Assignment on

Project Development and Implementation for Strategic Managers

Unit 17

Edexcel BTEC level 2 Extended Diploma in strategic Management and Leadership

(QCF)

Guildhall College, London

Prepared By:

Submitted To:

Date of Submission:

Page 2: Assignment - Project Development and Implementation for Strategic Managers

Assignment Topics

AC (1.1) Analyze the factors that contribute to the process of project selection.

AC (1.2) Develop outline project specifications for the implementation of a new

product, service or process.

AC (1.3) Produce a specification for an agreed project to implement a new product,

service or process

AC (2.1) Produce a project plan for an agreed project.

AC (2.2) Match appropriate resources to the project.

AC (2.3) Cost all resources required for implementing a project.

AC (2.4) Agree timescales for the management and implementation of a project.

AC (2.5) Plan an appropriate strategy for the implementation of a project.

AC (3.1) Implement a project in accordance with an agreed specification.

AC (3.2) Develop appropriate measures to monitor and evaluate progress and

Outcomes.

AC (3.3) Monitor the implementation of the project.

AC (4.1) Analyze the outcomes of a project in terms of the original project

specification.

AC (4.2) Evaluate the outcomes of a project.

AC (4.3) Make justified recommendations for improvements to the project.

AC (5.1) Produce a report of all project procedures used.

AC (5.2) Present the outcomes of the project to an audience using an agreed format

and appropriate.

2

Page 3: Assignment - Project Development and Implementation for Strategic Managers

3

Page 4: Assignment - Project Development and Implementation for Strategic Managers

Note: The Chosen Organization for the Assignment.

Happy Heart Events Management Private Limited

Happy Heart Events Management Private Limited, has organized more than hundreds

events of various types, like Annual Dinner and Dance events, wedding and

solemnization occasions, product launch functions, opening ceremonies, seminars,

exhibitions and carnivals, which mostly involved 150 – 300 personnel per event. Our

company, Happy Heart Event Management Pte Ltd, is a relatively new company that

have organized more than hundreds events of various types, like Annual Dinner &

Dance, Wedding & Solemnization, Product launching, Opening ceremony, Seminars,

Exhibition and carnivals etc, which mostly involved 150 – 300 personnel per event. Our

company provides customized, strategic event experiences where guests connect with our

clients' brands and products in ways that are personally relevant and memorable. Our

team offers the creative vision, professionalism, and event expertise to create winning

events - with a constant eye towards detail, quality, originality and results. Based on

devotion in our mission and jobWith high levels of professionalism and commitment, we

are well-trusted by our clients. Building our good reputation of excellent planning and

organization skills, this reputation comes with our experience teams of more than a

decade of experiences and the project manager well versed skills in project planning and

management.

Our company’s vision is to be the preferred event planning company in UK. Our current

business strategy is to create a new market and as well as establish long lasting

relationship with clients’ with a clear, well defined business plan, objectives and financial

criteria. We provide total solutions for event ranging from all sizes, sophistication, and

logistic supports to marketing and public relations function to ensure every aspect and

component is strategically put in place to deliver the best results. With an equipment of

good grasp of the strategic marketing and advertising skill, we will be able to understand

and fulfill our clients’ expectations and requirements. Our company motto is to be

responsive towards the queries and professionally address the issues that our clients have.

4

Page 5: Assignment - Project Development and Implementation for Strategic Managers

We adopt a strategic design and planning process to attain the most satisfactory results

with a well-managed timeline.

With all the successes and experiences on small scale events, we are currently presented

with the break-through opportunity of managing Hiticha Group’s annual Dinner and

Dance. Hiticha Group is an internationally reputable organization, this project will enable

us to prove our capability in handling multi-national company’s event. Also, this project

will put our reputation to the toughest test.

5

Page 6: Assignment - Project Development and Implementation for Strategic Managers

Table of Contents

Task Topic Page

AC (1.1)Analyze the factors that contribute to the process of project

selection.6

AC (1.2)Develop outline project specifications for the implementation of a

new product, service or process.7

AC (1.3)Produce a specification for an agreed project to implement a new

product, service or process8

AC (2.1) Produce a project plan for an agreed project. 12

AC (2.2) Match appropriate resources to the project. 16

AC (2.3) Cost all resources required for implementing a project. 18

AC (2.4)Agree timescales for the management and implementation of a

project.19

AC (2.5) Plan an appropriate strategy for the implementation of a project. 21

AC (3.1) Implement a project in accordance with an agreed specification. 23

AC (3.2)Develop appropriate measures to monitor and evaluate progress and

Outcomes.25

AC (3.3) Monitor the implementation of the project. 27

AC (4.1)Analyze the outcomes of a project in terms of the original project

specification.29

AC (4.2) Evaluate the outcomes of a project. 30

AC (4.3) Make justified recommendations for improvements to the project. 31

AC (5.1) Produce a report of all project procedures used. 32

AC (5.2)Present the outcomes of the project to an audience using an agreed

format and appropriate.34

- Reference 35

6

Page 7: Assignment - Project Development and Implementation for Strategic Managers

AC (1.1): A nalyze the factors that contribute to the process of project selection.

Technological factor

Advances in technology can help improve productivity of labor, also as reduce

transportation costs, distribution costs, communication costs and production costs.

Examples of it include changes that affect the production and distribution of a product or

services.

