Presentation to the Parliamentary Portfolio Committee on Energy
SANEDI Annual Report 2012/13
MR KM NASSIEPCEO
17 OCTOBER 2013
CONTENTS
Production / Costs
Reducing the Carbon Footprint
Corporate Information
SANEDI’s Assets – its People
Management of Income , expenditure , transfers , cash and assets
Inputs to different sections of the Financial Statements
Report on Financial Misconduct
Highlights
Achievements as per the APP
Audit and Risk Committee
Audit Findings and Action Plan
PRODUCTION/COSTS
Production • 100 hard copies• 400 copied to USB
Costs of Production• Hard copy – R425.00 each • USB – R95.00 each
REDUCING THE CARBON FOOTPRINT
Environmental responsibility
Collective responsibility
Recycled paper
Benefits of using recycled paper
Other initiatives too to reduce company’s carbon footprint
Actions of today will save the environment tomorrow
Using e- annual reports reduces company overheads – savings could be utilised elsewhere in the organisation
CORPORATE INFO
Vision
To serve as a catalyst for sustainable energy innovation, transformation and technology diffusion in support of South Africa’s sustainable development that benefits our nation.
Mission
Advance innovation of clean energy solutions and rational energy use that effectively supports SA’s national energy objectives and the transition towards a sustainable , low carbon energy future
Values
Innovation, Accountability, Transparency, Integrity, Professionalism, National Interest , Batho Pele
SANEDI’s ASSETS – IT’s PEOPLE
Category WM IM CM BM WF IF CF BF
Executive Management 0 0 1 0 0 0 0 0
Senior Management 4 1 0 1 0 0 0 1
Acting CFO 0 0 0 0 0 0 1 0
Manager : Corporate Support 0 0 0 0 0 1 0 0
IT Manager 0 1 0 0 0 0 0 0
Accountants 0 0 0 1 0 0 0 1
System Administrator 0 0 0 0 0 0 0 1
Centre Managers 1 0 0 0 2 0 0 0
Project Managers 0 0 0 2 0 0 0 0
Public Awareness Officer 0 0 0 2 0 0 0 2
Project Officers 0 0 0 2 0 0 0 1
Admin Officer 0 0 0 0 0 1 0 0
Research Assistants 0 0 0 0 1 0 0 1
Personal Assistant 0 0 0 0 0 0 1 1
SANEDI’s ASSETS – IT’s PEOPLE ..cont…
Category WM IM CM BM WF IF CF BF
Receptionist 0 0 0 0 0 0 0 1
Interns 0 0 0 2 0 0 0 0
Consultants 5 0 0 1 0 0 0 0
Refreshment
Officers
0 0 0 0 0 0 0 2
TOTAL 10 1 1 11 4 2 2 11
SANEDI’s ASSETS – IT’s PEOPLE ....continued
Permanent staff = 8
Contract staff = 14
HDI representation = 75%
Female representation = 53%
Total staff compliment = 42
Management of income, expenditure, transfers, cash and assets
Income/Accumulated surplus
Expenditure
DOE Transfer 50,110 33,552
IT Infrastructure 6,000 4,430
EU AIM project (smart grids
71,800 -
SDC 4,258 1,852
SACCCS 22,426 6,282
WFE 34,294 6,477
Green Transport 1,712 2,380
• Application in terms of section 53(3) was made to National Treasury for R16,558 surplus for the year.
• SANEDI is currently busy with implementation of its own ERP system; expected roll-out of the new system is November 2013.
• Processes used during the implementation is based on best practice; including PFMA, Treasury Regulations for Schedule 3A and all GRAP reporting requirements.
Inputs to different sections of financial statements
Commitments:
SANEDI has entered into various contracts with service providers
for the achievement of its key deliverables
Working for Energy programme (R19.6 m)
Centre for Energy Systems Research (R2.2 m)
Hub for Energy Efficiency & Demand Side Management (R4.2 m)
Clean Energy programme (R1.6 m).
Inputs to different sections of financial statements…cont…
Irregular expenditure:
SANEDI incurred R12.6 m irregular expenditure as a result of Procurement processes not being followed which are detailed below:
– R3.3 m – no notification for deviations from procurement process above R1m. The procurement decision enacted while SANEDI was still a Schedule 2 public entity within the CEF Group;
– R0.3 m – three responsive quotes were not obtained in all instances;
– R7.6 m – procurement of goods and services above R30,000.00 from 8 December 2012 were not evaluated as per PPPFA legislation; and
– R1.4 m – no approval of application in terms of Treasury Regulation 16A 6.4 to deviate from the standard procurement process.
