Budgeting the Project4-1
Budget
4-2
Homework #17
Overview Approaches for gather data Budgeting & Estimating costs Budget uncertainty and risk management CB Homework
4-3
4-4
$10,000$ 5,000$ 2,000
$17,000
4-5
Budgets are plans for allocating organizational resources to project activities.• forecasting required resources, quantities
needed, when needed, and costs Budgets help tie project to overall
organizational objectives. Budgets can be used as tool by upper
management to monitor and guide projects.
4-6
4-7
Analogous estimation
Parametric estimationIt will take 20 hours of a programmer’s time to write this module. The historical average rate for this type of programmer has been $100/hour. Therefore, the module cost will be $2,000.
Bottom-up estimation
4-8
Estimate
Uncertainty
Uncertainty
4-9
4-10
Simulation Technique for Uncertainty in Project Costs
4-11
What is the probability the project comes in at $5000 or less?
Simulation Technique for Uncertainty in Project Costs
4-12
Simulation Technique for Uncertainty in Project Costs
4-13
Simulation Technique for Uncertainty in Project Costs
4-14
€
EV = pii
∑ (Oi)
Materials Very Low Low Medium High Probability 0.1 0.1 0.5 0.3 Alternatives EVIn-house 12,500 13,800 15,200 22,000 16830Outsource 15,000 15,000 15,000 15,000 15000Combo 11,200 12,100 14,000 16,800 14370
4-15
BAC
EV or BCWP – value of the actually performed work for a given period of time.
AC or ACWP
PV or BCWS
Example: Project is the construction of a 16-mile road. The work is uniformly distributed over 12 weeks.Total budgeted amount is $600,000. At the end of the first 4 weeks, $125,000 has been spent, and 4 miles of road completed.
$
Work Perform
ed
Schedule/Time
4-16
4-17
4-18
•Why did FoxMeyer initiate the Delta III project?
•What was the solution? What was FoxMeyer implementing as part of the project?
•What were the problems and issues?
•What can we learn about managing projects?
Top Related