Economic factor

Economic factor affects the overall consumption and investment in a business. A stable

economy attracts firms that wish to do business. An unstable economy however increases

business risks and even deters investment. Examples of it include national income,

taxation policy, foreign exchange policy, inflation rate, etc.

Physical factor

It refers to the physical location and natural environment which directly affects the

economic development of the countries or a region. A favorable physical environment

with well-planned infrastructures likes the airport and transport facilities can attract firms.

Social and cultural factor

Social factor affects the productivity and labor supply. Examples of it include the

population structure, language ability, education level, etc. Cultural factor affects trhe

taste and preferences of costumers. Examples of it include whether a country encourage

women to go out and work and emphasis on virtue of hard work.

Political factor

This is related to the political system, laws and regulations of a country. Political systems

can be classified as authoritarian and democratic. Laws and regulations' examples include

licensing laws, customer laws, and labor laws, and licensing regulations. A country with

sound legal system and stable political condition can attract investments as it enhances

investors' confidence.

7

Page 8: Assignment - Project Development and Implementation for Strategic Managers

AC (1.2): D evelop outline project specifications for the implementation of a new

product, service or process.

Hiticha Group is a well-known multinational organization which specialized in

manufacturing electronic products for the retail market. With a budget of £120,000,

Hiticha Group has decided to shortlist our company as the most potential event company

to manage their 15th Annual Dinner and Dance event. With clients’ endorsement, it will

be named the “Starry Starry Night!!!!”

The objectives for this project are to provide our new client an extraordinary Annual

Dinner and Dance, and to make an impression in our client for future engagements for

our services. With the organizational commitment from top management to the team

members, it lays the fundamental structure for the project manager to develop and

execute the project plan.

8

Page 9: Assignment - Project Development and Implementation for Strategic Managers

AC (1.3): P roduce a specification for an agreed project to implement a new product,

service or process.

Scope of the Project:

Hiticha Group is a well-known multinational organization which specialized in

manufacturing electronic products for the retail market. Hiticha Group head-quarter is

based in Japan with more than 10 overseas branches. UK’s regional office deals with

marketing, sales and service support etc. In December 2011, Hiticha’s UK office will

host their 15th Annual Dinner and Dance event, gathering approximately 500 staffs

including clients, partners as well as business associates. With a budget of £120,000,

Hiticha Group has decided to shortlist our company as the most potential event company

to manage their 15th Annual Dinner and Dance event.

From the initial understanding, Hiticha Group will like to conceptualize their dinner and

dinner as per their latest marketing campaign – Like “The Shooting Star”. We are tasked

to create a theme that chosen embraces grandeur and glamour at a beach environment,

where the party will start from evening till the end. The underlying mission is to create an

environment, filled with special activities. We hope to provide all guests and staffs with

the experience of an extraordinary starry beach night and indulge in the wonderful and

splendid performances organize by our company. With clients endorsement, we will

name the event “Starry Starry Night!!!!”

Objective of the project:

Our objectives for this project are to provide our new client an extraordinary Annual

Dinner and Dance, and to make an impression in our client for future engagements for

our services. This project will be the critical stepping stone for our company to gain more

market share. The top management of the company will select the most suitable project

manager to lead this project. The project manager is desirable to be tactful with clients,

positive and committed, and experienced in managing a team to organize the larger scale

projects. The importance of leadership is to organize the project team and amplify

commitments in the team members. With the organizational commitment from top

9

Page 10: Assignment - Project Development and Implementation for Strategic Managers

management to the team members, it lays the fundamental structure for the project

manager to develop and execute the project plan.

The project cycle is the basis for the project manager to develop the project plan. The

Business aspect involves all the operational functions that relating to the overall business

management of the project issues from the perspective of customer management,

justification of the project. Whereas, Budget aspect involve events related to the

requisitioning of the project funds and its management throughout the life of the project

implementation. Whereas, Technical aspect identifies the list of activities and events

required to provide the optimum technical solution in the most efficient way. The

technical aspect spans from the determination of what our client wants to validation the

project solution that satisfies our clients. The below illustration will give a more concise

concept on the three aspects from our company perspective on this project.

Business aspect: Being labeled as medium-sized event company, we are lack of multi-

national company’s event to our portfolio to showcase our success. The milestone project

with Hiticha provides us with the opportunity to break-through our currently status and to

advance into the multi-national company market. It is very much critical that we can

clinch this project.

Budget Aspect: “Starry Starry Night” is an outdoor event, which is also the 15th years

anniversary celebration of the Hiticha company. It is expected to cater for about 500

guests. Our client has mentioned that they will be investing a considerable sum of

£120,000 for this event, however they also wish we able to assist them to reduce some

unnecessary cost for this project. While we are aiming at a forty percents profit from the

entire project, we will attempt to assist our client in reducing their cost. However, in

order for our company to have better case flow during the implementation period, as per

proposed contract, the payments will be made to us by 2 installments, which is 60%

follow by 40% of the total proposal cost. The first payment will be made to us when we

sign the official contract, while the second payment will be the day after the event. With

10

Page 11: Assignment - Project Development and Implementation for Strategic Managers

the first installment being received, we will have sufficient cash flow to carry out this

project.

Technical Aspect: One of the deciding factor for the project to be considered as

successful lies on the satisfaction of our clients. The smile on our client face, after the

event, is the deciding factor. Our challenge is to ensure that the setting is to be done as

per the expectation of the given theme, creating the right atmosphere for the guests,

within the given timeline.