Report on financial misconduct
There was no financial misconduct
Highlights : SACCCS
Core Parties – SANEDI – SASOL– Norwegian Embassy– Eskom – DoE
Participants – Anglo American – Xstrata Coal – Total Coal – PetroSA– Exarro – Alstom
Highlights : Carbon capture and storage globally and in South Africa
Large-scale carbon capture and storage (CCS) plants have been operating globally since 1996
South African has been looking at CCS since 2002
CCS may enable South Africa to continue utilising local, abundant coal reserves while reducing CO2 emissions
In 2009, the South African Centre for CCS was established
In 2010, the Atlas on Geological Storage of CO2 in South Africa was released
The next step in the South African CCS Roadmap (endorsed by cabinet in 2013) is the Pilot CO2 Storage Project
Highlights : The Pilot CO2 Storage Project
The Pilot CO2 Storage Project (PCSP) aims to store 10 – 50,000tCO2 in South Africa
Work is underway by SACCCS to identify a site for the PCSP with KZN and EC showing potential
SACCCS is currently analysing existing geological data while planning further data acquisition
The Department of Energy has committed R197 million to the PCSP with the World Bank allocating another USD25 million
Legal and regulatory clarity as well as positive public engagement are crucial for the success of the PCSP
Highlights : French-funded Technical Advisory Facility, (TAF)
16
A soft-credit facility to finance sustainable energy initiatives in South Africa, with the purpose of alleviating the current energy situation and addressing future supply concerns. The AFD credit line will finance small and medium-sized investments in the field of energy efficiency and renewable energy made by private South African companies in the industrial and commercial sectors, through 3 participating banks, (namely ABSA Bank Ltd, IDC Ltd and Nedbank Ltd).
Projects qualify for Energy Efficiency funding to retrofit existing installations, including on-site cogeneration, rehabilitation of boilers, regenerative burners, commercial energy efficient building construction and design, such as energy efficient heating and ventilation systems, construction materials, as well as combined heat and power generation.
Renewable Energy investments, including power generation for own consumption or for sale to the national grid, also qualify.
Highlights : Technical Advisory Facility, (TAF) ..cont….
17
The implementation of this form of financing requires a Technical Assistance Facility (TAF), to support the emergence of targeted investments and the evaluation of their technical eligibility for the credit line.
SANEDISANEDI will provide the required technical assistance in support of the sustainable energy credit line in South Africa and together with a consortium of local and international expertise, we will offer the service to the broader public, including educational, technical and communications support to the South African public.
AFD (Agence Française de Developement), is a French public bi-lateral development finance institution, acting on behalf of the French government in various countries throughout the world. Key strategic objectives of the AFD include poverty reduction, economic growth and combating climate change.
Residential Sector - ‘Limited Offer’ Tax Incentives
18
SANEDISANEDI believes that in-line with international trends, ‘limited offer/ duration’ tax incentives should be offered on specified energy efficient energy efficient household appliances, including SWH’s.
This can be aligned to the imminent compulsory implementation of the Energy Efficient Appliance Labelling Programme by the DoE and dti, in South Africa.
SANEDISANEDI will submit a proposal to NationalTreasury, via the DoE, in the 1st quarter of the2014/15 business cycle, to consider such anoption, ie. to first assess the implementation of the 12-L TaxRebate system, as well as progress with the finalisation of theNational Appliance Labelling roll-out.
Highlights : Corporate Social Responsibility
Children of Fire
Under privileged children who have been burnt
Staff contributed
Company contributed
ACHIEVEMENTS AS PER APP
Objectives Indicator Target Performance
Result Reason for non –
achievement of targets
Administration and Corporate Governance
Executive support Responses and presentations to DoE and the Minister of Energy as and when required
Achieved
EXCO minutes completed and distributed on a monthly basis
Achieved
Support Services (services dependent on CEF)
Quarterly evaluation of services as documented in the SLA
Achieved
Corporate Governance Compliance to relevant legislation Achieved
Effective and efficient operations /administration
Achieved
Corporate and Programme Marketing and communication services
Corporate Not Achieved The corporate communication plan is complete but has not been approved and implemented. The plan will be approved in the first quarter in 2014.
