Zou_12ARC
-
Upload
arul-sujin -
Category
Documents
-
view
218 -
download
0
Transcript of Zou_12ARC
8/3/2019 Zou_12ARC
http://slidepdf.com/reader/full/zou12arc 1/4
1
Pile-soil-tunnel interaction in some layered soil profiles
J. Zou, Y. K. Chow, G. R. Dasari, C. F. Leung, C. S. Ng Department of Civil Engineering, National University of Singapore, Singapore
engp1572; cvechow; cvegrd; cvelcf & [email protected]
Abstract: This paper presents the results of a study carried out to investigate the settlement induced in existing tunnel by piles during
loading in some layered soil profiles. The function of debonding is also investigated. The analysis indicates that while the debonded
pile may be able to mitigate its effects on tunnel, the interaction behavior is strongly affected by tunnel depth to pile length ratio and
soil properties.
1 INTRODUCTION
The effect of tunneling on piled foundations is a subject of
great interest. Mair & Taylor (1997) reviewed case histories, the
results of numerical analyses and model tests relating to this
problem. A two-step procedure has also been developed for the
analysis of this problem: (i) using semi-analytical (Loganathan &
Poulos, 1998; Chen et al., 1999) or numerical solutions (Cheng
et al., 2002) to predict tunneling induced ground movements, and
(ii) analyzing the performance of pile subjected to such ground
movements (Chen et al., 1999; Cheng et al., 2002).
An interrelated problem, which has received less attention but
nevertheless is important, is that of piled foundations constructed
close to existing tunnels. Benton & Phillips (1991) analyzed the
stress changes and deformations of two existing tunnels beneath a
building founded on bored piles. The method of analysis was based on two-dimensional finite element method, and the effects
on tunnel during both construction and loading of the piles were
considered. Calabrese & Monaco (2001) performed 2-D plane
strain analysis using FLAC and evaluated the effects induced in
the existing deep tunnels by driving foundation piles. The in-
crease in stresses in the lining was also estimated. Higgins et al.
(2000) proposed a five-stage procedure based on a two-
dimensional model and analyzed the effects of installation of
piles close to existing tunnels. Responses of tunnel during both
pile installation and loading of the piles were considered;
debonding of the piles was also taken into account. But, as only
two-dimensional analyses were found in the literature, it is ques-
tionable whether they can properly simulate a truly 3-D problem.
The pile-soil-tunnel interaction problem in an urban environ-
ment deserves more attention. However, such interaction is not
well understood. This is mainly due to its complexity in the di-
versity of pile construction methods, and more importantly the
problem is truly 3-D. Typical pile and tunnel configuration is
shown in Fig. 1.
The objective of this paper is to study the effects of piles on
existing tunnel via 3-D finite element analysis. Considering large
diameter bored piles are usually used in supporting high-rise
buildings in modern cities, the effects of loads acting on bored
piles on nearby tunnel are investigated. Emphasis is placed on the
function of debonding /sleeving, which is usually taken as a
measure to mitigate the effects of pile foundations on the tunnel.
2 DEBONDING
Debonding is a commonly adopted procedure to reduce the in-
teraction between piles and tunnels. There are mainly two types
of debonding: single permanent casing debonding and double
permanent casing debonding with bituminous membrane sheets
as debonding membrane. For piles with single permanent casing,
temporary casing is usually provided to prevent the debonding
membrane on the permanent casing from being damaged during
installation. There is no uniform practice concerning how the
debonding should be carried out, e.g. some piles are required to
be debonded within a certain zone of influence, as is shown in
Fig. 2 (LTA, 1996), while others are proposed to be debonded till
above the invert of tunnels (Higgins et al., 2000).
When a pile is fully debonded, theoretically, the applied load
is transferred to the ground below the debonded zone. The actualinteraction between piles, which are debonded or not debonded,
and an existing tunnel is, however, not well understood.
Fig. 1. Tunnel adjacent to single pile.
3 METHOD OF MODELING
The simulations carried out in this paper were performed us-ing the Finite Element computer program ABAQUS (HKS,
2002). The drained condition was simulated, as long-term effects
L
pile
S
D
tunnel
soil
d
Z
P
8/3/2019 Zou_12ARC
http://slidepdf.com/reader/full/zou12arc 2/4
2
were considered to be more significant. The soil was modeled as
a linear-elastic material with a Poisson’s ratio of 0.3. Concrete
material of grade 30 was assigned to properties of both pile and
tunnel lining to simplify the present analyses. The finite element
mesh was selected after consideration of mesh arrangement and
boundaries. In ABAQUS, debonding of the pile was simulated by
creating contact between the surface of pile (Master surface) and
the surface of its surrounding soil (Slave surface) in the debondedzone, and assuming a small friction coefficient close to zero.
Fig. 2. Zone of influence and length of debonding l (After LTA,
1996).
4 PILE-SOIL-TUNNEL INTERACTION IN SOME
LAYERED SOIL PROFILES
Settlement of a tunnel due to a loaded pile is governed by
many factors, such as load on the pile, soil properties, ratio of
tunnel depth to pile length, and distance from pile to tunnel. If a
pile is debonded, settlement of tunnel will inevitably be affected.
From preliminary studies by the authors, it has been identified
that soil properties and ratio of tunnel depth to pile length are
significant factors affecting the effect of debonding. In the fol-
lowing simulations, single pile-soil-tunnel interaction in some re-
alistic layered soil profiles is investigated. The effect of debond-ing is also studied.
