Download - By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Transcript
Page 1: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

By: Prof. Hoang HoeEng. Le Huy Cuong

Dr. Do Xuan Lan

ASIA GEOSPATIAL FORUMHanoi, 17-19 September, 2012

Page 2: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

• The overall objectiveTo make recommendations for the coordination between sectors in the land use planning, hydropower planning and development, forest management to benefit the sustainable socio-economic development and the environment.

• Specific objectives of the study to:- Assess impact of hydropower projects to forest, land use in terms of changes in area and quality;- Define some effects of hydropower projects on environment and socio-economic life of the community.

Page 3: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

• Mapping forest status in the year 2000 and 2010 using Remote sensing data.• Interpretation key and ground truthing.• Overlay maps of 2 periods to assess changes in forest area

between two date.• Assess the quality of the forest types after the

hydropower plants constructed.• Setting up temporary plots to measure forest characteristics;• analyzing survey data for assessment of forest quality

indicators• Investigate the environmental and socio-economic

conditions and production activities in the area of hydropower plant construction regarding resettlement though interviewing affected households.

Page 4: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.
Page 5: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

In the period from 2000 - 2010 in the Dong Nai river basin construct 18 hydropower plants of various scale

Page 6: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

# Hydropower Plant

CapacityMW

Elevation, AMSL

Status Remarks

1. Dong Nai 3 340 590 2010

2 Dong Nai 4 180 476 2011

3 Dong Nai 5 150 288 2014

4 Dong Nai 6 135 224 Under Approval

5 Dak Klong 7.5 487.5 Under Construction

6 Dak R’tin 144 618 2011

7 Dak Nong 2.0 600 Operation

8 Dak Nong 1 1.8 652 Operation

9 Dak Nong 2 2.0 520 Operation

10 Dak Rung 8.0 781 Operation

11 Dak Rung 1 6.0 695 Operation

12 Dak Buk So 1 0.65 745 Under Construction

13 Nhan Co 1.5 635 Under Approval

14 Dak Buk So 3 3.0 650 Under Approval

15 Dak Muong 2.2 568 Under Construction

16 Dak R’keh 5.0 549 Under Approval

17 Dak Kar 7.2 475 Under Construction

18 Dak Mia 6.5 611 Under Construction

Page 7: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Figure 1: Location map of the Hdropower plants of the Dong Nai River Basin in Dak Nong Province

Page 8: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

TT Forest and land use TotalNatural area 5.328,7

I Forested Lands 2.128,27 Rich Broadleaved Evergreen Forest -8 Medium Broadleaved Evergreen Forest 51,19 Poor Broadleaved Evergreen Forest 220,8

10 Regenerated Broadleaved Evergreen Forest 86,211 Deciduous Forest -17 Semi-Evergreen Forest -18 Coniferous Forest -24 Mix coniferous broad-leaved forest -25 Bamboo 803,926 Mixed bamboo-wood forest 902,129 Plantation 64,1II Non-Forest Land 3.200,534 Bare Land 565,343 Water body 467,942 Residential 202,740 Other Land 1.964,6

Land loss due to hydropower plants construction

Page 9: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Total natural area lost due to reservoir construction of 18 plants was 5,328.7 ha,

natural forest loss was 2,128.2 ha. in which: ◦ poor forest: 220.8 ha;◦ the newly regenerated forest: 86.2 ha; ◦ bamboo forest 803.9 ha; and ◦ mixed bamboo-wood forest: 902.1 ha.

Forest loss mostly occurs in the basin of Dong Nai 3 hydropower reservoir being submerged now.

Page 10: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Non-forest area lose is 3,200.5 ha, in which:◦ 565.3 ha of bare land, ◦ 1964.6 ha of agricultural land and industrial

plantations. Thus the actual area of forest and non-forest

land lost due to construction of hydropower reservoirs is only a small part of the total area of forest lost in the basin.

The indirect impacts of hydropower projects are also caused by the other factors should be assessed in detail.

