February 2011, there was
an article – “Time‟s up: Today‟s the day the first tram should have been running in
Edinburgh” published by Edinburgh Evening News [10]. The article stated that “The German
engineering giants charged with building the line have revealed that 72% of the construction
work remains with just 38% of the budget left.”
Introduction 14
The above projects are all examples of the cost overruns in transport megaprojects. However, it
is also a serious problem for routine or small-sized transport projects. For instance, the average
cost overrun was 5.9% for 127 road projects in the Vancouver Island Highway Project (VIHP)
implemented during 1993-2003 [11]. Furthermore, a study of 620 Norwegian road projects
constructed during 1992-1995 showed that there was 7.9% cost overrun on average [12]. A
recent study revealed an average 19% cost overrun for 36 road construction projects in
Slovenia (1995-2007) [13].
In Sweden, like other countries, the development of the infrastructure of the country is a major
term in the state budget. In December 2008, the Swedish Parliament decided to allocate 417
billion SEK for the transport infrastructure projects in the period 2010-2021 [14]. Cost overrun
problem is one of the key challenges for those investments since the problem has been large in
previous Swedish transport projects. The studies about the cost overrun problems in Swedish
transport projects are presented below.
The first study was conducted in 1994 by the Swedish National Audit Bureau
(Riksrevisionsverket: RRV) [15]. They investigated the performance of 8 road projects built by the
Road Administration (Vägverket) and 7 rail projects by the Rail Administration (Banverket)1. The
average cost overrun for the road projects was 86% (2-182%) and the average overrun for the
rail projects was 17% (-14-74%). In 2002, there was a study by the Swedish Institute for
Transport and Communications Analysis – SIKA. They examined cost outcomes of road and rail
projects which opened to service during 1997-1999. The key finding was that the average cost
escalations were 10% and 20% for road and rail projects, respectively [16]. SIKA also provided
one more study about cost overruns in 2002 [17]. They concluded that the average cost overruns
were 5% for the road projects and 14% for the rail projects which were opened during 1997-
2000. SIKA recommended that the Transport Administrations should calculate expected cost
overruns based on these outcomes including the standard deviations.
Recently, there were two audit reports provided by the Swedish National Audit Office
(Riksrevisionen). These reports showed the different cost overruns compared with calculations
made by the Transport Authorities. The main reasons for differences are found in assumptions
such as price index and what decision is used as the estimated cost. The first audit report was
published in 2010 and showed the results from road projects [18]. One of the key results was that
the total costs of road investments completed between 2005 and 2009 based on the Swedish
National Audit Office calculations increased at 8-18% while based on the Vägverket calculations
1 The Road and Rail Administrations were merged into a Transport Administration (Trafikverket) in April 2010.
Introduction 15
they were around -1% (means cost saving or no cost overrun). The second study was published
in 2011 and concerned rail projects [14]. A finding was that the average cost overrun for the rail
projects completed between 2005 and 2009 based on the Swedish National Audit Office
calculations was 55% while based on the Banverket calculations they were on average 26%.
Moreover, the Swedish National Audit Office concluded that the cost overruns problem as noted
by the RRV 15 years ago still remained and they could not see that any real improvements had
occurred in this aspect.
Responding to the last audit report by the Riksrevisionen, the Government has recently reported
that several steps have been taken to create cost control for major rail investments [19]. One of
the most important steps was the introduction of the Successive Calculation. The Successive
Calculation is a cost calculation method that was developed in the 1970‟s in Denmark. It has
had a limited use in Sweden, but was used to calculate the project costs in the latest national
transport investment plan for the period 2010-2021. The government has emphasized that
experiences are needed to be drawn from this first major use of the Successive Calculation
method.
Beyond the studies of cost overruns problem above, the Swedish media also publish their own
reports on this problem. For example, the Swedish newspaper Svenska Dagbladet (SvD)
published an article on 6 April 2011 [20] – “Uncontrollable note for light rail construction -
Skenande nota för spårvägsbyggen”. SvD revealed that the final bill for the first part of the
Stockholm ongoing light rail or city tram (between Hamngatan and Waldemarsudde) will be 380
million SEK which is 67% more than the planned cost (228 million SEK).
In sum, the cost overrun problem is one of the most important problems in transport planning.
According to the literature, the cost estimates used in transport planning are systematically and
significantly misleading. Cost overrun problems seem to be a global phenomenon. Thus, we
cannot avoid confronting the problem.
Introduction 16
1.3 Methodology
1.3.1 Research design
The study process has been as shown in Figure 1-1. It was initiated by doing literature studies
about the cost overruns in overall.
We study the situation and trends for cost overruns in transport projects in Sweden and
internationally. The material used for the study come from academic papers and independent
government audits. Regarding cost overruns in Sweden, we also analyse transport project cost
data from a database collected by VTI, Swedish National Road and Transport Research
Institute (detail of the data is shown in next section) and complemented in this study. The output
are general descriptive statistics such as average overruns and standard deviations (SD) for
both road and rail projects. The general descriptive statistics are compared with the results from
previous studies.
The next step is the study of what factors affect cost overruns for transport projects in Sweden
and internationally. In the VTI data, we test whether different main project types (i.e. road and
rail projects) perform differently with regard to cost overruns. We also test whether overruns
varies with year of project completion, size of project, detailed project type and complexity.
Then, we study the current method used to estimate project costs in Sweden – the Successive
Calculation. The general procedure of the method including applications and limitations is
reviewed. Next, how the method has been applied in Swedish investment planning is studied by
analysing a database on results of cost calculations using the method. To see the cost variance,
we calculate cost at 85% confident limit (the probability of keeping to budget) minus cost at 50%
confident limit as a percentage of cost at 50% confident limit. The average cost variances by
this method are then compared to the actual outcomes. In addition, we analyse the cost
variance in each planning phase.
Next, a new method called “Reference Class Forecasting (RCF)” is studied. As with the study of
the Successive Calculation, the general procedure of the RCF method including applications
and limitations is reviewed. The key concept of this method is to examine the experiences of a
class of similar projects, lay out a rough distribution of outcomes for the reference class, and
then position the current project in that distribution. Before demonstrating how to apply this
method, we review which distribution provides the best fit for the VTI project cost database.
Then, we apply the RCF method to estimate the project costs of our case studies. The case
study for road projects is the Stockholm bypass (Förbifart Stockholm). The case study for rail
Introduction 17
projects is the Västlänken tunnel in Göteborg. The cost estimations of the two case studies are
compared with the total costs estimated by the Successive Calculation method. The cost
variance results by the RCF method are compared with the cost variance analysed by the
Successive Calculation method. Lastly, we conclude our findings and suggest future
researches.
1.3.2 Data
In the thesis, there are two databases as shown in Figure 1-1. The first database is data on cost
estimations and outcomes of road and rail projects in Sweden which were completed during
1997-2009. The data are published in yearly reports from Vägverket and Banverket which had
originally been collected at the VTI and has then been complemented in our study. After refining
the data, 102 road projects and 65 rail projects are used in our analysis. The second database
is data on results of cost calculations using the Successive Calculation method. They are
collected from the projects in the latest national investment plan that covers the period 2010-
2021. For road projects, we receive the data from the Transport Administration calculation
sheets. For rail projects, we find the data from the Transport Administration website. The data
comprise 249 road projects and 46 rail projects.
1.3.3 Disposition
The thesis is organized as follow. This chapter serves as a first chapter which provides general
information of this thesis including cost overrun background. Chapter 2 further describes the
cost overrun problems in Sweden and internationally based on previous studies. This chapter
also provides the general descriptive statistics for transport projects in Sweden. Chapter 3
presents factors that affect cost overruns in transport projects. Chapter 4 and Chapter 5 show
the methods to improve cost estimations – the Successive Calculation and the Reference Class
Forecasting, respectively. Finally, Chapter 6 gives conclusions and a discussion, as well as
ideas for future researches.
Introduction 18
Preliminary literature study
Proposal preparation
Transport projects in Sweden
Analysis, comparison and application
Total picture and
statistics analysisVTI data
(102 Road + 65 Rail)
Reference Class Forecasting
- establishes probability
distribution for relevant reference
class (Road, Rail)
- Two case studies (Stockholm
bypass and Västlänken)
Conclusion and future research
Differences between
different types; Factors
- Year of project completion
- Project size
- Detailed project type
- Complexity
Statistics comparison with
previous studies
- Average inaccuracy (%)
- Standard deviation (SD)
Literature studies in each topic
Methods to improve cost estimations
Transport projects in
latest plan data
(249 Road + 46 Rail)
Successive Calculation
- Calculates cost intervals
analysis (Road, Rail)
- Shows an example
(Stockholm bypass)
Comparison
Cost variance
Cost estimations
- Stockholm bypass
- Västlänken
Figure 1- 1 Flowchart of study.
Cost overrun problem 19
2. Cost overrun problem
Cost overrun, sometimes called „cost increase‟ or „cost escalation‟, in transport projects is one of
the most important problems in transport planning as mentioned earlier. However, studies about
cost overruns are rather few. Unlike other kind of studies, the rigorous study of cost overruns
not only comes from academics but also independent government audits [21] as shown in Figure
2-1. The conventional cost overrun study has been carried out by academics at universities and
research institutes. The data of the studies are collected by the researchers themselves
(published sources or direct contacts), or come from other studies and audit reports. The study
results, including recommendations and new methods for better cost estimation are published in
scholarly articles, books and journals. In some cases, the transport organizations or authorities
employ academics and/or private consultants to study the cost overruns of their projects. In
these cases, the data can be acquired directly from the transport organizations. Sometimes, the
transport authorities do the cost overrun analysis by themselves.
The independent government auditors are responsible for monitoring the accountability,
effectiveness and efficiency of public spending. They give recommendations to the Parliament
on how to improve the use of the national budget. In some countries, government auditor
provides detailed investigations to explain the causes of cost overruns and study the frequency
and magnitude of cost overrun. Even though, the academics and the independent government
auditors have the same main interest which is cost overruns in transport projects, they have
different mandates, objectives and access to data. The academics use data from the
independent government auditors to their studies. However, the academics mainly refer to other
academic studies and often conduct less systematic analysis than independent government
auditors. In recent years, it has been found that the independent government auditors more
often refer to the academic studies than previously. An increased cooperation between the two
groups is needed in the future for better understand cost overruns and how they can be
avoided.
The definition of the cost overrun or inaccuracy in cost forecasts is measured as actual cost
minus forecasted cost as a percentage of forecasted cost (Equation 2.1) [5]. Forecasted cost is
the estimate made at the time of decision to build, or as close to this as possible if no estimate
was available for the decision to build. Actual cost is the construction cost measured after the
project was completed. All costs are calculated in constant prices or inflation-adjusted
currencies. This definition is used in the majority of the scholarly studies [21].
Cost overrun problem 20
For academics, the early studies of cost overruns in transport projects are the studies of
Merewitz in 1973 [22]. The Merewitz‟s studies compared cost overrun in urban rapid transit
projects including the San Francisco Bay Area Rapid Transit (BART) system. However,
Flyvbjerg and others [22] claimed that these studies had not produced statistically valid results.
Moreover, they stated that their study in 2002 was the first statistically significant study of cost
overruns in transport projects. Based on the 258 transport projects in 20 nations, they found that
9 out of 10 transport projects had cost escalation. The average cost overruns were 45%, 34%
and 20% for rail, fixed-link, and road projects, respectively. They concluded that the cost
escalation appeared as a global phenomenon. The overrun was constant for the 70-year period
and cost estimates had not improved over time.
Regarding independent government auditors, Siemiatycki [21] studied 13 audit reports (9 reports
from United States, 2 reports from England and 2 reports from Canada). These audit reports
cover rail, road and bridge projects completed between 1980 and 2007. The auditors studied
the performances of delivering transport projects by variety of sample sizes and different types
of investments. They systematically measured the frequency and magnitude of cost overruns in
transport sector.
In this chapter, the previous cost overrun statistics results are presented and summarized. The
VTI data is also analysed. Only statistics of the cost overruns are focused in this chapter such
as average cost overruns and standard deviations.
Equation 2.1
Cost overrun problem 21
Transport Authority
responsible for cost estimation
Independent government auditor Academic/Private Consultant/Transport Authoritypublished
sources or
direct contacts
Audit report and recommendationStudy result, recommendation and new
methods for better cost estimation
Parliament/GovernmentPublication
other studies
· The Independent government auditors
responsible for monitoring the
accountability, effectiveness,
efficiency, and probity of public
spending and providing
recommendations to Parliament on
how to improve using the national
budget.
· In some countries, government
auditors provided detailed
investigations to explain the causes of
cost overruns and studied the
frequency and magnitude of cost
overrun.
Flyvbjerg 2002
Study with small number of projectsEarly studies
since 1970's
Study with large number of projects
Study with large sample and
different project typesRecent studies
Figure 2- 1 Cost overrun study.
Note: Adapt from Siemiatycki [21]
, Flyvbjerg et al. [22] [23]
Cost overrun problem 22
2.1 Previous studies
The summary of previous studies is as shown in Table 2-1. The following is the brief result of
each study.
Urban Mass Transportation Administration (UMTA), 1990 [24]
The study was carried out by the UMTA (currently the Federal Transit Administration: FTA). This
study covered 10 major transit capital investment projects in the U.S. They were constructed
with partial federal financing during the period 1971-1987, with a total value of US$ 15.5 billion
at 1988 prices. 9 of 10 projects had cost overruns. The average cost overrun was 52% with the
standard deviation (SD)1 29%.
Transport and Road Research Laboratory, 1990 [25]
The Transport and Road Research Laboratory in the England studied the performance and
impact of Rail Mass Transit in 21 developing countries. Only 13 of the 21 metros capital cost
overruns could be estimated. Almost all of the metro systems incurred higher costs than
expected. Only the Hong Kong mass transit railway and the Proto Alegre metro in Brazil were
completed within budget. 6 metros had overruns above 50%.
Riksrevisionsverket, 1994 [15]
The Swedish National Audit Bureau (Riksrevisionsverket: RRV) investigated the performance of
8 road projects and 7 rail projects in Sweden with a total value of 13 billion SEK at 1994 prices.
The average capital cost overrun for the road projects was 86%, ranging from 2 to 182%, and
the average overrun for the rail projects was 17%, ranging from minus 14 to 74%. However, two
thirds of the projects were still under construction when the study was carried out. Therefore the
actual costs for these projects might be higher than the expected actual costs by the RRV [26].
Office of Program Policy Analysis and Government Accountability, 1996 [27]
The Office of Program Policy Analysis and Government Accountability reviewed the Florida
Department of Transportation‟s (FDOT) performance in controlling cost overruns and delays for
road and bridge projects. They investigated 3,969 construction contracts in Florida completed
during 1980-1995. Cost overruns had increased from an average of less than 2% during fiscal
years 1980-81 through 1984-85 to an average of 15% by fiscal year 1994-95.
1 The standard deviation (SD) is the square root of the average error between the mean and the
observations made [42]
(see more details in Appendix B).
Cost overrun problem 23
Skamris and Flyvbjerg, 1997 [26]
This article studied inaccuracy of traffic forecasts and cost estimates on large transport projects.
On seven large Danish bridge and tunnel projects since 1960, construction costs had been
underestimated (average cost overrun was 14%) and traffic had been overestimated in the initial
phases of planning. Cost overrun and benefit shortfall pattern is also found in studies from other
countries of large transport projects. The result of this overoptimism in the initial phases of
planning was that decisions were based on misleading forecasts that might lead to a
misallocation of funds and underperforming projects.
Swedish Institute for Transport and Communications Analysis (SIKA), 2002 [16] [17]
In 2002, there was a study by the SIKA. They examined cost outcomes of road and rail projects
in Sweden which were opened to service during 1997-1999. The key finding was that the
average cost escalations were 10% and 20% for road and rail, respectively. SIKA also provided
one more study about cost overruns in 2002. They concluded that the average cost overruns
were 5% for the road projects and 14% for rail projects which were opened during 1997-2000.
They recommended that the Transport Administrations should calculate expected cost overruns
based on these outcomes including the standard deviations.
Flyvbjerg, Holm, and Buhl, 2002 [22] , 2003 [6] [28] and Priemus, Flyvbjerg and Wee, 2008 [5]
In 2002, Bent Flyvbjerg and others carried out the first statistically significant study of cost
performance in transport projects. This is the only one study that covered the international
comparison. Based on a sample of 258 transport projects in 20 nations completed in 1927-
1998, they found that 9 out of 10 transport projects had cost overruns. On average, cost
overruns were 45% (SD=38%), 20% (SD=30%) for 58 rail projects and 167 road projects,
respectively. They concluded that cost overrun was a global phenomenon. The overrun was
constant for the 70-year period and cost estimates had not improved over time.
Federal Transit Administration (FTA), 2003 [29]
As mentioned, the UMTA [24] studied 10 major transit projects in the U.S. which opened between
1975 and 1990. Later, the FTA investigated 21 rail and busway projects that opened between
1990 and 2002. The capital costs of projects on average were 21% greater than the initial
estimates.
Cost overrun problem 24
Odeck, 2004 [12]
The study showed the cost overruns of road construction based on data of 620 Norwegian road
constructions during 1992-1995. The mean cost overrun was 7.9% ranging from -59% to 183%
(SD=29.2%). An interesting finding was that cost overruns appeared to more predominant
among smaller projects as compared to larger ones. Other factors found to influence the size of
cost overruns included completion time of the projects and the region where projects are
situated.
Indiana Department of Transportation (INDOT), 2004 [30]
The results of an agency survey showed that with regard to the problem of cost overruns, the
INDOT had an average rank compared to other states. The overall rate for cost overrun
amounts for the 2,668 road construction and maintenance projects by the INDOT between 1996
and 2002 was 4.5%. Moreover, 55% of all INDOT contracts experienced cost overruns. It was
determined that the average cost overrun amount and rate differed by project type. The average
cost overrun rates of bridge projects, road construction, road resurfacing, traffic projects and
maintenance projects were 8.1%, 5.6%, 2.6%, 5.6% and 7.5%, respectively
Dantata et al., 2006 [31]
This paper compared the results of the UMTA report [24] to cost overruns of transit projects
completed after 1990. The projects were on federally funded rail projects in the United States.
From comparison with selected 16 transit rail projects, they concluded that there was evidence
to suggest that cost overruns for projects completed before 1990 were different from that of
projects complete after 1994 (i.e. cost overruns had become smaller from 52% to 30%).
However, the data was not statistically proved this at a level of significance of 5%.
Wu, 2006 [11]
The study was analysed common risk factors and proposed analysis models for cost overrun
risk analysis in transport investments. The Vancouver Island Highway Project (VIHP) database
was used. There were 127 road and highway construction projects, 36 bridge and tunnel
projects in Canada implemented during 1993-2003. The average cost overruns were 5.9%
(SD=27%) and 5.2% (SD=23%) for road and bridge projects, respectively.
Cost overrun problem 25
UK National Audit Office, 2007 [32]
The study was examined how the costs of building and improving roads were estimated and
monitored from early forecasts through to the final cost of schemes. The UK Department for
Transport had approved expenditure of over £11 billion between 1998 and 2021 for the
development of new and existing trunk roads and motorways in the UK by the Highways Agency
and under £1.7 billion on major road schemes which were proposed and developed by the local
authorities. By 2006, the 36 schemes by the Highways Agency had been completed and had
cost 6% more than estimated. By 2006 the 20 schemes by the local authorities completed had
cost 18% more than initially estimated.
Flyvbjerg, 2007 [33]
The study presented the risks of cost and demand in urban rail projects. “Urban rail” was
defined as rail in an urban area, including both heavy and light rail, which may be underground,
at level or elevated. A sample of 44 urban rail projects was analysed (1966-1997). From the
previous data of Flyvbjerg‟s study [22], the 44 urban rail projects were a subset of the data (58 rail
projects). 18 projects were located in North America, 13 projects were in Europe and 13 projects
were in developing nations. The average cost overrun of the urban rail projects was 44.9%
(SD=37.3%). It also reported the average cost overrun of the other rail projects (14 rail projects)
was 44.1% (SD=43.3%).
