Why Kanban Systems Fail and What You Can Do About it
Saifallah BenjaafarCenter for Manufacturing Logistics
Department of Mechanical EngineeringUniversity of MinnesotaMinneapolis, MN 55455
2
Kanban
A “kanban” is a sign-board or card in Japanese and is the name of the flow control system developed by Toyota.
3
Outline 1. The JIT context
2. Basic mechanics
3. Advantages
4. Limitations
5. Alternatives to Kanban
6. CONWIP systems
7. PFB systems
8. MTO/MYS systems
9. Conclusions
4
Role
Kanban is a tool for realizing just-in-time. For this tool to work fairly well, the production process must be managed to flow as much as possible. This is really the basic condition. Other important conditions are leveling production as much as possible and always working in accordance with standard work methods.
--- Ohno 1988
5
Just-in -Time (JIT)
A collection of principles aimed at reducing inventory, increasing throughput, and minimizing manufacturing lead times.
6
Origins of JIT
• Japan’s attempt to become competitive with US and European manufacturers after WW II
• The Toyota Production System
7
JIT principles
• Reduce setup times
• reduce batch sizes
• Reduce variability
• Reduce material handling
• Reduce defects and rework
• Reduce breakdowns
• Increase capacity
• Smooth production schedules
8
JIT principles (cont.)
• Maintain constant WIP (limit WIP buffer sizes)
• Limit finished goods inventory and raw materials
• Synchronize operations within the factory
• Synchronize material delivery with suppliers and customers
• Improve worker flexibility and empower worker to make improvements
• Simplify workflow
9
The Seven Zeros
• Zero (excess) lot sizes• Zero setups• Zero breakdowns• Zero lead times• Zero surging• Zero material handling• Zero defects
10
Kanban Systems
A shop floor control strategy aimed at (1) reducing inventory, (2) simplifying workflow, (3) increasing throughput, (4) reducing cycle time, (5) improving customer lead times, and (5) improving quality.
11
Mechanics of Kanban
Push vs. Pull: Kanban is a “pull system”
• Push systems schedule releases
• Pull systems authorize releases
Synchronous manufacturing: Pull signals ensure tight coupling between operations throughout the system
14
One-Card Kanban
Outbound stockpoint
Outbound stockpoint
Productioncards
Completed parts with cards enter outbound stockpoint.
When stock is removed, place production card in hold box.
Production card authorizes start of work.
15
Two-Card Kanban
Outbound stockpoint
Inbound stockpoint
Production cards
Move stock to inbound stock point.
When stock is removed, place production card in hold box. Production
card authorizes start of work.
Move card authorizes pickup of parts.
Remove move card and place in hold box.
Move cards
16
MRP versus Kanban
…
Lover Level Inven-tory
…
MRP
Kanban
…
Kanban Signals Full Containers
Lover Level Inven-tory
Assem-bly
Assem-bly
19
Tradeoffs
• Too many Kanbans Too much WIP and long cycle times
• Too few Kanbans Lower throughput and vulnerability to demand and process variability
21
Example
• Four identical tools in series.
• Each takes 2 hours per piece.
• No variability.
• Constant WIP.
23
Throughput and Cycle Time vs. WIPT
hrou
ghpu
t (Jo
bs/h
r)
0 2 4 6 8 10 12 140
.2
.4
.3
.5
.1
WIP (Jobs)
24
Throughput and Cycle Time vs. WIP (cont.)C
ycle
tim
e (H
ours
)
0 2 4 6 8 10 12 140
8
16
12
20
4
WIP (Jobs)
25
The Case of an Unbalanced Line
• The maximum feasible throughput rate is the processing rate of the bottleneck
• Critical WIP = (Bottleneck rate)(Total processing time)
26
The Impact of Variability
• Processing times are subject to variability, material handling is not instantaneous, processes are subject to breakdowns, demand is subject to fluctuation
• Longer cycle times and lower throughput
27
Number of Kanbans at Toyota
• Number of cards = WIP
• Number of cards = D/QL(1 + )
• D: Demand
• Q: Container
• L: Raw processing time
• : safety (variability) factor
28
Guidelines for allocating Kanbans
• Allocate Kanbans evenly in a balanced system
• Allocate more Kanbans to slower processes or processes with higher workloads
• Always protect the bottleneck
29
Guidelines for allocating Kanbans (cont.)