Area loss under reservoirs (cont’d)

Page 11: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

The map showing the state of forest resources in 2000

Page 12: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

The map showing the state of forest resources in 2010

Page 13: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

TT Forest Land category Total, haPercentag

eNatural area 193.807,6 100

I Forested Lands 91.486,5 47.2

7 Rich Broadleaved Evergreen Forest 1.600,3 1.7

8 Medium Broadleaved Evergreen Forest 26.273,0 28.7

9 Poor Broadleaved Evergreen Forest 25.722,1 28.1

10 Regenerated Broadleaved Evergreen Forest 16.018,9 17.5

11 Deciduous Forest 5,8 -

24 Mix coniferous broad-leaved forest 75,7 -

25 Bamboo 8.875,0 9.7

26 Mixed bamboo-wood forest 9.032,7 10.0

29 Plantation 3.882,9 4.2

II Non-Forest Land 102.321,1 52.8

34 Bare Land 12.392,5

43 Water 1.106,3

42 Residential 5.600,8

40 Other Land 83.221,5

Forest and land use status in 2000

Page 14: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

# Forest Land category Total, haPercent

ageNatural area 193,807.9 100

I Forested Lands 48,803.7 25.2

1 Rich Broadleaved Evergreen Forest 1,653.4 3.4

2 Medium Broadleaved Evergreen Forest 6,383.7 13.1

3 Poor Broadleaved Evergreen Forest 14,065.5 29.0

4 Regenerated Broadleaved Evergreen Forest 6,618.9 14.0

6 Semi-Evergreen Forest 37.1 -

7 Coniferous Forest 223.8 0.5

8 Mix coniferous broad-leaved forest 58.5 -

9 Bamboo 5,358.8 11.0

10 Mixed bamboo-wood forest 10,612.9 14.0

11 Plantation 3,791.2 8.0

II Non-Forest Land 145,004.2 74.8

12 Bare Land 13,619.7

13 Water 2,766.6

14 Residential 4,017.1

15 Other Land 124,600.8

Forest and land use status in 2010

Page 15: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

By 2010, the total forest area in the basin remains very low, just 48,803.7 ha accounted for only 25.2% of the total land area.

High percentage of poor forest while the medium and rich forests have very small ratio, showing that quality of the forest is increasingly declined.

Non-forest land accounted for 74.8%, in which:◦ agricultural and other land covers a large area with

124,600.8 ha showing that agricultural production activities are growing and the large area of forest were converted to meet the needs of population.

◦ Forest cover of only 25.2% this is a big concern

Page 16: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

TT Forest Land category 2000 2010 Change

Natural area 193,807.9 193,807.9 0.0

I Forested Lands 91,486.5 48,803.7 -42,682.8

1 Rich Broadleaved Evergreen Forest 1,600.3 1,653.4 53.1

2 Medium Broadleaved Evergreen Forest 26,273.0 6,383.7 -19,889.3

3 Poor Broadleaved Evergreen Forest 25,722.1 14,065.5 -11,656.6

4 Regenerated Broadleaved Evergreen Forest 16,018.9 6,618.9 -9,400.0

5 Deciduous Forest 5.8 - -5.8

6 Semi-Evergreen Forest   37.1 37.1

7 Coniferous Forest   223.8 223.8

8 Mix coniferous broad-leaved forest 75.7 58.5 -17.3

9 Bamboo 8,875.0 5,358.8 -3,516.2

10 Mixed bamboo-wood forest 9,032.7 10,612.9 1,580.2

11 Plantation 3,882.9 3,791.2 -91.7

II Non-Forest Land 102,321.1 145,004.2 42,682.8

12 Bare Land 12,392.5 13,619.7 1,227.2

13 Water body 1,106.3 2,766.6 1,660.2

14 Residential 5,600.8 4,017.1 -1,583.7

15 Other Land 83,221.8 124,600.8 41,379.1

Forest and land use change during 2000-2010

Page 17: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Forest area in 2010 has lost 42,682.8 ha compared to 2000 corresponding to 46%.◦ 42,682.8 hectares of forest disappear after 10 years is

worrying figures for the forests protection and management.

The area of agricultural land and other land increased by 41,379.4 ha, ◦ forest loss has converted into industrial plantations and

agricultural land. ◦ The reason of forest loss is to grow agricultural crops and

industrial trees by Dak Nong province, after separation from the Dak Lak: Plateau flat terrain fertile basalt soil suitable to species cash

crops such as coffee, pepper.

Page 18: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Lagest changes is medium and poor forests. ◦ The medium forest in 2000 was 26,273 ha; after 10 years

only 6383.7 ha, ◦ Poor forest 25,722.1 ha in 2000 and in 2010 only

14,065.5 ha. Regeneration forest also decreased by 9,400 ha

after 10 years◦ in 2000: 16,018.9 hectares whereas in 2010: 6,618.9 ha.

Other land area increased 41,379.4 ha, while 42,682.8 hectares of natural forest are lost after 10 years. This suggests that most of the deforestation area converted into other land.

