8.3 Critical Path MethodDr. Tarek A. Tutunji
Philadelphia University, Jordan
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
Overview In the previous sequence, Gantt Chart was introduced.
In this sequence, another graphical project planning technique, the Critical Path Method (CPM) will be presented.
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
Critical Path Method (CPM) There are similarities between CPM and Gantt Chart.
In order to do the CPM, First, you have to
Identify the tasks.
Specify the dependency among the tasks.
Estimate the task duration.
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Network In a CPM network, tasks are shown as nodes.
Arrows are used to connect the nodes.
The duration of the tasks are written above the arrows.
A connected series of nodes are used to show the dependencies among tasks.
The order of tasks is given by the flow of the connections left to right.
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM network Basics
A B Task A must finish before task B starts
A C
B
Tasks A and B must finish before task C starts
AC
B
Task A must finish before either task B or C start
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM network Basics
A B5
Duration for task A is 5 units
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM network
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example Consider a construction project with the tasks defined
in table below
Task Name Duration Predecessor
A Excavation 4 --
B House Foundation 5 A
C House Gutter 2 A
D House Base 1 C
E House Wall 1 B,D
F House Roof 2 E
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
Task Name Duration Predecessor
A Excavation 4 --
B House Foundation 5 A
C House Gutter 2 A
D House Base 1 C
E House Wall 1 B,D
F House Roof 2 E
0
4
4
5
2
1 2
1
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
Critical Path
Critical Path is the sequence of tasks that defines the minimum amount of time for the project to be completed.
These are the tasks that a delay within will delay the entire project
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
0
4
4
5
2
1 2
1
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
0
4
4
5
2
1 2
1
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
0
4
4
5 ?
2 ?
1 2
1 ?5 > 1+2
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
0
4
4
5
2
1 2
1
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
0
4
4
5
2
1 2
1
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
CPM Example
Start A
C
EB F
D
End
0
4
4
5
2
1 2
1
Critical Path A B E F
Minimum Duration for finalizing the project: 4+5+1+2=12
Dr. Tarek A. TutunjiEngineering Skills, Philadelphia University
Conclusions In this sequence, Critical Path Method was
introduced.
An detailed project example was used to clarify the use of CPM.