Construction Analysis during the

Design Process

Construction Analysis during the

Design Processwww.ddss.arch.tue.nl

Bauke de Vrieswww.ddss.arch.tue.nl

Bauke de Vries

Page 2: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

4D-CAD4D-CAD

•Linking building components with construction activities•Manual task of the construction planner•Dedicated systems: NavisWorks, 4D Suite, …•Advantages: Simulation, Visualization

Page 3: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

ChallengeChallenge

Automation of the planning process.

Advantages:• Independency from the planner• Quick first concept plan

Page 4: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

ImplementationImplementation

EquipmentLabour

Constr.Analysis

Comp.Rel. +Dur.

CADmodel

Formulas

CAD ProjectPlanning

PlanningSchema

Design evaluation

Page 5: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction algoritmsConstruction algoritms

Analysis by object name:Walls are bearing floors, colums are bearingbeams, etc.

Page 6: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction algorithmsConstruction algorithms

Analysis by object elevation:Object with a lower elevation is bearing an object with a higher elevation

Page 7: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction algorithmsConstruction algorithms

Analysis by directed graph:Each object is a node in a connection graph.

Page 8: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction algorithmsConstruction algorithms

Analysis by object adjacency:Each object is a node in a topological graph

A

C

B I

G

FD

JE

H K

L

M

N

- Objecten zonder voorganger

Page 9: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction analysisConstruction analysisObject of anlysis

Page 10: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction analysisConstruction analysisMove down

– Inleiding – Oriëntatie – Doelstelling van het onderzoek – De algoritmen – Implementatie –– Case Study – Reactie uit het bedrijfsleven – Conclusie en Aanbevelingen – Einde –

Page 11: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction analysisConstruction analysisThe green objects have an intersection in the verticaldirection with the red object

– Inleiding – Oriëntatie – Doelstelling van het onderzoek – De algoritmen – Implementatie –– Case Study – Reactie uit het bedrijfsleven – Conclusie en Aanbevelingen – Einde –

Page 12: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction analysisConstruction analysisThe red object has in intersection with the green objectsin the horizontal direction

Page 13: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Construction analysisConstruction analysis

Example:Objects adjacent to floor

Page 14: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Pilot studyPilot study

Page 15: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Planning comparisonPlanning comparisonReal planning

Generatedplanning

Page 16: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

DifferencesDifferences

• Concurrency whenever possible• Unlimited resources• Construction method

Page 17: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

Complete processComplete process

Page 18: Construction Analysis during the Design Processinfo.tuwien.ac.at/cf2005/caad/presentations/cf2005_1_82_21.pdfConstruction Analysis during the Design Process Bauke de Vries Bauke de

www.ddss.arch.tue.nl

ExperiencesExperiences

• Model preperation through clash detection• Generated planning 2 months longer than

real planning over a a period of 1 ½ year• Suitable for a quick first guess• Further development of: Construction

method, Humen resources, Material resources