Page 19: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Impact on population distribution Construction of hydropower plants occupy area

along the rivers and streams where locate agricultural and residential land. ◦ Resettlement of large number of households. ◦ Resettlement work may take in place or relocation to a

new place i.e. process of redistribution of the population in a small area or a region.

◦ Small and medium-sized hydropower plants: usually on-site resettlement. People use cash (compensation) to buy a piece of land and continue to live in the old place.

◦ Large hydropower projects: due to large scale land acquisition, people have to resettle to new place

Page 20: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

# Category Area By Category (ha)Agr. Water Res. Forest

1 Reservoir Construction 1,264.0 1,102.2 1.4 26.6 133.8

2 Resettlement 1,195.9       1,195.9

3 Quarry 17.5       17.5

4 Main and auxiliary objects          

- SFE Quang Khe 102.3 9.8 85.6 6.9  

- Ta Dung Nature Reserve 31.4 23.5 7.9    

- Gia Nghĩa Company 88.0 2.5 85.5    

5 Road to the main dam 11.6       11.6

6 By pass road 65.7   45.4   20.3

7 Supporting objects 204.0       204.0

8 Main dam and power

stations

6.1       6.1

Total2,986.5 1,138.0 225.8 33.5 1,589.2

Total occupied land for Dong Nai 3 hydropower Plant

Page 21: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

Huyện Đăk GlongNo. of HHs/ Persons

affected

No. of HHs/ Persons

Resettled

Đak Plao Comm. 532/2,377 424/1,998

Quảng Khê Comm 10/60 1/6

Đak Som Comm 113/701 103/630

Total 655/3,138 528/2,634

Affected households in Dong Nai 3 hydropower plant

Page 22: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

The hydropower largely built in the watershed areas of rivers and streams, where many ethnic minorities live. ◦ Nearly half of the households are poor, ◦ material and spiritual life more difficult and also offers many living

traditions of their people. The resettlement process lead to lose of all traditional

architecture. ◦ Households are arranged in a standard house built by investors with

an area of 55m2. ◦ Houses are located along the route as a new urban center. ◦ Living in conditions of high concentration, cultural and ethnic identity

eroded gradually, no longer wear traditional clothing, no festival, singing and cultural activities also decrease.

◦ Life of the ethnic minority people in the resettlement areas were also changed. The family does not use firewood that use gas, do not use mineral water wells but tap water, no longer countryside living community but urban environment.

Page 23: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

In resettlement communes, the social welfare significantly improved ◦ Typically in resettlement new Dak Plao commune has built 5

kindergartens, 5 cultural community, one clinic, three schools and institutions of social work nicely. Transport systems, electricity and water supply relatively complete.

In contrast to the resettlement communes, in the other communes where people resettled in place, investors just pay compensation (in cash) and do not focus on improving the welfare of the people.◦ No improvement of roads, electricity, schools. Even some households

agreed on resettlement compensation without electricity and water. ◦ Communication system severely degraded due vehicles for building

hydropower. ◦ People are affected by dust, waste from the construction work.

Page 24: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

The survey of 50 households affected by hydroelectric plant construction shows: ◦ in 2000 the average household had 2.44 ha (the highest upto

6.9 ha);◦ by the end of 2010 the average households has only 1.33 ha

(highest only 4 hectares). The average household lost one hectare of arable land

due to hydropower plant construction. The loss of productive land has a huge impact on people's social and economic life.

The survey results showed that:◦ 31.1% of households were completely change production

practices.◦ 56.6% of households changed production practices.◦ 13.3% of households no or little change in production practices.

Page 25: By: Prof. Hoang Hoe Eng. Le Huy Cuong Dr. Do Xuan Lan ASIA GEOSPATIAL FORUM Hanoi, 17-19 September, 2012.

From 2000 to 2010, in the Dong Nai River Basin of Dak Nong province and forests lost 48,804 ha, in the area of natural forest is 45.013ha. Average annual forest loss of 4268ha, the average annual loss of 4.65% of forest area from 2000.

By 2010, forest cover in the Dong Nai River Basin is only 25.18% that is an alarming number for watershed area.

The main reason for forest change is conversion to agriculture land. Hydropower projects contribute only a small part to the process of deforestation, but largely impact indirectly on change by resettlement, construction of supporting facilities.

Very high density of Hydropower plants in the basin, while forest cover is down to alarming levels lead to:◦ low protection capacity for the reservoir and dam, ◦ increase risk and danger for downstream, ◦ lack of water in the dry season and floods in rainy season

Construction of hydropower plants affects on socio-economic life of the local people due to loss of arable land, change of lifestyle.