APPENDIX C2
Construction Methodology Statement
Construction & Delivery Statement DIRFT III October 2012
DIRFT III : Construction Methodology Statement
3180111v1
Contents
1.0 Introduction 1
2.0 Programme of Works 2 Timetable 2
3.0 Description of Works 5 Earthworks and cut-and-fill 5 Demolition and site clearance 5 Construction of rail and rail bridges 6 Construction of roads, sewers and services (transport and utilities infrastructure) 7 M1 boundary works 7 General construction works 8
4.0 Site Logistics 9
5.0 Environmental Mitigation Measures 11 Construction Environmental Management Plan 11 Waste management and minimisation 12 Traffic and access management 13 Control of noise, vibration and dust 13 Pollution Control 13 Considerate Constructor Scheme 14 Communication Strategy 14
DIRFT III : Construction Methodology Statement
3180111v1 P1
1.0 Introduction
1.1 The Infrastructure Planning (Environmental Impact Assessment) Regulations 2009 (as amended in 2012) require that both the permanent and also temporary environmental effects of a development are assessed. To assist in identifying the effects arising during the construction phase, this statement establishes the key construction parameters that will be used to bring forward the construction of the scheme.
1.2 At this stage of carrying out the EIA, a contractor has not yet been appointed to undertake the construction works. However, the information and parameters within this document will form part of any tender documentation issued and the appointed contractor will be required to comply with the outline methodology described, as well as in any relevant requirements of the Development Consent Order (DCO).
1.3 This statement describes the anticipated programme of demolition and construction works and the key activities that will be undertaken on the site in relation to the development.
1.4 The broad principles of a framework site wide Construction Environmental Management Plan (CEMP) are identified in Section 5.0 of this report. As part of the tendering process the main contractors will be required to submit a statement demonstrating how they will comply with the CEMP and, after appointment, provide detailed documentation to demonstrate this compliance.
DIRFT III : Construction Methodology Statement
P2 3180111v1
2.0 Programme of Works
Timetable
2.1 Given the scale of the proposed development, it is the current expectation that the construction will take approximately 17 years. Whilst the construction work is likely to be broadly continuous, with for example elements of earthworks, landscaping and infrastructure provision overlapping, for the purposes of assessment it has been divided into four broad phases of development. It is anticipated that Phase 1 will commence in 2014.
2.2 The phasing plans for the proposals are provided at Appendix 1 to this document.
2.3 Each phase will consist of infrastructure works to prepare the land prior to built development being commenced. A broad timetable for all four phases is identified in Table 2.1 below.
Table 2.1 Sequence of works for the development
Phase Date Detail
2014-2016
Infrastructure works
See below for further details
1
2015-2016
Development
Up to 100,000 sqm of storage, distribution and industrial units with ancillary office accommodation.
2016 Infrastructure works
See below for further details
2
2016-2019
Development
Up to 120,000 sqm of storage, distribution and industrial units with ancillary office accommodation.
2019-2022
Infrastructure works
See below for further details
3
2019-2026
Development
Up to 300,000 sqm of storage, distribution and industrial units with ancillary office accommodation.
2025-2026
Infrastructure works
See below for further details
4
2026-2031
Development
Balance of storage, distribution and industrial units with ancillary office accommodation.
Phase 1 Works
1 Ecological and archaeological investigations
DIRFT III : Construction Methodology Statement
3180111v1 P3
2 Earthworks
3 Ground investigations
4 Ecological licensing trapping and translocation
5 Offsite electricity supply and primary sub-station
6 Demolition of masts, farm houses and B Station
7 Decommissioning of existing telecoms infrastructure and other services
8 Lilbourne Meadows earthworks (Stages 1 and 2) and associated landscaping and habitat creation
9 Landscaping including A5 and M1 boundaries landscaping
10 Roads
11 Sewers and services both on and off site
12 Access roads and haul routes
13 Phase 1 rail works (extension of single line branch across the A5, commencement of Phase 1 intermodal sidings).
14 Phase 1 rail bridges: new bridge crossing the A5, new bridge crossing internal road, 3 nos. bridleway bridges.
15 Rail control building
16 Path diversions
Phase 2 Works
1 Earthworks and associated archaeological investigations to include excavation in other zones that have been cleared of ecology to secure fill material
2 Roads, sewers and services, access roads and haul routes (including new roundabout on the A5 to provide access to DIRFT III)
3 Lorry Park (first phase)
4 Completion of Phase 1 rail works (Rail hub building 4 nos. intermodal sidings, warehouse sidings as required and first gantry cranes)
5 DIRFT III Terminal access
6 Move rail operations to new terminal
7 Existing Railport removed once Phase 2 of rail works is completed and rail operations moved to new terminal
8 Landscaping works
9 High pressure gas pipe diversion
DIRFT III : Construction Methodology Statement
P4 3180111v1
Phase 3 Works
1 Landscape works
2 Earthworks and associated archaeological investigations to include excavation in building zones F & G to secure fill material for Stage 2 built area
3 High pressure gas pipe diversion if not carried out in Stage 2
4 Roads, sewers and services
5 Lorry Park (second phase)
Phase 4 Works
1 Phase 3 rail works (twin track from reception sidings to DIRFT III including reconstruction of A5 box to accommodate twin tracks and new viaduct or embankment adjacent to DIRFT II if necessary)
2 A428 bridge and A5 bridge twin tracking works if required
3 Landscape works
4 Earthworks and associated archaeological investigations
5 Completion of M1 boundary works
6 Roads, sewers and services
DIRFT III : Construction Methodology Statement
3180111v1 P5
3.0 Description of Works
3.1 The following provides a broad description of the likely nature of activities for the different workstreams included in the construction of DIRFT III.