In order to meet the above objectives, the following portions will highlight on the each of

the cycles. Basically Business, Budget and Technical cycle are each made up of three

periods, study, implementation and operation periods, which will be illustrated in the

later part

Project management, planning and implementation cycle:

Project management and planning coordinate and optimize the resources necessary to

successfully complete a project. The resources referring to are manpower, skills, budget,

commitment, systems and equipment. Goal of planning is to meet project objectives -

meeting company and client's requirements. Project plan coordinates and optimizes

coordination, mitigating risk and plan for contingencies. Importantly, it aims to obtain

commitment from team members to see through the project from planning to operation

and disposal. The plan puts in-place a control system to ensure for accountability of

processes and expenditure, meeting schedules and clarity.

For the project to be successful and achieve the given objectives, it is critical to

understand and plan our project cycle. Project cycle is defined as an orderly sequence of

integrated activities, performed in phases, leading to success (Forsberg, Mooz and

Cotterman, 2005). Like all projects, we will need to break down our project cycle into

three aspects – business, budget and technical. The team should see project cycle as the

foundation for achieving predictable performance which is tailored with special

characteristics. The resultant project cycle then becomes the parent or driver of the

11

Page 12: Assignment - Project Development and Implementation for Strategic Managers

project’s logic network – represented by PERT and GANTT charts that will be developed

during the planning. (Forsberg, Mooz and Cotterman, 2005) The project cycle should be

planned throughout the study period, implementation period and operation period.

12

Page 13: Assignment - Project Development and Implementation for Strategic Managers

AC (2.1): P roduce a project plan for an agreed project.

Scope of the Project:

Hiticha Group is a well-known multinational organization which specialized in

manufacturing electronic products for the retail market. Hiticha Group head-quarter is

based in Japan with more than 10 overseas branches. UK’s regional office deals with

South-East Asia marketing, sales and service support etc. In December 2011, Hiticha’s

UK office will host their 15th Annual Dinner and Dance event, gathering approximately

500 staffs including clients, partners as well as business associates. With a budget of £

120,000, Hiticha Group has decided to shortlist our company as the most potential event

company to manage their 15th Annual Dinner and Dance event.

From the initial understanding, Hiticha Group will like to conceptualize their dinner and

dinner as per their latest marketing campaign – Like the shooting starThe Shooting Star.

We are tasked to create a theme that chosen embraces grandeur and glamour at a beach

environment, where the party will start from evening till the end. The underlying mission

is to create an environment, filled with special activities. We hope to provide all guests

and staffs with the experience of an extraordinary starry beach night and indulge in the

wonderful and splendid performances organize by our company. With clients

endorsement, we will name the event “Starry Starry Night!!!!”

Objective of the project:

Our objectives for this project are to provide our new client an extraordinary Annual

Dinner and Dance, and to make an impression in our client for future engagements for

our services. This project will be the critical stepping stone for our company to gain more

market share. The top management of the company will select the most suitable project

manager to lead this project. The project manager is desirable to be tactful with clients,

positive and committed, and experienced in managing a team to organize the larger scale

projects. The importance of leadership is to organize the project team and amplify

commitments in the team members. With the organizational commitment from top

13

Page 14: Assignment - Project Development and Implementation for Strategic Managers

management to the team members, it lays the fundamental structure for the project

manager to develop and execute the project plan.

The project cycle is the basis for the project manager to develop the project plan. The

Business aspect involves all the operational functions that relating to the overall business

management of the project issues from the perspective of customer management,

justification of the project. Whereas, Budget aspect involve events related to the

requisitioning of the project funds and its management throughout the life of the project

implementation. Whereas, Technical aspect identifies the list of activities and events

required to provide the optimum technical solution in the most efficient way. The

technical aspect spans from the determination of what our client wants to validation the

project solution that satisfies our clients. The below illustration will give a more concise

concept on the three aspects from our company perspective on this project.

Business aspect: Being labeled as medium-sized event company, we are lack of multi-

national company’s event to our portfolio to showcase our success. The milestone project

with Hiticha provides us with the opportunity to break-through our currently status and to

advance into the multi-national company market. It is very much critical that we can

clinch this project.

Budget Aspect: “Starry Starry Night” is an outdoor event, which is also the 15th years

anniversary celebration of the Hiticha company. It is expected to cater for about 500

guests. Our client has mentioned that they will be investing a considerable sum of £

120,000 for this event, however they also wish we able to assist them to reduce some

unnecessary cost for this project. While we are aiming at a forty percents profit from the

entire project, we will attempt to assist our client in reducing their cost. However, in

order for our company to have better case flow during the implementation period, as per

proposed contract, the payments will be made to us by 2 installments, which is 60%

follow by 40% of the total proposal cost. The first payment will be made to us when we

sign the official contract, while the second payment will be the day after the event. With

14

Page 15: Assignment - Project Development and Implementation for Strategic Managers

the first installment being received, we will have sufficient cash flow to carry out this

project.

Technical Aspect: One of the deciding factor for the project to be considered as

successful lies on the satisfaction of our clients. The smile on our client face, after the

event, is the deciding factor. Our challenge is to ensure that the setting is to be done as

per the expectation of the given theme, creating the right atmosphere for the guests,

within the given timeline.