Roxas Jr. and Chalermpong, 2008 [34]
They studied the cost forecasting inaccuracies in road and bridge projects in Thailand and the
Philippine. It had been verified that there were no significant differences in cost forecasting
inaccuracies between road and bridge projects. In Thailand, average cost overrun of 44 road
and bridge projects was -10.8% (SD=30.5%)2. The negative value for the average cost overrun
2 The authors indicated that the forecast inaccuracies found in Thailand and the Philippines were much
smaller in magnitude compared to those found from previous studies. However, due to the small sample
size of the database in this study, it might not be a representative of the population used and thus the
results should be interpreted with caution. Moreover, most of the projects considered in this research
were funded by international agencies such as the Asian Development Bank (ADB), World Bank and the
Japan Bank for International Cooperation (JBIC). Therefore, locally funded projects and Public Private
Partnership (PPP) projects were not well represented in the database. They also explained that
Flyvbjerg‟s database was bigger and more diverse. There were more projects included and the project
size in terms of the project cost was much bigger when compared to their study.
Cost overrun problem 26
indicated that the actual cost was less than the forecasted cost. In Philippines, average cost
overrun of 85 road and bridge projects was 5.4% (SD=35.9%).
Lee J.K., 2008 [35]
This study was carried out cost overrun and cause in Korean Social Overhead Capital (SOC)
projects i.e. roads, rails, airports, and ports. There were data of 161 completed projects, which
was including 138 road projects, 16 rail projects, 2 airport projects and 5 port projects from 1985
and 2005. The results indicated that 95% and 100% of road and rail projects, respectively, had
a maximum cost overrun of 50%. The average cost overruns were 11% and 48% for road and
rail projects, respectively.
Federal Transit Administration, 2008 [36]
The study based on the previous studies by the UMTA [24] in 1990 and the FTA [29] in 2003. It
was conducted an analysis of the predicted and actual impacts of 21 major transit projects in the
U.S. (opened 2003-2007). On average, the actual construction costs exceeded the inflation-
adjusted estimates by 40.2%. The average cost overrun in this study was higher than the result
of study in 2003. However, the cost estimates of the projects in 2003 and 2007 were more
accurate than was found in the 1990 UMTA study. Thus, there was an improvement in cost
estimations for major transit projects in the U.S.
Singh, 2009 [37]
This study investigated the delays and cost overruns in public funded infrastructure projects in
India. The author concluded that the problem of time and cost overruns in India was widespread
and severe. The 894 projects from 17 infrastructure sectors in the period 1992-2009 were
analysed including 122 railway projects and 157 road and highway projects. The railway
projects had average cost overruns at 95% (SD=179%) while road projects had cost overrun at
16% (SD=62%).
Cost overrun problem 27
RGL Forensics, Faber Maunsell/Aecom and Frontier Economics, 2010 [37]
The paper provided for the European Commission on Ex post Evaluation of Cohesion Policy
Programmes 2000-2006. They analysed 19 rail, 21 road and 7 urban transport projects located
in Germany, Spain, France, Greece, Ireland, Italy, Poland and Portugal. It showed that average
cost overruns were 26.9%, 9.4% and 45.4% for rail, road and urban transport, respectively. The
study was also studied water and energy projects and the total average cost overruns was
21.2%.
Chevroulet and Reynaud, 2010 [38]
The study investigated 6 European high speed rail projects i.e. Frankfurt-Cologne ICE,
Eurotunnel, Öresund Fixed Link, Paris-Lille TGV, Madrid-Sville AVE and Lyon-Marseilles TGV.
The cost overruns ranged from 8% to 116% with 51% on average (SD=40%).
Riksrevisionen, 2010 [18] 2011 [14]
There were two audit reports provided by the Swedish National Audit Office (Riksrevisionen).
They showed the differences of cost overruns compared with calculations made by the
Transport Authorities. The main reasons are differences in assumptions such as price index and
what decision is used as the estimated cost. The first audit report was published in 2010 and
showed results from 35 road projects completed between 2005 and 2009 [18]. One of the key
results was that cost overruns of road investments were at 8-18%. The second study was
published in 2011 and concerned 28 rail projects completed between 2005 and 2009 [14]. A
finding was that the average cost overrun for the rail projects was 55%.
Makovsek et al., 2011 [13]
In this study, the authors focused on cost performance of road infrastructure constructed
through the National Motorway Construction Programme in Slovenia. It was found that 19%
(SD=46.1%) cost overrun for 36 road projects which were completed in the period 1995-2007.
Cost overrun problem 28
Summary
The summary of the literature above is shown in Table 2-1. The literature confirms that the cost
overrun problem in transport projects is a global problem3. Cost overruns in transport projects
happen around the world – the U.S., Canada, the Philippines, South Korea, India, Sweden,
England and Slovenia. Most of the studies focus on the problems on a national level and two of
the studies analyses the problems on a continental level (in Europe). There is only one
database used in the studies of Bent Flyvbjerg and others that shows international results of
cost overruns in transport projects.
Almost all of the studies that examines both road and rail projects (6 of 7 studies) show average
cost overruns for road projects that are lower than the cost overruns for rail project4. In road
projects, the mean cost overruns range between 4.5% (2,668 road projects in Indiana, USA)
and 86% (8 road projects in Sweden). In rail projects, the cost overruns are between 14% (rail
projects in Sweden) and 95% (122 railway projects in India). Cost overruns of less than 10% are
found in 8 studies and all of them deal with cost overruns for road projects. In the next section,
comparisons between cost overruns in Swedish transport projects and the results of the above
studies are shown.
3 Only one study by Roxas Jr. and Chalermpon showed cost underrun but the study was not well
represented results as explained.
4 There was only one study by Riksrevisionsverket in 1994 that indicated that the average cost overrun for
road projects was higher than the average cost overrun for rail projects.
Cost overrun problem 29
Table 2- 1 Summary of reviewed studies.
Number and types of project examined
Years covered by
study sample
Countries covered in
sample
Average estimated cost per project
Average difference of cost (%)
Standard deviation
Min. - Max. difference of
cost (%)
Percentage of projects
experiencing escalating
project costs
Authors/Year of publish
Type of study
Ten major transit projects 1971-1987 USA. $1.5 billion 52% 29 -11% - 106% 90% UMTA /1990 Academic1
15 projects: 7 rail; 8 road
Before 1994 Sweden $130 million2 7 rail: 17%
8 road: 86% N/A -14% - 74%
2% - 182% 71%
100% Riksrevisionsverket/1994
Audit
3,969 construction contracts by FDOT
1980-1995 Florida, USA. $1.7 million 7%3 N/A 0.8% - 15.1% N/A Office of program
Policy Analysis and Government Accountability/1996
Audit
Seven large bridge and tunnel projects
Since 1960 Denmark N/A 14%4 N/A -10% - 33% 71% Skamris,
Flyvbjerg/1997 Academic
Rail and road projects 1997-2000 Sweden N/A Rail: 14% Road: 5%
27 20
N/A N/A SIKA/2002 Academic
258 projects: 58 rail; 33 fixed-link; 167 road
1927-1998 20 countries on 5 continents
$348 million ($1.5 million - $8.5 billion)
Overall: 28% 58 rail: 45% 33 fixed-link: 34% 167 road: 20%
39 38 62 30
N/A 86% Flyvbjerg, Holm, and Buhl/2002, 2003 and Priemus, Flyvbjerg and Wee/2008
Academic
21 rail and busway projects 1990-2002 USA. $524 million ($98 million - $4.4 billion)
21% N/A -28% - 72% 76% Federal Transit Administration/2003
Academic2
620 road projects 1992-1995 Norway Less than $100 million
8% 29 -59% - 183% 52% Odeck/2004 Academic
2,668 road construction and maintenance projects
1996-2002 Indiana, USA. N/A 4.5% N/A N/A 55% INDOT/2004 Academic2
16 urban rail 1995-2004 USA. $486 million ($94 million-
$1,625 million)
30% 39 -28% - 133% 81% Dantata et al./2006 Academic
127 road projects 36 bridge projects
1993-2003 Canada N/A 127road: 5.9% 36 bridge: 5.2%
27 23
4.8% - 23.4% 8.0% - 19.0%
82% 81%
Qing Wu/2006 Academic
36 road projects by National Highway Agency 20 road projects by Local Authorities
2002-2006 England $65 million
$24 million
National Highway: 6% Local Authorities : 18%
N/A N/A 64%
N/A
UK National Audit Office/2007
Audit
1 The study was studied by academic and/or private consultant. It was sponsored by transport authority.
2 Adjust by current exchange rate (1 SEK = $0.15).
3 The average value was calculated from cost overruns in all fiscal years of the study.
4 The average construction cost overrun was only for the five completed projects.
Cost overrun problem 30
Number and types of project examined
Years covered by
study sample
Countries covered in
sample
Average estimated cost per project
Average difference of cost (%)
Standard deviation
Min. - Max. difference of
cost (%)
Percentage of projects
experiencing escalating
project costs
Authors/Year of publish
Type of study
44 urban rail projects 1966-1997 18 in North America 13 in Europe
13 in developing
nations
N/A 44.9% 37.3 N/A N/A Flyvbjerg/2007 Academic
129 road and bridge projects Before 2008 85 in Philippines 44 in Thailand
N/A Philippines: 5.4% Thailand: -10.8%
36 30
-67% - 167% -59%-106%
N/A Roxas Jr., Chalermpon/2008
Academic
161 projects; 138 road 16 rail 2 airport 5 port
1985-2005 South Korea Road $19 million
Rail $ 455 million
Road: 11% Rail 48%
N/A N/A Road 87% Rail 94%
Lee J.K./2008 Academic
21 major transit projects 2003-2007 USA $566 million ($58 million - $2.2 billion)
40% N/A -1% - 185% 94% Federal Transit Administration/2008
Academic1
894 projects from seventeen infrastructure sectors; 157 road and highway 122 railway
1992-2009 India N/A 157 road and highway: 16% 122 railway: 95%
62
179
N/A 54% 83%
Singh/2009 Academic
Transport projects; 19 rail 21 road 7 urban transport
2000-2006 Europe N/A Rail: 26.9% Road: 9.4% Urban transport: 45.4%
N/A -10% - 81% N/A RGL Forensics, Faber Maunsell/Aecom and Frontier Economics/2010
Academic
6 European high speed rail projects
Before 2010 Europe $ 6 billion 51% 40% 8% - 116% 100% Chevroulet, Reynaud/2010
Academic
35 road and 28 rail projects 2005-2009 Sweden N/A Road : N/A Rail : 55%
N/A N/A
8% – 18% N/A
N/A N/A
Riksrevisionen /2010, 2011
Audit
36 road projects 1995-2007 Slovenia N/A 19% 46 N/A N/A Dejen Makovsek et al./2011
Academic
Cost overrun problem 31
2.2 Cost overruns in Swedish transport projects
2.2.1 Descriptive statistics
As mentioned, data on cost estimations and outcomes of road and rail projects in Sweden
completed during 1997-2009 are analysed in this thesis. There was a regulation adopted in
1997 that made it compulsory to compare between forecast costs and actual costs of large
transport project investments. Consequently, the data have been published in yearly reports in
Vägverket and Banverket. After our data collection, it was found that a rail project completed in
1998, Vallstanäs-Rosendal line had extreme cost overrun. The estimated cost was 8 million
SEK and the actual cost was 40 million SEK. Thus, the cost overrun was 400%. It has been
regarded as an outlier. After refining the data, 102 road projects and 65 rail projects are used in
this thesis (as shown in Appendix A).
Figure 2-2 shows a histogram of the distribution of inaccuracies of cost estimates. The
distributions of inaccuracies of cost estimations divided on road and rail projects are shown in
Figure 2-3. Table 2-2 shows the general descriptive statistics of the data.
Figure 2- 2 Inaccuracy of cost estimates in 167 road and rail projects.
Cost overrun problem 32
Figure 2- 3 Inaccuracy of cost estimates in road projects (a) and rail projects (b).
(a)
(b)
Cost overrun problem 33
Table 2- 2 Inaccuracy of transport project cost estimates by types of projects.
Project type Number of Cases (N)
Cost escalation (%) Standard deviation
Level of significance, p*
Minimum Maximum Average
Road 102 -46.6 134.4 11.1 24.6 <0.001
Rail 65 -54.2 250.0 21.1 50.5 <0.001
All projects 167 -54.2 250.0 15.0 37.1 <0.001
* Level of significance from zero (see details in Appendix B).
** For all project types, average cost overrun is different from zero with very high significance.
From the statistics results above, there are cost overruns in both road and rail projects in
average. Like in the literature results, the average cost overrun in road projects is lower than in
rail projects. In road projects, the average cost overrun is 11.1% with very strong significant
difference from zero (p < 0.001). The cost overruns in road projects range between -46.6% and
134.4%.
In rail projects, the average cost overrun is 21.1% with very strong significant difference from
zero (p < 0.001). The cost overruns in rail projects are between -54.2% and 250.0%. It should
be noted that the standard deviation of cost overruns in rail projects is very high (50.5%). As
show in Figure 2-3, the distribution of inaccuracy of cost estimates in rail projects is widely
spread from mean. For road projects, the standard deviation of cost overruns is not as high as
in rail projects and the data mostly lies in the range of 0% to 25%.
Next, the comparisons of cost overruns in transport projects in Sweden and of the previous
studies are conducted. There are two comparisons. The first one is the comparison with results
from the most cited studies by Flyvbjerg and other [5] [6] [22] [28]. The studies cover transport
megaprojects and the project characteristics are thus different from the projects in this thesis.
The second comparison is with the other international studies that were published after the most
cited studies. These studies analyse transport projects that are more similar to this thesis
projects in terms of size of project.
Table 2-3 shows cost overrun comparison of cost overrun between Swedish transport projects
and results of Flyvbjerg studies. Average cost overruns in Swedish road and rail projects are
lower than the average cost overruns from Flyvbjerg studies with very strong significance (p <
0.001). Thus, the cost overrun problems in Sweden seem to be less serious than other
countries in magnitude. The standard deviation of cost overruns in road projects is not much
Cost overrun problem 34
different than the result of Flyvbjerg studies. The standard deviation of cost overruns in rail
projects is however much higher than the result of the Flyvbjerg studies.
As shown in Table 2-4, the average cost overruns in the other studies are 8.1% and 45.7% for
road and rail projects, respectively. In road projects, the average cost overrun is higher in
Sweden than the average cost overrun in other studies. In rail projects, the average cost
overrun is lower than the average cost overrun in other studies. Thus, the cost overrun problem
of Swedish road projects seems to be slightly more severe than in other countries. For the rail
projects, the conclusion is the same as when we compare with the Flyvbjerg studies.
Table 2- 3 Comparison of cost overruns between Swedish transport projects and results of Flyvbjerg studies.
Project type Number of Cases (N)
Average cost overrun
Standard deviation
Level of significance, p*
Road 167 / (102) 20.4 / (11.1) 29.9 / (24.6) <0.001
Rail 58 / (65) 33.8 / (21.1) 38.4 / (50.5) <0.001
* The test of the difference between means of the two studies (see details in Appendix B).
** ( ) Results of Swedish transport projects.
Table 2- 4 Comparison of cost overruns between Swedish transport projects and result of other studies.
Project type Number of Cases (N)
Average cost overrun
Road 3,988 / (102) 8.1 / (11.1)
Rail 300 / (65) 45.7 / (21.1)
* Other studies are the studies that were published after Flyvbjerg studies.
** ( ) Results of Swedish transport projects.
2.2.2 Differences in cost calculations
The comparison of observed costs with the costs estimated at the time of project approval gives
results that are similar to international studies‟ results but deserve some comments [39]. There
are two main difficulties in cost overrun comparisons – price index and the decision used as the
estimated cost1. These factors affect the project costs.
1 Another problem that is obvious from an ongoing project at VTI is that there are shortcomings in the
follow-up of actual costs at the Transport Administration in Sweden since the costs are not always
registered correct, or even at the correct project. It is however outside the scope of this thesis to discuss
the reasons behind this and its possible consequences.
Cost overrun problem 35
When cost overruns are studied, all costs (actual cost and forecasted cost) should be calculated
in constant prices or inflation-adjusted currencies. Constant prices are obtained by deflating
current prices to a certain base year. Thus, the inflation is neutralised. There are several
possible indexes for such deflation for example Consumer Price Index (CPI). Therefore, the
price index affects cost overrun. Figure 2-4 is an example of cost calculations of rail projects [29]
in the U.S. In this example, nominal outcome costs are as reported and are not adjusted.
Forecasted costs are adjusted by price index. If the price index is changed and make the
estimated cost increase, some projects may change from cost underrun projects to cost overrun
projects. Conversely, if the price index is changed and make the estimated cost decrease, some
projects may change from cost overrun projects to cost underrun projects.
Another difficulty is what decision is used as the estimated cost. As mentioned, the definition of
the cost overrun or inaccuracy in cost forecasts is measured as actual cost minus forecasted
cost as a percentage of forecasted cost. Forecasted cost is the estimate made at the time of
decision to build, but when exactly is this time of decision? [39] Bent Flyvbjerg et al. [6] discussed
this as follows:
“Ideally, we would calculate cost development on the basis of the cost estimate
at the time of the real decision to build. However, in most cases, it is virtually
impossibly to identify the specific, real decision date.”
A study [21] investigated 10 academic studies and 13 audit reports about cost overruns. It
showed that the actual construction costs were not adjusted for inflation in 2 academic studies.
Cost overruns were calculated as the difference between the price at the time of the contract
award and the final construction cost in 2 academic studies. For audit reports, 5 of them
explicitly accounted for inflation, while the other did not state whether their findings are inflation-
adjusted. More than a third of the audit reports focused on escalating payments above winning
bid or the contractually agreed upon price.
These difficulties were also found in cost overrun calculation for Swedish transport projects.
Therefore, the cost overruns calculated by the audit office were different from what was
calculated by the Transport Authorities. The first explanation is that the transport agencies use
different price indexes which are shown in Figure 2-5. The road and rail authorities use their
own price indexes while the audit office uses Net Price Index (NPI) which is similar to CPI (KPI
in Swedish) as shown in Figure 2-5. The second explanation is the decision that is used as the
estimated cost. The Transport Authorities choose the estimated cost in the latest plan. They
Cost overrun problem 36
agree that the latest action plan is the plan that the Government later decided for the current
plan period, hence it is relevant to follow up analysis. However, the audit office claims that if
choosing the latest plan, cost comparison hides the cost increases that occur between the first
and the last action plan. Thus, they use the estimated cost at the earliest plan.
Table 2-5 shows the costs of major rail projects in Sweden (opened between 2005 and 2009).
Cost calculations differ by using different indexes and plan. For example, the estimated cost of
the Öxnered-Trollhättan line was 682 million SEK in earliest plan cost by using NPI index. At the
same time, the estimated cost was 958 million SEK in the latest plan by using BV-index or
Banverket index. In this case, the estimated project‟s cost by the Swedish National Audit Office
is 276 million SEK lower than by the Banverket. The calculation of road projects uses the same
concept as the rail projects. This is the reason why the cost overruns calculated by the Swedish
National Audit Office are higher than the ones calculated by the Transport Authorities
(Vägverket and Banverket).
Cost overrun problem 37
Figure 2- 4 Capital cost estimates – base estimate, inflation, and actual.
Cost overrun problem 38
Figure 2- 5 Price indexes for Swedish road projects (a) and rail projects (b).
(a)
(b)
Cost overrun problem 39
Table 2- 5 Cost of major rail projects (2005-2009).