Earthworks and cut-and-fill
3.2 Firstly, ecological habitat creation works will be undertaken to provide an appropriate environment for newts. Amphibian fencing will be erected, and the newts collected and translocated to the new habitat. When the area is cleared haulage routes will be determined, established and maintained as far as possible to minimise reversing. Fencing will be positioned to create safeworking zones as well as to provide an on-going protection for amphibians. Other areas that are outside the works will be fenced. On site haul roads and bridges will be constructed at agreed locations.
3.3 The areas to be excavated will be set out by the Contractor. After confirmation that the site is clear of protected species, remaining masts and other buildings will be demolished and services will be decommissioned. Topsoil will be then stripped and taken to stockpile for re-use on the development or direct to the Lilbourne Meadows ridge. Material will be excavated using excavators bulldozers, scraper boxes and where appropriate loaded onto dumper trucks to areas of fill.
3.4 Fill material will be compacted in accordance with an appropriate earthworks compaction plan to achieve primary earthworks plateau levels.
3.5 Whilst the cut and fill is planned to achieve a balance, if there were to be any surplus excavated material, disposal would be carried out by appropriately licensed contractors to disposal sites licensed to accept material of the quality excavated.
3.6 Table 3.1 below shows the anticipated overall volumes of cut and fill.
Table 3.1 Anticipated earthworks volumes
Topsoil cut (m)
Topsoil fill (m) as landscaped ridge or re-used in landscaped areas
Structural cut (m)
Structural fill (m)
686,000 686,000 3,024,000 3,024,000
Demolition and site clearance
3.7 During site preparation, appropriate security fencing will be erected in order to maintain site security and safety around the construction areas.
DIRFT III : Construction Methodology Statement
P6 3180111v1
The fencing will be maintained throughout the construction of the works in question to ensure safety of the public and visitors.
3.8 Demolition will be carried out in accordance with relevant legislation current at the time of the demolition, and with standard industry procedures.
3.9 Existing services on the site will be surveyed, tested and diverted or cut off as appropriate. Key and retained services will be temporarily protected and weather proofed to ensure a safe clearance process.
3.10 Prior to demolition of any buildings, internal soft furnishing will be stripped and removed. An intrusive inspection will also be undertaken to identify the presence of any potential hazardous materials, including asbestos. If found present, these will be removed from the site and disposed of by appropriately licensed contractors following prescribed health and safety procedures.
3.11 Throughout the demolition process, materials will be carefully selected and sorted for re-use, recycling or sensitive disposal. It is anticipated, subject to approval by relevant authorities, that some materials can be retained on site and crushed to provide recycled materials.
3.12 Table 3.2 provides an indication of the major types of materials likely to arise from demolition.
Table 3.2 Indicative materials arising from demolition
Material Material sources
Concrete Superstructures, floor slabs, retained walls
Brick External and internal walls
Glass Windows
Metal components Windows, plant, superstructures
Timber and plasterboard Partitions and ceilings
Hardstanding, tarmac Internal pathways, car parks
Earth spoil Excavation
Steel Radio masts
Construction of rail and rail bridges
3.13 A rail bridge will be constructed over the route of A5 to form part of the new railway infrastructure.
3.14 The rail link will connect to the existing rail link at the northern end of DIRFT II, before passing over the A5 via the new bridge and descending into the new rail terminal at the heart of the DIRFT III site. Here the railway will fan out to provide eight new rail sidings flanked by container stacks and HGV roads. Rail mounted gantry crane rails will be installed within the terminal and the gantry cranes will also be assembled on site.
DIRFT III : Construction Methodology Statement
3180111v1 P7
3.15 A rail control building will also be constructed, to include a control room, estate management offices, meeting rooms and other welfare facilities.
3.16 One rail bridge crossing an internal road and 3 nos. bridleway bridges will also be built.
3.17 The rail infrastructure will be delivered during Phases 1, 2 and 4 of the assumed construction programme to match demand.
3.18 Phase 1 comprises extension of a single line branch across the A5, construction of Phase 1 intermodal sidings, locomotive stabling and servicing facilities, a new bridge crossing the A5, a new bridge crossing an internal road and 3 nos. bridleway bridges.
3.19 Phase 2 comprises 4 nos. intermodal sidings and 2 nos. warehouse sidings.
3.20 No rail works are anticipated during Phase 3 of the construction programme.
3.21 Phase 4 includes twin tracking from the DIRFT II reception sidings, including the reconstruction of the A5 box to accommodate twin tracks, twin track works to the A428 and A5 bridges and a new viaduct adjacent to DIRFT II.
Construction of roads, sewers and services (transport and utilities infrastructure)
3.22 A network of internal access roads will facilitate access within the site and serve each building, linking to individual service yards and car parking.
3.23 The scheme includes the creation of a network of footpaths and cycleways connecting to the surrounding area.
3.24 The roads will be built to appropriate standards. The roads will be constructed by approved contractors who will be required to follow best practice guidelines and ensure that road users both within and external to the Site are not unduly affected by the construction process.
