LAHORE WASTE MANAGEMENT COMPANY
Expression of Interest Published in July 22, 2013 in local and international press Published in Gulf international, Zamaan Turkey,
Daily China & international websites and Pakistani newspapers
EOI Validity was till September 15, 2013 Seventy (70) companies were contacted by
the LWMC Twenty Nine (29) companies submitted their
EOIs.
2
List of Companies
Twenty (20) companies are being shortlisted and Letter of acceptance are sent to all
20 companies as yet. These companies are called for meeting
with MD LWMC for further proceedings.
3
4
5
Sr. #
Name of company
Technology
Generation of Power
Amount of waste (tons/day)
Estimated cost (US$ Million)
1. Reality Renewables, Manchester UK(BOO)
Pyrolysis Mr. Neil and Kevin visited LWMC, landfill site, Signing of MOU in
process, Technical team will visit LWMC after MOU
2. EAWC, Technologies, Miami USA(Rep visited LWMC, Skype conf.)
Plasma 1 MW 12 4
3. IMPACT GLOBAL EMISSION
SOLUTIONS, London UK
Pyrolysis
30 MW 800 -
6
Sr. #
Name of company
Technology
Generation of Power
Amount of waste (tons/day)
Estimated cost (US$ Million)
4 COWI, Denmark (Turn Key project)
Incineration 25 MW 1500 -
5 Hitz, Hitachi Zosen corp. Tokyo Japan(DBO)
Incineration 6.6 MW 420 -
6 Mumtaz Construction Company with Naanovo energy Inc., Ottawa Canada (BOT or BOO)
Mass burn /Incineration
30 MW 2000 -
7
Sr. #
Name of company Technology
Generation of Power
Amount of waste (tons/day)
Estimated cost (US$ Million)
7 Omega/ GTS energy private Ltd., Oregon USA(BOO)
Plasma Arc/gasification
3.9 250 -
8 Vinci Environnement / Technical Assosiate Pakistan Pvt Ltd
Inceneration
- - -
9 Salman & Associates with Energy Projeckt i Serverige AB, Sweden
Incineration
0.5 to 4 MW
100 -
10 Global Green International, Singapore
Pyrolysis 2 MW/h 20 -
8
Sr. #
Name of company Technology
Generation of Power
Amount of waste (tons/day)
Estimated cost (US$ Million)
11AFCO Enterprises Gasification
4 MW 100 -
12 AL - WASEH INTERNATIONAL CO, JV (BMEI & Co) TIAJIN DESIGN & RESEARCH
INSTITUTE OF ELECTRIC DRIVE CO.
Ltd
Incineration
- - -
13 Swede Tech International (Pvt) Ltd
Incineration - - -
9
Sr. #
Name of company Technology Generation of Power
Amount of waste (tons/day)
Estimated cost (US$ Million)
14 DESCON ENGINEERING PVT Ltd., A Group Of
CnimMass -Burn
- - -
15 CONSORTIUM OF EUROCONSULT -46 K-I Model Town Lahore
Anaerobic Digestion
- - -
16Albario Engineering
Pvt Ltd
Inineration/ Gasification
- - -
17Se Group Rebuilding
Society
Pyrolysis 37 1000
10
Sr. #
Name of company
Technology
Generation of Power
Amount of waste (tons/day)
Estimated cost (US$ Million)
18Satarem A.G -
20-60 - -
19K-axis Engineering
(incineration)
- - -
20Escorts Pakistan
biomass energy
- 1500-2000
-
11
Mr. Neil Vaughan Jones, and Mr. Kevin King of M/s Reality Renewables meeting
with LWMC on 12-09-2013
Eight (08) Consultants/companies have shown interest in WtE project in Lahore and submitted their Proposals. Technical evaluation of all the consultants is done.
BOD of LWMC principally approved in its meeting held on 16-09-2013 to build the capacity of LWMC for WTE projects and hiring of consultants
12
13
Professor Nickolas J Themelis has been
selected
His services will be backed by the firm
M/s Ecoair
Vast experience of WTE projects
US $ 27,500/- for four weeks of
assignment Consultant is expected to be mobilized in
2nd week of October 2013.
TORs
CV
Review and Screening of EOIs for WTE Technologies
by 3rd week of October 2013
Int. consultant on board by 2nd Week of October
2013.
Preparation of technical feasibility by January 2014
Start of construction of project by June 2014
Start of production of electricity by April 2015
14
Production of 1 MW from 100 tons/day with US$ 1.5 to 2 million with huge Environmental emissions – as per Indian Model
Technical Feasibility to be conducted by the consultant
Efficient options available from current EOIs with possibility of investor
Companies from Japan, Denmark, China etc., provide incineration technology
15
State of the art Thermal waste Treatment plant – Grate fired incineration
Maximum output of 11.4 MW
600 tons of feedstock per day
Total investment of US$ 3,600,000 Commissioning start October 2015 First waste fire January 2016
16
State of the art Combustion plant Maximum output of 4 MW
100 tons of feedstock per day
Total investment of 3.75 Million €
17
Decision on upfront tariff for waste to energy projects
Investment subsidy on capital investment
Capacity building for Implementation of WTE project
18