Monitoring and evaluation of corporate and programme marketing and communication plan
Not Achieved As above
Financial Management and management accounting
SANEDI budget coordinated and aligned to strategic plan and annual performance plan by 30 November 2012
Achieved
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target
Performance Result Reason for non – achievement of
targets Spending monitored and financial performance reported on the monthly basis at the Budget Sub Committee
Achieved
Debt and revenue due to SANEDI managed and accurately and timeously recorded and the cash book managed on a monthly basis
Achieved
SANEDI assets managed on a monthly basis
Achieved
SANEDI expenditure and creditors managed on a monthly basis
Achieved
Programme Management Accounting reported monthly
Achieved
IT infrastructure and systems ICT strategic plan developed, approved and implemented
Achieved
Mechanisms to enhance energy data collection and storage provided
Achieved
Project Management system implemented SLA with CEF for ICT services approved
Achieved
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance
Result Reason for non – achievement of
targets IT Disaster Recovery plan developed, approved and implemented
Not achieved The SANEDI IT Disaster Recovery Plan has not been developed due to the delay of the Enterprises Resources Management system. SANEDI has adopted the CEF ICT Disaster Recovery Plan until the SANEDI ICT plan is developed
Enterprises resources management system implemented
Not Achieved The Enterprises Resources management system has not been implemented due to delays in the procurement process and funding received
Applied Research : Advanced Fossil Fuels
Clean Coal technologies (CCT) to facilitate the optimisation and efficient use of coal and decrease greenhouse gas emissions
Complete 4 existing CCT projects by 31 March 2013
Achieved
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance
Result Reason for non – achievement
of targets
Technical support to the Coal Road Map
Achieved
Financial Management of the South African Coal Road Map (SACRM)
Achieved
Oil and Gas R&D Frameworks – to facilitate the optimisation and efficient use of oil and gas and decrease greenhouse gas emissions
Framework for oil and gas R&D frameworks and submission to DoE by 31 March 2013
Partially Achieved The frameworks was completed by 31 March 2013 but the reports to the DoE were only submitted in the first quarter of 2013/14 financial year
Carbon capture and storage (CCS) to determine the potential and appropriateness of technologies for the geological storage and carbon dioxide in SA
Sourcing of funding Achieved
Completion of current projects
Not Achieved The draft final report was received but was returned to the consultant to revise after review by Technical Committee
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target
Performance Result Reason for non –
achievement of targets
Preparation of further exploration of the Zululand Basin
Achieved
International cooperation Achieved
Applied Research : Smart grids
SA smart grid vision which will set the direction to enhance supply reliability and the effective operations of the electricity distribution industry (EDI)
Minutes of stakeholder workshops
Achieved
Report and presentation to SANEDI Board of Directors
Achieved
Submit a briefing document to the DoE by 31 March 2013
Achieved
Current state assessment to amongst others define the EDI constraints from a holistic system reliability and real time data availability perspective
Terms of reference document s
Achieved
ACHIEVEMENTS AS PER APP….cont….
Objective Indicator Target
Performance Result
Reason for non – achievement
of targets
Resource requirement identified Achieved
Smart grid scoping document Achieved
Technology, governance and service gap analysis and defined solutions /actions to realise the smart grid vision
Minutes of work group Achieved
Technology, regulatory , institutional policy , skills , ICT gaps and propose solutions identified
Achieved
Smart grid business case Motivation for smart grid with clearly defined project proposals including a funding plan
Achieved
Smart grid Implementation plan
Pilot project running , applied research and results as defined in respect of the pilot project demonstrated
Achieved
Optimised solution portfolio to underpin the business case
Documented results and defined smart grid benefits
Achieved
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance
Result Reason for non – achievement of
targets Data enhancement , energy management improvement, reliability improvement and contribution to effective energy planning documented
Achieved
Consolidated smart grid industry guideline
Business case and guidelines and National strategy for smart grids developed by 31 March 2013
Achieved
Applied Research : Renewable Technologies /Clean Energy Solutions
Co ordinate RE (renewable energy)research in South Africa , facilitate RE research ,collaboration, participation, standards development and technology evaluation, contribute to RE skills development , support RE business development and RE awareness creation to stakeholders and students
RECORD RE research co ordination mandate is confirmed, a co ordinated renewable energy research effort in SA with stakeholder buy in and support , a number of research projects are funded by RECORD, value offering to serve RE research paying clients , a platform for international inter-institutional research is expanded and RECORD participates effectively in standard development and technology evaluation
Achieved
Projects, pilots and demonstrations – Wind Atlas South Africa (WASA) , Waste to Energy plant, Algal biofuels and solar road map
Continue as per work plan and seek funding extension from RDE for WASA
Achieved
Pre- feasibility investigations Achieved
ACHIEVEMENTS AS PER APP….cont….
Objective Indicator Target Performance
Result Reason for non –
achievement of targets
Set – ups Achieved
Support to Solar park Meteorological (MET) station
Set up solar measuring station
Not Achieved Project delayed due to land matters that need to be addressed at the solar park.