3.25 During construction a number of access and haul roads will be established to support each stage of delivery.
M1 boundary works
3.26 The development includes the lowering of site levels by up to 20m in the vicinity of the M1 boundary. Material will be excavated from parts of the site near the boundary and cutting slopes constructed to the existing site boundary. The cutting slopes and retaining walls will be designed to ensure stability of the M1 to Highways Agency standards.
DIRFT III : Construction Methodology Statement
P8 3180111v1
3.27 There is also a proposed localised diversion of a bridleway to run along the boundary of the DIRFT site and the M1.
General construction works
Warehouses
3.28 Distribution warehouse units will be built as stand alone units or linked to the new intermodal sidings and railway sidings. Each unit will have a loading dock and service yard.
Lorry Park
3.29 The Lorry Park will provide spaces for over 300 lorries. It will include a rest area with showers and toilets.
DIRFT III : Construction Methodology Statement
3180111v1 P9
4.0 Site Logistics
Plant and equipment
4.1 Consideration has been given to the types of plant and equipment that are likely to be used during the demolition and construction works. An indication of typical types of plant and equipment associated with each key element of the construction process is set out within Table 4.1.
Table 4.1 Indicative plant and equipment used during construction
Earthworks and archaeology
Demolition and clearance
Ground investigations &
works
Landscaping
Utilities
Construction of rail and rail
bridges
Construction of roads, sewers
and services
General construction work
Bulldozers
Lorries / vans
360 degrees excavators
Dumper trucks
Fork lift trucks
Tipper lorries
Crushers
Rollers/ Vibrating plates
Compressors
Diesel/ fuel bowsers
Cranes and hoists
Generator
Welding plant
Rail tampers
Concrete plant
Concrete splitters and saws
Cutters, drills and small tools
Hydraulic benders and cutters
Tarmac laying equipment
Scaffolding and hydraulic
access platforms
DIRFT III : Construction Methodology Statement
P10 3180111v1
Earthworks and archaeology
Demolition and clearance
Ground investigations &
works
Landscaping
Utilities
Construction of rail and rail
bridges
Construction of roads, sewers
and services
General construction work
Floodlights
Hours of working
4.2 Hours of working are the subject of a requirement. Construction work (excluding archaeological investigations, landscaping and any non-intrusive internal fit-outs) shall not take place other than between 7.30am 7.00pm weekdays and 8.00am 1.00pm on Saturdays (excluding public holidays) unless otherwise agreed in writing by the relevant local planning authority. Sunday and bank holiday working is permitted for works which do not cause noise that is audible outside the boundary of the site.
DIRFT III : Construction Methodology Statement
3180111v1 P11
5.0 Environmental Mitigation Measures
Construction Environmental Management Plan
5.1 All construction sites have the potential to cause temporary nuisance and disruption to site users, neighbouring occupants, car users, pedestrians, local wildlife and other sensitive receptors.
5.2 Each construction contract will include a contract specific Construction Environmental Management Plan (CEMP) prepared in accordance with the site wide framework CEMP which would place stringent procedural performance obligations upon Contractors. A clear management structure and description of the responsibilities and authority of a specific Environmental Coordinator would be included with all agreements. It is anticipated that regular meetings would take place to review progress and to agree necessary actions. Notwithstanding this, it is recognised that positive action and reaction by site operatives at the time of any environmental incident or breach of targets are essential components for effective environmental management.
5.3 The framework CEMP will include the following headings:
1 Site Description
2 Summary of proposed works
3 Environmental Policy
4 Environmental Management System
- Environmental roles and responsibilities of the Environmental Coordinator
- Assessment of significant environmental aspects
- Pollution control
- Wheel washing
5 Construction Traffic Routing
6 Waste and Recycling
7 Discharge to Water and Land
- Construction methods
- Construction drainage strategy
8 Noise and Vibration
- Noise
- Maintenance
- Vibration
9 Air Quality
10 Lighting
11 Ecological Management
DIRFT III : Construction Methodology Statement
P12 3180111v1
- Background
- Features of interest on site
- Applicable legislation, licences and consultation
- Implementation of mitigation works
- General ecological considerations
- Ecological monitoring of effects and control
12 Communication strategy
5.4 Individual Contracts would incorporate appropriate requirements in respect of environmental control, based largely on the standards of good working practice outlined in the CEMP in addition to statutory requirements. Contractors would therefore be required to demonstrate how they would achieve the provisions of the CEMP, how targets would be met, and how potential adverse environmental effects would be minimised.
5.5 Environmental issues would be considered in the procurement of raw materials and manufactured building components and all such materials would be appropriately stored on the site to minimise damage by vehicles, vandals, weather or theft. Pollution control would include the use of bunded compounds for the storage of tanks and drums of liquid chemicals and fuels. Packaging materials would be returned, where possible.
Waste management and minimisation
5.6 Waste would inevitably be generated during all stages of the demolition and construction works. Major sources of waste within the demolition and construction process are anticipated to include:
1 Demolition, site clearance and spoil from excavations - concrete, brick rubble, steel, plastics, wood, soil, etc;
2 Packaging - plastics, pallets, expanded foams etc;
3 Secondary waste materials generated from inaccurate ordering, poor usage, badly stored materials, poor handling, spillage etc; and
4 Measures will be taken to avoid contamination run off as set out in the site specific CEMP.
5.7 A Site Waste Management Plan would be developed by each Contractor in accordance with prevailing legislation detailing how wastes would be disposed and managed during the demolition and construction. All relevant contractors would be required to investigate opportunities to minimise waste arisings at source and, where such waste generation is unavoidable, to maximise the recycling and re-use potential of demolition and construction materials. Wherever feasible, such arisings would be re-used on the Site.