• Start with current averages
• Gradually reduce Kanbans at stations that are always full
• Increase Kanbans at stations that are always empty
30
Advantages of Kanban
• Simplifies workflow
• Synchronizes manufacturing
• Reduces WIP accumulation at all processes stages
• Improves performance predictability and consistency
• Fosters communication between neighboring processes
• Reduces defects and enables 100% inspection
31
Advantages of Kanban (cont.)
• Encourages line balancing and process variability reduction
• Encourages focused and cellular manufacturing
• Y2K robust
32
Limitations of Kanban Systems
• Ideal for high volume and low variety manufacturing
• Vulnerable to fluctuations in demand volume and product mix
• Vulnerable to process variability and machine breakdowns
• Inefficient in handling infrequent orders or expediting special orders
• Vulnerability to raw material shortages and variability in supplier lead times
33
Alternatives to Kanban
• Constant Work-in-Process (CONWIP)
• Pull from the Bottleneck (PFB)
• Hybrid Make-to-stock/Make-to-order system
35
Basic Configurations
• Constant work-in-process
• Input/output control
• Asynchronous operation
• Dispatching list
• Example: Flow lines
36
CONWIP Control
PC
R G
PC
DD PN Quant–— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— ––––––— –— –––––
Dispatching list
LAN
. . .
Work Centers
38
• A new job is introduced whenever one completes
• The next job is selected from a dispatching list based on current demand
• The mix of jobs is not fixed
• Priorities can be assigned to jobs in the dispatching list
• WIP level can be dynamically reduced
CONWIP Mechanics
39
Advantages of CONWIP-based Control
• Accommodates multiple products and low production volumes
• Allows expediting and infrequent orders
• Less vulnerable to demand and process variability
• Less vulnerable to breakdowns
• Protects throughput and prevents bottleneck starvation
• Simpler to implement and manage
40
Coupled and Uncoupled CONWIP Loops
Bottleneck
Buffer
Card FlowMaterial FlowCONWIP Card
JobCONWIP Loop
41
Splitting Loops at Shared Resource
Routing A Routing A
Routing B Routing B
Buffer
Card Flow
Material Flow
CONWIP Loop
42
Modifications of Basic CONWIP
Multiple Product Families:• Capacity-adjusted WIP
• CONWIP Controller
• Running a card deficit
Assembly Systems:• CONWIP achieves synchronization naturally
• WIP levels must be sensitive to “length” of fabrication lines
44
CONWIP Assembly
Processing Timesfor Line B
Processing Timesfor Line A
Assembly
1
3233
2 4
1
Material FlowCard FlowBuffer
45
Pull From the Bottleneck
Problems with CONWIP/Kanban:• Bottleneck starvation due to downstream failures
• Premature releases due to CONWIP requirements
PFB Remedies:• PFB ignores WIP downstream of bottleneck
• PFB launches orders when bottleneck can accommodate them
PFB Problem:• Floating bottlenecks
47
Make-to-order/Make-to-stock Configurations
• Build components and subassemblies to stock
• Build final assemblies to order
• Pull system for MTS
• Push System for MTO
48
Conclusion
• There are Pros and Cons to everything
• Pull systems are one piece of the puzzle
• Change throughout the organization is essential
• An integrated supply chain strategy is critical
49
• Factory Physics, W. J. Hopp and M. Spearman, Irwin, 1996 (and teaching notes)
• The Race, E. M. Goldratt and R. E. Fox, North-River Press, 1986
• QRM Revisited: Don't Push or Pull - POLCA, APICS Magazine, Vol. 8, No. 11, 1998.