Representation of South Africa in an international forum whereby technical knowledge is gained and skills are transferred . Globalisation of expertise and leveraging of research funding
Maintain IEA and EU FP7 agreements, build up more collaborations and attempt to increase funding
Achieved
Applied Research: Green Transport Programme
A national Green Transport strategic vision and technology development plan including a status quo and gap analysis for the alternate fuels and propulsion systems in RSA developed
Develop a national Green Transport strategic vision and technology development plan including a status quo and gap analysis for alternate fuels and propulsion systems in SA by 31 March 2013
Not Achieved Delays in funding and scope definition with the Department of Transport . Until funding is secured the sustainability of the project is not guaranteed and it can result in wasteful expenditure to commence the programme until a funding stream has been secured
ACHIEVEMENTS AS PER APP….cont… Objective Indicator Target
Performance Result
Reason for non – achievement of targets
Develop a technology development incubation centre to offer “Soft Start” facilities to companies and technology partners who are entering the Green Transport sector
Develop the institutional framework and participation Charter for the incubation centre by 31 March 2013
Not Achieved The terms of reference and request for proposals are being prepared
Initiate the call for proposals and expression of interests for prospective partner organisations n or benefactors
Not Achieved As above
Operate the Centre Not Achieved Delays in funding and scope definition with the Department of Transport. Until funding is secured the sustainability of the project is not guaranteed and it can be wasteful expenditure to commence the programme until a funding stream has been secured
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance Result Reason for non
– achievement of targets
Develop various demonstration projects in the various alternate fuels and propulsion systems to showcase these technologies and create an enabling environment to bring these alternatives to the market
Develop various demonstration projects in the various alternate fuels and propulsion systems to showcase these technologies . Standards and best practices developed
Not Achieved Funding constraints
Modelling and regulation frameworks developed
Not Achieved Funding constraints
Situational Analysis completed
Not Achieved Funding constraints
Demonstration projects commissioned
Not Achieved Funding constraints
Lessons learnt and best practices communicated through Public Advocacy Programme
Not Achieved Funding constraints
Participate in international knowledge sharing for a to bring best of breed to full commercialisation
Participate in international collaboration partnerships
Achieved
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance Result Reason for non
– achievement of targets
Establish knowledge sharing clusters
Achieved
Participated in both local and international events and activities
Achieved
Promote technology and knowledge sharing through the SANEDI website and communicated through the Public Advocacy Programme
Achieved
Develop a substantive public advocacy programme to create market acceptability for alternate fuels and propulsion systems to allow successful market penetration and sustainability
Viral portal platforms developed
Achieved
Print media platforms developed
Achieved
ACHIEVEMENTS AS PER APP….cont… Objective Indicator Target
Performance Result
Reason for non – achievement of targets
Events and exhibitions staged
Achieved
Feedback loops created Achieved
Applied Research : Data Knowledge management
Development of the integrated data repository – functional , accurate , integrated and user- friendly database
Coordinate and facilitate development of database by 31 March 2013 and oversee project
Achieved
Review and develop a strategic plan and develop a funding plan by 31 March 2013
Review strategic direction , develop a strategic plan and develop a funding plan by 31 March 2013
Not Achieved A proposal has been sent to the DST and DEA for funding. Discussions being held
Applied Research : Working for Energy
Renewable Energy : Invite tenders, process, assess and approve project proposals
Approve project proposals to develop 5 megawatt (MW) by 31 March 2013
Achieved
Renewable Energy : Kwa- Mashu Biomass to Energy project
Negotiated Management and operational agreement for the Kwa- Mashu biomass to energy plant
Not Achieved The governance process of the project (PPP) is currently in the hands of Ethekwini Metro . Once this process is complete , SANEDI will contribute towards the project
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance
Result Reason for non –
achievement of targets
Bela Bela Biogas (Phase 2)
Procurement and implementation
Not Achieved Project is delayed due to non – responsiveness of the service provider
Reticulation of the biogas to the neighbouring community
Not Achieved Project is delayed due to non – responsiveness of the service provider
Phillipi Biogas Project Implementation of the revised interventions
Not Achieved Delayed due to the prioritisation to streamline to streamline learning from the Bio energy cluster project
University of Fort Hare – Renewable Energy Research Facility
Implementation of revised interventions
Achieved
Rehabilitation of the bio- digester for research and development under faculty of science
Achieved
ACHIEVEMENTS AS PER APP….cont….