Project / year opened to service
Index
Cost (million SEK) Percentage deviation, the
final cost against the first plan Plan
1994 Plan 1998
Plan 2004
Final- cost
Kävlinge–Lund BV-index 800 1263 963 1220 53%
2005 NPI 537 941 902 962 79%
Lekarekulle–Frillesås BV-index 896 458 680 691 -23%
2005 NPI 602 356 637 635 5%
Sthlm S–Årstaberg BV-index 2479 1413 1610 1788 -28%
2005 NPI 1665 1100 1508 1660 0%
Hallsberg rangerbangård
BV-index - - 467 517 11%
2005 NPI - - 437 483 11%
Öxnered–Trollhättan BV-index 1087 693 958 1180 9%
2006 NPI 682 504 838 1063 56%
Mjölby bangårds-ombyggnad
BV-index 103 295 218 546 430%
2006 NPI 64 215 191 486 659%
Blekinge kustbanan BV-index - - 894 915 2%
2007 NPI - - 726 838 15%
Torebo–Hedberg BV-index - 1259 1621 1355 8%
2008 NPI - 825 1278 1228 49%
Vännäs–Bastuträsk BV-index - - 1091 1044 -4%
2008 NPI - - 860 837 -3%
Arlöv–Malmö BV-index - - 857 777 -9%
2008 NPI - - 676 668 -1%
2.3 Key findings and discussion
The problems of cost overrun appear worldwide. The average cost overrun in rail projects
is higher than in road projects.
Cost overruns among the studies are not directly comparable. Although concept and
definition of the cost overrun are commonly understood, a variety of assumptions are
used in cost overrun studies especially in audit reports.
Comparing cost estimations and outcomes of 167 road and rail projects in Sweden during
the period 1997-2009, it is found that average cost overruns are 11% (SD = 24.6%) and
21% (SD = 50.5%) for road and rail projects, respectively.
The average cost overrun in Swedish road projects (11.1%) is much lower than the result
from the most cited international studies (29.9%). However, it is slightly higher than the
result from the average of other studies (8.1%). Therefore, the cost overrun in road
projects in Sweden is not obviously better or worse than in other countries.
For Swedish rail projects, the average cost overrun (21.1%) is lower than the results from
both the most cited studies (33.8%) and the average of the other studies (45.7%). Thus,
cost overrun problems in rail projects in Sweden are less severe than in other countries.
Cost overrun problem 40
However, the standard deviation of cost overrun in Swedish rail projects is very high
(50.5%).
Two main aspects that should be considered when comparing between cost overrun
studies are price index and the decision that is used as the estimated cost. These factors
make a significant difference in project costs. One recommendation is that cost
calculations with and without adjusted price indexes should be provided by the transport
administration.
Factors contributing to cost overruns 41
3. Factors contributing to cost overruns
Before we begin to study the factors contributing to cost overrun, there are two words that we
need to clarify – causes and explanations. From the definition in the study of Bent Flyvbjerg and
others [40], the meaning by „cause‟ is „to result in‟; the cause is not the explanation of the result.
Causes refer to the variables or factors that influence the cost overruns, such as the
implementation period or the size of the project [41]. Explanations are more general and might
comprise several causes [41]. There are four categories of cost overrun explanations – technical,
economic, psychological and political explanations. However, this thesis only concentrates on
causes (or factors) of cost overruns, not explanations.
The first section of this chapter reports the literature study about the factors contributing to cost
overruns. Next, it gives a brief explanation of statistic methods which are used to analyse the
VTI data. The results are shown in the last section. In the next chapter, the currently used
method in Sweden for cost estimations – “Successive Calculation” - will be explained.
3.1 Previous studies
The summary of some previous studies is shown in Table 3-1. The followings are the brief
results of each study.
Urban Mass Transportation Administration, 1990 [24]
The study covered 10 major transit capital investment projects in the U.S. cities. The transit
projects were constructed during the period 1971-1987. It was stated that the changing in
project scope was not the factor contributing to cost overruns. Changes in the physical
characteristics of these projects between their planning and construction stages were generally
quite minor, and many of the changes that were made should have reduced than increased
project costs. Most of projects with the unanticipated inflations had cost underruns. Since actual
inflation proceeded more slowly than it was forecast, actual cost would have been lower than
those forecast if construction of the project had processed according to its planned schedule.
Both delays in the start of construction and lengthening of planned construction schedules were
the factors contributing to cost overruns.
Office of Program Policy Analysis and Government Accountability, 1996 [27]
The Office of Program Policy Analysis and Government Accountability reviewed the Florida
Department of Transportation‟s (FDOT) performance in controlling cost overruns and delays when
building roads and bridges. To identify the reasons why FDOT had experienced cost overruns in
Factors contributing to cost overruns 42
transport projects, they examined a sample of 132 projects that had experienced cost overrun
problems (1993-1995). These projects had cost increases at 17%. They found that there were
complex and interrelated reasons why FDOT experienced cost increases in transport projects.
The main factors accounting for cost overruns were errors and omissions in design plan,
inadequate coordination with local government and utility companies, problems in identifying the
scope of work that needed to be done during project development, changes in project
specifications after design plans had been completed and damages to construction site due to
extreme weather.
Flyvbjerg, Holm, and Buhl, 2002 [22] , 2003 [6] [28] and Priemus, Flyvbjerg and Wee, 2008 [5]
The sample of this study was used covering 258 transport projects in 20 countries completed in
1927-1998. They discussed whether different types of projects (rail, fixed link and road)
performed differently with respect to cost overruns. They set a null hypothesis that type of
project had no effect on cost overrun. An F-test falsified the null hypothesis at a very high level
of statistical significance. Thus, project type mattered.
They also tested whether cost overrun varied with geographical location among Europe, North
America, and “other geographical areas” (a group of 10 developing nations plus Japan).
Considering all project types, they found that the difference between geographical areas in
terms of cost overrun is highly significant. Thus, geography mattered to cost overruns. However,
they found that when considered in each project type, the difference between the geographical
areas is nonsignificant or does not influence cost overruns. They explained it might be because
of the limited number of observations. Next, they analysed an effect from time (year of decision
and year of completion) on cost overrun. They concluded that cost overrun had not decreased
over time. Cost overrun was constant for the 70-year period and cost estimates had not
improved over time.
Flyvbjerg, Holm, and Buhl, 2004 [40]
From database in the previous studies by Flyvbjerg and others (a sample of 258 rail, bridge,
tunnel and road projects in 20 countries completed in 1927-1998), they furthered their analysis
about what caused cost overruns. This study focused on the dependence of cost overrun on the
length of the project-implementation phase, the size of the project and the type of project
ownership. They found that the cost escalation was strongly dependent on the length of the
implementation phase.
Factors contributing to cost overruns 43
Next factor was the size of the project. They found that only bridges and tunnels were
statistically significant that larger projects had larger cost overruns, whereas this did not appear
in road and rail projects. For all project types, bigger projects did not have a larger risk of cost
escalation than did smaller ones.
Lastly, by comparing the cost overruns for three types of project - ownership-private, state-
owned enterprise and other public ownership, they concluded that the data did not support the
general claim that public ownership is problematic per se and private ownership a main source
of efficiency in curbing cost escalation [40]. They stated that the general claim was an
oversimplification and the issue of project ownership was more complex than was usually assumed.
Odeck, 2004 [12]
The paper investigated the cost overruns of road construction using data from 620 Norwegian
road constructions over the years 1992-1995. A regression model was conducted to explain the
cost overruns. The coefficient of the factors used in the model showed the cost overrun causes.
From regression model results, the factors that contributed to cost overruns were the size of
estimated cost (or project size), completion time, and location. It was found that cost overruns
were larger and more predominant among smaller projects. It was suggested that one possible
reason was the amount of attention given to larger projects. Thus, larger projects were most
probably better managed as compared to smaller ones.
For the correlation between completion time and cost overrun, the results showed that cost
overrun increases within certain range of completion (about 200 weeks or 2.7 years) after which
it declined. It might imply that cost overrun tended to be higher the shorter the completion time
was expected to take. The study stated that a possible explanation was that accuracy in cost
prediction was difficult the shorter the construction was expected to take, meaning that
uncertainties decreased with time. Another explanation could be that project management got better
oversight over causes of overrun and were able to control for them the longer the project lasted.
About location, only the region of middle Norway was found to be different from the base region
of eastern Norway. Thus, locations of projects were correlated with cost overruns. The study
stated shortly about a correlation between the year of project and cost overrun. It specified that
considering the dummies for vintage year of project, only 1993 were found to differ from the
base year of 1992 (Since no details about this factor in the study, this factor will not be shown in
Table 3-1). Lastly, the study showed that type of project (bridge, tunnel or ordinary road) had no
correlation with cost overruns.
Factors contributing to cost overruns 44
Dantata et al., 2006 [31]
This paper studied the effect of project size (in terms of actual cost) on cost overrun. Data was
collected on 37 rail transit projects in the U.S. These included the 10 projects in UMTA report [24]
in 1990, the 16 project completed after 1990 and 11 other projects. The relationship between
the project size and cost overrun showed no clear pattern between the two variables. The
correlation coefficient between the actual capital cost and the cost overrun is 0.37. They
concluded that this was a weak correlation and therefore the relationship between the project
size and cost overrun was weak. Moreover, they concluded that there was evidence to suggest
that cost overruns for projects completed before 1990 were different from that of projects
complete after 1994 (i.e. cost overruns had become smaller from 52% to 30%), but they did not
have sufficient data to statistically prove this at a level of significance of 5%.
Roxas Jr., Chalermpong, 2008 [34]
The paper studied the cost forecasting inaccuracies in 44 road and bridge projects in Thailand
and 85 road and bridge projects the Philippines. It was verified that there were no significant
differences in cost forecasting inaccuracies between road and bridge projects in both countries.
They tested that whether project size, location (urban and rural) and source of funding
influenced on the amount of cost overruns.
The researchers analysed road and bridge projects in Thailand into two groups - costs less than
one billion baht and costs of one billion baht and more. The result was the size of the project
significantly influences the amount of cost overrun incurred. Interestingly, the average cost
overrun and standard deviation of the second group were less than those of the transport
projects with smaller costs. They concluded that it implied that bigger projects have smaller cost
overruns. Regarding location, they concluded that there were no significant differences in the
cost overruns in transport projects from both the urban and rural areas. They suggested that
projects were planned, evaluated, and implemented consistently, despite the different area
classifications. For the source of funding (foreign and locally funded projects), the researcher‟s
hypothesis was if a project was funded by a foreign institution, then it is expected that the cost
overruns were less pronounced due to the fact the there were less incentives or no incentives at
all, for the foreign agencies to manipulate the figures in the project proposals. The result
showed the source of funding significantly influences the cost overruns. Moreover, the average
cost inaccuracy of foreign projects is smaller than those of locally funded projects, thus
supported the researcher‟s hypothesis.
Factors contributing to cost overruns 45
For the road and rail projects in the Philippines, all the factors – project size (project cost less
than 1 billion pesos or more), location (urban or rural) and source of funding had significant
effects on the amount of cost overruns. Bigger or more expensive projects experienced lower
cost overruns. One explanation is bigger projects often had international consultants and longer
planning and evaluations. Projects from the urban areas has less cost overruns probably
because of better monitoring, quality of contractors and many other factors. Lastly, they stated
that projects funded by JBIC/PJHL had less cost overruns when compared to other funding
agencies (The authors did not provide the meaning of “JBIC/PJHL” and “other funding
agencies”, thus it is not clear about this conclusion whether it means the foreign and locally
funded projects.).
Singh, 2009 [37]
This study investigated the delays and cost overruns in publically funded infrastructure projects
in India. The 894 projects from 17 infrastructure sectors in the period 1992 and 2009 were
analysed including 122 railway projects and 157 road and highway projects. It was found that
first, since 1980s the cost overruns had declined. Cost overruns had systematically declined not
only in absolute terms but also as a percentage of project cost. Second, delays were one of the
crucial correlations behind the cost overruns. Third, bigger projects had experienced much
higher cost overruns compared to smaller ones. Fourth, percentage cost overruns also escalate
with length of the implementation phase. Fifth, compared to other sectors, projects from road,
railways, urban development sectors had significantly higher cost overruns. Sixth, compared to
other states, projects located in southern states had experienced lower cost overruns.
Performance of rich states was not significantly better than that of the poorer states.
All above findings were statistically significant and robust to regression techniques. However,
the results were analysed from the infrastructure projects in India. They are not only transport
projects but include other types of project such as petroleum, telecommunication, mine and
coal. Thus, it should be noted that the study did not focus only on transport projects like this
thesis.
Factors contributing to cost overruns 46
Summary
From the summary of factors contributing to cost overruns in Table 3-1, it shows that project
type, location, length of implementation and size of project are the common factors used to
explain cost overruns in transport projects. Some studies find that project type matters while two
studies find that the project type does not matter. Studies of Flyvbjerg and others [5] [6] [22] [28]
state that cost overruns in road, fixed link (bridge and tunnel) and rail projects perform differently
with respect to cost overruns. Another study [34] states that there are no significant differences in
cost overruns between road and bridge projects in Thailand and the Philippines. Another study [12]
also states that type of project (bridge, tunnel or ordinary road) does not influence to cost
overruns in Norwegian road projects.
Furthermore, all studies find that location of projects affected cost overruns. However, one study [34]
shows that location affect cost overruns in road and bridge projects in the Philippines but not in
Thailand. All studies also indicate that length of implementation and delay are factors
contributing to cost overruns. The cost overruns increase with the length of implementation and
delay.
There are varying conclusions in the size of project aspect. One study [31] shows that the
relationship between the project size and cost overrun is weak. One study [37] finds that bigger
projects have experienced higher cost overruns compared to smaller ones. On the other hand,
two studies [12] [34] state that more expensive projects experience lower cost overruns. One study [40]
concludes in two directions – larger bridge and tunnel projects have larger cost overruns,
whereas this appears not to be the case for ordinary road and rail projects.
One interesting factor is historical period or the time of the project. This factor shows whether
cost overruns improve over time. Some studies [5] [6] [22] [28] [31] find that cost overruns have not
statistically significant decreased over time while one study [37] states that since the 1980s the
cost overruns of transport projects in India have declined.
Factors contributing to cost overruns 47
Table 3- 1 Summary of factors contributing to cost overruns.
Authors/ Year of publish
Number and types of project examined
Factors1
Pro
ject ty
pe
Locatio
n
His
torical perio
d
Length
of im
ple
me
nta
tio
n/
Dela
y
Siz
e o
f pro
jects
(cost)
Pro
ject ow
ners
hip
Changin
g in
pro
ject scope,
desig
n,
regula
tory
requirem
ent
Unanticip
ate
d I
nfla
tio
n
Poor
coord
inatio
n
Weath
er
Sourc
e o
f fu
ndin
g
UMTA /1990 10 major transit projects in the U.S.
+ ✘ -
Office of program Policy Analysis and Government Accountability/1996
132 road projects in Florida by FDOT
+ + +
Flyvbjerg, Holm, and Buhl/2002, 2003 and Priemus, Flyvbjerg and Wee/2008
258 projects in 20 nations: 58 rail; 33 fixed-link; 167 road
✓ ✓ ✘
Flyvbjerg, Holm, and Buhl/2004
Same data as previous study
+ + 2✘ ?
Odeck/2004 620 Norwegian road projects
✘ ✓ ± -
Dantata et al./2006 37 rail projects in the U.S.
✘ ✘3
Roxas Jr., Chalermpon/2008
129 road and bridge projects 85 in the Philippines 44 in Thailand
✘
✘
✓
✘
-
-
✓
✓ Singh/2009 894 projects from 17
infrastructure sectors in India; 157 road and highway 122 railway
✓ ✓ + +
1 ✓ means that the factor affects cost overruns.
✘ means that the factor does not affect cost overruns.
+ means that a higher factor value contributes to more cost overruns.
- means that a higher factor value contributes to less cost overruns.
± means that the more factor value contributes to more and less cost overruns.
? means that the factor is needed to further study whether it affects cost overruns.
2 Only fixed-link (bridges and tunnels) larger projects statistically had lager cost overruns.
3 It was found that the relationship between the project size and cost overrun was weak.
Factors contributing to cost overruns 48
3.2 Statistical methods
As mentioned, the VTI data are analysed to find the factors affecting cost overruns for transport
projects in Sweden (the results are shown in next section). This section explains the general
statistical methods which are used to analyse the data. More details in each method are
provided in Appendix B.
For statistical analyses, we use the SPSS or PASW software. Most of the analyses are general
descriptive statistics (means and standard deviations). The data are explored by graphs such as
bar charts and scatterplots. Regression models are also used. Analyses in each factor are
explained in the following.
The first factor is project type (road and rail projects). The Levene‟s test is used for this part. It
tests the hypothesis that the variances in different groups are equal [42]. It basically does a one-
way ANOVA on the deviations (i.e. the absolute value of the difference between each score and
the mean of its group). Therefore, if the Levene‟s test is significant, we can be confident in the
hypothesis that the variance are significantly different and that the assumption of homogeneity
of variances has been violated. In our analysis, it means that project type matters.
Regarding significance, we use the convention of terms: very strong significance (p < 0.001),
strong significance (0.001 ≤ p < 0.01), significance (0.01 ≤ p < 0.05), nearly significance (0.05 ≤
p < 0.1) and non-significance (0.1 ≤ p). [40]
In the next step, we test whether cost estimates have improved over time. The scatterplot of the
differences between actual and estimated costs against year of project completion is applied.
The null hypothesis is that year (or time of project) has no effect on the difference between
actual and estimated costs. The compare means in one-way ANOVA function is used.
Next, the size of the project measured in costs is considered. In each project, there are two
costs – forecasted cost and actual cost. From study of Bent Flyvbjerg and others [40], it is
recommended that forecasted costs should be used. There are two reasons. First, cost
escalation is statistically confounded with actual construction costs being part of it, whereas
forecast construction costs are not. Second, the decision about whether to go ahead with a
given project is based on the forecasted construction costs. We scatterplot the percentage cost
escalation against project size. We also make regression models to see the relationship or
correlation between project type and cost overruns. It should be noted that correlation does not
imply causation. Even if we can see that there is a correlation or relationship between size of
the project and cost overrun, it does not imply that size of the project causes cost overrun.
Factors contributing to cost overruns 49
After this, we investigate the relationship between project size and cost escalation. The
distribution of the cost overrun against project size is used to divide the projects into different
groups – small, medium, large and very large projects. We provide summary descriptive
statistics of percentage and monetary amount of cost overruns in each group.
Then we analyse detailed project type. For road projects, they are categorized into major roads
(including interchanges), motorways, secondary roads and urban roads. For rail projects, they
are classified into new tracks in existing lines, new tracks in new lines, stations and rail yards
and upgrading existing lines. Descriptive statistics of percentage and monetary amount of cost
overruns in each group are provided. The Levene‟s test is used to test whether there are
different variances in each detailed project type.
Lastly, for road projects, complexity of project affect cost overruns is analysed. The complexity
of project is approximated by the ratio of construction cost and length of project. The scatterplot
of the cost difference against complexity of project is conducted. Regression models are used to
find the relationship between cost overrun and complexity.
3.3 Factors of cost overruns in Swedish transport projects
3.3.1 Types of projects
There are two types of projects (102 road projects and 65 rail projects). Whether different types
of projects perform differently in cost overruns is tested. Statistical analysis in Table 3-2 shows
the Levene‟s test falsifies the null hypothesis at a very high significance (p < 0.001). The
assumption that homogeneity of variances or type of project has no effect on cost overrun has
been violated. Therefore, it is verified that the variance are significantly different and project type
does matter. Thus, in the analyses that follow in this thesis, each type of project will be
considered separately.
The result is in line with findings in studies of Flyvbjerg and others [5] [6] [22] [28]. They found that
there were significant differences in the practice of cost overruns among different types of
projects - rail, fixed-link and road projects.
We conclude that the Swedish road and rail projects perform differently in terms of cost
overruns. The different cost overrun performances between road and rail projects seem to be a
general characteristic in transport projects as found in previous chapter that the average cost
overruns in rail projects are often higher than in road projects.
Factors contributing to cost overruns 50
Table 3- 2 Independent samples test by types of projects.
Independent Samples Test
Cost escalation
Levene's Test for Equality of
Variances t-test for Equality of Means
F Sig. t df Sig. (2-tailed)
Mean Difference
Std. Error Difference
95% Confidence Interval of the
Difference
Lower Upper
Equal variances assumed Equal variances not assumed
20.298 .000 -1.713 165 .089 -10.03048 5.85452 -21.58991 -1.52894
-1.492 83.601 .140 -10.03048 6.72364 -23.40211 -3.34114
3.3.2 Years of project completion
In this section, we test whether the cost estimations have improved over time. We start by
plotting a scatterplot between percentage of cost inaccuracies against the years of project
completion for the 167 road and rail projects as shown in Figure 3-1. The diagram does not
seem to indicate an effect from year of project completion on cost overrun.