In order to meet the above objectives, the following portions will highlight on the each of

the cycles. Basically Business, Budget and Technical cycle are each made up of three

periods, study, implementation and operation periods, which will be illustrated in the

later part

Project management, planning and implementation cycle:

Project management and planning coordinate and optimize the resources necessary to

successfully complete a project. The resources referring to are manpower, skills, budget,

commitment, systems and equipment. Goal of planning is to meet project objectives -

meeting company and client's requirements. Project plan coordinates and optimizes

coordination, mitigating risk and plan for contingencies. Importantly, it aims to obtain

commitment from team members to see through the project from planning to operation

and disposal. The plan puts in-place a control system to ensure for accountability of

processes and expenditure, meeting schedules and clarity.

For the project to be successful and achieve the given objectives, it is critical to

understand and plan our project cycle. Project cycle is defined as an orderly sequence of

integrated activities, performed in phases, leading to success (Forsberg, Mooz and

Cotterman, 2005). Like all projects, we will need to break down our project cycle into

three aspects – business, budget and technical. The team should see project cycle as the

foundation for achieving predictable performance which is tailored with special

characteristics. The resultant project cycle then becomes the parent or driver of the

15

Page 16: Assignment - Project Development and Implementation for Strategic Managers

project’s logic network – represented by PERT and GANTT charts that will be developed

during the planning. (Forsberg, Mooz and Cotterman, 2005) The project cycle should be

planned throughout the study period, implementation period and operation period.

16

Page 17: Assignment - Project Development and Implementation for Strategic Managers

AC (2.2): M atch appropriate resources to the project.

SL. Deliverable Quantity Purpose

1. Contract of service provision 1 set Event Setup

2. Venue for conduct of event 1 set Event Setup

3. Tentage for conduct of event 1 set Event Setup

4. Stage in tentage 1 set Event Setup

5. Activities area 1 set Event Setup

6. Dining area 1 set Event Setup

7. Games booths 6 Booths Event Setup

8. Pot-flower & plants TBC Decoration

9. Directional signs TBC Logistic

10. Mobile generator 2 Power supply

11. Prizes for games TBC Logistic

12. Customized gift TBC Logistic

13. Customized balloon TBC Decoration / special effects

14. Invitation card 550 Logistic

15. License for usage of copyright media 1 Special effects

16.Eight-Course Dinner with alcoholic

and non-alcoholic drinks1 Dinner

17. Audio system amplifier 1 Special effects

18. Audio Mixer & equalizer 1 Special effects

19. Speakers with stand 6 Special effects

20. Wireless microphones with stand 4 Special effects

21. Wireless microphones (hands-free) 2 Special effects

22. Audio Technician 4 Special effects

23. Dancing-man tube 6 Special effects

Continued

SL. Deliverable Quantity Purpose

17

Page 18: Assignment - Project Development and Implementation for Strategic Managers

24.City color architectural lightings 4 Special effects

25.MAC-700 intelligent spot lightings 10 Special effects

26. AVOLITE PEARL 2000

intelligent stage lighting controller1 Special effects

27. Digital video camera with camera

man1 Broadcasting

28.Rear screen projectors 6 Special effects

29.Photographer 2 Photography

30.Emcee 2 Entertainment

31.Standup comedy 1 Kumar - 20 mins

32.Singing 1 Olivia Ong - 3 songs

33.A3-size poster 30 Decoration

34.Banner (4ft by 2by) 3 Decoration

35.Banner (6ft by 3ft) 3 Decoration

36.Live Feed Photo Shoot 1 Decoration

37.Tattoo Dauber 1 Entertainment

18

Page 19: Assignment - Project Development and Implementation for Strategic Managers

38.Who Dares To Win games 2 Entertainment

39.Magic Performance 1 Entertainment

40.Bhangara Dancers 1 Entertainment

41.Shaolin Matrix 1 Entertainment

42.Street fusion 1 Entertainment

43.Confetti cannon 10 Entertainment

44.Carbon desire TBC Entertainment

19

Page 20: Assignment - Project Development and Implementation for Strategic Managers

AC (2.3): C ost all resources required for implementing a project.

SL. Detail Description Proposal to Client (£) Cost (£) Profit (£)

1.

Provision of Stage & deco for event

inclusive of: Food Catering at events

hall for 500 pax

27,500 20,000 7,500

(A) Portable rental stage 9,500 5,000 4,500

(B) 1 set of 3 dimension Backdrop

and entrance specially design for

event

6,500 3,500 3,000

(C) Decoration of event areas 5,500 2,000 3,500

2.Audio Visuals Productions inclusive

of electricity supply18,000 6,000 12,000

3. Photography and Videography 3,500 2,500 1,000

4. EMCEE and show productions 4,500 2,800 1,700

5.Celebrity Acts – Kumar & Olivia

Ong5,500 2,800 2,700

6. Licenses and Fees 1,000 300 700

7. Promotion of Event 1,000 500 500

8. Pre Dinner Entertainments 3,500 2,000 1,500

9. Spectacular Special Effects 4,000 2,500 1,500

10.Professional Events Mgmt.

(Manpower Cost)10,000 6,000 4,000

11.

Fixed hidden cost inclusive: wages,

project incentives for staffs,

transports allowances, etc

N/A 2,600 (2,600)

12.