Objective Indicator Target Performance Result Reason for non –
achievement of targets
Melani Village Biogas Project
Implementation of the revised interventions
Not Achieved The contract has been concluded between SANEDI and Fort Cox College. The College is finalising BEE accreditation
Fort Cox Bio energy Project Phase 2
Implementation of the revised interventions , addition of 1 digester , connection of the gas to the kitchen and other facilities for utilisation
Not Achieved The contract has been concluded between SANEDI and Fort Cox College. The College is finalising the BEE accreditation
Mpfuneko Biomass Project Implementation and roll out of community bio- digesters
Not Achieved A contract has been concluded between SANEDI and the service provider – implementation will commence in 2014
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance
Result Reason for non – achievement of
targets
Lucingweni Biomass Project
Implementation and rehabilitation of control battery room to become a community early childhood centre retrofitted with energy efficiency and renewable energy technologies
Not Achieved Stakeholder consultation completed and the agreement reached for the establishment of the ECD centre. Community negotiations are on –going with the Nyandeni District Municipality for the joint implementation of the Green ECD Centre
Walter Sisulu University RECORD Establishment
Implementation and re- establishment of the renewable energy facility for rural energy research under the facility of science
Not Achieved Delayed due to the slow response form the University contact persons . A decision has been taken to establish a parallel facility at the Nelson Mandela University
Coal Fuel Tablet (CFT) Implementation and feasibility study using coal dust to produce alternative energy
Not Achieved Project delayed due to non – responsiveness of the service providers .
Working for Energy Outreach programme
Implementation of the outreach programme for the WFE programme
Not Achieved Finalisation of the proposed roll out plan with the Department is still work in progress
ACHIEVEMENTS AS PER APP….cont…
Objective Indicator Target Performance Result Reason for non –
achievement of targets
Tshireleco School Renewable Energy Demonstration Centre project
Implementation and establishment of a demonstration centre for renewable energy and energy efficiency under the department of science within the school
Not Achieved The MoA between SANEDI and Tshireleco High School has been finalised – implementation will commence in the first quarter of 2014
Energy Management : Invite tenders , process, assess, approve project proposals
Approved project proposals to deliver 500 kilowatt energy management projects
Partially Achieved The MoA negotiations with the Gauteng department of Infrastructure Development (DID) is in the process for the greening of at least 4 schools. Technology supply tenders will be issued between SANEDI and DID
ACHIEVEMENTS AS PER APP….cont….
Objective Indicator Target Performance Result Reason for non
– achievement of targets
Applied Research : Energy Efficiency
Integrated public advocacy plan, draft consultation paper in place, coordinate and facilitate implementation and overseeing implementation
Integrated plan developed and submitted to DoE
Achieved
Measurement and verification – integrated on line system developed
Integrated on line system fully operational
Achieved
Demand side energy diversification ; Multi Stakeholder Advisory Group
Advisory Group in place and fully functional
Achieved
Ad hoc project development and technical support : Number of projects proposed
2 projects developed and proposed to the DoE
Achieved
International collaboration : Contributions to international collaboration efforts
Membership and participation in CEM-GSEP activities and IEA 4E Implementing Agreement on behalf of DoE
Achieved
Audit and Risk Committee
The Audit and Risk Committee currently consists of two independent non-executive members.
The Chairperson is a CA(SA) and a CIA (Certified ) Internal Auditor) – Mr Viren Magan
Other member is a registered CA(SA) – Ms Mizeria Nyathi
Regarding independence - Members sign declaration of interests. They are also not involved in daily activities of SANEDI nor do they have any business with SANEDI
Audit and Risk Committee ..cont…
The audit committee has noted that the system of internal controls that is in place needs to be reviewed and improved to ensure that it is appropriate in all material respects to:
‑ reduce risks to an acceptable level;
‑ meet the business objectives;
‑ ensure all assets are adequately safeguarded; and ‑ ensure that transactions undertaken are recorded in the accounting records.
Audit and Risk Committee ...cont…
Internal and external audit provides the audit committee with reasonable assurance that the majority of internal controls are appropriate and effective. This is achieved by means of the risk management process, as well as the identification of corrective actions and suggested enhancements to the controls and processes. From the various reports of the internal and external auditors, the Audit Committee noted that matters which indicated any deficiencies in the system of internal control have been brought under management's attention and corrective measures are being implemented.
Audit and Risk Committee …..cont…
The company implemented a risk management strategy which includes the fraud prevention plan. A formal risk assessment was undertaken for the year ended 31 March 2013 with quarterly reviews, updates and reports. Consequently, internal audit used this data to prepare the 3 year rolling strategic plan and the annual operating audit plan. The risk committee monitored the significant risks faced by the company through reviewing risk reporting and participation in the risk assessment workshop. The Committee is satisfied that significant risks were managed to an acceptable level.
Audit and Risk Committee …..cont…
The Committee acknowledge that the company continues to strive towards complying sound principles of corporate governance. As per our discussions with management, management confirms that the content and quality of monthly and quarterly reports prepared and issued by the Chief Executive Officer during the year under review were properly formulated and have complied with the PFMA in this regard.
Audit and Risk Committee ….cont…
The Committee have: • Reviewed and discussed the audited annual financial statements to
be included in the annual report, with the Auditor‑General of South Africa and the Accounting Officer;
• Reviewed the entity's compliance with legal and regulatory provisions;
• Reviewed the Auditor‑General of South Africa's management report and management's responses thereto;
• Reviewed changes in accounting policies and practices; and • Reviewed significant adjustments resulting from the audit.