Next, we conduct the scatterplot in different types of projects (road and rail) as shown in Figure
3-2. The interpolation lines in the diagram show that cost overruns have declined since 2005,
especially in road projects. The trend is tested by a statistical analysis. If the cost estimations have
improved over time, the average cost overruns in each year will be different. Thus, the null
hypothesis is average cost overruns in each year are the same. The null hypothesis is analysed
by the comparing means in one-way ANOVA function. The results are shown in Table 3-3. It is
statistically significant (p < 0.05) for both road and rail projects to reject the null hypothesis. Thus,
it can be concluded that the year of project completion has effect on cost overruns. Therefore, the
statistical analysis supports that cost overruns have declined since 2005 especially in road
projects.
However, it was stated in two audit reports [14] [18] by the Riksrevisionen that the Road and Rail
Administrations have changed to use their own self-constructed price indexes since 2005. Thus,
this is the reason why it is obvious that cost overruns had declined since 2005. But it is still not
clear whether the cost estimations really have improved over time. To clarify about this, the
further analyses are done separately into two groups – before and after 2005. The results are
shown in Table 3-4. From the results of F-test of cost overruns after 2005, the null hypothesis
cannot be rejected, for both road and rail projects. Thus, year of project completion has no clear
effect on cost overruns.
Factors contributing to cost overruns 51
Regarding the results of F-test of cost overruns before 2005, it is statistically significant (p <
0.05) for both road and rail projects to reject the null hypothesis. It can be concluded that year of
project completion has effect on cost overruns. However, as shown in Figure 3-3, it cannot
explain the trend of cost overruns during 1997-2004, for both road and rail projects. For road
projects, during 1999-2002, cost overruns increased, then decreased in 2003 and increased
again in 2004. Moreover, average cost overrun was very high in 1998 because there were two
outliers (cost overruns were 134% and 110%). These two projects were secondary roads which
was a group where average cost overrun was high. For rail projects, the cost overruns were
very high in 1999 and 2002 and were almost zero in the rest of years. There were outliers in
each year (cost overruns were 250% in 1999 and 146% in 2002). The outlier projects were
stations and rail yards which was a group where average cost overrun was high.
Figure 3- 1 Inaccuracy of cost estimates in Swedish transport projects over time, 1997-2009.
Factors contributing to cost overruns 52
Figure 3- 2 Inaccuracy of cost estimates in road and rail projects over time, 1997-2009.
Table 3- 3 F-statistic of average cost overruns in road and rail projects over time, 1997-2009.
Road Sum of Squares df Mean Square F Sig.
Between Groups 19392.720 12 1616.060 3.444 .000
Within Groups 41764.741 89 469.267
Total 61157.460 101
Rail Sum of Squares df Mean Square F Sig.
Between Groups 53762.565 12 4480.214 2.126 .031
Within Groups 109604.201 52 2107.773
Total 163366.766 64
Factors contributing to cost overruns 53
Table 3- 4 F-statistic of average cost overruns in road and rail projects, before and after 2005.
Road 05-09 Sum of Squares df Mean Square F Sig.
Between Groups 209.284 4 52.321 .411 .799
Within Groups 3946.377 31 127.302
Total 4155.661 35
Rail 05-09 Sum of Squares df Mean Square F Sig.
Between Groups 9073.935 4 2268.484 1.095 .376
Within Groups 66277.638 32 2071.176
Total 75351.573 36
Road 97-04 Sum of Squares df Mean Square F Sig.
Between Groups 10936.135 7 1562.305 2.396 .032
Within Groups 37818.364 58 652.041
Total 48754.499 65
Rail 97-04 Sum of Squares df Mean Square F Sig.
Between Groups 44673.884 7 6381.983 2.946 .027
Within Groups 43326.563 20 2166.328
Total 88000.446 27
Factors contributing to cost overruns 54
Figure 3- 3 Inaccuracy of cost estimates in road and rail projects over time with SD, 1997-2009.
In sum, we conclude that cost overruns in Swedish transport project are more or less constant
for the 13-year period and that cost estimates have not improved over time. It should be noted
that this conclusion holds true regardless of the change of using price indexes by Road and Rail
Administrations. The conclusion corresponds to the studies of Flyvbjerg and others [5] [6] [22] [28] but
does not correspond to a study of transport projects in India which stated that cost overruns had
declined. The conclusion also supports the statement in the recent two audit reports [14] [18] that
the cost overruns problem in Swedish transport projects as noted by the RRV 15 years ago still
remained and it could not be seen that any real improvements had occurred in this aspect.
Factors contributing to cost overruns 55
3.3.3 Sizes of projects
In this section, we test whether the size of project in terms of forecasted cost influences cost
overrun. First, the scatterplot of the percentage cost inaccuracy against project size is provided
in Figure 3-4. From the diagram, it is not clear to conclude a relationship between the forecasted
cost and cost inaccuracy. From the regression models, the coefficients of forecasted cost in
both road and rail projects are negative. Thus, it can be concluded that the higher forecasted
cost have less cost overrun both in road and rail projects. However, it should be noted that the
correlations between project size and cost overruns are very low in both road and rail projects
(adjusted R2 = 0.178 and 0.065 for road and rail, respectively). Thus, it also can be concluded
that the relationship between the project size and cost overrun is weak in both road and rail
projects.
Then, the road and rail projects are divided into four groups - small (cost ≤ 100 million SEK),
medium (100 million SEK < cost ≤ 500 million SEK), large (500 million SEK < cost ≤ 1000
million SEK) and very large (cost > 1000 million SEK). Figure 3-5 shows the distribution of cost
overruns in each group. From the graph, it is obvious that small transport projects (< 100 million
SEK) have much higher cost overruns than large projects, especially in road projects. It also
shows that cost overruns in rail projects have very high standard deviation.
Next, the descriptive statistics are conducted by sizes of projects. The results are shown in
Table 3-5. It shows that the average cost overruns are 29% and 43% in small road and rail
projects, respectively while the average cost overruns are 11% and 21% in all road and rail
projects, respectively. That means cost overruns in small projects in both road and rail projects
are higher than the average of them by more than two times. They also constitute 27% and 23%
of the total costs in road and rail projects, respectively. Moreover, it also shows that the average
cost overruns are very low in bigger projects especially in rail projects (only 2.1%).
Factors contributing to cost overruns 56
Figure 3- 4 Forecasted costs and inaccuracy of cost estimates.
Figure 3- 5 Distribution of inaccuracy of cost estimates by project sizes.
Road Projects
y = -10.22ln(x) + 64.491
Adjusted R² = 0.178
Rail Projects
y = -11.17ln(x) + 80.244
Adjusted R² = 0.065
Factors contributing to cost overruns 57
Table 3- 5 Distribution of cost overruns in percent and in million SEK by project sizes.
Road
Size of projects in terms of forecasted cost (million SEK)
Total Small (cost ≤ 100)
Medium (100<cost≤500)
Large (500<cost≤1000)
Very large (cost>1000)
Number of projects 31 54 10 7 102
Sum forecasted costs (mill. SEK) 2,004 12,157 7,013 14,751 39,925
Average cost overrun (%) 29.1 2.8 3.1 6.3 11.11
Standard deviation (%) 34.0 14.3 8.4 8.6 24.6
Sum overrun (mill. SEK) 450 330 268 595 1,643
% of sum overrun (mill. SEK) 27.4 20.1 16.3 36.2 100
Rail
Size of projects in terms of forecasted cost (million SEK)
Total Small (cost ≤ 100)
Medium (100<cost≤500)
Large (500<cost≤1000)
Very large (cost>1000)
Number of projects 21 27 10 7 65
Sum forecasted costs (mill. SEK) 1,146 6,639 7,289 11,615 26,689
Average cost overrun (%) 43.1 14.5 6.0 2.1 21.12
Standard deviation (%) 74.1 33.7 28.2 11.9 50.5
Sum overrun (in mill. SEK) 447 932 373 184 1,936
% of sum overrun (in mill. SEK) 23.1 48.1 19.3 9.5 100
We conclude that the small transport projects in Sweden (< 100 million SEK) have much higher
cost overruns than large projects especially in road projects. However, the correlation between
project size and cost overrun is weak.
The result corresponds with a study of 620 Norwegian road projects [12]. In the study, it was
suggested that one possible explanation was the amount of attention given to larger projects.
Thus, larger projects were most probably under better management compared with smaller
ones. This explanation may also be the case for road and rail projects in Sweden. The result
also corresponds with a study of 129 roads and bridges in Thailand and the Philippines.
However, the result is not in line with finding for transport projects in India which stated that
bigger projects had experienced much higher cost overruns compared to smaller ones.
Furthermore, the result is the same as in a study of 37 rail projects in the U.S. finding that the
relationship between the project size and cost overrun is weak.
1 It is the average cost overrun of road projects.
2 It is the average cost overrun of rail projects.
Factors contributing to cost overruns 58
3.3.4 Detailed project types
In Section 3.3.1, we investigated whether road and rail projects perform differently in terms of
cost overruns. The detailed project type is further analysed in this section. There are four
categories in road projects – major roads, motorways, secondary roads and urban roads. For
rail projects, they are divided into four groups – new tracks in existing line, new tracks in new
line, stations and rail yards and upgrading existing line.
The results are shown in Figure 3-6 and Table 3-6. For road projects, the average cost overruns
are lowest in motorways (only 3.0%) and highest in secondary roads (20.2%). The standard
deviation of cost overruns in secondary roads is high (37.7%). Furthermore, motorways
constitute more than half (51.3%) of the total amount of cost overruns in million SEK.
For rail projects, new tracks in new lines are underrun (-8.8%). This means the forecasted cost
is higher than the actual costs in average. One explanation is that when constructing new tracks
in new line corridors it is usually easier to control costs than when constructing in existing line
corridors. There are no conflicts with the existing lines during construction. The highest average
cost overrun is found in stations and rail yards (34.7%) with very high standard deviation
(68.7%). The large standard deviations in rail projects are as interesting as the large average
cost overruns. The size of standard deviations demonstrates that uncertainty and risk regarding
cost overruns are large, indeed. Furthermore, construction of new tracks in existing line
corridors constitutes a lot of the total amount of cost overruns (75.5%) in million SEK.
Factors contributing to cost overruns 59
Figure 3- 6 Distribution of inaccuracy of cost estimates in road projects (a) and rail projects (b) by detailed project types.
(a)
(b)
Factors contributing to cost overruns 60
Table 3- 6 Distribution of cost overruns in percent and in million SEK by detailed project types.
Road
Project types
Total Major roads Motorways Secondary roads
Urban roads
Number of projects 24 32 30 16 102
% of projects 23.5 31.4 29.4 15.7 100
Average cost per project (in mill. SEK)
252 719 108 228 352
Average cost overrun (%) 13.6 3.0 20.2 6.2 11.11
Standard deviation (%) 18.1 11.6 37.7 14.5 24.6
Sum overrun (in mill. SEK) 424 843 250 126 1,643
% of sum overrun (in mill. SEK) 25.8 51.3 15.2 7.7 100
Rail
Project types
Total New tracks, existing line
New tracks, new line
Stations and rail yards
Upgrading existing line
Number of projects 14 7 19 25 65
% of projects 21.5 10.8 29.2 38.5 100
Average cost per project (in mill. SEK)
843 779 147 266 405
Average cost overrun (%) 23.4 -8.8 34.7 17.8 21.12
Standard deviation (%) 28.6 13.1 68.7 48.6 50.5
Sum overrun (in mill. SEK) 1,462 -499 695 278 1,936
% of sum overrun (in mill. SEK) 75.5 -25.8 35.9 14.4 100
Table 3- 7 Test of homogeneity of variance of detailed project types.
Test of Homogeneity of Variance
Levene Statistic Sig.
Road Based on Mean 7.962 .000
Rail Based on Mean 1.982 .126
As seen in the previous results there are different means of cost overruns in each detailed
project type. The cost overruns in each detailed project type may statistically differ from the
others and we should not combine analysis of each detailed projects together. Thus, we do a
further test whether there are different variances in each detailed project type of road and rail
projects. The null hypothesis is that the variances in different groups are equal. The Levene‟s
test based on mean (more explanations as shown in Appendix B) is applied. The result is shown
in Table 3-7. The Levene‟s test result is non-significant for the rail projects (p > 0.1) indicating
1 It is the average cost overrun of road projects.
2 It is the average cost overrun of rail projects.
Factors contributing to cost overruns 61
that they are similar in variances. However, for the road projects, the Levene‟s test is significant
(p < 0.001) indicating that they are different in variances in each detailed project type. Thus, the
road projects should be analyzed separately in each detailed project type (major roads,
motorways, secondary roads, and urban roads). However, there are some constrains to do
analysis separately in road projects. First, it will not be a statistically valid analysis because of
the small sample size in each detailed project size (around 16-32 observation in each group).
Second, it is impossible to find the reference studies to compare. None of our literature studies
classifies the road into sub-groups as in this thesis. Therefore, even though it is significant that
road projects are different in variance in each detailed project type, the road projects are not
analysed separately in each detailed project type in this thesis.
3.3.5 Complexity
In this section, it is tested whether the complex projects have higher cost overruns. The
complexity of project is measured somewhat crudely by the ratio of construction cost and length
of project. In this thesis, the analysis of complexity is focused only on road projects because the
lengths of projects are provided only in road projects. First, the scatterplot of the percentage
cost inaccuracy against complexity of project is provided in Figure 3-7. From the diagram, it is
seen that the more complex projects have lower cost overruns. This result is confirmed by the
regression model, as shown in Figure 3-7. The coefficient of complexity is negative. However,
the relationship between cost overrun and complexity is very weak (adjusted R2 = 0.038).
Factors contributing to cost overruns 62
Figure 3- 7 Complexity and inaccuracy of cost estimates.
The result shows that the more complex projects have lower cost overruns with low adjusted R2.
The next question is whether this trend is different in each type of road. The scatterplot of the
percentage cost inaccuracy against complexity of road project in each type are shown in Figure
3-8. It shows that the correlation between cost overrun and complexity is weak in major roads.
Moreover, there are no relationship between cost overrun and complexity in motorways,
secondary roads and urban roads. Therefore, our conclusion is that complexity does not affect
cost overruns. Note that our measure to complexity is crude and that we are not sure it deflects
complexity very well.
y = -5.794ln(x) + 29.984
Adjusted R2 = 0.038
Factors contributing to cost overruns 63
Figure 3- 8 Complexity and inaccuracy of cost estimates by detailed project types.
y = -6.057ln(x) + 31.94
R2 = 0.1299
y = -0.09ln(x) + 21.15
Adjusted R2 = -0.04
y = -2.89ln(x) + 15.64
Adjusted R2 = -0.04
y = 0.44ln(x) + 1.27
Adjusted R2 = -0.03
y = -6.06ln(x) + 31.94
Adjusted R2 = 0.09
Factors contributing to cost overruns 64
3.4 Key findings and discussion
The literature study shows that researchers commonly test the following factors
contributing to cost overruns – project type, location, length of project implementation and
project size. Most studies show that the location of projects affects cost overruns. The
effect of such projects characteristics are hard to generalize since they will differ between
countries as well as between urban and rural areas. However, there is one factor that
has the same pattern of effect to cost overruns in all studies - the length of project
implementation and delay. Higher length of project implementation and delay always
increase cost overruns.
It is obvious that road and rail projects in Sweden perform differently in terms of cost
overruns. Moreover, this result supports the conclusion from previous studies that the
average cost overruns are higher in rail projects than in road projects. The Swedish rail
projects also have very high standard deviation of cost overruns. It shows that uncertainty
and risk regarding cost overruns are large.
The cost overruns in road and rail projects in Sweden are constant for the 13-year period
and cost estimates have not improved over time. Note that this finding is regardless of the
change in use of price indexes by Road and Rail Administrations.
We find that small Swedish transport projects (< 100 million SEK) have much higher cost
overruns than large projects. Moreover, they constitute around one fourth of the total
amount of budget used for cost overruns in both road and rail projects. We also find that
the average cost overruns are very small in bigger projects especially in rail projects.
Average cost overrun in motorways is very low but they still constitute more than half of
the total amount of cost overruns in million SEK. For secondary roads, the average cost
overrun is high but they do not constitute much of the total budget for cost overruns.
Among the rail projects, stations and rail yards have high average cost overrun with very
large standard deviation. Therefore, planners should pay more attention to these
investments. Moreover, it should be realized that constructing new tracks in existing line
corridors constitute a lot of the total amount of cost overruns in million SEK.
For road and rail projects in Sweden, the more complex projects do not seem to have a
larger risk of cost overrun than the less complex projects. This finding is however
uncertain.
Methods to improve cost estimations – Successive Calculation 65
4. Methods to improve cost estimations - Successive Calculation
This chapter explains one of the methods that are used for more realistic assessments of
uncertainty in cost estimations. It is the Successive Calculation. The key concept of this method
is that risk and uncertainty in cost estimation is considered by group analysis. In principle, the
group should include individuals who can contribute to creativity and prevent optimism (and
perhaps also too much pessimism). However, in practice, the group mainly includes people who
relate with the projects. According to some researches in this area, applying this method still
gives risk of optimistic cost estimation. The consideration from the planners or people who
relate with the projects is mostly optimistic. Thus, this method is still what is called an inside
view analysis. In the next chapter, we focus on another method which is the Reference Class
Forecasting. It is an outside view analysis. The method examines the experiences of a class of
similar projects, lays out a rough distribution of outcomes for this reference class, and then
positions the considered project in that distribution [2]. In some studies, it is claimed that the
resulting forecast from an outside view analysis is more accurate than an inside view analysis.
4.1 Successive Calculation method
The development of the Successive Calculation was initiated at the Technical University of
Denmark by Steen Lichtenberg in the beginning of the 1970s [43]. The principle is originally a tool
for fast, early cost estimating and scheduling in the construction industry. Later it has developed
into a multi-purpose management instrument. From the 1980s onwards, it has functioned as a
risk management tool and has been applied professionally [43]. Two important features of the
method are using the group analysis and procedure of working top down.
4.1.1 General procedure
In this section, the general procedure of the Successive Calculation is summarized [44]. The
procedure is shown in Figure 4-1. There are two main phases; the qualitative and the
quantitative phases. The procedure applies a “top-down” philosophy. The main items of the
project are considered first, followed by sub-items of the main items. The “top-down” philosophy
forces the analysis group to proceed and analyse project systematically.
Methods to improve cost estimations – Successive Calculation 66
Figure 4- 1 Successive Calculation procedure.
Quantitative Phase
Qualitative Phase
Methods to improve cost estimations – Successive Calculation 67
The qualitative phase
Establishing an analysis group
A properly balanced analysis group of key individuals is established to suit the specific
purpose of the analysis. The analysis group implements the process outline below. The first
task of the analysis group is an in-depth discussion of the actual programme, project or task,
its objectives, characteristics, scope and other fixed preconditions.
General sources of uncertainty
All general or overall sources of potential uncertainty are identified, organized in groups, and
defined according to relevant sub-routines. Brainstorming is used in this step.
The quantitative phase
Establishing and evaluating the basic structure
A set of main items or main activities is chosen and described. Their numerical values are
evaluated, using the technique of “group triple estimating”. According to the probability
theory1, the mean values can be calculated by using this formula:
The set of items includes correction items which reflect the effect from the general sources
of uncertainty mentioned above. The correction items are any other factors both external
and internal, such as competition, organization etc.
Next, the uncertainty calculation is conducted. The uncertainty of a given parameter is either
measured as the so-called “range”, defined as the difference between the minimum and the
maximum limits of the triple estimate, or as the standard deviation. The standard deviation is
approximately equal the formula below;
The standard deviation (S) reflects the local uncertainties of each parameter. However, they
do not affect the grand total figure with their full value. They contribute only via square of S
(S2) to the total sum of squares. This value is called the variance in statistical analysis. Here,
the S2 is called the Priority Figure (P) because it illustrates the relative importance of the
item to the uncertainty of the total result. Lastly, the global standard deviation (S) for the
grand total result needs to be calculated by deriving the square root of the sum of the S2.