DIRFT III : Construction Methodology Statement
3180111v1 P13
5.8 The designation of all waste or other materials removed from the Site would be notified to the relevant authority by the Contractor/Construction Manager for approval. Loads would only be deposited at authorised waste treatment and disposal sites.
5.9 No burning of demolition and construction waste would be undertaken on site.
5.10 The issue of hazardous waste is addressed in more detail below at Section 5.18.
Traffic and access management
5.11 All construction traffic entering and leaving the Site would be closely controlled HGVs making deliveries to the site or removing demolition material etc, would avoid prohibited routes which would have been previously agreed with the local Highways Authority and other relevant bodies.
5.12 Detailed information regarding these issues and measures to minimise the risk of traffic congestion would be presented in detail through a Construction Traffic Management Plan that would be compiled by the Contractor and agreed with the appropriate authority prior to commencement of site works. Reference should be made to Chapter D, the Transport Assessment for details.
Control of noise, vibration and dust
5.13 In a project of this scale and nature, it is recognised that noise, vibration and dust could give rise to local disturbance. These effects are an inevitable consequence of the demolition works, HGV traffic, ground excavations, piling works and other heavy construction activities. Site-specific measures would be covered in the CEMP and therefore be implemented by contractors to minimise the disturbance to local residents, businesses and other potentially sensitive receptors.
5.14 With regard to potential dust nuisance, dust control measures would be implemented to prevent the release of potentially contaminated dust entering the atmosphere and/or being deposited on nearby receptors. These would include, where appropriate, the use of water sprayers and hoarding, dust covers, the restriction of drop heights onto lorries and appropriate storage locations of dusty materials.
5.15 These issues have been subject to Environmental Impact Assessment and the findings of these assessments provided in the DIRFT III ES.
Pollution Control
5.16 Prior to demolition and construction, the Contractor would be required to prepare a safety statement demonstrating how the safety of construction
DIRFT III : Construction Methodology Statement
P14 3180111v1
workers and the public would be addressed in terms of potentially harmful substances.
5.17 Measures for the control of construction-derived surface water run-off would be set out in the CEMP. As such, particular care would be taken to prevent any release or mobilisation of pollutants, which could pose a potential risk to receptors such as groundwater.
5.18 Pollution prevention measures would be put in place to isolate environmentally damaging substances and prevent of their release. These measures would be agreed in consultation with the Environment Agency and the relevant utilities provider.
5.19 An Emergency Plan would be implemented, forming part of the CEMP, outlining procedures to follow in the instance of any accidents involving spillages. This would involve the provision of on-site equipment for containing spillages, such as emergency booms and chemicals to soak up spillages. Should an incident occur, the Environment Agency and relevant utilities provider would be contacted immediately.
5.20 These issues have been subject to Environmental Impact Assessment and the findings of these assessments provided in the DIRFT III ES.
Considerate Constructor Scheme
5.21 All contractors working on the development will be required to register the individual construction contracts with the Considerate Constructors scheme and will be required to commit to the achievement of the points under the scheme.
Communication Strategy
5.22 A newsletter would be produced at regular intervals to notify of progress, anticipated works, potential disruption and supplementary issues of interest to the local community and businesses.
DIRFT III : Construction Methodology Statement
3180111v1
Appendix 1 Phasing Plans
Dra
in
Issues
Dra
in
Issues
Dra
in
Pond
Pond
Pond
Pond
Drain
Sinks
Drain
Pond
Dra
in
Pond
Pond
Pond
Pond
Pond
Balancing Pond
Dra
in
Marina
Hillm
ort
on W
