Construction Report
5/22/2012
Operations Division
Denton Independent School
District
Prepared by:
Paul Andress, Director of Operations
Glen Martin, Construction Coordinator
Rod Reeves, Facilities Coordinator
Michael Elmore, SHW Architects
Leesa Vardeman, VLK Architects
Project – 02
Ryan High School Track and Field
(2002 Bond Referendum)
1
05.09.2012
Ryan High School - Track and Field Replacement (1133.00)
Ryan High School - Track and Field Replacement
Construction Progress
• Utility work is complete• Installed drainage beds for track and fi eld• New track is installed• Some of the new turf has been installed
Forecasted
• Complete new turf installation• Stripe new track• Regrade soil around retaining wall
The construction progress through April is 96% complete.
2
05.09.2012
Ryan High School - Track and Field Replacement (1133.00)
North end of track
Northwest end of track
Northeast end of track
Project – 05
Strickland Middle School
(2004 Bond Referendum)
1
05.09.2012
Additions and Renovations to Strickland Middle School (2833.00),
Denton ISD
Strickland Middle School
Construction Progress
• Structural steel is complete• Masonry work is complete• Roofi ng is complete• Windows are installed• MEP overhead is complete• Music and casework cabinets are installed• Sound rooms are complete• Most of the new exterior doors and hardware is
installed
Forecasted
• Finishes including paint, fl ooring, and ceiling are in progress
• Will begin secured main entry and offi ce area once the school year has ended
• Will begin new lockers once the school year has ended
The construction progress through April is 82% complete.
2
05.09.2012
Additions and Renovations to Strickland Middle School (2833.00),
Denton ISD
Northeast corner of building
Northeast corner of building
Northwest corner of the band hall
Project – 06
McMath Middle School
(2004 Bond Referendum)
1
05.09.2012
Additions and Renovations to McMath Middle School (2833.00),
Denton ISD
McMath Middle School
Construction Progress
• Structural steel is complete• Masonry work is complete• Roofi ng is complete• Windows are installed• MEP overhead is complete• Music and casework cabinets are installed• Sound rooms are complete
Forecasted
• Finishes including paint, fl ooring, and ceiling are in progress
• Begin renovations to the reception area including new desk
• Provide new secured vestibule
The construction progress through April is 86% complete.
2
05.09.2012
Additions and Renovations to McMath Middle School (2833.00),
Denton ISD
Northwest corner of the band hall
South wall of the band hall
Southeast corner of the band hall
3
05.09.2012
Additions and Renovations to McMath Middle School (2833.00),
Denton ISD
North wall of Band Hall
West exterior of Band Hall
North exterior wall of Band Hall
Project – 12
Lee Elementary School
(2004 Bond Referendum)
1
05.09.2012
Additions and Renovations to Lee Elementary School (2833.00),
Denton ISD
Lee Elementary School
Construction Progress
• Structural steel is complete• Masonry work is complete• Roofi ng is complete• Windows are installed• MEP overhead is complete• Ceramic tile work is complete• Geothermal well drilling has begun
• Forecasted
• To begin fi nishes including paint, fl ooring, and ceiling are in progress
• Casework to be fabricated and installed• Marker boards and tack boards to be installed
The construction progress through April is 72% complete.
2
05.09.2012
Additions and Renovations to Lee Elementary School (2833.00),
Denton ISD
Drilling of geothermal wells
North wall of classroom addition
South wall
3
05.09.2012
Additions and Renovations to Lee Elementary School (2833.00),
Denton ISD
Northwest corner
Rainwater collection cistern
Project – 08
Evers Park Elementary School
(2007 Bond Referendum)
1
05.09.2012
Additions and Renovations to Evers Park Elementary School (2834.00),
Denton ISD
Out for Proposal - April 12, 2012
Proposals Due - May 8, 2012
Proposed Board Approval - May 22, 2012
Begin Construction - June 4, 2012
Project – 09
Ginnings Elementary School
(2007 Bond Referendum)
Ginnings Elementary School
05.09.12
Ginnings Elementary School
05.09.12
• This project is
currently in the
Construction
Document Phase.
• Complete contract
documents May 31.
• School board to
approve bids in June.
• Construction to start in
July.
Project – 11
Houston Elementary School
(2007 Bond Referendum)
Houston Elementary School
05.09.12
Houston Elementary School
05.09.12
• This project is
currently in the
Construction
Document Phase.
• Complete contract
documents May 31.
• School Board to
approve bids in June.
• Construction to start in
July.
Project – 52
Middle School #7
(2007 Bond Referendum)
1
05.09.2012
Middle School No. 7 (2854.00), Denton ISD
Milestones• Construction bids were received• The School Board approved the project• The Contractor was given notice to proceed and begin construction• Construction fencing is being installed
Forecasted• Clearing site to prepare for construction• Utilities to begin• Foundation work to begin
The construction progress through April is 0% complete.
2
05.09.2012
Middle School No. 7 (2854.00), Denton ISD
First Floor
3
05.09.2012
Middle School No. 7 (2854.00), Denton ISD
Second Floor
4
05.09.2012
Middle School No. 7 (2854.00), Denton ISD
North Elevation - Front Entry
Shady Shores Elevation