1 The mean value and standard deviation calculation above is based on “Erlang distribution”. However, if
it is stressed that other distribution functions may be more relevant, the transformation formulas for the
mean value and standard deviation must be adjusted accordingly.
Equation 4.1
Equation 4.2
Methods to improve cost estimations – Successive Calculation 68
The first numerical calculations of the total result are performed, using the statistical rules
above. They result (1) in a mean value and its related variability, and notably (2) in a “Priority
Figure” (P) for every discrete element which indicates its relative importance to the reliability
of the total result. An example of calculation details is shown in Figure 4-2.
Figure 4- 2 Example of calculation details.
As discussed earlier, each main item is evaluated, specified during the qualitative phase of
the analysis. In the first line, the greatest optimist in the analysis group has evaluated that
the costs of item 1 will certainly be higher than £10m. Similarly, the greatest pessimist has
evaluated that the costs will not exceed £40m. The average or most likely value is £20m.
The mean values (M) are calculated according to the Equation 4.1. For example, the first
line, M = (10 + 3x20 + 40)/5 = 22.0. The standard deviations (S) are calculated by the
Equation 4.2. Continuing with the first line as an example, S = (40-10)/5 = 6. The mean values
and standard deviations are calculated for all items as well as their Priority Figures (S2). The
Methods to improve cost estimations – Successive Calculation 69
mean value of the grand total is the sum of all mean values (£123m). The global standard
deviation (S) is approximately equal to the square root of the sum of Priority Figures (140).
In the example it is approximately £12m or around 10% of the mean value.
The systematic, successive detailing process
The most crucial items are detailed successively. The above Priority Figure is the efficient
guide. This successive detailing and re-evaluating process continues until the analysis
group has approached what they believe is an unavoidable minimum level of uncertainty.
In this step, the Priority Figure is reduced by considering sub-divisions in each parameter. In
the parameters with high Priority Figure values, the statistic values in their sub-divisions are
calculated. Then, a previous figure is cancelled and is replaced with the new set of detail
items. An example of this process is in Figure 4-3.
Figure 4- 3 Example of systematic and successive process.
Methods to improve cost estimations – Successive Calculation 70
Figure 4-3 shows how to reduce the total uncertainty by a systematic, successive process.
The items no.1 and no.2 are calculated in sub-divisions. In this case, they are relevant to the
item no.3. Thus, the item no.3 needs to be re-evaluated after the calculation. The two new
sub-divisions (item no.1 and no.2) and a re-evaluation (item no.3) of the major main items
have reduced the total uncertainty significantly. In this case, the standard deviation reduces
from £12m to £10m.
Establishing conclusions
The analysis group finally identifies and ranks a set of suggested action plans or other
conclusions which is likely to optimize the venture, including relevant measures against any
major commercial risks.
The top ten risk items are summarized. Moreover, knowing the mean value and standard
deviation from the previous step, it can provide the statistical S curve or cumulative
distribution function. An example of the curve is shown in Figure 4-4. The normal distribution
is a reasonable approximation. Only in case of a dominant skewed local uncertainty will the
resulting curve be slightly skewed. In such cases, it is possible to make a more exact
calculation of the resulting curve.
The statistical S curve or cumulative distribution function of the total result is the probability
that the actual future costs will not exceed a certain given budget value. It shows the
probability inherent in a given budget. This S curve allows management to develop safe and
workable budgets while a conventional budget estimate consists of only on definite figure.
The two levels of budgets that are reported as a result of the Successive Calculation are
explained as follows.
o A working budget usually includes, as a minimum, the expected total sum (assumed
base case conditions). In Figure 4-4, it equals £123.9m. It may typically be defined
as being equal to the expected costs for the overall influences. Project managers are
typically responsible for handling this.
o A higher-level budget is the cost for the higher level of responsibility, therefore
requires a further margin or reserve in the budget in order to support for such risk
and uncertainty of the project. For example in Figure 4-4, at a 90% confidence limit,
the higher-level budget is £135.6m.
Methods to improve cost estimations – Successive Calculation 71
Figure 4- 4 Example of S curve or cumulative distribution function related to the budget estimation.
4.1.2 Applications and limitations
The Successive Calculation has been applied professionally since 1980 [43] [44]. It is considered a
multi-purpose management tool. It supports such processes as quality assurance of budgets,
bid or tender estimates, and schedules, profitability analyses and other financial analyses. It is
also applied in risk analyses, ranking of alternative solutions and team building. However, the
application to cost estimations is focused in this thesis. Two examples of practical experiences
and results in cost estimation are shown in Table 4-1.
From Table 4-1, the results of both projects are excellent by using the Successive Calculation.
Nevertheless, this method has some limitations;
The necessity of a modern, open management policy.
A supplement to, not a substitute for, existing planning techniques.
Only the overall total result is reliable, not each sub-item or activity.
Focus on quantitative objectives.
Catastrophes or disasters require a supplementary sub-procedure.
Trained facilitators are required.
Subjective uncertainty must be accepted.
The implementation process requires effort, time and the support of senior management.
An inside view, meaning optimism bias is likely to remain.
Methods to improve cost estimations – Successive Calculation 72
Table 4- 1 Two examples of applications and results in cost estimation by the Successive Calculation.
Projects Original
budget
Budget by Successive
Calculation
Results
working
budget
higher-level
budget
Complex high-tech, multi-
purpose 10,000-seat arena, Oslo
Spectrum in Norway
$45M $80M ± $10M $125M The official project account after
the construction deviated by less
than 1% from the calculated
mean value or working budget.
Lillehammer Olympic Games in
Norway
$1230M $800M ± $90M - The final official accounts equaled
the analysis mean value of $800M,
so the reserve fund was saved
and was used to operate the
facilities after the games.
4.2 Use in Swedish investment planning
4.2.1 Successive Calculation in transport investment planning
In Sweden, Transport Investment Plans are conducted by the Swedish Government via public
agencies. The plans cover a period of around ten years and are typically revised every five
years [3]. The latest plan is the plan of the period 2010-2021. In this plan, the Road
Administration and the Rail Administration carried out the entire planning process jointly during
2008-2009. The plan comprises one part with national road and rail investments and one part
with 21 regional plans, one for each county region.
The Successive Calculation method was used in the latest plan. In 2008, there was a regulation
stating that all transport projects with a total cost greater than 500 Million SEK needed to do the
Successive Calculation [14] [18] [45].
The Successive Calculation that has been applied in the Swedish investment planning actually
is similar to the general procedure of the method shown in Figure 4-1. However, it is applied in
two different ways – the full uncertainty analysis and the simplified uncertainty analysis [45]. The
summary of the two analyses is as follows.
Methods to improve cost estimations – Successive Calculation 73
The full uncertainty analysis
The full uncertainty analysis is used for large and complex projects. It is carried out by a cross-
compound analysis group (8-15 members) for 2 days under the direction of a trained moderator.
The result of the cost calculation is provided in a report (“Kalkyl-PM”). Before the uncertainty
analysis is implemented, the project has developed its own basic calculation. The result of the
basic calculation is not presented to analysis members before the analysis is carried out. The
uncertainty analysis is made in accordance with the requirements of Annex 1 (“Kalkylbok”) and
Annex 2 (“Kalkyl-PM”). After the full uncertainty analysis, a comparison with the basic calculation is
done. Then, it is the responsibility of the project manager to update the estimate and implement
appropriate measures to eliminate the largest uncertainties.
The simplified uncertainty analysis
The simplified uncertainty analysis follows the same methodology as the full analysis. However,
it is done with a smaller analysis group and in less time. The analysis group should be at least 5
people, including at least 2 people who are not actively included in the project team. Before the
analysis, the project develops its own basic calculation. The uncertainty analysis is carried out
step by step according to Annex 1 (“Kalkylbok”) and Annex 2 (“Kalkyl-PM”). This analysis is
performed in-house (with the support of regional staff).
Example of the Successive Calculation result
An example of a Successive Calculation result is shown in Figure 4-5. It is the result of
Stockholm bypass (Förbifart Stockholm). From the left, the first results are the general issues or
general sources of uncertainties. It shows the base case situation and the future situation. The
results come from brainstorming. The second result is the basic hierarchical Work Breakdown
Structure (WBS) of the project. This WBS is used in the analysis of the next step which is the
top-level estimate sheet. An estimate sheet is a calculation sheet that shows the statistics
values such as mean, Priority Figure and standard deviation.
The fourth one is the uncertainty profile or top ten risks. The fifth and the sixth results are the
Bell-curve and S-curve of the cost estimation, respectively. The curves show the probability
inherent in a given budget. For Swedish transport projects, they use cost at an 85% confident
limit as the higher-level budget. The last result is the report of the Successive Calculation.
It should be noted that the cost at an 84.13% confident limit equals the probability that the cost
will be within the estimate plus one standard deviation from the mean as shown in Figure 4-6 [46].
Therefore, it can be simplified that the higher-level budget at the 85% confident limit in Swedish
transport projects is the value at the one standard deviation above the mean.
Methods to improve cost estimations – Successive Calculation 74
1
2
3
4
5
6
7
Figure 4- 5 Example of the Successive Calculation result of the Stockholm bypass (Förbifart Stockholm).
Methods to improve cost estimations – Successive Calculation 75
Figure 4- 6 Standard deviation of normal distribution.
4.2.2 Cost variance analyses
The Successive Calculation method has only been applied since 2008 in Swedish transport
projects, so there are not yet any evaluations on the outcomes. Instead, in this thesis, we
compare the results of the method with the standard deviations of the actual outcomes. The
actual outcomes are the standard deviations of road and rail projects completed during 1997-
2009 that are reported in Chapter 2. As explained earlier, the budget at 85% confident limit is
located at the one standard deviation from mean. Thus, the variances can be compared with the
standard deviation of the actual outcomes. We assume that the distribution of cost estimate
inaccuracy reflects the distribution of project cost. To see the cost variance, we calculate cost at
85% confidence limit minus cost at 50% confidence limit as a percentage of cost at 50%
confidence limit as in Equation 4.3.
%Difference of cost = (Cost at 85% - Cost at 50%) x 100
Cost at 50%
Equation 4.3
Methods to improve cost estimations – Successive Calculation 76
The variances are calculated both in road and rail projects. The data of the budget at 85% and
50% confident limit are collected from the projects in the latest national investment plan. For
road projects, we received the data from the Transport Administration calculation sheets. For
rail projects, we find the data from the Transport Administration website. The variances are
compared with the historical actual outcomes as explained above. Moreover, the variances in
different planning phases are investigated. The results show whether cost estimates are more
certain the longer an investment has come in the physical planning process. The cost estimates
ought to be more certain the longer an investment has come in the physical planning process as
shown in Figure 4-7 [47].
Figure 4- 7 Cost uncertainty during the project cycle.
Methods to improve cost estimations – Successive Calculation 77
The phases of planning for road and rail projects in Sweden are shown in Figure 4-8. We
categorize road projects, in “Bristanalys” or very early planning, “Förstudie” or initial study,
“Vägutredning” or feasibility study and “Arbetsplan” or design plan. Rail projects are categorized
similarly. We have considered how for the projects had advanced at the time when the cost
calculation was carried out.
Phases of planning for road projects.
Phases of planning for rail projects.
Figure 4- 8 Phases of transport planning.
After refining the data, 249 road projects and 46 rail projects are used. We calculate the
differences of cost estimates or variances according to Equation 4.3 for each project. Then we
analyse the descriptive statistic in each phase of planning. The mean value of each phase reveals
the thinking of transport planners to the projects in each phase. Higher value of variance means
they think the project more uncertainties. The results in each phase are as follows.
Bristanalys Arbetsplan Vägutredning Förstudie
Järnvägsutredning Järnvägsplan Idéstudie Förstudie
Methods to improve cost estimations – Successive Calculation 78
Table 4- 2 Descriptive statistics of road projects.
Descriptive Statistics
Road N
Cost differences (%) between 85%
and 50% confident limit Std. Deviation
Minimum Maximum Mean
Bristanalys 42 3.33 13.33 9.52 2.33
Förstudie 70 1.10 28.20 9.31 4.91
Vägutredning 76 1.70 18.30 9.68 3.39
Arbetsplan 61 .90 13.20 7.98 3.13
Total 249 .90 28.20 9.13 3.73
Valid N (listwise) 42
Figure 4- 9 Comparison between road project variances and actual outcome.
Methods to improve cost estimations – Successive Calculation 79
Table 4- 3 Descriptive statistics of rail projects.
Descriptive Statistics
Rail N
Cost differences (%) between 85%
and 50% confident limit Std. Deviation
Minimum Maximum Mean
Idéstudie 6 8.93 21.27 14.93 4.04
Förstudie 18 3.73 26.87 11.27 5.11
Järnvägsutredning 8 6.05 20.08 13.05 5.03
Järnvägsplan 14 3.69 24.26 11.32 7.09
Total 46 3.69 26.87 12.07 5.64
Valid N (listwise) 6
Figure 4- 10 Comparison between rail project variances and actual outcome.
Methods to improve cost estimations – Successive Calculation 80
For road projects, the differences of variances between each phase are small as shown in
Figure 4-9. Table 4-2 shows descriptive statistics of variances in each phase. It shows that the
variances are similar in means and standard deviations. The exception being that projects in the
latest phase – Arbetsplan - have a somewhat smaller variance. Still, it can be concluded that the
cost estimates in road projects are not more certain the longer an investment has come in the
physical planning process. Moreover, we find that the average variance is significantly lower than
actual outcome. The variance mean is only 9.1% while the actual outcome is 24.6% as shown in
Figure 4-9.
For rail projects, there are no significant differences of variances between each phase as shown in
Figure 4-10. Table 4-3 shows descriptive statistics of variances in each phase. The means and
standard deviations of variances in each phase are also not significantly different. However, the
highest uncertainty is found in “Idéstudie” phase. The “Järnvägsutredning” phase has higher
uncertainty than the “Förstudie” phase. It may be because the projects in “Järnvägsutredning”
phase are much larger and complex objects. Uncomplicated projects do not need
“Järnvägsutredning” (they can go directly from Förstudie to Järnvägsplan). Furthermore, the
average variance is much lower than the actual outcome. The variance mean is only 12.1%
while the actual outcome is 50.5%.
In sum, we find that the differences between actual outcomes and variances are surprisingly
small between projects in different planning stage in both road and rail projects. Therefore, we
can conclude that planners believe that investments in early planning stages feel equally certain
as in late planning stages. Moreover, their cost estimations seem optimistic. The actual
outcomes in terms of cost overruns are considerably higher than the variances of the projects in
the latest plan.
As size of projects is one of the factors identified in international studies that contributes to cost
overruns, further analyses that consider different size of projects are conducted. The actual
outcomes are the standard deviations which are stated in Chapter 3. The differences of cost
estimates according to Equation 4.3 for each project size are calculated. Table 4-4 shows the
results. As can be seen, for road projects the variance decrease slightly with project size. For
rail projects the opposite is true, i.e. variances increases with project size. Figure 4-11 and
Figure 4-12 are the graphs of variances in different project sizes for road and rail projects,
respectively. The variances of small projects in both road and rail projects are much lower than
the actual outcomes especially in rail projects. The difference is very large, 74% compared to
8%. For the large projects, the differences between actual outcomes and variances are much
Methods to improve cost estimations – Successive Calculation 81
lower. The actual outcome is even lower than in the Successive Calculation for very large rail
projects. Our results are similar to those in a cost overrun study of Norwegian road projects [12].
The researcher explained that cost overruns were more predominant among smaller projects
because more attention was given to cost estimates of large projects.
Table 4- 4 Variances by project sizes.
Road
Size of projects in terms of forecasted cost (million SEK)
Total Small (cost ≤ 100)
Medium (100<cost≤500)
Large (500<cost≤1000)
Very large (cost>1000)
Number of projects 116 118 11 4 249
Variances in latest plan (%) 9.7 8.7 8.6 6.4 9.1
Standard deviation (%) 4.1 3.4 2.8 3.1 3.7
Actual outcomes (%) 34.0 14.3 8.4 8.6 24.6
Differences between actual outcomes and variances in latest plan (Percentage units)
24.3 5.6 -0.2 2.2 15.5
Rail
Size of projects in terms of forecasted cost (million SEK)
Total Small (cost ≤ 100)
Medium (100<cost≤500)
Large (500<cost≤1000)
Very large (cost>1000)
Number of projects 14 11 4 17 46
Variances in latest plan (%) 8.1 11.0 17.6 14.7 12.1
Standard deviation (%) 3.7 5.6 3.6 5.2 5.6
Actual outcomes (%) 74.1 33.7 28.2 11.9 50.5
Differences between actual outcomes and variances in latest plan (Percentage units)
66.0 22.7 10.6 -2.8 38.4
Methods to improve cost estimations – Successive Calculation 82
Figure 4- 11 Road project variances in different project sizes.
Figure 4- 12 Rail project variances in different project sizes.
Methods to improve cost estimations – Successive Calculation 83
4.2.3 Discussions
As the Successive Calculation has recently been applied, there are different opinions about the
use of the method from people who have been involved in the planning. Some opinions are
described below.
A planner who used to work at the Rail Administration thinks that the use of the Successive
Calculation it will actually dramatically increase the cost of new infrastructure. He gives two
explanations. Firstly, when everyone try to make cost estimates that they are more or less sure
are not too high this will result in larger project budgets and these budgets will then be spent
even if it would be possible to find more cost-effective solutions (since the project leaders have
no incentives to keep costs down). Secondly, because the building companies know of the cost
estimates, they will give high bids for constructing the infrastructure (which will increase their
profits).
A researcher‟s response to above opinion: This is an issue for how the uplift should be used. If
the uplift is constructed as a completely general multiplier like 1.4 for railway projects this could
lead to incentives for project managers of railway projects to use up the corresponding
resources. Such fears could however be countered by bonuses paid to project managers for
delivering cost underruns.
A planner at the Trafikverket explains about the Successive Calculation that they do not
increase the budget for the project during the Successive Calculation. They only reduce the
variance by the successive approach, making them more secure on each main item. This
continues until they reach a low enough variance of approximate 10% between 50% and 85%
confident limit.
If the above explanation is true, budgets will not increase because of the use of the Successive
Calculation and thus the fears of the previous cited planner will not come true. However, there is
a risk that the resulting variance is smaller than it will actually turn out in reality.
Methods to improve cost estimations – Successive Calculation 84
4.3 Key findings and discussion
Using the Successive Calculation in cost estimation has advantage in evaluating
uncertainty. However, the method has its limits. Some measures need to be incorporated
with the use of the Successive Calculation. One recommendation is that the Trafikverket (or
the Government) should start a systematic follow-up of the Successive Calculations.
Incentive for the project manager who can efficiently control project cost is also an
alternative.
The variance analysis results show that the transport planners believe investments in
different planning phases are equally certain. However, the cost uncertainty should
decrease when the project advances towards later stages. Moreover, the variance is
significantly lower than actual outcomes especially in small-sized projects. These results
indicate that the transport planners still calculate the project costs too optimistically. Thus,
we conclude that applying the Successive Calculation in Swedish transport projects do not
put enough emphasis on uncertainties.
Methods to improve cost estimations – Reference Class Forecasting 85
5. Methods to improve cost estimations – Reference Class Forecasting
As explained in the previous chapter, the Successive Calculation is one of the methods to
improve cost estimations. Comparing to the conventional contingency approach, the Successive
Calculation is better in terms of considering the risk and uncertainty in cost estimations.