harf
Marina
Dra
in
Pond
Oxf
ord
Can
al
Pond
Pond
Spring
Pond
Pond
Ponds
Pond
Pond
Sl
Pond
Pond
Oxfo
rd C
anal
Pond
Pond
Dra
in
Pond
Ponds
Pond
Pond
Balancing
Pond
Balancing
Sl
Pond
Pond
Drain
Pond
Drain
Drain
Pond
Pond
Dra
in
Pond
Dra
in
Dra
in
Dra
in
Dra
in
Dra
in
Dra
in
Drain
Pond
Dra
in
Dra
in
Drain
Pond
Ponds
Pond
Dra
in
Pond
Pond
Pond
Dra
in
Pond
Dra
in
Dra
in
Dra
in
Pond
Pond
Dra
in
Dra
in
Issues
Drain
Drain
Drain
Pond
Drain
Drain
Drain
Pond
Pond
Drain
Clift
on
Bro
ok
Dra
in
Pond
Dra
in
Pond
Pond
Drain
Pond
Pond
Ponds
Pond
Dra
in
Clif
ton
Bro
ok
Dra
in
Issues
Dra
in
Dra
in
Pond
Pond
Pond
Pond
Pond
Pond
Dra
in
Pond
Pond
Dra
in
Pond
Dra
in
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Pond
Nortoft
Farm
Cedars
The
Depot
Strongs Farm
Nortoft Farm
Nortoft Lodge
Cloverlea
El Sub Sta
Farm
ESS
El Sub Sta
Tank
Hotel
El Sub Sta
21
WB
17
7
80
1
2
28
The Old Royal Oak
22
38
6
1
3
34
The Wharf
14
Warley
Cro
wn P
oin
t
Eastfield Farm
Depot
Depot
Halfway House
(PH)
Garage
Sub
Sta
El Sub Sta
ESS
El Sub Sta
Sub Sta
13
El Sub Sta
72
26
54
El
1
46
66
56
Dollman Farm
El Sub Sta
El
El Sub Sta
Haythog Cottage
Tanks
Haythog Farm
Cottage
Haythog
Rugby
Radio Station
Rugby Radio Station
New House Farm
Crick Lodge
Shenley Farm
Pavilion
Rugby Radio Station
Meadows
The
Dunsmore
Dunsmore
Gardens
Cottage
Blaise
Lodge
Hall Farm
Hamslade
Hous
e
Cottage
Dunsmore
Two Trees
Haslemere
Duns
mor
e
Cottage
Magpie Lodge Farm
Pump House
27
25
6a
Hob
6
5
1
9
6
House
39
5
15
4
The
2
7
Church
Farmhouse 11
Hall
4
2
28
El Sub Sta
1
31
6
8
Evangelical
1
11
15
9
6
2
The
Shires
6
Green Farm
Lilbourne
12
Old3
Lilbourne Fields
37
Farmhouse
Lodge
Lilbourne
Morningside
Farm
New Clarks Farm
Clarkes
Lodge
Farm
ED
& W
ard
Bdy
1.2
2m
RH
DefD
ef
CD
EER
& Co
Con
st Bd
y
1.22
m R
H
EE
R &
Co C
onst
Bdy
1.2
2m
RH
Def
1.2
2m
RH
EER & Co Const Bdy
Def
ED and Ward Bdy
Und
EER Bdy and Co Const Bdy
1.2
2m
RH
1.22m RH
1.22m RH
ED
& W
ard
Bdy
CD
1.2
2m
RH
Def
CD
1.2
2m
RH
ED
& W
ard
Bdy
Und
Und
ED and Ward Bdy
CH
RH
1.22m RH
De
f
Def
De
f
ED & Ward Bdy
EE
R a
nd
Co
Co
ns
t B
dy
Def
Def
Def
Def
EE
R a
nd C
o C
onst B
dy
Def
1.22m
RH
Ward
Bdy
Def
EE
R a
nd C
o C
onst B
dy
War
d Bd
y
1.22m
RH
1.22m
RH
Def
Def
1.22m RH
1.22m R
H
Def
1.22m RH
1.22m R
H
Def
EE
R a
nd C
o C
onst B
dy
Def
1.2
2m
RH
Def
EE
R a
nd C
o C
onst B
dy
Def
De
f
Def
1.22m RH
EE
R a
nd C
o C
onst B
dy
Def
RH
FW
1.22m
FF
1.2
2m
RH
1.2
2m
Def
A 5
A 428
CELT
IC W
AY
A 428
RA
ILP
OR
T A
PP
RO
AC
H
A 5
CE
LTIC
WA
Y
A 428
ELD
ON
WA
Y
A 5
A 428
LE
NN
ON
CL
OS
E
CRICK
LENN
ON
ROAD
LENN
ON
CLO
SE
A 428
CLOS
E
CRICK ROAD
A 428
A 5
DA
NE
S W
AY
A 5
PARK
LAND
S
M 1
LE
NN
ON
CLO
SE
MO
ORS LA
NE
A 5
DANE
S W
AY
A 5
M 1
A 5
M 1
A 5 M
1
M 1
LILBOURNE
ROAD
HIL
LMO
RTO
N L
ANE
A 5
RUGB
Y ROA
D
TH
E G
RE
EN
ST
ON
EH
OU
SE
CO
UR
T
CHAP
EL LA
NE
HIL
LM
OR
TO
N L
AN
E
ST
AT
ION
RO
AD
YELVERTOFT ROAD
YELVERTOFT ROAD
M 1 Junction 18
M 1
RFT Staff
Welfare
Building
RFT
Fueling/
MaintenanceArea
+100m
AOD
+105m
AOD
+110m
AOD
+114m
AOD
+100m AOD
+105m AOD
+110m AOD
+113m AOD
1:1 SLOPE APPROX
70m SSD
Pond
Ponds
Pond
Dra
in
Drain
Drain
New House Farm
Drain
Pond
Shenley Farm
Dra
in
Dra
in
Pond
Def
1:1 SLOPE APPROX1:1 SLOPE APPROX
70m SSD70m SSD70m SSD
El Sub StaEl Sub StaEl Sub StaEl Sub StaEl Sub StaEl Sub Sta
Pond
De
f
EE
R a
nd
Co
Co
ns
t B
dy
Dra
in
Drain
Drain
Pond
Pond
Pond
Pond 1.22m
RH
Issues
Drain
Drain
Drain
Pond
Drain
Pond
Pavilion
Rugby Radio Station
Pond
RA
ILP
OR
T A
PP
RO
AC
H
Drain
Pond
Dra
in
ED & Ward Bdy
Pond
1.22m R
H
Def
1.22m RH
+100m AOD
+105m AOD
+110m AOD
+113m AOD
+113m AOD
+113m AOD
+113m AOD
+100m
AOD
+105m
AOD
+110m
AOD
+114m
AOD
+114m
AOD
+114m
AOD
Ponds
Dra
in
Pond
Dra
in
Ponds
ED & Ward BdyED & Ward BdyED & Ward BdyED & Ward Bdy
Def
Def
Def
Def
1.22m
RH
Ward
Bdy
1.22m
RH
A 5
A 5
RFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT Staff
WelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfare
BuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuilding
RFTRFTRFT
Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/
MaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceAreaAreaArea
Pond
DANE
S W
AY
DANE
S W
AY
DANE
S W
AY
Dra
in
Dra
in
Dra
in
Pond
Pond
Pond
Pond
+100m AOD
Temporaryemergencyaccess
0m 500m100m0m 500m100m0m 500m100mN
SHEET 2
SHEET 3
SHEET 1
The Daventry International Rail
Freight Interchange Expansion
(DIRFT III) Order [20...]