Various hidden cost inclusive:

printing, entertainment fees, OT

wages, etc

N/A 1,500 (1,500)

Total 100,000 60,000 40,000

20

Page 21: Assignment - Project Development and Implementation for Strategic Managers

AC (2.4): A gree timescales for the management and implementation of a project.

SL. Task Name Duration Start Date Finish Date

1. START 0 days 18-Sep 18-Sep

2. Meet clients for theme and budget 1 day 18-Sep 18-Sep

3. First budget drafting 2 days 19-Sep 22-Sep

4.Brainstorming for program activities &

games2 days 23-Sep 24-Sep

5. Proposed ideas and venue 2 days 25-Sep 26-Sep

6. source quotation 3 days 29-Sep 01-Oct

7. Evaluation of budget 1 day 02-Oct 02-Oct

8. segregation of task for proposal 2 days 29-Sep 30-Sep

9. consolidation of information 1 day 01-Oct 01-Oct

10. confirmation of final proposal 1 day 03-Oct 06-Oct

11.final budget draft & breakdown budget

draft1 day 06-Oct 07-Oct

12. presentation to client 1 day 07-Oct 08-Oct

13.negotiation with client & revision of

proposal3 days 08-Oct 13-Oct

14.finalization of proposal and theme

concept1 day 13-Oct 14-Oct

15. draft agreement 1 day 14-Oct 15-Oct

16. legal consultant 2 days 15-Oct 17-Oct

17. endorsement of contract 1 day 17-Oct 20-Oct

18. receive of first payment 7 days 20-Oct 29-Oct

19. source of venue 2 days 14-Oct 16-Oct

20. tentative booking of venue 1 day |16-Oct 17-Oct

21. confirmation of venue 1 day 29-Oct 30-Oct

22. selection of Project Team member 2 days 20-Oct 22-Oct

23. formation of sub team 1 day 22-Oct 23-Oct

24. design of games and activities 2 days 31-Oct 04-Nov

Continued

21

Page 22: Assignment - Project Development and Implementation for Strategic Managers

SL. Task Name Duration Start Date Finish Date

25. site visit to the venue 1 day 30-Oct 31-Oct

26. design of general floor plan 5 days 31-Oct 07-Nov

27. design of stage and dinner table layout 3 days 07-Nov 12-Nov

28. booths and game activities layout 3 days 07-Nov 12-Nov

29. cable and power point layout 3 days 12-Nov 17-Nov

30.verify no. of pot-flower & balloons

required2 days 17-Nov 19-Nov

31. design of signage 2 days 19-Nov 21-Nov

32. confirmation of contractor 1 day 17-Nov 18-Nov

33. preparation of construction material 7 days 21-Nov 02-Dec

34.construction of tent age and power

cables1 day 02-Dec 03-Dec

35. selection of prizes and gifts 3 days 04-Nov 07-Nov

36. design of customized gift 4 days 07-Nov 13-Nov

37. making of customized gift and balloons 7 days 19-Nov 28-Nov

38. collection of customized item 2 days 28-Nov 02-Dec

39. design of invitation card 3 days 23-Oct 28-Oct

40. printing of invitation card 5 days 28-Oct 04-Nov

41. sending of invitation card to client 1 day 04-Nov 05-Nov

42. application of required license 8 days 07-Nov 19-Nov

43. selection of food caterer 2 days 23-Oct 27-Oct

44. food tasting with client 5 days 27-Oct 03-Nov

45. confirmation of food caterer 1 day 03-Nov 04-Nov

46. source of entertainers 10 days 04-Nov 18-Nov

47. confirmation of entertainers 5 days 18-Nov 25-Nov

48. design of entertainer dressing 5 days 25-Nov 02-Dec

49. Rehearsal 5 days 03-Dec 10-Dec

50. Actual day of event 0 days 10-Dec 10-Dec

22

Page 23: Assignment - Project Development and Implementation for Strategic Managers

AC (2.5): P lan an appropriate strategy for the implementation of a project.

Functions of strategy planning:

1. Planning a vital aspect of management, serves several important functions.

2. It provides basis for organizing the work on the project and allocating

responsibilities for the individuals.

3. It is a means of communication and coordination between all those involved in

the project.

4. It induces the people to look ahead.

5. It instills a sense of urgency and time consciousness.

6. It establishes the basis of monitoring and control.

Areas of strategy planning:

1. Planning the project work.

2. Planning the resources and organization.

3. Planning the money.

4. Planning the information system.

Steps in project strategy planning:

1. Setting the project objectives.

2. Identifying the work activities.

3. Creating the project organization.

4. Preparing project schedule.

5. Making budget and resource plan.

6. Preparing forecast of time, work, cost and performance projections.

Project objectives and Strategies:

Often, the focus of project planning is on questions like who does what and when. Before

such operational planning is done, the objectives and policies guiding the project

planning exercise must be articulated. The questions to be answered in this context here:

1. What are the technical and performance objectives?

23

Page 24: Assignment - Project Development and Implementation for Strategic Managers

2. What are the time and cost goals?

3. To what extent should the work be given outside contractors?

4. How many contractors should be terms of contract?

Well-defined objectives and policies serve as the framework for the decisions to be made

by the project manager. Throughout the life of a project, he has to seek a compromise

between the conflicting goals of technical performance, cost standard, and time target.

Work breakdown structure:

The work breakdown structure, as its name suggests, represents a systematic and logical

break down of the project into its component parts. Thus breakdown structure helps in:

1. Effective planning by dividing the work into manageable elements, which can be

planned, budgeted, and controlled.