The Committee concurs and accepts the Auditor‑General of South Africa's (AGSA) report on the annual financial statements, and is of the opinion that the audited financial statements be accepted and read together with the report of the AGSA.
Audit and Risk Committee…..cont…
The following major findings were discussed at the Audit and Risk Committee meeting held on 30 July 2013:
Irregular expenditure on Procurement; this resulted in disclosure in the annual financial statements of R12.6 million.
Fruitless and wasteful expenditure of R0.02 million. A penalty of 5%, amounting to R2,090.18, was raised for late payment of a previous supplier invoices.
Restating of prior year figures due to error identified.
Audit and Risk Committee ..cont…
The Audit and Risk Committee concluded the following :
Proper Procurement processes need to be put in place. The procurement policy needs to be aligned to prevent; detect and mitigate any fruitless and wasteful; unauthorised and irregular expenditure.
The revised procurement policy and procedure should also include all recommendations made by AG.
All staff to undergo training on Procurement process for Schedule 3A public entity.
The Board will need to condone the irregular expenditure incurred in 2012/13.
AUDIT FINDINGS AND ACTION PLAN
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Material adjustments made to the financial statements after submission
Financials In its establishing business case, SANEDI proposed that a transitional plan be implemented that would see a gradual shift away from the dependence on CEF (SOC) Ltd. An 18 month period was originally envisaged .
The SANEDI policies and processes will be drafted to specifically include the appropriate processes to be followed during the preparation of annual financial statements. Controls should be put in place to ensure proper financial management and reporting lines to be communicated to all staff
The following policies and /or procedures have been drafted and will be submitted to EXCO for approval•Journal Management •Revenue Management •Asset Management •Petty Cash •Fruitless and wasteful expenditure
A copy of all contracts and agreements must be submitted to Finance to ensure that the accounting treatment is in terms of the GRAP statements
Request copies of all contracts from CEF Legal All draft contracts will be submitted to the CFO office before sending to the CEO for signature
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Incorrect accounting for the Centre for Carbon Capture and Storage : the assets , liabilities and income are to be recognised separately with SANEDI showing liability for any funds invested on behalf of CCS
Financials SANEDI established SACCCS as an instrument to house and administer funds and activities on behalf of donors and private sector partners. At no stage , was the Centre intended to be an autonomous structure outside of SANEDI. The SANEDI Board on the strength of a previous recommendation fro m the AG insisted that the annual workplan be approved by the SANEDI Board as this is the accounting authority responsible for the budget since neither SACCCS nor its Board of Governance are a legal entity.
Awaiting the Governance review for SACCCS.
All procurement over R1m is sent to the SANEDI Board for approval. Some of the staff costs are paid directly from the SANEDI base allocation from MTEF.
All procurement above R1m must be tabled at the SANEDI Board for approval. National Treasury and AG should be notified
Unauthorised accumulation of surpluses
Financials The surpluses as well as the contingent liability will be disclosed in the financial statements and a request will be done to NT to retain the surpluses
Commitments which relate to the following financial year must be disclosed as Contingent Liability.Application for surplus funds or accumulated deficits should be sent to NT by 31 May (together with unaudited financial statements )
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
SANEDI specific policies and procedures
SANEDI entity SANEDI currently still has a SLA in place with CEF (SOC) Ltd for support services , therefore the CEF systems , policies and procedures are still being used
The current SLA with CEF needs to be revised. The following services should be housed within SANEDI – Procurement , Finance , Logistics and Facilities, Secretariat and IT
SANEDI is currently in the process of implementing its own ERP system and the policies and procedures will be drafted during this process to be in line with PFMA requirements for Schedule 3A public entity and industry best practice
The ERP implementation is scheduled for 25 November 2013. As the system is tested, the policies and procedures will be amended.
Assets not in the Assets Register
Assets A reasonableness calculation was submitted to the Auditors taking the opening balances and any additions and disposals into account. The balance was then compared to information in the asset register. The difference between the reasonableness calculation and the asset register was not material.
All assets are to be delivered to Logistics for receipting and then to Finance to barcode before issuing to user.
Assets not bar coded Assets There is a control deficiency identified by management due to the fact that SANEDI was operating using a decentralised process. SANEDI has now implemented controls to ensure that one line function is responsible for receiving and bar coding assets
All assets are to be delivered to Logistics for receipting and then to Finance to barcode before issuing to user.