Existing Buildings
Consented DIRFT II Buildings
Extent of Stage#1A
Order Limits
Key:
Extent of Stage#1B
Extent of Stage#2
Extent of Stage#3
Extent of Stage#4
The phasing of rail infrastructure
is not directly linked to the
development of buildings and is
set out in the Rail OperationsReport.
Earthworks as part of Stage#1B
Drawing status:
CAD reference:
Drawn:
Team:
Date:
Scale:
Project no: Rev:
Ref:
Dwg no:
1 Monkspath Hall Road
Solihull, West Midlands B90 4FY
t: 0121 7116929 f: 0121 2248759
www.stephengeorge.co.uk
Phasing Plan (Key Plan)
Reg. 5(2)(o)/ Document 2.15
Approval
10127A049
BW
JN
05/2011 (Original)
1:5,000@A0
10127 A049 (KEY) D
This drawing, the works and concepts depicted are copyright of Stephen George & Partners and may not be reproduced or made use of, either directly or indirectly without express written consent. All heights, levels, sizes and dimensions to be checked on site before any work is put to hand.
Notes:
Ordnance Survey Data:
Crown Copyright 2009. All rights reserved.
Licence No: 100020449
The stages of development shown on this
drawing are to inform the Environmental
Impact Assessment and illustrate which
elements of the scheme are likely to be
built together and the anticipated
sequence of construction of the major
elements of earthworks, buildings,
infrastructure and landscaping. There are
other sections of work that are less
significant to the EIA such as ancillary
buildings, foul and surface water drainage
and the provision of mains services that
are not shown on this phasing drawing.
Such elements are still essential and their
phasing will be planned in detail in the
pre-construction stage for each stage of
development when the precise scope of
each phase is known.
Stages can overlap and are indicative.
Location of sources of fill are indicative.
Revisions:
A BW 26.05.2011
Stage 1B eathworks revised and Stage 1A
earthworks removed
B PS 25.05.2012
Red line boundary and notation amended;
additional sheets added with this drawing
to serve as a key plan
C BW 30.07.2012
Red line boundary amended; phasing
zones updated to reflect new boundary
D PS 08.08.2012
Annotation amendment
Dra
in
Issues
Dra
in
Issues
Dra
in
Pond
Pond
Pond
Pond
Drain
Sinks
Pond
Pond
Pond
Pond
Pond
Balancing Pond
Dra
in
Pond
Pond
Ponds
Pond
Sl
Nortoft
Farm
Cedars
The
Depot
Strongs Farm
Nortoft Farm
Nortoft Lodge
Cloverlea
El Sub Sta
Farm
ESS
El Sub Sta
Tank
Hotel
El Sub Sta
21
WB
Halfway House
(PH)
Garage
El Sub Sta
ESS
El Sub Sta
ED
& W
ard
Bdy
1.2
2m
RH
1.2
2m
RH
EER Bdy and Co Const Bdy
1.2
2m
RH
1.22m RH
1.22m RH
ED
& W
ard
Bdy
1.2
2m
RH
CD
1.2
2m
RH
A 5
A 428
CELT
IC W
AY
A 428
RA
ILP
OR
T A
PP
RO
AC
H
A 5
CE
LTIC
WA
Y
A 428
ELD
ON
WA
Y
A 5
A 428
A 428
A 5
A 5
PARK
LAND
S
M 1
M 1 Junction 18
El Sub StaEl Sub StaEl Sub StaEl Sub StaEl Sub Sta
Pond
RA
ILP
OR
T A
PP
RO
AC
HZone H
0m 100m 200mN
CUT LINE, PLEASE SEE A049 (SHEET 2)
The Daventry International Rail
Freight Interchange Expansion
(DIRFT III) Order [20...]
Existing Buildings
Consented DIRFT II Buildings
Extent of Stage#1A
Order Limits
Key:
Extent of Stage#1B
Extent of Stage#2
Extent of Stage#3
Extent of Stage#4
The phasing of rail infrastructure
is not directly linked to the
development of buildings and is
set out in the Rail OperationsReport.
Earthworks as part of Stage#1B
This drawing, the works and concepts depicted are copyright of Stephen George & Partners and may not be reproduced or made use of, either directly or indirectly without express written consent. All heights, levels, sizes and dimensions to be checked on site before any work is put to hand.Ref:
Phasing Plan (Sheet 1)
Reg. 5(2)(o)/ Document 2.15A
Approval
10127A049
PS
JN
05/2012 (Original)
1:2,500@A0
10127 A049 (SHEET 1) B
Project no: Rev:Dwg no:
Drawing status:
Cad reference:
Drawn:
Team:
Date:
Scale:
Project no: Rev:Dwg no:
1 Monkspath Hall Road
Solihull, West Midlands B90 4FY
t: 0121 711 6929 f: 0121 224 8759
www.stephengeorge.co.uk
Notes:
Ordnance Survey Data:
Crown Copyright 2009. All rights reserved.