2. Assignment of responsibility for work elements to project personnel and outside

agencies.

3. Development and control and information system.

Essentials strategies for successful project implementation:

1. Adequate formulation.

2. Sound project organization.

3. Proper implementation planning.

4. Advance action.

5. Timely availability of funds.

6. Better contract management.

7. Effective control and monitoring the progress of the project.

24

Page 25: Assignment - Project Development and Implementation for Strategic Managers

AC (3.1): I mplement a project in accordance with an agreed specification.

Implementation Period:

As the project moves into the implementation period, the project manager needs to

translate organizational business strategy into directions and instructions to the project

team. This is a critical task for the project manager. When the scope of undertaking is as

clear as crystal, the team can focus and optimize resources to achieve the stated

objectives. Although timeline and budget given may be tight, the project manager should

not compromise the quality of the event. Instead, he is required to manage the risk

involved / assessed in the project. The project risk management will be discussed in detail

in the later part.

As budgeted, this project will require us to be spending a considerable sum of money;

therefore the project manager can try to improve relationship with our entertainers,

suppliers and venue owners while bargaining for the best value contract for the project.

For example, we will be engaging famous celebrities like Kurman and SINGER – to

make the event looks prestigious, it will be promotes the company’s image if the

celebrities are to comment well on our project. Also, the project manager will need to

ensure that the project is proper licensed with the rights to play music, MTV or fireworks.

The concept of this arrangement is because our client, Hiticha Group will be inviting

their top clients and business associates from the region to attend this event. Therefore, it

is critical for the project manager to make the event grand so that the guests will feel the

importance of their presence in this event which is the primary reason. This will ensure

these top clients and business associates to feel pampered and indulged themselves during

the entire event. Meanwhile, we would be able to build rapport between us and the guest

as this will aid in our business expansion through the conduit of our customers’

networking as well as enable us to explore the opportunity to gain more sales pipelines

for future projects.

25

Page 26: Assignment - Project Development and Implementation for Strategic Managers

Lastly, the business decision gates lie on the shoulder of the project manager, with the

assistant of the advisory panel. They should be informed with any hiccups or changes

during the project. The project manager needs to be in control and stay in control while

overseeing the overall activities.

Operation Period:

During the rehearsal and the day of the event, we continue to liaise with contractors for

on-site support. All defects reported are to be rectified immediately. At the same time, the

project team will continue to evaluate the performance of the contractors. The evaluation

will aid the company to retain and improve industrial relationship with reliable

contractors. For cost effectiveness and ensure reliability, our top management may

consider negotiating for a term contact with selected contractors.

After the successful conduct of the event, the project team will be gathering client’s

feedback. Project Manager will also consolidate lessons learnt for better improvements in

future events. A final evaluation is whether key performance indicators, such as meeting

company’s objectives are met. This report will aid in faster evaluation on feasibility for

similar projects.

26

Page 27: Assignment - Project Development and Implementation for Strategic Managers

AC (3.2): D evelop appropriate measures to monitor and evaluate progress and

outcomes.

As mentioned in the risk management, it is important that the project is closely

monitored. However, the rationale of having a project tracking and reviewing process is

to ensure the four major project variables – performance, cost, time and scope are been

taken care of and well monitored by our company throughout the whole project. This is

important especially when the project has advanced to the phase of performance, having a

consistent and constant flow of information on the actual and accurate status of the

project would be essential. Furthermore, reviewing also play an important role in working

hand in hand with both tracking and monitoring as well in the project. This is to ensure

all issues have been addressed during the process.

The key elements in the project that are required for tracking purpose include:

• Scope of Work

• Project Functional

• Success Factors

• Work Breakdown Structure (WBS) – Activity list and network

• Work Packages for critical path tasks to develop an additional level of detail

• Budgets and Estimates

• Master and supporting schedules

• Financial and funding plans

• Quality and Configuration Management Plans

• Stakeholder Analysis, including management and clients

The Management functions of tracking and monitoring are indispensable to the effective

and efficient control of the project. In another word, tracking is been defined as the fact

finding process whereas monitoring is the analysis of these facts. Both are required for

the management of the project.

27

Page 28: Assignment - Project Development and Implementation for Strategic Managers

The Card-On-Wall (COW) methodology will be used during the implementation period

to facilitate monitoring of the overall progress. OBS, WBS, PPL, network diagrams,

estimated budget allocation and schedules using PERT and CPM will be made available

on the server. This is to facilitate easy access for the top management and project team. In

addition, team members will be submitting Weekly Update Reports (WUR) to the project

manager. The WUR is a simple report that reports the status of the each task, the task

owner and the expected time of completion. Team members may include pictures or use

any means to provide these information. Team members are encouraged to do open

reporting on any problems, especially problems that occur in the critical path. The Project

manager is expected to look into the problems and resolve it as soon as possible. If

further endorsement is required, the Project Manager is encouraged to approach the top

management, such as the Chief Operations Officer (COO). The Project Manager will also

be providing a fortnightly report to the COO. The report focuses on the planned schedule

and expenditures against the actual schedule progress and expenditure. The changes in

client’s requirements and the related actions taken are also reported in this report.

28

Page 29: Assignment - Project Development and Implementation for Strategic Managers

AC (3.3): M onitor the implementation of the project.