However, using group analysis in the Successive Calculation means it still has human bias. In
this chapter, we present another method called “Reference Class Forecasting - RCF” which
bypasses human bias. Human bias can be because of optimism bias or strategic
misrepresentation [2] [4]. In some studies [2] [4], it is claimed that the method promises more
accuracy in forecasts or estimations by taking an “outside view” on prospects being estimated,
while the conventional contingency method and also the Successive Calculation take an inside
view. The key concept of this method is to examine the experiences of a class of similar
projects, lay out a rough distribution of outcomes for this reference class, and then position the
current project in that distribution [2]. Apart from the RCF method, we discuss some similar
methods, namely hybrid estimating approach and Risk-Based estimating (RBE).
5.1 Reference Class Forecasting method
Reference Class Forecasting is based on theories of decision making under uncertainty that
won Princeton psychologist Daniel Kahneman the Nobel prize in economics in 2002. Later, the
concept of RCF method was developed by Bent Flyvbjerg.
This section shows the general procedure, applications and limitations of the RCF method. First,
we explain why using the reference class forecasting can make the cost estimations more
accurate. In general, the main explanations of cost overruns are technical, psychological and
political-economic. As was specified in some studies, psychological and political-economic
explanations seem to be the main reason for inaccurate forecasts [4]. Psychological explanations
account for inaccuracy in terms of optimism bias, that is, a cognitive predisposition found with
most people to judge future events in a more positive light than is warranted by actual
experience. Political-economic explanations explain inaccuracy in terms of strategic
misrepresentation. Here, when forecasting the outcomes of projects (in this thesis – cost
estimations), forecasters and planners deliberately and strategically overestimate benefits and
underestimate costs in order to increase the likelihood that it is their projects, and not the
competitors, that gain approval and funding. Optimism bias and strategic misrepresentation are
both deception, but where the latter is intentional, the first is not since optimism bias is self-
deception. Although the two types of explanation are different, the result is the same: inaccurate
estimations. As shown in Figure 5-1 [4], explanations in terms of optimism bias have their relative
Methods to improve cost estimations – Reference Class Forecasting 86
merit in situations where political and organizational pressures are absent or low, whereas
explanations in terms of strategic misrepresentation have their relative merit where political and
organizational pressures are high. Competition between projects and authorities creates political
and organizational pressures. An example of the political pressures is an interview with a
planner at UK local transport authority which was published in a study [2] :
You will often as a planner know the real costs. You know that the budget is too low
but it is difficult to pass such a message to the counsellors [politicians] and the
private actors. They know that high costs reduce the chances of national funding.
Both optimism bias and strategic misrepresentation are examples of human bias. The bias can
be found in the inside view decision. This is because experts and the other team members
make forecasts by focusing tightly on the case at hand, considering its objective, the resources
they need to carry it out, and the obstacles to its completion. They construct in their minds
scenarios of their coming progress and extrapolate current trends into the future. The resulting
forecasts, even the most conservative ones, have often been shown to be overly optimistic.
Even applying the Successive Calculation, cannot fully eliminate the human bias. We may
reduce the strategic misrepresentation by choosing the group analysis members who are not
directly involved in the project. However, they still have optimism bias because people make
decisions based on their intuition or on past experiences.
The Reference Class Forecasting method bypasses human bias by cutting directly to outcomes.
Thus, it is an outside view decision. It completely ignores the details of the project at hand, and
it involves no attempt at forecasting the events that influence the project‟s future course.
Instead, it examines the experiences of a class of similar projects, lays out a rough distribution
of outcomes for this reference class, and then positions the current project in that distribution.
Methods to improve cost estimations – Reference Class Forecasting 87
Figure 5- 1 Explanatory power of optimism bias and strategic misrepresentation, respectively, in accounting for forecasting inaccuracy as a function of political and organizational pressure.
5.1.1 General procedure
The Reference Class Forecasting for a particular project requires the following three steps:
Step 1 Identification of a relevant reference class of past or similar projects
The class must be broad enough to be statistically meaningful but narrow enough to be truly
comparable with the specific project.
Step 2 Establishing a probability distribution for the selected reference class
This requires access to credible, empirical data for a sufficient number of projects within the
reference class to make statistically meaningful conclusions.
Step 3 Comparing the specific project with the reference class distribution
This step is in order to establish the most likely outcome for the specific project.
Figure 5-2 shows a stylized example of the probability distribution for budget increase in a
selected reference class of projects. It also illustrates the link between the observed ex-post
cost increases for historical projects and the required up-lift for a new project to ensure that the
probability of the final cost being higher than the initial budget plus the up-lift is less than a given
threshold level.
If the new project is similar to the projects in the reference class (same type of transport
scheme) and the initial budget is established in a similar manner (not including budget
Methods to improve cost estimations – Reference Class Forecasting 88
contingencies reflecting the risk of cost overruns above the level of contingencies used in the
reference cases), the project should be placed at the point marked “initial budget”.
It should be expected that the final budget – on average – will exceed the initial budget by the
average budget increase. This also implies that there is 50% chance of the budget increase
being less than the average budget increase and 50% of the budget increase being higher than
the average budget increase. If it is not acceptable that there is a 50% chance of the realized
cost being higher than the budget at the average budget increase in Figure 5-2, the up-lift needs
to be higher. Figure 5-2 shows an example of the necessary uplift to ensure that the probability
of a realized cost above the budget (including up-lift) is below a given threshold (x%).
Figure 5- 2 Definition of Up-lifts within a certain class of transport scheme.
5.1.2 Applications and limitations
Applications
The first application of the RFC approach was carried out 2004-2005 under the auspices of HM
Treasury and the UK Department for Transport [2] [4]. In 2005, this method was also officially
endorsed by the American Planning Association and since then it has been used by
governments and private companies in the UK, the Netherlands, Denmark, Switzerland,
Australia, and South Africa, among others [2]. In this literature study, the application for cost
Methods to improve cost estimations – Reference Class Forecasting 89
estimations in transport projects is reviewed. We have studied examples of applying this method
in the UK, the Netherlands, South East Asian, Australia and Canada.
The first study in the methodology for systematic, practical Reference Class Forecasting for
transport projects was developed 2003-2004 and published by the UK Department for Transport
in 2004 [4] [47]. Based on the study [47], the Treasury and the Department for Transport decided to
employ Reference Class Forecasting as part of project appraisal for large transport projects in
the UK.
In the study, they started to do step 1 in the three-step procedure for RFC method described
earlier. The specific categories and the types of project allocated to each category are shown in
Table 5-11. Projects are placed in the same reference class if tests showed no significant
differences between projects.
Table 5- 1 Categories and types of projects used as basis for Reference Class Forecasting.
Category Types of projects Source of optimism bias uplifts
Roads Motorway/Highways
Trunk roads
Local roads
Bicycle facilities
Pedestrian facilities
Park and ride
Bus lane schemes
Guided buses on wheels
Reference class of 172 road
projects (of which 128 are British)
Rails Metro
Light rail
Guided buses on tracks
Conventional rail
High speed rail
Reference class of 46 rail projects
(of which 3 are British)
Fixed links Bridges
Tunnels
Reference class of 34 bridge and
tunnel projects (of which 4 are
British)
For each category of projects, a reference class of completed, comparable transport projects is
used to establish probability distributions for cost overruns for new projects, as required by step
2 in Reference Class Forecasting. The histograms of cost overruns are initiated first and then
the probability distributions are provided. Based on the probability distributions, the required
1 In this thesis, we focus only in road, rail and fixed link projects. However, the study also shows results of
building projects, IT projects, standard civil engineering and non-standard civil engineering.
Methods to improve cost estimations – Reference Class Forecasting 90
uplifts are needed to carry out step 3 in Reference Class Forecasting. Figures 5-3 to 5-5 show
the results from the UK study of step 2 and 3 for roads, rails and fixed links, respectively. The
required uplifts share the same basic S-shape, but at different levels, demonstrating that the
required uplifts are significantly different between project categories for a given level of risk of
cost overrun.
From the required uplifts, the lower the acceptable risk for cost overrun, the higher the uplift. For
instance – a rail project (Figure 5-4), with a willingness to accept a 50% risk for cost overrun in a
rail project, the required uplift for this project is 40%. If the decision planners are willing to
accept only a 10% risk for cost overrun, then the required uplift is 68%.
Figure 5- 3 Probability distribution of cost overruns for road projects according to the UK study.
Methods to improve cost estimations – Reference Class Forecasting 91
Figure 5- 4 Probability distribution of cost overruns for rail projects according to the UK study.
Figure 5- 5 Probability distribution of cost overruns for fixed links projects according to the UK study.
Methods to improve cost estimations – Reference Class Forecasting 92
Table 5- 2 Required uplifts by the Reference Class Forecasting according to the UK study.
Category Types of projects Applicable optimism bias uplifts
50%
per-
centile
60%
per-
centile
70%
per-
centile
80%
per-
centile
90%
per-
centile
Roads Motorway
Trunk roads
Local roads
Bicycle facilities
Pedestrian facilities
Park and ride
Bus lane schemes
Guided buses on wheels
15% 24% 27% 32% 45%
Rail Metro
Light rail
Guided buses on tracks
Conventional rail
High speed rail
40% 45% 51% 57% 68%
Fixed links Bridges
Tunnels 23% 26% 34% 55% 83%
Table 5-2 presents an overview of applicable optimism bias uplifts for the 50% and 80%
percentiles for projects in Table 5-1. The 80% percentile corresponds to a risk of cost overrun of
20% - is the level of risk that the UK Department for Transport is typically willing to accept.
From Table 5-2, if a group of planners are preparing the business case for a new motorway, and if
they or their client decide that the risk of cost overrun must be less than 20%, they should then
use an uplift of 32% on their estimated capital expenditure budget. Thus, if the initially estimated
budget was £100 million, then the final budget-taking into account the bias at the 80%-level is
£132 million. If the planners or their client decide instead that a 50% risk of cost overrun is
acceptable, the uplift is 15% and the final budget is £115 million.
The results from the study above are referenced in many documents such as in a study by Kim
Bang Salling and other [48], Developing Harmonised European Approaches for Transport Costing
and Project Assessment (HEATCO) [49].
In October 2004, the first instance of practical use of the optimism bias uplifts was recorded, in
the planning of the Edinburgh Tram Line 2. Ove Arup and Partners Scotland had been
appointed by the Scottish Parliament‟s Edinburgh Tram Bill Committee to provide a review of
Methods to improve cost estimations – Reference Class Forecasting 93
the Tram business case developed on behalf of Transport Initiatives Edinburgh (TIE). TIE is
project promoter and is a private limited company owned by the City of Edinburgh Council
established to deliver major transport projects for the Council. The business case had estimated
a base cost of £255 million and an additional allowance for contingency and optimism bias of
£64 million – or 25% - resulting in total capital costs of approximately £320 million. Using the
result from the study above, Arup then calculated the 80th percentile value for total capital costs
(the value at which the likelihood of staying within budget is 80%) was £400 million (i.e. £255
million x 1.57, see Table 5-2). The 50th percentile for total capital costs (the value at which the
likelihood of staying within budget is 50%) was £357 million (i.e. £255 x 1.40).
Arup remarked that these estimates of total costs were likely to be low, because the optimism
bias uplifts should be applied to the budget at the time of decision to build, which typically
equates to business case submission. The Tram had not yet even reached the outline business
case stage, indicating that risks are substantially higher at this early stage and that this would
affect uplifts. On that basis Arup concluded that the optimism bias uplifts may had been
underestimated. Moreover, Arup mentioned that the study does allow for optimism bias to be
adjusted downward if strong evidence of improved risk mitigation can be demonstrated.
However this was not the case for the Tram. Thus the overall conclusion of Arup was that the
promoter‟s capital cost estimate of app. £320 million was optimistic. Most likely Tram Line 2
would cost significantly more [4]. Today the line is constructed and Arup has been proven right.
As mentioned in Chapter 1, the cost of this tram system is now uncertain and it is anticipated to
be over £600 million.
The first Reference Class Forecasting in the Netherlands was carried out in 2006 for cost and
traffic projections on the proposed high-speed rail Zuiderzee Line project [50]. As step one of the
reference class forecast of costs – and in order to establish the outside view – a reference class
of 68 comparable rail projects was established. As step two, the probability distribution of cost
overrun in the reference class was found. The distribution is shown in Figure 5-6. Finally, on the
basis of this distribution and the base cost (€4,084 million), it was established that the expected
construction cost of the Zuiderzee Line project was €5,660 million (or approximately 38% uplifts)
at 50% risk of cost overruns. If the decision maker was willing to accept only a 20% risk of cost
overrun, then the budget should be €6,084 million (or approximately 64% uplifts). The project
has since been cancelled; therefore these forecasts cannot be evaluated.
Methods to improve cost estimations – Reference Class Forecasting 94
Figure 5- 6 Probability distribution of cost escalation for rail projects in the Netherlands. Based on reference class of 68 projects.
For South East Asia, a study about the application of the RCF method to transport projects in
selected South East Asian countries (Thailand and the Philippines) was carried out in 2008 [34].
For Thailand, there are a total of 44 transport projects, 15 bridges and 29 roads. For the
Philippines, there are a total of 85 transport projects, 25 bridges and 60 roads. In both courtiers,
from statistic testing, there is no necessity to separate the reference class to road and bridge.
Figure 5-7 shows the results of the RCF application for transport projects in Thailand. If we
allow 10% risk that cost overrun may happen, a 15% uplift of the budget is needed. Figure 5-8
shows the results of the RCF application for transport project in the Philippines. Here 22% uplift
is needed for the same risk. However, findings from the study should be used and interpreted
with caution due to the small sample size and limited types of projects are considered in the
study as mentioned in Chapter 2.
Methods to improve cost estimations – Reference Class Forecasting 95
Figure 5- 7 Road projects in Thailand.
Methods to improve cost estimations – Reference Class Forecasting 96
Figure 5- 8 Road projects in the Philippines.
Next, we summarize a study in 2010 that presents the results of estimation accuracy of a
sample of road projects (between 2000 and 2005) conducted by the Australian State Road &
Traffic Authority using a hybrid estimating approach blending primarily RCF with fixed
contingency approach [51]. To clarify about the hybrid estimating, there is an Authority‟s
estimating manual which specify the contingency value for each project depending on the
planning stage and the project type of the estimate. For example, in the manual, contingency for
detailed estimates needs to be within the range of 10-20% and 20-35% at the concept estimate
stage. Contingencies outside the ranges specified in the manual need to be justified. The
contingency ranges are determined based on historical performance data - a practice that
mirrors the RCF approach. Thus it is called hybrid estimating. For the conventional project
Methods to improve cost estimations – Reference Class Forecasting 97
sample, it is a sample of Australian construction projects (before 1999-2000) using the
conventional fixed contingency approach2.
The last sample is the Risk-Based Estimating (RBE) sample. It contains 11 water infrastructure
projects in Australia (between 2003 and 2007) using the RBE approach. The RBE has recently
been introduced in Australia. The RBE models the cost of individual components with base
estimates and stochastic risk contingencies. The distribution of the overall project cost is derived
by summing the stochastic cost.
The study finds that the average accuracy of the sample using the RCF (or hybrid approach)
compares favorably to historical results. They analyzed cost overruns of a variety of projects in
the past and got an average cost overrun at 34.7% and standard deviation 37.8%., which those
projects typically are used the fixed contingency approach. A comparison with the conventional
contingency approach shows that the hybrid approach can produce more conservative
estimates than the conventional contingency approach, either by less overbudgeting or, more
likely, underbudgeting. Moreover, a comparison with a small RBE sample provides the
preliminary evidence that RBE can in turn be more accurate than the hybrid approach. The
descriptive statistics of cost estimations are shown in Table 5-3.
Table 5- 3 Descriptive statistics of estimation errors in the three samples in Australia.
Recently, a related study was published (in January 2011) – Incorporating Risk of cost overruns
into transportation capital projects decision-making [52]. In the study, the distribution-fitting
method was used and the concept is similar to the RCF method. The main objectives of the
study are to propose methods for estimating the risk of cost overruns and suggest ways to
incorporate it into project decision-making. They proposed distribution-fitting models to create
2 The conventional contingency approach adds a percentage to the base estimate to account for risks.
The contingency amount is typically determined based on an estimator‟s intuition or past experience. The
contingency percentage depends on the type and life cycle phase of the project. [51]
Methods to improve cost estimations – Reference Class Forecasting 98
the probabilities of cost overruns for the Vancouver Island Highway Projects (VIHP). The VIHP
database comprises of 163 projects in Vancouver Island (1993-2003), 127 highway projects and
36 bridge and tunnel projects. They used the Cost Overrun Ratio (COR) instead of the
traditional cost overrun calculation. The COR is the ratio of real costs to planned budget. For
example, if the budget for a project is $1 billion and the actual cost is $1.2 billion, COR = 1.2; if
the actual cost is only $0.8 billion for the $1 billion budget, then COR = 0.8. The COR
histograms for the highway and bridge projects in Vancouver Island are shown in Figure 5-9.
They applied a variety of distributions and concluded that the Cauchy distribution is best fit to
the COR distribution of the projects in Vancouver Island. The three risk levels are categorized:
low (COR ≤ 1), medium (1<COR≤1.2), and high (COR>1.2). The result of three different cost
overrun risk levels in each distribution is shown in Table 5-4 (only for highway projects). It is
comparable with the probability distribution in step two of the RCF method.
Figure 5- 9 COR histograms for highway and bridge projects in Vancouver Island.
Methods to improve cost estimations – Reference Class Forecasting 99
Table 5- 4 COR probabilities of highway projects in Vancouver Island.
Limitations
The RFC method was officially published in 2004. However, the real practical applications of
this method are scarce. The real challenge in doing a Reference Class Forecasting lies in
assembling a valid dataset that will allow a reliable forecast [4]. Such datasets are rare in real-life
policy-making and planning. Large publicly financed projects usually take a very long time from
decision to build until open to service. So reconstructing the actual total costs of a public project
is typically difficult and complex. For private projects, the cost information tends to be kept only
within companies or owners. And for both publicly and privately financed projects, project
owners are not encouraged to show cost escalations data of their projects. It is also quite time
consuming to produce such data. For example, four years of data collection and refinement
were needed for the study of Bent Flyvbjerg et al. to establish a sample of 258 transport projects
with data on both actual construction costs and estimated costs at the time of decision to build
[22]. In sum, establishing reliable data on actual costs for even a single transport project is often
highly time consuming or simply impossible.
Choosing the right reference class of comparative past projects becomes more difficult when
evaluating initiatives, for which precedents are not easily found, for instance the introduction of
new and unfamiliar technologies [2]. Moreover even the same technology, but implemented in
different areas or countries, may give different results.
The potentials for and barriers to Reference Class Forecasting will be different in situations where
(1) optimism bias is the main cause of inaccuracy as compared to situations where (2) strategic
misrepresentation is the chief reason for inaccuracy. In the first type of situation, the potential for
using the outside view and Reference Class Forecasting will be good. Forecasters can be
encouraged to use any methods that will improve their forecasts. However in the second type of
situation, the potential for Reference Class Forecasting is low and barriers are high. That means
Methods to improve cost estimations – Reference Class Forecasting 100
the forecasters may not be interested in other estimation methods to improve their forecasts
because inaccuracy of the forecasts is deliberate. In order to lower barriers, incentives much be
aligned to reward accurate forecasts and punish inaccurate ones.
One weakness of the RFC methods is that it is based on historical outcomes. Thus it may fail to
predict or estimate extreme outcomes, that is, those that lie outside all historical precedents.
However, this is a problem that is shared with all methods.
Another disadvantage is that the method is based on aggregated follow-ups of completed
projects. No information is therefore obtained on which components of a project constitutes the
largest risks for cost overruns. Since a new project will never be exactly the same as a previous
one, there is a risk that the reference class is not fully relevant.
Lastly, it could be argued that in some cases the use of Reference Class Forecasting may result
in such large reserves set aside for a project that this would in itself lead to risks of inefficiencies
and overspending in the same way as when the Successive Calculation which was discussed in
Chapter 4. It is therefore important to combine the introduction of Reference Class Forecasting
and optimism bias uplifts with tight contracts, maintained incentives for promoters to undertake
good risk assessment, and prudent control during procurement and project implementation.