Licence No: 100020449
The stages of development shown on this
drawing are to inform the Environmental
Impact Assessment and illustrate which
elements of the scheme are likely to be
built together and the anticipated
sequence of construction of the major
elements of earthworks, buildings,
infrastructure and landscaping. There are
other sections of work that are less
significant to the EIA such as ancillary
buildings, foul and surface water drainage
and the provision of mains services that
are not shown on this phasing drawing.
Such elements are still essential and their
phasing will be planned in detail in the
pre-construction stage for each stage of
development when the precise scope of
each phase is known.
Stages can overlap and are indicative.
Location of sources of fill are indicative.
Revisions:
A BW 30.07.2012
Red line boundary amended; phasing
zones updated to reflect new boundary
B PS 08.08.2012
Annotation amendment
Depot
Depot
Halfway House
(PH)
Sub
Sta
El Sub Sta
ESS
El Sub Sta
El
El Sub Sta
Haythog Cottage
Tanks
Haythog Farm
Cottage
Haythog
New House Farm
Shenley Farm
Pavilion
Rugby Radio Station
1.22m RH
1.22m RH
CD
1.2
2m
RH
Def
CD
ED
& W
ard
Bdy
Def
De
f
ED & Ward Bdy
EE
R a
nd
Co
Co
ns
t B
dy
Def
Def
Def
Def
EE
R a
nd C
o C
onst B
dy
Def
1.22m
RH
Ward
Bdy
Def
EE
R a
nd C
o C
onst B
dy
War
d Bd
y
1.22m
RH
1.22m
RH
Def
Def
1.22m R
H
Def
1.22m RH
1.22m R
H
Def
Def
1.2
2m
RH
Def
Pond
Pond
Spring
Pond
Pond
Ponds
Pond
Pond
Sl
Dra
in
Pond
Ponds
Pond
Pond
Balancing
Pond
Balancing
Sl
Dra
in
Dra
in
Dra
in
Dra
in
Dra
in
Drain
Pond
Dra
in
Dra
in
Drain
Pond
Ponds
Pond
Dra
in
Dra
in
Issues
Drain
Drain
Drain
Pond
Drain
Drain
Drain
Pond
Pond
Drain
Pond
Dra
in
Pond
Pond
Drain
Pond
Pond
Ponds
Pond
Dra
in
Dra
in
Pond
Pond
Pond
Pond
Dra
in
Pond
Pond
A 428
A 5
DA
NE
S W
AY
PARK
LAND
S
A 5
DANE
S W
AY
A 5
M 1
A 5
M 1
M 1
RFT Staff
Welfare
Building
RFT
Fueling/
MaintenanceArea
1:1 SLOPE APPROX
70m SSD
New House Farm
Pond
Ponds
Pond
Dra
in
Drain
Drain
Ponds
Dra
in
Dra
in
Def
Dra
in
Dra
in
Pond
Dra
in
1:1 SLOPE APPROX1:1 SLOPE APPROX1:1 SLOPE APPROX
70m SSD70m SSD70m SSD
Shenley Farm
Pond
Drain
De
f
EE
R a
nd
Co
Co
ns
t B
dy
Pond
Dra
in
Drain
Drain
Drain
Pond
Pond
1.22m R
H
Pond
Pond
Issues
Drain
Drain
Drain
Pond
Drain
Pavilion
Rugby Radio Station
Pond
Pond
Drain
ED & Ward Bdy
Pond
Dra
in
Pond
1.22m R
H
Def
1.22m RH
ED & Ward BdyED & Ward BdyED & Ward Bdy
Def
Def
Def
Def
Ward
Bdy
Ponds
A 5
A 5
Dra
in
Pond
Dra
in
Ponds
RFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT StaffRFT Staff
WelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfareWelfare
BuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuilding
RFTRFTRFT
Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/Fueling/
MaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceMaintenanceAreaAreaArea
1.22m
RH
1.22m
RH
1.22m
RH
1.22m
RH
1.22m
RH
1.22m
RH
1.22m
RH
1.22m
RH
DANE
S W
AY
DANE
S W
AY
DANE
S W
AY
PondPond
PondPond
Dra
in
PondPondPondPond
Temporaryemergencyaccess
0m 100m 200mN
CUT LINE, PLEASE SEE A049 (SHEET 1)
CUT LINE, PLEASE SEE A049 (SHEET 3)
The Daventry International Rail
Freight Interchange Expansion
(DIRFT III) Order [20...]
Existing Buildings
Consented DIRFT II Buildings
Extent of Stage#1A
Order Limits
Key:
Extent of Stage#1B
Extent of Stage#2
Extent of Stage#3
Extent of Stage#4
The phasing of rail infrastructure
is not directly linked to the
development of buildings and is
set out in the Rail OperationsReport.