The most dreadful incident that could happen to an event company is failing to meet the

deadline given by our clients. In our case, the entire team is to work closely and

effectively to ensure that this event will be ready by 10th Dec 2011 - as set by our client.

In order to reduce the possibilities of failing to meet the deadline, we have planned out

the scheduling of each activity, the inter-relationship of individual activity and given a

timeline to each activity. However, according to our PERT calculation, there is a

possibility that our project can be delayed by 4.14 days. Therefore, the project is to be

completed on 4th Dec 2011, which is 4 working days before the actual event. Hence, we

have planned the rehearsal to be held on 3rd Dec 2011, with 5 days of time allowance for

completion.

Even with additional time allowance, we can still be in the danger of failing to meet the

deadline if each activity is not carried out within their given timeline, specially the

activities found within the critical path. Since we are unable to forecast or prevent

mishaps, we have opted to be safe than sorry. While we are working out on the Gantt

chart, we have given more timeline to activities, which have more likelihood to be

delayed.

With reference to the above network diagram and grant chart, we have noticed that there

is a timing lapse between both the critical path and non-critical path. In another word,

there might be some delays that hold up or slow down the whole process. Hence, for

example, the construction of tentage and installation of power cable are the activities

which fall under the critical path. These two activities supposedly to be completed by 3rd

Dec 2011. However, due to unforeseeable circumstances like raining on the day that we

plan to set up of tentage. This will eventually leads to the delay of setting up the tentage

and delay in installation of sound systems and stage setup etc. The whole process is

disrupted which causes the planning to be delayed as well as affected the whole progress

of implementation process. Thus, our deadline might not be meets as result we are not

29

Page 30: Assignment - Project Development and Implementation for Strategic Managers

able to complete the project as schedule or plan. Whereas, the non critical path activity

like collection of customized gifts have been deferred to another date due to the delay in

shipment that causes the original collection date schedule to be delayed rather than

completed by 2nd Dec 2011 - the actual collection date. But, it does not disrupt the

whole progress as the other functions still able to carry out without delay. Hence,

precautionary measurement has been taken into account as we arranged the tentage to be

set up by at least one day earlier than the actual plan as this will helps to prevent the

disruption of the critical activities like raining. The early setup of tentage will act as a

buffers, this is to prevent unforeseeable circumstance for disrupting the progress or delay

of the whole process.

With the above precautionary measurements, we believed that we will be able to meet

our deadline or finish the event early which won’t fail the expectation that our clients

have in us.

30

Page 31: Assignment - Project Development and Implementation for Strategic Managers

AC (4.1): A nalyze the outcomes of a project in terms of the original project

specification.

The accomplishment of this project provides many benefits to the company. Besides

having a higher reputation for events planning services, there will be a boost in

company’s revenue and sense of achievement in employees. Essential to the growth of

the company, the knowledge management processes will aid future project teams in

managing similar projects, improving cost effectiveness and work efficiency.

31

Page 32: Assignment - Project Development and Implementation for Strategic Managers

AC (4.2): E valuate the outcomes of a project.

One of the main concerns with regards to this project is on the accuracy of the project’s

budgeting plan. The objective is to create an accurate and well monitored budget plan, in

order to reduce the risk of getting into cash flow difficulties or over-spending the given

budget.

In order to meet the clients expectation and given event theme, we will be engaging

external companies to perform several activities and to custom-make gifts and decoration

items. As we have forecasted that the number of items required and its quantity and

quality required may varies, it is critical for our logistics and external liaison team to be

precise on the quotations gathered during the sourcing phase in the study period. Such

variable cost includes the entertainers’ fees, cost to customize-make items, cost of

construction, cost of printing and cost of external manpower. The logistic team is to

tabulate a project product list as according to projected quantity and quality. Whenever

there is any update or changes to the project product list, our logistic team is to notify the

finance department. The finance department’s role is to control and monitor the

budgeting. We will discuss on the methods of monitoring in the later part.

Based on the information and quotation gathered, the finance department, together with

the project manager will draft out a budget proposal which include the project cost,

proposed pricing for client and estimated profit. This budget plan has to be reviewed and

agreed by all other departments, especially the logistic department. The project manager

and the external liaison team will liaise with the client to confirm on the pricing and

revised the plan if necessary. Upon endorsement of contract, client will be invoiced with

60% of the contracted price and remaining balance on a later date. To ensure a flow cash

flow, the estimated date of payment received from client is scheduled to be ahead of the

estimated date of payment payable to the external parties. By doing so, we can be ensured

that our finance department have the cash available for any out-going payment required,

if the budget is well-maintained.

32

Page 33: Assignment - Project Development and Implementation for Strategic Managers

AC (4.3): M ake justified recommendations for improvements to the project.

Based on our experience, one of the factors that can cause an event to fail is due to the

client’s expectation and requirement. Although being contracted, most clients have the

habits of making last minutes changes to the theme or requirements. If the project

manager fails to cater sufficient timeline within the project scheduling, the project will

fail either in terms of meeting the deadline or meeting the client’s expectation. As the old

saying goes “Customer is always right”, we have to anticipate any changes, which our

client will have and ensure that there is always sufficient time to work on the changes

incurred.