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Depreciation of assets bot done according to policy
Assets The tangible asset policy used by SANEDI will be amended to reflect the correct depreciation rates for all assets. This will be submitted to the Board for approval
SANEDI to relook at the Asset Management policy and ensure depreciation rates are amended accordingly. This will be submitted to Board for approval
SANEDI is currently busy with the implementation of a new ERP system. Busy with the exercise to determine the correct depreciation period for all assets as well as the residual life for assets. . When the exercise is completed , all amendments to assets will be revised and correcting entries processed before implementation of the new system
Differences between the fixed assets register and the financial statements
Assets The office equipment costs were incorrectly mapped to the office furniture., hence the difference. The computer equipment difference is merely a rounding difference as caseware rounds off to the nearest rand . The IT infrastructure costs are for IT software which were purchased for the new ERP system. The disclosure in the AFS was corrected .
Segregation of duties- Accountant should prepare the financial statements , Finance Manager should review and the CFO must perform the final review
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Appropriate procurement processes not followed : City Square
Procurement In its establishing business case , SANEDI proposed that a transitional plan be implemented that would see a gradual shift away from dependence on CEF (SOC) Ltd . An 18 month period was initially envisaged . Seeing that the budget required to ensure independence from CEF was not secured through the MTEF , a more gradual move away from CEF was required . The business case that refers to the independence from CEF and the related transitional plan was approved by National Treasury.
All SANEDI staff are to undergo training on Supply Chain Management. SANEDI to establish relevant committees as recommended in the PPPFA, namely BEC and BSC. Active interactions with the AG and NT regarding specific procurement matters within SANEDI.
Due to the abovementioned , SANEDI had to acquire premises in close proximity to CEF as we shared telephony, network and other support services. An underground cable serves to connect the two buildings in terms of the network and telephony network. SANEDI is highly dependent on CEF for financial management systems and HR systems as well as Legal, Secretariat, and Internal Audit services.
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Incorrect scoring of bids Procurement The SANEDI policy does indicate a scoring process and the requirements of the 80/20 principle for bids below R1m and the 90/10 principle for bids over R1m
The revised policy aligned to PPPFA submitted to EXCO and then Board for approval
A scoring criteria practice note is also operationalised . As the bid was not based on commercial scoring only, the base score was not material to the outcome
Incorrect thresholds used when evaluating bids
Procurement In terms of Practice note 8, entities may use lower thresholds than that stipulated in the Treasury Regulations. SANEDI therefore took a prudent approach and used lower thresholds as SANEDI is still in its infancy stage as a schedule 3A entity. The Procurement policy was approved by the SANEDI Board.
Limit will remain R200 000.00 until the ERP system is fully operational and procurement irregularities identified, mitigated and prevented
Supplier SBD4’s do not contain correct information- bidders do not supply correct bidding documentation
Procurement The SBD 4 document was attached to Bid documents as the CEF standard document. When tenderers were tested for responsiveness this conflict was not raised. A SANEDI staff member acted inappropriately by declaring her knowledge of this company. This SANEDI staff member who has knowledge of this company played no part or influence in the award.
Ensure that the SBD 1-9 documents are aligned to the prescripts of National Treasury Regulations . SBD forms are used as per National Treasury’s guidelines
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Errors in request for proposal documentation – Software tender
Procurement The RFP was issued by CEF Procurement office without being submitted to the Procurement Committee for review. The use of a base document and a cut and paste probably led to the errors in the document which was further exacerbated by the lack of proof reading
All Bid documents to be tabled before the Procurement Committee for vetting prior to release
Functionality not used to evaluate Microsoft tender
Procurement The Bid Evaluation Committee as chaired by CEF Procurement erred in this regard as functionality was determined on limited criteria which was not consistent with the RFP. The remedial steps as reflected hereunder will prevent recurrence.
Complete bid documents to be tabled at the Procurement Committee before authority to release is granted.. A standing Bid Evaluation Committee is constituted to ensure consistence. Members appointed July 2013.
Unfair disqualification of bidders
Procurement The Bid Evaluation Committee as chaired by CEF Procurement erred in this regard as functionality was determined on limited criteria., which was not consistent with the RFP. It is not fair to expect their Procurement Manager to lead the process with due diligence and procedural correctness
Complete bid documents to be tabled at the Procurement Committee. Before authority to release is granted. A standing bid evaluation is constituted to ensure consistence.
Information Technology Service Continuity – Management have nit tested the IT disaster recovery plan
SANEDI entity Shortcomings of the current Disaster Recovery Plan were identified and are being addressed . The new plan will be tested by the end of Q3
Need to draft a disaster recovery plan and business continuity for tabling at EXCO once the ERP system is implemented – Dec 2013 or Jan 2014
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Procurement Control Deficiencies
Procurement The CEF Procurement staff should be competent and current on all matters, Treasury Regulations , practice notes and guidelines irrespective of the different classifications of a schedule 2 or 3 public entity and be able to handle the matters pertaining to the procurement requirements for SANEDI in accordance with the SLA.
