Introduction
These charts are used for
1.Strategic Management
2.Project Management
Project ManagementApplication of knowledge, skills, tools and
techniques for project activities in order to meet or exceed stakeholder needs and expectation from a project.
3
Introduction
Helps project manager and team in term ofScope managementTime managementCost managementQuality management
Charts for project scheduling Gantt Chart, also known as (Time Line Charts) PERT chart (Evaluation Review Technique)-
network diagram.
4
Gantt Chart
A Gantt chart is a graphical representation of the duration of tasks against the progression of time.
useful tools for planning and scheduling projects. allow you to assess how long a project should take. lay out the order in which tasks need to be carried
out. help manage the dependencies between tasks. determine the resources needed.
5
Advantages
Gantt charts are useful tools when a project is under way.
monitor progress. You can immediately see what should have been achieved at a point in time.
Show how remedial action may bring the project back on course.
7
PERT chart
"PERT" developed by the United States Department of Defense as a management tool for complex military projects is an acronym for "Program Evaluation and Review Technique".
This technique was soon adapted for used in educational research and evaluation. Through PERT, complex projects can be blueprinted as a network of activities and events (Activity Network Diagram).
8
PERT chart
It is used for project scheduling. Pert charts allow software planners, or individuals to:Determine the critical path a project must follow.
Critical path is the longest overall duration, determining the shortest time to complete the project
Establish most likely time estimates for individual task by applying statistical models.
Calculate boundary times that define a time ‘window’ for a particular task.
10
Project Management Software
Among the project management software used to create charts and graph are:Microsoft ProjectMicrosoft Visio
13
Microsoft Project-Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
Symbols include:A black diamond: milestones or significant events on a
project with zero durationThick black bars: summary tasksLighter horizontal bars: tasksArrows: dependencies between tasks
14
Creating a Gantt Chart
The Gantt chart is constructed with a horizontal axis representing the total time span of the project, broken down into increments (days, weeks, or months).
constructed with a vertical axis representing the tasks that make up the project and constructed with a graph area which contains horizontal bars for each task connecting the period start and period ending symbols.
15
The Gantt chart also has variants such as: Milestones: important checkpoints or interim
goals for a projectResources: for team projects, it often helps to
have an additional column containing numbers or initials which identify who on the team is responsible for the task
16
Status: the projects progress, the chart is updated by filling in the task's bar to a length proportional to the amount of work that has been finished
Dependencies: an essential concept that some activities are dependent on other activities being completed first
20
To enter details of the project•Click Menu File•then Properties
•Enter details on:•Title•Subject•Author•Manager•Company•Category•Keywords
22
Enter task name in Task Name and determine the timeline using Duration, Start and Finish Date
Enter details here
Entering TasksEntering Tasks
24
Entering sub tasks
There two ways: :
i. Indent. Click on the starting of task name and drag to the right
ii. Using the buttons
28
Connecting Tasks
Connecting Tasks Highlight Two tasks that is going to be connected Click Edit. Click Link Task
Determining the dependency type FS, SF, SS, FF
Double click on the first task Click Tab Predecessor. Select the task name in the drop-
down menu. Choose the dependency type.
30
Milestone
MilestoneNormally show the eventThe time period is usually 0 or 1 day only..
Example: Start Project, End ProjectDouble click on the cell. Choose Tab Advance
and Mark Task As Milestone.
32
Time scale
To change the Time scale For example days, weeks, months
1. Click on Format.
2. Choose Timescale.
3. Choose the time scale unit desired
34
Gantt Chart View
To update the Gantt chart viewClick Format. Click on Gantt Chart Wizard to show
1.Critical Path
2.Date
3.Resources
38
Work Breakdown Structure
a results-oriented family tree that captures all the work of a project in an organized way
portrayed graphically as a hierarchical tree, tabular list of "element" and tasks or the indented task list that appears in Gantt chart schedule
41
Starting Pert Chart in Ms Project
Click on View. Choose PERT Chart or Click on PERT Chart icon on the left
side of Ms Project window
42
Pert Components
PERT has two main components:1. Arrows2. Node/ field Every node has information on task name, task ID,
duration, start, finish and resources Arrows shows the activities flow
Every arrows is possible to have crictical path.
2 format:AoA (ADM) = activity-on-arrow (arrow
diagramming method)AoN (PDM) = activity-on-node (precedence
diagramming method)
44
Arrow Diagramming Method (ADM)
Known as activity-on-arrow (AOA)Every activities is presented by arrowsNode shows the starting and finishing
date
45
ACTIVITY - ON – ARROW (AoA) NETWORKThe advantages are :Show the project’s time length Show the activities which the starting point and
end point are flexible or can be edited without changing the project’s time length - float.
1 A B
CD
E F
G
2 4 6
3 5
46
Precedence Diagramming Method (PDM)Activities are presented by boxesArrows show the dependency between
activities More popular compared to ADM (AOA)Better in showing different types of
dependencies
47
Creating PERT Chart
Creating PERT chartDetermine the activitiesDetermine the flow of the activities Estimate the time for each activities Prepare a time-scale chart for activities to
determine the critical path
49
Critical Path
The flow of activities that must be completed in order to complete the whole project
The delay in critical path will delayed the whole project.
50
Simple Example of Determining the Critical Path
Consider the following project network diagram. Assume all times are in days.
2 3
4
5
A=2 B=5C=2
D=7
1 6
F=2
E=1
start finish
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?
52
PERT Estimates
Activity Estimate = ((Optimistic Time + (4 x Most Likely Time) + Pessimistic Time)) 6
n
Total Expected Time of Project = Activity Estimates i=1
53
Activity Analysis for PERT
Activity Predecessor Optimistic Estimates
(Days)
(a)
Most Likely Estimates
(Days)
(b)
Pessimistic Estimates
(Days)
(c)
Expected Duration
(a+4b+c)
6
A None 1 2 4 2.2
B A 3 5 8 5.2
C B 2 4 5 3.8
D B 2 3 6 3.3
E B 1 1 1 1.0
F C,D 2 4 6 4.0
G D,E 2 3 4 3.0
H F,G 1 2 5 2.3
I G 4 5 9 5.5
J H,I .5 1 3 1.3