To avoid the unpleasant situation, it is the responsibility of our external liaison team to be

in constant contact with our client, updating them on our current process and informing

that the upcoming process. This allows our client to alert us before hand on the changes,

which they have in mind. Also, external liaison team will constantly remind the client on

the timeline given to them for making changes before we execute each important activity

like design of gifts or arrangement of floor plan. Meanwhile, we will be closely

monitoring the timeline and progress advancement that set by us internally in order to

have more buffers when required as well as from our clients. This is to prevent us from

having any hiccups or letting our clients to have any unpleasant experience with us.

Building a good rapport with clients will enable us to give them a sense of satisfactory

and that is what our company have been emphasizing.

33

Page 34: Assignment - Project Development and Implementation for Strategic Managers

AC (5.1): P roduce a report of all project procedures used.

Before the project commence, the event manager and the team members are identified as

early as possible. This is because the team members are chartered from various

departments in the company. Early identification allows event manager and department

managers to manage work load of the team members. In the company, the matrix

functional structure is always adopted. Employees from various departments are assigned

to be team members in project teams. This is because they are in the best position to

assist the project team in their primary scope of work. Hence, for example, an accountant

is assigned to manage financial accounting and payments for the event. With all the

required staffing, the Organization Breakdown Structure (OBS) provides the reporting

structure for the project. Importantly, it identifies the all group members, stake holders

and management. It is the structure that to organize the project team. The organization

structure provides one of the fundamental structures to support the project through its

project cycle.

From the PPL listed, the Work Breakdown Structure (WBS) is used to assist the project

team to allocate budget, assign tasks and scheduling. It is also developed to provide an

effective visual overview of identifying of tasks, statuses and task owner. The WBS

diagram, as below, is divided in four main categories of work – Venue Setup,

Entertainment, Food and Beverage and Industrial Relations. Industrial Relationship is an

important component to ensure continuous communication with the clients,

understanding and managing client’s requirements, and translating into time, cost and

tasks. In addition, task owners help to market the company’s services. Another category,

Venue Setup, is essential as the foundation for the rest of the activities to fall in-place.

Achieving the theme at the beach is unique and challenging, and requires a lot of

resources. The entertainment category also consists of resources. It is also the key

performance indicator for our company to make the mark in Hitacha and their business

partners. The fourth category is Food and Beverages, which is baseline for customer

satisfaction.

34

Page 35: Assignment - Project Development and Implementation for Strategic Managers

Each category of work in the WBS is further broken down into sub-categories and

eventually into tasks. WBS dictionary and WBS package compliments by further

elaborating on the tasks. The WBS dictionary defines the tasks, task requirements and

expectations in the WBS. The WBS package states the critical information about

completing the task. Such critical information includes the dates for commencement and

completion, task owner, allocated budget and conditions. The comprehensive WBS helps

the event manager to identify the tasks which are critical to fulfil the requirements for

each system or activity. During the initiation ceremony, the WBS will be signed off by

the process owners, signifying top management’s recognition and commitment to the

team members. Intangibly, the signing-off event harnesses organizational commitments

from task owners. The WBS will be placed on the company’s server for easy access to all

team members and top management. This enhances communication and better

understanding among top management and project team.

From the work breakdown structure (WBS), the project manager will allocate the

members with responsibility that suit the team member’s capability. Based on their job

scope, each member will attempt to assist the client’s D&D committees in their concept

planning, coordinating, and sourcing for alternative resources during the implementation

period. The purpose is to show our clients what we are capable of. As one of the main

objective to the create the special effects for the theme, it is essential for the logistic team

to design and build the special effects lighting in order to lift up the atmosphere and the

moods of the audiences. The setting of the special effect and lighting will be pre set up

and test during the rehearsal, prior to the actual event.

35

Page 36: Assignment - Project Development and Implementation for Strategic Managers

AC (5.2): P resent the outcomes of the project to an audience using an agreed format

and appropriate.

A competent project manager is selected to lead the biggest event for our company. It

will be an opportunity to develop the company’s profile and improve reputation. With

commitment from top management, the project manager leads the team in proposing a

unique and feasible theme to clinch the deal. To ensure highest success rate, the project

managers will develop a detailed and comprehensive project development plan. Risks

will be identified and mitigated. Control measures will be put in-place to monitor and

react to problems as soon as possible.

The accomplishment of this project provides many benefits to the company. Besides

having a higher reputation for events planning services, there will be a boost in

company’s revenue and sense of achievement in employees. Essential to the growth of

the company, the knowledge management processes will aid future project teams in

managing similar projects, improving cost effectiveness and work efficiency.

36

Page 37: Assignment - Project Development and Implementation for Strategic Managers

References:

Forsberg, K. & Mooz, H. & Cotterman, H., 2005. Visualizing Project Management. 3rd

ed. USA: John Wilsey & Sons, Inc.

Allen, J., 2004. Marketing Your Event Planning Business. Canada: John Wilsey & Sons,

Inc.

Rounds, M., 2004. Common Sense Project Management. UK: Prentice Hall.

Young, T.L., 2001. Implementing Projects. London: The Industrial Society.

Phillips, J.J. & Zuniga L., 2011. Cost and ROI. USA, John Wilsey & Sons, Inc.

http://wiki.answers.com/Q/What_are_the_factors_affecting_business_decisions

http://www.ehow.com/how_5936144_monitor-project-progress.html

http://www.management-hub.com/project-plan-implementation.html

http://www.projecttimes.com/articles/10-steps-to-creating-a-project-plan.html