5.1.3 Probability distributions
For both road and rail projects, in this thesis, it is quite straightforward to do the step 1 and step
3 of RCF method. For step 2, we first need to find the most suitable distribution to fit the VTI
database. To determine this, we use the Maximum Likelihood Estimation (MLE) method and
review the previous studies. The following is the summary of the literature study.
The first document is a master thesis – “Transportation Infrastructure Project Cost Overrun Risk
Analysis” in 2006 [11]. The cost overrun ratio (COR) distribution fitting of Vancouver Island Highway
Projects (VIHP) data was provided. The Distribution Fitting method (by Beta distribution) and
Monte Carlo method were used. According to the study, the advantage of the Distribution Fitting
method is that it is based on real data and therefore its results are expected to be more objective
and realistic. Hence, they recommended using the Distribution Fitting method. Furthermore, they
focused on Beta Distribution Fitting, since COR is expected to follow Beta distributions. The result
of estimating COR probabilities from both methods is shown in Table 5-5. As explained earlier,
the COR is the ratio of real costs to planned budgets. For example, if the budget for a project is
$1 billion and the actual cost is $1.2 billion, COR = 1.2; if the actual cost is only $0.8 billion for
the $1 billion budget, then COR = 0.8. From Table 5-5, 57.9% of the projects had cost overruns
Methods to improve cost estimations – Reference Class Forecasting 101
based on Monte Carlo Simulation and Beta Distribution Fitting. At the same time, 87.6% and
88.2% of the projects had the ratio of actual costs to budgets higher than 0.75 based on Monte
Carlo Simulation and Beta Distribution Fitting, respectively.
Table 5- 5 Cost overruns probability estimation comparison between Monte Carlo method and Beta Distribution Fitting method.
The COR probabilities of VIHP data were also studied in another study. It is “Incorporating risk
of cost overruns into transportation capital projects decision-making” [52] in 2011. In the study,
they fitted the following four distributions:
the Normal distribution: N(µ,σ), where the mean µ and the standard deviation σ are the
location and scale parameters, respectively;
the generalized Gamma distribution: Gamma(θ,β,γ) where θ is the location parameter (which
reflects the minimum value of the distribution‟s variable), β and γ are the scale and shape
parameters, respectively;
the Beta distribution: Beta(P, Q, A, B), where P and Q are shape parameters, and A and B are
scale parameters, reflecting the minimum and maximum values of the distribution‟s variable;
the Cauchy distribution: Cauchy(a,b) where a is the location parameter (indicating the
median of the distribution‟s variable), and b is the scale parameter.
The Goodness-of-Fit Statistics are the log-likelihood (LL), the Kolmogorov-Smirnov (KS) and the
Chi-square (x2) test. For the road and highway project data, for example, the Goodness-of-Fit
Statistics of each distribution is shown in Table 5-6. It is obvious that the Cauchy distribution is
the best by providing the maximum Log-Likelihood. Regarding to the goodness-of-Fit test, the
null hypothesis that a given distribution “correctly” represents the data is rejected when the test
statistics for the KS and x2 are less than the Critical Value (CV) at a given level of significance.
The test results in Table 5-6 indicate that the values for KS and x2 for the Cauchy distribution
are the smallest compared with the other three distributions tested. The results further show that
the p-value for the Cauchy distribution model is significantly higher than that for the other three
Methods to improve cost estimations – Reference Class Forecasting 102
models. They concluded, therefore, that the Cauchy distribution best fits the COR distribution of
the VIHP database. This conclusion was further ascertained by running the same tests on the
Flyvbjerg database [22].
Table 5- 6 Goodness-of-fit Statistics of distributions of road and highway projects in VIHP.
From a PhD thesis – “Assessment of transport Projects – Risk analysis and decision support” in
2008 [53], the following four conditions for estimating construction costs with probability
distributions had been proposed:
Upper and lower limits which the analyst is relatively certain the values do not exceed.
Consequently, a closed-ended distribution is desirable.
The distribution must be continuous.
The distribution will be unimodal; presenting a most likely value.
The distribution must be able to have a greater freedom to be higher than lower with respect
to the estimation – skewness must be expected.
There are three distributions that fulfill the conditions above - Triangular distribution, Beta-PERT
distribution and Gamma distribution. Moreover, Steen Lichtenberg, who has developed the
principle of the Successive Calculation, further documents the applicability of an Erlang
distribution for the estimation of the construction costs which corresponds to the conditions
above. The properties of the Erlang distribution require a shape (k) and a scale (θ) parameter.
The Erlang distribution is a special case of the Gamma distribution where the shape (k) is an
integer. In the Gamma distribution, this parameter is not restricted to the integers. Based on
experience it is found that a shape parameter in the range of k = 5-15 matches the distribution
of the variability uncertainty for construction costs. In fact the Erlang function with k = 1 is
identical to the exponential distribution. Using k = 5 the function resembles a Lognormal
distribution. Finally, when k ≥ 10, the distribution is closer to the Gaussian distribution (Normal
distribution).
Methods to improve cost estimations – Reference Class Forecasting 103
In conclusion from the study, the Erlang distribution is recommended to apply for the
construction costs derivation in transport appraisal. Figure 5-10 and 5-11 illustrate the fits of
using the Erlang distribution for the data defined from Bent Flyvbjerg study [28]. For road projects,
the distribution function is fitted with a shape parameter of k = 8 and a scale parameter of θ =
0.09. For rail projects, the distribution function is fitted with a shape parameter of k = 23 and a
scale parameter of θ = 0.075.
Lastly, a study – “The accuracy of hybrid estimating approaches: A case study of an Australian
State Road & Traffic Authority” in 2010 states that past studies showed that Lognormal
distribution is appropriate for modeling cost estimation performance [51]. Figure 5-12 shows the
lognormal distribution curves of cost accuracies for each case in the study.
Figure 5- 10 Inaccuracies of cost estimates of 167 road projects by the Erlang distribution. (database from Flyvbjerg et al., p.17 [28])
Methods to improve cost estimations – Reference Class Forecasting 104
Figure 5- 11 Inaccuracies of cost estimates of 58 rail projects by the Erlang distribution. (database from Flyvbjerg et al., p.17 [28])
Figure 5- 12 Inaccuracies of cost estimations of the hybrid, RBE and convention methods by Lognormal distribution.
Methods to improve cost estimations – Reference Class Forecasting 105
Summary
A Distribution Fitting method using Maximum Likelihood Estimation (MLE) is applied in this
thesis while the Monte Carlo method is not considered. The MATLAB Distribution Fitting Tool
(Dfittool) function is used for the analyses. The Distribution Fitting Tool is a function for fitting a
variety of distributions to data. There are 21 main distributions in the function such as Beta,
Exponential, Gamma, Lognormal, Normal and Poisson. However, not all of the distributions are
available for all data sets. The function determines the extent of the data (nonnegative, unit
interval, etc.) and displays appropriate distributions in the distribution drop-down list. For our
data, the function displays the following appropriate distributions; extreme value, generalized
extreme value, generalized Pareto, logistic, non-parametric, normal and t location-scale
distribution. Figure 5-13 shows examples of each distribution except the normal distribution. In
the next section we will discuss which distribution best fits our data.
Methods to improve cost estimations – Reference Class Forecasting 106
Figure 5- 13 Examples of distributions in the thesis.
Extreme value distribution From: MATLAB
Generalized extreme value distribution From: MATLAB
Generalized Pareto distribution From: MATLAB
Logistic distribution
From: http://en.wikipedia.org/wiki/File:Logisticpdfunction.png
Non-parametric distribution From: MATLAB
t location-scale distribution
From: http://en.wikipedia.org/wiki/File:Student_t_pdf.svg
Methods to improve cost estimations – Reference Class Forecasting 107
5.2 Application in case studies
In this section, we apply the RCF method to estimate the project costs of our case studies.
There are two case studies. The case study for road projects is the Stockholm bypass (Förbifart
Stockholm). The case study of rail projects is the Västlänken. We create the uplifts for road and
rail projects by using the VTI database as the reference class. The uplifts results are compared
with the previous study by Bent Flyvbjerg. Moreover, the cost estimations of the two case
studies are compared with the total costs estimated by the Successive Calculation.
5.2.1 Case study projects
The Stockholm bypass (Förbifart Stockholm) is a new motorway linking southern and northern
Stockholm (as shown in Figure 5-14) resulting in a new route for the European highway (E4)
past Stockholm.
The new link west of Stockholm has been under investigation for several decades and a large
number of different alternatives have been studied [54]. To reduce the impact on sensitive natural
and cultural environments, 18 km of the total of 21 km of the project are in tunnels.
The construction work is planned to start in 2012 and it will take 8 to 10 years to finish. When
the link opens for traffic it will be one of the longest road tunnels in the world. By 2035, the
Swedish Transport Administration (Trafikverket) estimates that the project will be used by
140,000 vehicles per day.
The second case study is the Västlänken. It is about 8 km double-track railway tunnel in
Gothenburg. It will increase the accessibility of the city with two new stations, at Haga and
Korsvägen (as shown in Figure 5-15). The Trafikverket is planning for it. The total construction
period will be 9 to 10 years. When the link opens to service, it will connect the commuter rail
service to the existing lines and open up the new stations in the city.
Methods to improve cost estimations – Reference Class Forecasting 108
Figure 5- 14 Stockholm bypass (Förbifart Stockholm).
Route of Stockholm bypass
The main tunnels
Methods to improve cost estimations – Reference Class Forecasting 109
Figure 5- 15 Västlänken.
Route of Västlänken
Station
Methods to improve cost estimations – Reference Class Forecasting 110
5.2.2 Results of road projects
For road projects, we use the 102 road projects to be the reference class. The following is the
details in each step of the RCF method.
Step 1 Identification of a relevant reference class of past or similar projects
We do not divide our reference class to a number of categories. As mentioned in Section 3.3.4,
it is impossible to establish valid optimism bias uplift for each category. Hence, the reference
class for road projects is shown in Table 5-7.
Table 5- 7 Types of projects used as basis for Reference Class Forecasting of road projects.
Category Types of projects Source of reference class
Roads Major road
Motorway
Secondary road
Urban road
Reference class of 102 road
projects
Step 2 Establishing a probability distribution for the selected reference class
The probability curves of each distribution are shown in Figure 5-16. The Likelihood of t
location-scale, normal and generalized extreme value distributions are -440.42, -470.94 and
-453.99 respectively. Thus the t location-scale distribution is best fit for our road project data.
Figure 5-17 shows the cumulative probability of cost overruns by the distribution. On the basis of
the probability distribution, required uplifts are calculated as shown in Figure 5-18. The summary of
uplifts for selected percentiles for road projects is shown in Table 5-8. With a willingness to
accept a 50% risk for cost overrun in a road project, the required uplift will be 5%. If a planner is
willing to accept only a 10% risk for cost overrun, then the required uplift will be 24%. Compared
with the previous study by Bent Flyvbjerg and COWI consultant [47], the road projects in our
study require lower uplifts.
We use the required uplift results to compare with the action of planners. As shown in Figure
5-19, using the RFC method, the different between cost estimation at 85% confident and 50%
confident is approximately 13%. From the previous chapter, we find that the average difference
is around 9% (when the Successive Calculation is applied in cost calculations)3. It shows that
planners seem to estimate project costs with either optimism bias or strategic misrepresentation.
3 For Stockholm bypass (Förbifart Stockholm), it was 5%.
Methods to improve cost estimations – Reference Class Forecasting 111
However, we cannot conclude that using the RCF will result in a higher estimated project cost
because we do not know the project initial budgets.
Figure 5- 16 Probability curves of road projects.
Figure 5- 17 Distribution of cost overruns of road projects.
Methods to improve cost estimations – Reference Class Forecasting 112
Figure 5- 18 Required uplift of road projects.
Table 5- 8 Cost uplifts for selected percentiles of road projects.
Category Types of projects Required uplifts
50%
per-
centile
60%
per-
centile
70%
per-
centile
80%
per-
centile
85%
per-
centile
90%
per-
centile
Roads Major road
Motorway
Secondary road
Urban road
5%
(15%)
8%
(24%)
11%
(27%)
15%
(32%)
19%
(-)
24%
(45%)
Note : ( ) is the required uplift from Bent Flyvbjerg study.
Methods to improve cost estimations – Reference Class Forecasting 113
Past
Conventional Contingency Method
(102 observations of completed projects)
Reference Class Forecasting
(Based on the 102 completed projects)
Present
Successive Calculation(249 observations of planned projects)
Estimated Cost (EC) +
Contingency
= Initial Budget (IB)
Estimatation Actual
11 % Cost escalation
or 1.11 x IB
?
Should be better
than past
At 50 % confident
Factor 50 x IB
At 85 % confident
Factor 85 x IB
At 50 % confident
1.05 x IB
At 85 % confident
1.19 x IB
Unknown in this study
Future outcome
Estimated Cost (EC) +
Contingency?
= Initial Budget (IB)
Estimated Cost (EC) +
Contingency
= Initial Budget (IB)
At 50 % confident
1.11 x IB
At 85 % confident
1.38 x IB
Figure 5- 19 Cost estimations for road projects.
Step 3 Comparing the specific project with the reference class distribution
By using the Successive Calculation for the Stockholm bypass, the expected project cost is 27.9
billion SEK at 50% risk of cost overruns. At 15% risk of cost overruns, or 85% confident that
costs will be within budget, the cost is 29.2 billion SEK.
We want to apply the RFC method to estimate cost of the Stockholm bypass project. One
constraint is that the initial budget is not provided. We therefore assume that the cost at 50%
confident is the same as calculated by the Successive Calculation. From the result in step 2, the
required uplift at the likelihood of 50% of staying within budget is 5%. Thus the assumed initial
budget is 26.6 billion SEK (27.9 billion SEK / 1.05). As the required uplift for the 85% confident
is 19%, the estimated cost equals 31.7 billion SEK (i.e. 26.6 billion SEK x 1.19). In this case, the
project cost at 85% confident level by using the RCF method is higher than the corresponding
cost using the Successive Calculation.
Diff. ≈ 9.1%
Diff. ≈ 13.3%
Diff. ≈ 24.6%
Methods to improve cost estimations – Reference Class Forecasting 114
5.2.3 Results of rail projects
For rail projects, we use the 65 rail projects in the VTI database to be the reference class. The
following is the details in each step of the RCF method.
Step 1 Identification of a relevant reference class of past or similar projects
As for road projects, we do not divide our reference class to a number of categories. As
mentioned earlier, it is statistically significant that the rail projects are similar in variances in
each detailed project type. Hence, we can combine analysis of each detailed project type
together. The reference class for rail projects is shown in Table 5-9.
Table 5- 9 Types of projects used as basis for Reference Class Forecasting of rail projects.
Category Types of projects Source of reference class
Rails New track, existing line
New track, new line
Station and rail yard
Upgrading existing line
Reference class of 65 rail projects
Step 2 Establishing a probability distribution for the selected reference class
The probability curves of each distribution are shown in Figure 5-20. The Likelihood of t
location-scale, normal and generalized extreme value distributions are -332.42, -346.69 and -
327.67 respectively. Thus the distribution by generalized extreme value is the best fit for our rail
project data. Figure 5-21 shows the cumulative probability of cost overruns by the distribution. On
the basis of the probability distribution, required uplifts are calculated as shown in Figure 5-22. The
summary of uplifts for selected percentiles for rail projects is shown in Table 5-10. With a
willingness to accept a 50% risk for cost overrun in a rail project, the required uplift will be 11%.
If a planner is willing to accept only a 10% risk for cost overrun, then the required uplift will be
77%. Comparing with the previous study by Bent Flyvbjerg and COWI consultant [47], the rail
projects in our study require lower uplifts at low confidence levels but higher uplifts at high
confidence. The explanation of this result is that our rail project data is very high in variance (SD
= 50.5%).
We use the required uplift results to see the action of planners. As shown in Figure 5-23, using
the RFC method, the difference between cost estimation at 85% confident and 50% confident is
approximately 44%. From the previous chapter, we find that the difference is only 12% when the
Successive Calculation is applied in cost calculations. It shows that planners seem to estimate
Methods to improve cost estimations – Reference Class Forecasting 115
project costs with very high optimism bias or strategic misrepresentation. The optimism bias is
much bigger in rail project cost estimations than in road projects. However, we cannot conclude
that using the RCF will result in higher estimated project costs because we do not know the
project initial budgets.
Step 3 Comparing the specific project with the reference class distribution
The Västlänken project is our case study for the rail project. By using the Successive
Calculation, the expected project cost was 16.2 billion SEK at 50% risk of cost overruns. At 15%
risk of cost overruns or 85% confident that cost will be within budget, the cost is 19.3 billion
SEK.
We want to apply the RFC method to estimate the cost of the Västlänken project. As with the
road project case study, the initial budget is not provided. In response to this constraint, we
assume that the cost at 50% confident is the same as calculated by the Successive Calculation.
Thus the assumed initial budget is 14.6 billion SEK (16.2 billion SEK / 1.11). The required uplift
for the 85% confident is 60%, so the estimated cost will be 23.4 billion SEK (i.e. 14.6 billion SEK
x 1.60). In this case, the project cost by using the RCF method is much higher than the project
cost by using the Successive Calculation.
Figure 5- 20 Probability curves of rail projects.
Methods to improve cost estimations – Reference Class Forecasting 116
Figure 5- 21 Distribution of cost overruns of rail projects.
Figure 5- 22 Required uplift of rail projects.
Methods to improve cost estimations – Reference Class Forecasting 117
Table 5- 10 Cost uplifts for selected percentiles of rail projects.
Category Types of projects Required uplifts
50%
per-
centile
60%
per-
centile
70%
per-
centile
80%
per-
centile
85%
per-
centile
90%
per-
centile
Rails New track, existing line
New track, new line
Station and rail yard
Upgrading existing line
11%
(40%)
20%
(45%)
32%
(51%)
49%
(57%)
60%
(-)
77%
(68%)
Note : ( ) is the required uplift from Bent Flyvbjerg study.
Past
Conventional Contingency Method
(65 observations of completed projects)
Reference Class Forecasting
(Based on 65 completed projects)
Present
Successive Calculation(46 observations of planned projects)
Estimated Cost (EC) +
Contingency
= Initial Budget (IB)
Estimatation Actual
21 % Cost escalation
or 1.21 x IB
?
Should be better
than past
At 50 % confident
Factor 50 x IB
At 85 % confident
Factor 85 x IB
At 50 % confident
1.11 x IB
At 85 % confident
1.60 x IB
Unknown in this study
Future outcome
Estimated Cost (EC) +
Contingency?
= Initial Budget (IB)
Estimated Cost (EC) +
Contingency
= Initial Budget (IB)
At 50 % confident
1.21 x IB
At 85 % confident
1.82 x IB
Figure 5- 23 Cost estimations for rail projects.
Diff. ≈ 44.1%
Diff. ≈ 12.1%
Diff. ≈ 50.5%
Methods to improve cost estimations – Reference Class Forecasting 118
5.3 Key findings and discussion
With the first reference class forecasts carried out 2004-2005, it is still difficult to draw
conclusions about the impacts of adopting the practice of Reference Class Forecasting.
This is an area for further research. However, it is clear that in Sweden planners are
increasingly aware of risks and uncertainties in cost estimations of transport projects and it
is likely that the international studies referenced in this report have contributed to this.
The RFC method has some limitations. Conducting the reference class is often highly time
consuming or simply impossible. However, it worked well in our study. In our study, as well
as in the international ones, it may however fail to predict or estimate extreme outcomes,
that is, those that lie outside all historical precedents.
If the RFC method is to be introduced as a standard tool in Sweden, it is important to
combine the introduction of the method with other measures such as tight contracts,
maintained incentives for promoters to undertake good risk assessment, and prudent
control during procurement and project implementation.
By the Reference Class Forecasting method, we find that with a willingness to accept a
50% risk for cost overrun in a road project, the required uplift will be 5% and 11%, for road
and rail projects respectively. If a planner is willing to accept only a 10% risk for cost
overrun, then the required uplift will be 24% and 77%, for road and rail projects
respectively.
For method used for improving transport cost estimations in Swedish transport projects is
the Successive Calculation. However, compared with uplifts suggested by the RFC
method, we find that planners still estimate project costs with optimism bias or strategic
misrepresentation.