Earthworks as part of Stage#1B
Drawing status:
CAD reference:
Drawn:
Team:
Date:
Scale:
Project no: Rev:
Ref:
Dwg no:
1 Monkspath Hall Road
Solihull, West Midlands B90 4FY
t: 0121 7116929 f: 0121 2248759
www.stephengeorge.co.uk
Phasing Plan (Sheet 2)
Reg. 5(2)(o)/ Document 2.15B
Approval
10127A049
PS
JN
05/2012 (Original)
1:2,500@A0
10127 A049 (SHEET 2) B
This drawing, the works and concepts depicted are copyright of Stephen George & Partners and may not be reproduced or made use of, either directly or indirectly without express written consent. All heights, levels, sizes and dimensions to be checked on site before any work is put to hand.
Notes:
Ordnance Survey Data:
Crown Copyright 2009. All rights reserved.
Licence No: 100020449
The stages of development shown on this
drawing are to inform the Environmental
Impact Assessment and illustrate which
elements of the scheme are likely to be
built together and the anticipated
sequence of construction of the major
elements of earthworks, buildings,
infrastructure and landscaping. There are
other sections of work that are less
significant to the EIA such as ancillary
buildings, foul and surface water drainage
and the provision of mains services that
are not shown on this phasing drawing.
Such elements are still essential and their
phasing will be planned in detail in the
pre-construction stage for each stage of
development when the precise scope of
each phase is known.
Stages can overlap and are indicative.
Location of sources of fill are indicative.
Revisions:
A BW 30.07.2012
Red line boundary amended; phasing
zones updated to reflect new boundary
B PS 08.08.2012
Annotation amendment
Clif
ton
Bro
ok
Dra
in
Dra
in
Dra
in
Pond
Pond
Pond
Pond
Pond
Pond
Dra
in
Pond
Dra
in
Pond
Pond
Pond
Pond
Pond
A 5 M
1
M 1
HIL
LMO
RTO
N L
ANE
RUGB
Y ROA
D STON
EH
OU
SE
CO
UR
T
HIL
LM
OR
TO
N L
AN
E
YELVERTOFT ROAD
M 1
Meadows
The
27
25
6 1
9
39
5
15
4
The
2
2
28
1
6
8
1
11
Green Farm
12
Lilbourne Fields
37
Farmhouse
Def
EE
R a
nd C
o C
onst B
dy
Def
OUT
OUT
OUT
Male
WC/S
hw
rs
Fem
ale
WC/S
hw
rs
Acc.
WC/S
hw
r
Clean
ers
Lobby
Lorry Park
Amenity
Building
+100m
AOD
+105m
AOD
+110m
AOD
+114m
AOD
+100m AOD
+105m AOD
+110m AOD
+113m AOD
70m SSD
Dra
in
Pond
Def
70m SSD70m SSD70m SSD70m SSD70m SSD70m SSD70m SSD
Pond
Pond
OUT
OUT
OUT
Male
Male
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
Fem
ale
WC/S
hw
rs
WC/S
hw
rs
WC/S
hw
rs
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
Acc.
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
WC/S
hw
r
Clean
ers
Clean
ers
Clean
ers
Clean
ers
Clean
ers
Lobby
Lorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry ParkLorry Park
AmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenityAmenity
BuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuildingBuilding
+100m AOD
+105m AOD
+110m AOD
+113m AOD
+113m AOD
+113m AOD
+113m AOD
+100m
AOD
+105m
AOD
+110m
AOD
+114m
AOD
+114m
AOD
+114m
AOD
Dra
in
Dra
in
Dra
in
Pond
Pond
+100m AOD
Pond
PondPond
PondPondPondPond
Zone A
Intermodal
terminal entry/
exit gateway
Lorry Park - 311 spaces
Public
Artwork
Lilbourne Meadows
0m 100m 200mN
CUT LINE, PLEASE SEE A049 (SHEET 2)
The Daventry International Rail
Freight Interchange Expansion
(DIRFT III) Order [20...]
Existing Buildings
Consented DIRFT II Buildings
Extent of Stage#1A
Order Limits
Key:
Extent of Stage#1B
Extent of Stage#2
Extent of Stage#3
Extent of Stage#4
The phasing of rail infrastructure
is not directly linked to the
development of buildings and is
set out in the Rail OperationsReport.
Earthworks as part of Stage#1B
This drawing, the works and concepts depicted are copyright of Stephen George & Partners and may not be reproduced or made use of, either directly or indirectly without express written consent. All heights, levels, sizes and dimensions to be checked on site before any work is put to hand.Ref:
Phasing Plan (Sheet 3)
Reg. 5(2)(o)/ Document 2.15C
Approval
10127A049
PS
JN
05/2012 (Original)
1:2,500@A1
10127 A049 (SHEET 3) B
Drawing status:
CAD reference:
Drawn:
Team:
Date:
Scale:
Project no: Rev:Dwg no:
1 Monkspath Hall Road
Solihull, West Midlands B90 4FY
t: 0121 711 6929 f: 0116 254 1095
www.stephengeorge.co.uk
Notes:
Ordnance Survey Data:
Crown Copyright 2009. All rights reserved.
Licence No: 100020449
The stages of development shown on this
drawing are to inform the Environmental
Impact Assessment and illustrate which
elements of the scheme are likely to be
built together and the anticipated
sequence of construction of the major
elements of earthworks, buildings,
infrastructure and landscaping. There are
other sections of work that are less
significant to the EIA such as ancillary
buildings, foul and surface water drainage
and the provision of mains services that
are not shown on this phasing drawing.
Such elements are still essential and their
phasing will be planned in detail in the
pre-construction stage for each stage of
development when the precise scope of
each phase is known.
Stages can overlap and are indicative.
Location of sources of fill are indicative.