Clean TeQ Sunrise
CCC Meeting – 19 June 2020
Clean TeQ Sunrise
Project Update
Community Engagement Update
Environmental Management Update
CCC Member Questions
Summary
CCC Meeting Presentation – 19 June 2020 Page 2
Project Update
Page 3
Clean TeQ Sunrise
Project Update
Page 4
• COVID 19 Response– Risk assessments completed - Visitor declaration forms– Physical distancing (1.5m) - Temperature checks– Regular office sanitisation - Stay at home if feeling unwell– Meeting room limits - Hand sanitiser and regular hand washing
• Personnel Changes– Justine Fisher
• Project Execution Plan– Schedule and funding
• Raw Water Pipeline – Continue to work with the Lachlan and Forbes Shires on agreement
CCC Meeting Presentation – 19 June 2020
Clean TeQ Sunrise
Project Update
Page 5
• 132kV Electrical Transmission Line from Parkes to Site– The ETL will supply the required grid connected power to Sunrise for the approved mine life– ETL is proposed at 132 kilovolts (kV) requiring a 45m wide corridor– ETL will be owned by the network service provider– Route options are currently being considered – Key stakeholders include:
• Parkes and Lachlan Shire Councils
• DPIE – Crown Lands
• Private landholders
• TransGrid
• Essential Energy
• Transport for NSW
– Approval sought via Part 5 of the EP&A Act by the network service provider
CCC Meeting Presentation – 19 June 2020
Community Engagement Update
Page 6
Clean TeQ Sunrise
Community – Working Together
Page 7
• Sponsorship of Local Agricultural Shows– Pending plan to proceed due to Covid
• Education and Investment– Supporting the Condobolin Public school
through our education sponsorship program to assist with their Breakfast Club
• Fox Baiting Program – Commenced early June on ML 1770 with
other near neighbours
CCC Meeting Presentation – 19 June 2020
Clean TeQ Sunrise
Voluntary Planning Agreement Funds
Page 8
• Lachlan Shire Council has constructed a new playground at Gum Bend Lake which is now open to the public
• This playground was funded by:– Clean TeQ VPA funds– NSW Government “Everyone Can Play” grant– Lachlan Shire Council funds
CCC Meeting Presentation – 19 June 2020
Photo courtesy of LSC Facebook page
Clean TeQ Sunrise
Keeping People Informed
Page 9
• Community Communication– Transition to more regular updates via
online platforms such as Facebook– Newsletter published in December, next
edition expected later this year at a reduced frequency
– Steve Karaitiana profiled in Summer edition
– Parkes and Condobolin shopfronts will open regularly for enquiries when safe
• Clean TeQ Website– Complaints register published monthly,
zero complaints YTD– Community Complaints line listed on our
website – 1800 752 277
CCC Meeting Presentation – 19 June 2020
https://www.cleanteq.com/sunrise-
project/registering-a-complaint/
Environmental Management Update
Page 10
Clean TeQ Sunrise
• Annual Review– 2019 Annual Review was submitted and accepted by DPIE– No non-compliances identified– Copy can be found on the Clean TeQ website
• Annual Return – Submitted and accepted by NSW EPA– No non-compliances identified
Environmental Annual Reporting
Page 11CCC Meeting Presentation – 19 June 2020
Clean TeQ Sunrise
• A Mining Lease Compensation Agreement has been signed between Clean TeQ, DPIE-Crown Lands and Local Land Services (LLS) for the use of Crown Land within Mining Lease 1770
• ML 1770 varied to include land to the west of Wilmatha Road for ancillary mining activities
• Water Management Plan has been approved by DPIE– copy can be found on the Clean TeQ website
• Noise Management Plan revised– Monitoring suspended until construction
Secondary Approvals
Page 12CCC Meeting Presentation – 19 June 2020
Clean TeQ Sunrise
Environmental Monitoring – Air, Noise and Water
Page 13
• Continuing environmental monitoring in accordance with Development Consent, Environmental Protection Licence and relevant Environmental Management Plans:– Air Quality
– Noise
– Surface Water
– Groundwater
• Results are reported on the Clean TeQwebsite and within the Annual Review
• Particulate Matter monitors (PM10 and PM2.5)– Installed December 2019
– Commissioning underway
CCC Meeting Presentation – 19 June 2020
Clean TeQ Sunrise
• Vegetation screens– Additional 5,000 trees and shrubs planted early June to
replace seedlings that did not survive the drought
Vegetation Screens
Page 14CCC Meeting Presentation – 19 June 2020
Clean TeQ Sunrise
• Vegetation screen locations– Include Mining Lease 1770 and the
Fifield Bypass
Vegetation Screens
Page 15CCC Meeting Presentation – 19 June 2020
CCC Member Questions
Page 16
Clean TeQ Sunrise
• Nil received
CCC Member Questions
CCC Meeting Presentation – 19 June 2020 Page 17