CEF no longer involved in SANEDI Procurement. All SANEDI staff to undergo training on Supply Chain Management. SANEDI to establish relevant committees as recommended in PPPFA, namely the BEC and BSC. Active interactions with the AG and NT regarding specific procurement matters with SANEDI
Bids not evaluated in required time period
Procurement Bids will be evaluated within 14 days as per Treasury guidelines
Bids will be evaluated within 14 days as per Treasury guidelines
No Bid Adjudication Committee
Procurement SANEDI is busy building capacity to take over the entire SCM functionality
Operational 1st July 2013 . Enhanced by training sessions and monthly dialogue session.
Delays in awarding of tenders
Procurement A Bid Evaluation Committee was constituted although a record of proceedings was not adequate.Procurement process enhancement Development of a template to ensure all relevant information is recorded
BEC appointed 18 July 2013
Meetings are now being recorded . Minutes need to be circulated to members and should be signed by the Chair
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Poor IT controls over tender submission email address
Procurement The Procurement buying office is outsourced to CEF Procurement under a SLA. It is not fair to expect their Procurement Manager to lead the process with due diligence and procedural correctness
As from July 2013 , SANEDI will be responsible for its own buying. A Procurement Officer and a Procurement Manager should be appointed.
Development of a control sheet for all bids to be signed off by the BSC , ICT, Procurement and the Senior Manager responsible before tabling at the Procurement Committee and bid documents released
Only submissions that comply with the required sign offs are considered at the Procom meetings
Functionality criteria not objective
Procurement When purchasing a commercially developed and off the shelf product one needs not specify too deeply for such items. For instance , when wanting to purchase Microsoft office , it would be reasonable to assume that this is the sole developer and that one would need to specify would be the level of package.
Complete bid documents to be tabled before the Procurement Committee before authority to release is granted
Misstatements in the bonus provision
Provision Internal Audit checked the calculation and based on the outcome adjustments have been processed
SANEDI Finance to submit bonus provision calculation to Internal Audit for review before passing entry in financial statements
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Inadequate evidence for performance appraisals
CEF HR HR will ensure that senior and line managers are well informed about the performance review policy and their respective monitoring role/responsibility in this regard. The GM Corporate Services will be the accountable officer in this regard.
All staff to submit quarterly reviews to the Manager : Corporate Services by 15th of month after expiry of the last quarter. This will then be submitted to HR. Once SANEDI ha s the ERP system implemented , quarterly reviews will be done electronically and available on the system.
Provision of receivables understated
Receivables The journal for provision for bad debt for DoE, Alstom and NYSDP was submitted on 3 July 2013
Debtors outstanding for longer than 60 days are followed up by the Accountant during the year. This should be reported to the FM or the CFO on a quarterly basis.
Interest not levied on long overdue debtors
Receivables The nature of a majority long overdue invoices is in respect of grants, donor funds and membership fees that SANEDI receives for its operations and applied research and therefore no interest is charged on this . The debtors management procedure will be updated to include interest to be charged to other debtors . The nature of the debtors will be specified in the revised SANEDI debtors policy
The Revenue Management policy drafted will indicate the nature of SANEDI’s debtors and stipulate the interest clauses for debtors where interest will be applicable
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Creditors reconciliations not done correctly
Payables Auditors findings noted . With the implementation of the new ERP system the monthly reconciliations will be done monthly and not when payments are made only.
The intern and /or creditors clerk will prepare monthly creditor reconciliations and submit to the Accountant for review. Any long outstanding creditors should be followed up by the Accountant.
Accruals are overstated Payables Various Accruals will only be raised for PO’s where the invoice is still outstanding . All other invoices should be raised in AP.
Incorrect accounting for Donor Funding
Income The deferred income for SANEDI and Green Transport has been corrected
All finance staff to attend GRAP training
No accounting policy for membership fees
Income SANEDI will also draft its own Revenue Policy which will include the recognition and measurement criteria for membership fees
Revenue management policy should address all items of income for SANEDI
AUDIT FINDINGS AND ACTION PLAN …cont…
AUDIT FINDINGS SUMMARY
COMPONENT MANAGEMENT RESPONSE ACTION PLAN PROPOSED
Interest expense not valid
Expenses In terms of the agreements signed with the third parties it specifically states that any interest accrued on surplus funds must be accounted for in that specified period
Interest should be accounted for as per the signed agreements
Expenses not correctly classified
Expenses The accounting fees were for an external company to provide assistance with the SACCCS reporting and were not services provided by CEF in terms of the SLA. The classification between advertising and marketing was corrected
All items must be correctly classified. Monthly review by the Accountant of reconciliations will identify and prevent possible incorrect classification