Who is CFX
The Central Florida Expressway Authority (CFX) is an independent, locally-controlled toll agency responsible for construction, maintenance and operation of 125 miles of expressway.
Click to edit Master title styleFY 2021-2025 Work PlanProject Cost Summary ($000’s) Fiscal Year
Category 2020/21 2021/22 2022/23 2023/24 2024/25 TotalsExisting System Improvements 136,210 510,001 499,440 165,309 31,234 1,342,194
System Expansion Projects 23,134 81,155 246,823 337,947 238,739 927,798
Interchange Projects 15,340 3,086 31,432 39,439 43,772 133,069
Facilities Projects 6,397 7,323 6,127 6,508 4,787 31,142
Transportation Technology Projects 15,136 6,214 5,634 698 2,894 30,576
Information Technology Projects 29,094 24,294 11,535 2,260 2,260 69,443
Signing and Pavement Markings 3,495 19,703 5,585 8,134 2,299 39,216
Renewal and Replacement Projects 33,064 71,473 9,151 19,937 7,528 141,153
Landscape Projects 769 787 1,413 799 794 4,562
Non-System Projects 19 580 0 0 144 743
TOTALS 262,658 724,616 817,140 581,031 334,451 2,719,896
SR 417 and SR 429 Corridor Widening
Projects
SR 417: Five Total Projects - $467M Construction Cost EstimateSR 429: Three Total Projects - $380M Construction Cost EstimateFEATURES: • Median Widening
• 35 Centerline Miles• 82 Bridges• Part Time Shoulder Use (PTSU)
Typical Section with PTSU
$45M Construction Cost Estimate
• New/widened bridges
• New and reconstructed ramps
• 2 new ramp tolling locations
• Local road improvements:
roundabouts, pavement
widening/reconstruction/
resurfacing, lighting,
landscaping, drainage and
sidewalks
Tampa Avenue Interchange Tampa Avenue to Orange Blossom Trail
Poinciana Parkway Extension
CR 532 to Ronald Reagan Parkway
SR 538: Three Projects
• Currently in Design
• CEI Upcoming Advertisements Late 2021
• Anticipate Construction Start 2022
$92M Construction Cost Estimate
• 4 Bridges*2 bridges over 3000’
• Reedy Creek Mitigation Bank
Segment 1 Poinciana Parkway Extension
South of US 17/92 to Ronald Reagan Parkway
CR 532 to South of US 17/92
Segment 2 Poinciana Parkway Extension
$54M Construction Cost Estimate
• 9 Bridges
• Utility Relocations
• CSX Railroad
• FDOT (US 17/92 Interchange)
• Toll Plazas (2)
Local Road ImprovementsPoinciana Parkway Extension
Old Lake Wilson Road to US17/92
$30M Construction Cost Estimate
• 2.9 miles of widening from two to four lanes
• New stormwater ponds
• ITS, Lighting, Landscaping
• CSX Railroad Crossing
SR 516 Lake/Orange Expressway
US 27 to SR 429 Connector
NEW 5-mile ExpresswayThree Total Projects - $231M Construction Cost Estimate4 LanesNew Interchange @ US 27, CR 455, and SR 429
Typical Section
Click to edit Master title styleWork Plan Design Projects
SR 414 Expressway Extension• Pending results of PD&E and Viability
Dallas Blvd Interchange• 2022 Advertisement
Osceola Parkway Extension (OPE)• Osceola Parkway Extension Segments 1, 2, and 3
Click to edit Master title styleCFX Infrastructure Department
Glenn Pressimone, PEChief of [email protected]
Ben Dreiling, PEDirector of [email protected]
Will Hawthorne, PEDirector of [email protected]
Click to edit Master title style
Jack Burch, P.E.CFX Resident Engineer/ Construction [email protected]
Questions?
Click to edit Master title styleCEI AdvertisementsSummary
Project # Description Construction Cost Estimate
Anticipated Advertisement*
429-153 SR 429 Widening West Rd to SR 414 $72 Million 2nd Quarter 2021
538-234 SR 538 Extension South of US 17/92 to Ronald Reagan Parkway $92 Million 3rd Quarter 2021
538-235 SR 538 Extension South of CR 532 to South of US 17/92 $54 Million 4th Quarter 2021
408-315 SR 408 Tampa Avenue Interchange $45 Million 4th Quarter 2021
538-235A SR 538 from CR 532 to South of US 17/92 $30 million 2022
516-236 SR 516 from US 27 to Cook Road $71 million 2022
516-237 SR 516 from Cook Road to Lake/Orange County Line $73 million 2022
516-238 SR 516 from Lake/Orange County Line to SR 429 $87 million 2022
*Calendar Year/Quarter and subject to change.
Click to edit Master title styleConstruction AdvertisementsSummary
Project # Description Construction Cost Estimate
AnticipatedAdvertisement*
417-149 SR 417 Widening from Landstar Boulevard to Boggy Creek Road $80 Million 1st Quarter 2021
417-150 SR 417 Widening from Narcoossee Road to SR 528 $113 Million 2nd Quarter 2021
417-151 SR 417 Widening from Boggy Creek Road to Narcoossee Road $75 Million 2nd Quarter 2021
429-152 SR 429 Widening from Florida’s Turnpike to West Road $142 Million 3rd Quarter 2021
429-154 SR 429 Widening from Tilden Road to Florida’s Turnpike $66 Million 3rd Quarter 2021
429-153 SR 429 Widening from West Rd to SR 414 $72 Million 4th Quarter 2021
538-234 SR 538 Extension South of US 17/92 to Ronald Reagan Parkway $92 Million 2022
538-235 SR 538 Extension South of CR 532 to South of US 17/92 $54 Million 2022
408-315 SR 408 Tampa Avenue Interchange $45 Million 2022
*Calendar Year/Quarter and subject to change
Click to edit Master title styleConstruction AdvertisementsSummary
Project # Description Construction Cost Estimate
Anticipated Advertisement*
523-235A SR 538 from CR 532 to South of US 17/92 $30 million 2022
516-236 SR 516 from US 27 to Cook Road $71 million 2023
516-237 SR 516 from Cook Road to Lake/Orange County Line $73 million 2023
516-238 SR 516 from Lake/Orange County Line to SR 429 $87 million 2023
*Calendar Year/Quarter and subject to change