For both case studies, the anticipated project costs by using the RCF method are higher
than the project costs by using the Successive Calculation at the equal cost at 50%
confident.
The two case study projects chosen are more complex than the projects in the reference
classes. The resulting required uplifts are therefore somewhat uncertain and likely to be too
low. However the reference classes collected will be very useful, should the method be
applied more frequently in future Swedish transport planning. The material is also large
enough to be subdivided further, at least for road projects. Thus reference classes more
similar to the project in question can be constructed. Moreover, the costs of each
component of completed projects should be collected.
Conclusion and future research 119
6. Conclusion and future research
Based on cost estimations and outcomes of 167 road and rail projects in Sweden during
the period 1997-2009, the average cost overruns are 11% (SD = 24.6%) and 21% (SD =
50.5%) for road and rail projects, respectively. In Sweden, the average cost overrun in
road projects is similar to other countries, while the average cost overrun in rail projects
is lower than in other countries. However, the standard deviation of cost overruns in
Swedish rail projects is very high.
The small Swedish transport projects (< 100 million SEK) have much higher cost
overruns than large projects. Moreover, the average cost overruns are very low in bigger
projects especially in rail projects.
The cost overruns in road and rail projects in Sweden have been constant for the 13-
year period and cost estimates have not improved over time. However this finding is
regardless of the change in use of price indexes by Road and Rail Administrations.
Using the Successive Calculation has advantage in evaluating uncertainty. However, the
method has its limits. Some measures need to be incorporated with the use of the
Successive Calculation. One recommendation is that the Trafikverket (or the
Government) should start a systematic follow-up of the Successive Calculations.
Incentive for the project manager who can efficiently control project cost is also an
alternative.
The variance analysis results show that the transport planners believe investments in
different planning phases are equally certain. However, one would expect the cost
uncertainty to decrease when the project advances towards later stages. Moreover, the
variance is significantly lower than actual outcomes - especially in small-sized projects.
These results indicate that the transport planners still calculate the project costs too
optimistically. Thus, we conclude that applying the Successive Calculation in Swedish
transport projects do not put enough emphasis on uncertainties.
In our opinion, the Successive Calculation method is not likely to significantly reduce the
variance of the cost overruns, even though it may reduce the average cost overruns.
Special policies for the high variance project types such as small-sized projects ought to
be developed.
By the Reference Class Forecasting method, we find that with a willingness to accept a
50% risk for cost overrun of a project, the required uplift will be 5% and 11%, for road
Conclusion and future research 120
and rail projects respectively. If a planner is willing to accept only a 10% risk for cost
overrun, the required uplift will be 24% and 77%, for road and rail projects respectively.
For both case studies, the anticipated project costs by using the RCF method are higher
than the project costs by using the Successive Calculation at the equal cost at 50%
confident.
The two case study projects chosen are more complex than the projects in the reference
classes. The resulting required uplifts are therefore somewhat uncertain and likely to be
too low. However, the reference classes collected will be very useful, should the method
be applied more frequently in future Swedish transport planning. The material is also
large enough to be subdivided further, at least for road projects. Thus reference classes
more similar to the project in question can be constructed.
An interesting way to improve cost calculation might be to develop a cost estimation
method which considers the risks of the costs in each individual component based on
the experiences of a class of similar projects. This is the same concept as the RBE
method used in Australia. It combines advantages from both the Successive Calculation
and the RFC method.
Potential future researches;
o Further analyses in factors that contribute to cost overruns such as whether cost
overruns in Swedish transport projects differ in different areas and cost overrun
effects from several factors by multiple regression.
o Explanations of the cost overruns in Swedish transport projects such as why the
largest overruns are found in small projects. Lessons learnt from the success
projects should be studied.
o In-depth analysis of how and why project costs develop over time.
o Starting building a database of completed project costs with the costs in each
individual component.
o Analysis of the result of the first use of Successive Calculation in terms of
general statistics description and also ways to improve the method. Moreover,
one assumption that should be investigated is whether Successive Calculation
increases the project cost.
o Developing a decision support system that covers all in Cost Benefit Analysis
(CBA) with evaluating uncertainty. Cost estimation is just one component of CBA.
To better transport planning, it is very important to develop a tool for all
processes of CBA.
Appendix A: Data from VTI 121
Appendix A: Data from VTI
Road 102 projects Rail 65 projects
Years Number of projects Years Number of projects
2009 3 2009 3
2008 9 2008 6
2007 7 2007 13
2006 5 2006 3
2005 12 2005 12
2004 9 2004 3
2003 12 2003 2
2002 7 2002 3
2001 9 2001 3
2000 9 2000 1
1999 6 1999 3
1998 9 1998 7
1997 5 1997 6
Average actual cost per
project (Million SEK)
368
Average actual cost per
project (Million SEK)
440
Maximum actual cost
(Million SEK)
4,000 Maximum actual cost
(Million SEK)
2,438
Minimum actual cost
(Million SEK)
50 Minimum actual cost
(Million SEK)
6.6
Total actual cost
(Million SEK)
37,568
Total actual cost
(Million SEK)
28,625
Percentage of projects experiencing escalating project costs1
68% Percentage of projects experiencing escalating project costs1
57%
1 The projects that estimated cost equal actual cost are not included.
Appendix B: Statistical analyses 122
Appendix B: Statistical analyses
Standard deviation
The standard deviation is the square root of the variance. It is a widely used measurement of
variability of diversity used in statistics and probability theory. It shows how much variation or
dispersion there is from the average (mean). A low standard deviation indicates that the data
points tend to be close to the mean, whereas high standard deviation indicates that the data are
spread out over a large range of values.
The independent t-test
This test is used to test for a difference between two independent groups on the means of a
continuous variable.
µ1, µ2= the true mean of database 1 and 2.
, = the average of database 1 and 2.
N1, N2= the size of the sample of database 1 and 2.
s1, s2= the standard deviation of database 1 and 2.
The Null Hypothesis, H0
H0: µ1 - µ2 = 0 (or µ1 = µ2); that is true mean of both data base are the same. The result of the t-
test is to see if we can refute this hypothesis.
The Alternative Hypothesis, Ha
Ha: µ1 > µ2; that is the mean of database 1 is higher than database 2. The test of this Ha is called
a one-tailed test because it considers only one end of the distribution.
The test statistic t is calculated from Equation (2):
The above equation is true only when the sample sizes are equal. When we compare two
groups that contain different numbers of participants, we use the pooled variance estimate t-test
instead which takes account of the difference in sample size by weighting the variance of each
Equation (2)
Equation (1)
Appendix B: Statistical analyses 123
sample. We actually weight by the number of degrees of freedom, which is the sample size
minus 1). Therefore, the pooled variance estimate is Equation (3):
The resulting weighted average variance is then just replaced in the Equation (1):
Then, the p-value is calculated by using the t distribution. P-value is the area under the curve of
t-score. If the result p-value is less than critical value (in this thesis is p ≤ 0.1), the null
hypothesis can be rejected and it is concluded that true mean of both data base are not the
same.
Levene‟s test
Levene‟s test is an inferential statistic used to assess the equality of variances in different
samples. It tests the null hypothesis that the population variances are equal (called homogeneity
of variance). If the result p-value of Levene‟s test is less than critical value (in this thesis is p ≤
0.1), the obtained differences in sample variances are unlikely to have occurred based on
random sampling. Thus, the null hypothesis of equal variances is rejected and it is concluded
that there is a difference between the variances in the population.
Compare means by one-way ANOVA
One-way ANOVA is an analysis of variance in which there is only one independent variable. It is
used to test the hypothesis that several means are equal. This technique is an extension of the
two-sample t-test.
Regression analysis
Regression analysis is the analysis of how the typical value of the dependent variable changes
when any one of the independent variables is varied, while the other independent variables are
held fixed. The coefficient of determination (R2) is the proportion of variability in a data set that is
accounted for by the statistical model. For linear regression, the R2 is the square of the sample
correlation coefficient. The R2 ranges from 0 to 1. Adjusted R2 is a modification of R2 that
adjusts for the number of explanatory terms in a model. The adjusted R2 can be negative, and
will always be less than or equal to R2.
Equation (3)
Equation (4)
Appendix C: Data from latest Transport Investment Plan 124
Appendix C: Data from latest Transport Investment Plan
Road 249 projects
Road1
Phases Total
Bristanalys Förstudie Vägutredning Arbetsplan
Number of projects 42 70 76 61 249
Average forecasted cost per
project (Million SEK) 108 139 201 286 189
Maximum forecasted cost
(Million SEK) 392 773 1,042 3,378 3,378
Minimum forecasted cost
(Million SEK) 20 18 25 25 18
Total forecasted cost
(Million SEK) 4,518 9,755 15,310 17,427 47,010
Rail 46 projects
Rail1
Phases Total
Idéstudie Förstudie Järnvägsutredning Järnvägsplan
Number of projects 6 18 8 14 46
Average forecasted cost per
project (Million SEK) 945 746 7,354 744 1,920
Maximum forecasted cost
(Million SEK) 3,243 5,198 25,578 2,696 25,578
Minimum forecasted cost
(Million SEK) 83 28 430 24 24
Total forecasted cost
(Million SEK) 5,667 13,432 58,829 10,412 88,340
1 All costs are the costs at 50% confident level.
125
References
1. From Nobel Prize to Project Management: Getting Risks Right. Flyvbjerg, Bent. August 2006, Project
Management Journal, Vol. 37, pp. 5-15.
2. Survival of the unfittest: why the worst infrastructure gets built-and what we can do about it.
Flyvbjerg, Bent. 2009, Oxford Review of Economic Policy, Vol. 25, pp. 344-367.
3. Eliasson, Jonas and Lundberg, Mattias. Do cost-benefit analyses influence transport investment
decisions? Experiences from the Swedish transport investment plan 2010-2021. Center for Transport
Studies, Royal Institute of Technology.
4. Curbing Optimism Bias and Strategic Misrepresentation in Planning: Reference Class Forecasting in
Practice. Flyvbjerg, Bent. 1, January 2008, European Planning Studies, Vol. 16.
5. Priemus, Hugo, Flyvbjerg, Bent and Wee, Bert van. Decision-Making on Mega-Projects (Cost-Benefit
Analysis, Planning and Innovation). s.l. : Edward Elgar Publishing Limited, 2008. pp. 120-144.
6. How common and how large are cost overruns in transport infrastructure projects? Flyvbjerg, Bent,
Holm, Mette K. Skamris and Buhl, Søren. 2003, Transport Reviews, Vol. 23: 1, pp. 71-88.
7. Wikipedia. Toei Ōedo Line. [Online] http://en.wikipedia.org/wiki/Toei_%C5%8Cedo_Line.
8. Wikipedia. Big Dig. [Online] http://en.wikipedia.org/wiki/Big_dig.
9. Wikipedia. Edinburgh Trams. [Online] http://en.wikipedia.org/wiki/Edinburgh_Trams.
10. Edinburgh Evening News. Time's up: Today's the day the first tram should have been running in
Edinburgh. [Online] February 25, 2011. http://edinburghnews.scotsman.com/12445/Time39s-up-
Today39s-the-day.6724290.jp.
11. Wu, Qing. Transportation infrastructure project cost overrun risk analysis - risk factor analysis
models. The faculty of graduate studies (Business Administration), The University of British Columbia.
2006. Master thesis.
12. Cost overruns in road construction-what are their sizes and determinants? Odeck, James. 2004,
Transport Policy, Vol. 11, pp. 43-53.
13. A cost performance analysis of transport infrastructure construction in Slovenia. Makovšek, Dejan,
Tominc, Polona and Logožar, Klavdij. s.l. : Springer, January 30, 2011, Transportation. DOI:
10.1007/s11116-011-9319-z.
14. Riksrevisionen. Kostnadskontroll i stora järnvägsinvesteringar? 2011. Audit report. RiR 2011:6.
15. Riksrevisionsverket. Infrastrukturinvesteringar- en kostnadsjämförelse mellan plan och utfall i 15
större projekt inom Vägverket och Banverket. Swedish National Audit Bureau. 1994. RRV 1994: 23.
126
16. Analysis, SIKA-Swedish Institute for Transport and Communications. UPPFÖLJNING AV
INVESTERINGAR. Stockholm : s.n., 2002. SIKA Rapport 2000:11.
17. —. METODER OCH RIKTLINJER FÖR BÄTTRE SAMHÄLLSEKONOMISKT BESLUTSUNDERLAG.
Stockholm : s.n., 2002. SIKA Rapport 2002:19.
18. Riksrevisionen. Kostnadskontroll i stora väginvesteringar? 2010. RiR 2010:25.
19. Regeringens skrivelse. Riksrevisionens granskning av kostnadskontroll i stora järnvägsinvesteringar.
Stockholm : s.n., May 12, 2011. Skr. 2010/11:139.
20. Svenska Dagbladet, Swedish newspaper. SvD. Skenande nota för spårvägsbyggen. [Online] April 6,
2011. http://www.svd.se/nyheter/inrikes/skenande-nota-for-sparvagsbyggen_6067407.svd.
21. Academics and Auditors, Comparing Perspectives on Transportation Project Cost Overruns.
Siemiatycki, Matti. s.l. : Journal of Planning Education and Research, 2009, Vol. 29:, pp. 142-156.
22. Underestimating Costs in Public Works Projects, Error or Lie? Flyvbjerg, Bent, Holm, Mette Skamris
and Buhl, Søren L. 3, s.l. : Journal of the American Planning Association, 2002, Vol. 68, pp. 279-295.
23. Large Transport Infrastructure Projects: Improving Institutions and Decision Making. Flyvbjerg, Bent
and Wee, Bert van. 1, s.l. : European Journal of Transport and Infrastructure Research, March 2010, Vol.
10, pp. 1-4.
24. Pickrell, Don H. Urban Rail Transit Projects: Forecast versus Actual Ridership and Costs. U.S.
Department of Transportation. s.l. : Urban Mass Transportation Administration, 1990.
25. P R Fouracre, R J Allport and J M Thomson. The Performance and Impact of Rail Mass Transit in
Developing Countries. Department of Transport. Crowthorne : Transport and Road Research Laboratory,
1990. Research Report 278. ISSN 0266-5247.
26. Inaccuracy of traffic forecasts and cost estimates on large transport projects. Skamris, Mette K. and
Flyvbjerg, Bent. 1997, Transport Policy, Vol. 4: 3, pp. 141-146.
27. Review of the Florida Department of Transportation's Performance in Controlling Cost Overruns and
Delays When Building Roads and Bridges. s.l. : Office of Program Policy Analysis and Government
Accountability, January 11, 1996. Audit Report.
28. Flyvbjerg, Bent, Bruzelius, Nils and Rothengatter, Werner. Megaprojects and risk: An anatomy of
ambition. United Kingdom : Cambridge University Press, 2003.
29. Predicted and Actual Impacts of New starts Projects; Capital Cost, Operating Cost and Ridership Data.
Federal Transit Administration. s.l. : U.S. Department of Transportation, 2003.
30. An Analysis of Cost Overruns and Time Delays of INDOT Projects. Indiana Department of
Transportation, Federal Highway Administration. Indiana : Purdue University, 2004.
127
31. Dantata, Nasiru A., Touran, Ari and Schneck, Donald C. TRENDS IN U.S. RAIL TRANSIT PROJECT COST
OVERRUN. Transportation Research Board. s.l. : Annual Meeting CD-ROM, 2006.
32. Estimating and monitoring the costs of building roads in England. Department for Transport. s.l. :
National Audit Office, 2007. Audit report.
33. Cost Overruns and Demand Shortfalls in Urban Rail and Other Infrastructure. Flyvbjerg, Bent. 1, s.l. :
Taylor&Francis Group, February 2007, Transportation Planning and Technology, Vol. 30, pp. 9-30.
34. Forecasting Inaccuracies in Transportation Projects in Selected South East Asian Countries. Nicanor,
R. Roxas Jr. and Saksith, Chalermpong. 2008. 16th Annual Conference of the Transportation Science
Society of the Philippines.
35. Cost overrun and Cause in Korean Social Overhead Capital Projects: Roads, Rails, Airports, and Ports.
Lee, Jin-Kyung. 2, June 2008, Journal of Urban Planning and Development, Vol. 132, pp. 59-62.
36. The Predicted and Actual Impacts on New Starts Projects - 2007 (Capital Cost and Ridership). Federal
Transit Administration. s.l. : US Department of Transportation, 2008.
37. Singh, Ram. Delays and Cost Overruns in Infrastructure Projects: An Enquiry into Extents, Causes and
Remedies. Department of Economics, Delhi School of Economics, Centre for Development Economics.
2009. Working Paper No. 181.
38. Assessment of High Speed Rail projects: selection of European cases and recommendations from EVA-
TREN research. Chevroulet, Tristan and Reynaud, Christian. Lisbon, Portugal : s.n., 2010. 12th World
Conference on Transport Research (WCTR).
39. Ex-Post evaluation of transport infrastructure projects in France: Old and New concerns about
assessment quality. David, Meunier. Lisbon, Portugal : s.n., 2010. 12th World Conference on Transport
Research (WCTR).
40. What Causes Cost Overrun in Transport Infrastructure Projects? Flyvbjerg, Bent, Holm, Mette K.
Skamris and Buhl, Søren L. January 3-18, 2004, Transport Reviews, Vol. 24.
41. Cost Overruns in Large-scale Transportation Infrastructure Projects: Explanations and Their
Theoretical Embeddedness. Cantarelli, Chantal C., et al. 2010, European Journal of Transport
Infrastructure Research (EJTIR), Vol. 10(1), pp. 5-18.
42. Field, Andy. Discovering statistics using SPSS. Third Edition. s.l. : SAGE Publications Ltd, 2009.
43. How to avoid overruns and delays successfully-nine basic rules an associated operable procedure.
Lichtenberg, Steen. s.l. : International Cost Engineering Council Internet Journal, October 2005.
44. Lichtenberg, Steen. Proactive Management of Uncertainty using the Successive Principle. Denmark :
Polyteknisk, 2000. 87-502-0822-5.
128
45. Vägverket, Eriksson, Lars and Trollius, Magnus. Handledning Successiv kalkylering inkl Lathund.
Version 1. 2008-03-18.
46. Moore, David S. Statistics: Concepts and Controversies. Second Edition. s.l. : W.H. Freeman and
Company, 1985.
47. Flyvbjerg, Bent and COWI Consult. Procedures for Dealing with Optimism Bias in Transport Planning.
The British Department for Transport, UK. 2004. Guidance Document.
48. Reference Scenario Forecasting: A new approach to transport project assessment. Salling, Kim Bang,
Leleur, Steen and Skougaard, Britt Zoëga. Lisbon, Portugal : s.n., 2010. 12th World Conference on
Transport Research (WCTR).
49. HEATCO: Developing Harmonised European Approaches for Transport Costing and Project
Assessment. [Online] 2006. http://heatco.ier.uni-stuttgart.de/hstart.html.
50. Flyvbjerg, Bent. Truth and Lies about Megaprojects. s.l. : Delft University of Technology, September
26, 2007. Inaugural speech.
51. The accuracy of hybrid estimating approaches: A case study of an Australian state road & traffic
authority. Liu, Li, Wehbe, George and Jonathan, Sisovic. s.l. : Taylor&Francis, 2010, The Engineering
Economist, Vol. 55, pp. 225-245.
52. Incorporating Risk of Cost Overruns into Transportation Capital Projects Decision-Making.
Berechman, Joseph and Chen, Li. 1, January 2011, Journal of Transport Economics and Policy, Vol. 45,
pp. 83-104.
53. Salling, Kim Bang. Assessment of Transport projects - risk analysis and decision support. Department
of Transport, Technical University of Denmark. 2008. PhD Thesis.
54. Trafikverket. The Stockholm bypass. Trafikverket. [Online] June 2011.
http://www.trafikverket.se/Om-Trafikverket/Andra-sprak/English-Engelska/Railway-and-Road/Road-
Construction-Projects/E4-the-Stockholm-bypass/.
TSC-MT 11-018
www.kth.se
Top Related