4.1 Typical soil profiles
There are four typical soil profiles adopted in the analyses.
Soil profile 1 at the site is constituted by Fill and Fluvial layers
down to about 12m depth, below this level are thick upper Old
Alluvium and lower Old Alluvium layers. In soil profile 2 there is
approximately 6m of made ground above 10m thick Marine clay.
Beneath Marine clay are a layer of sandy silty clay and a very
thick layer of Bouldery clay. While, profile 3 and profile 4 are
mainly made up of Kallang Formation, Old Alluvium and Kal-
lang Formation, Jurong Formation, respectively. The properties
of different soil layers, which are used in subsequent FEM analy-ses, are summarized in Table 1.
Table 1. Soil properties of four typical soil profiles.
4.2 Geometries and working load
The pile and tunnel geometries used in this study in different
soil profiles are listed in Table 2. They are chosen based on sim-
plification of realistic pile-tunnel interaction problems as follows:
(i) piles within the influence zone of tunnel are fully debonded
(refer to Fig 2); (ii) length of pile is determined based on the full
material strength with a factor of safety of 2.5. The working load
of 13250kN, determined from material capacity of pile, is applied
in all the cases.
Table 2. Geometries for pile and tunnel in FEM modeling (refer
to Figs 1 & 2).
Soil Profile1 Thickness(m) γt (kN/m3) K 0
Fill 2 19 0.5
Fluvial 10 18 0.5
Old Alluvium (upper) 8 - -
Old Alluvium (lower) 100 - -
Ф' Cu (kPa) Es (MPa)
Fill 30 - 3
Fluvial 30 - 20
Old Alluvium (upper) - 150 75
Old Alluvium (lower) - 240 120
Soil Profile2 Thickness(m) Cu (kPa) Es (MPa)
Fill 6 123 62
Marine clay 10 22 11
Sandy silty clay 2 47 24
Bouldery clay 82 477 239
Soil Profile3 Thickness(m) Cu (kPa) Es (MPa)
Fill 8 50 10
Kallang Formation 10 25 5
Old Alluvium 102 250 100
Soil Profile4 Thickness(m) γt (kN/m3) K 0
Fill 2 18 0.5
Kallang Formation 4 - -
Jurong Formation 94 - -
Ф' Cu (kPa) Es (MPa)
Fill 30 - 8
Kallang Formation - 20 6
Jurong Formation - 600 300
L (m) d (m) l (m) D (m)
Profile1 70 1.5 14 6
Profile2 42 1.5 18 6
Profile3 70 1.5 12 6
Profile4 24 1.5 6 6
t (m) S (m) Z (m)
Profile1 0.25 12 20
Profile2 0.25 12 24
Profile3 0.25 12 18
Profile4 0.25 12 12
6
Z
6 + R Z - R 34 - (Z - R)
2nd1st 3rd Reserves
l
45°
Zone of influence
40 + R
Railway safety zone
( unit: m )
Pile
Tunnel
R
d
L
P
l
8/3/2019 Zou_12ARC
http://slidepdf.com/reader/full/zou12arc 3/4
3
4.3 Selection of pile length
Practically, a normally designed pile and a pile designed for
debonding under the same working load may not have the same
length, as contribution from top soil layers is not considered in
the latter. Therefore, tunnel settlements induced by a pile with
both a normally designed length (case 1) and a debonding de-
signed length (case 2) in soil profiles 1 and 2 are examined be-fore the study of debonding effect is carried out. In both cases,
piles are not debonded, the results of which are illustrated in Ta-
ble 3, where 1t W and 2t W are settlements of tunnel in case 1 and
case 2, respectively.
Table 3. Tunnel settlement by a pile with both normally designed
and debonding designed pile length.
It can be seen that the pile length which is normally designed
in case 1, as expected, is shorter than that designed for debonding
in case 2. In profile 1, the pile length only increased by 4m if
debonding-design is used, while there is an even smaller increase
in profile 2. This is because the top soil layers are much weaker
than lower soil layers in the adopted profiles, and hence the con-
tribution of top soil layers is small. Therefore, although tunnel
settlement is reduced when a debonding designed pile length is
used, the reduction is rather small, as it is only 0.9% and 1.5% in
profiles 1 and 2, respectively.
Theoretically, normally designed pile length should be used to
study the effects of a normal pile. However, it is shown by theabove analyses that if debonding designed pile length is adopted,
it will only reduce tunnel settlement by a small amount. There-
fore, to simply the process of modeling, debonding designed pile
length will be used in the subsequent analysis comparing the in-
fluence of a normal pile and a debonded pile.
5 RESULTS AND DISCUSSIONS
5.1 Settlement of tunnel
Typical variations of settlement along the longitudinal and
transverse directions of tunnel in profile 1, when the pile is
debonded and without debonding, are illustrated in Figs 3 and 4,
respectively. It is clear that starting from the cross-section of tun-
nel which is closest to the pile (where x coordinate is zero), set-
tlement of tunnel decreases along the longitudinal direction, since
the influence of pile reduces with the increase of distance, i.e. the
distance between pile and any cross-section of tunnel. As far as
the transverse section of tunnel with the smallest distance from
the pile is concerned, larger settlement of tunnel occurs in the
side closer to the pile; and the maximum value occurs when θ is
about thirty degrees (refer to Fig 4). Similar trends of variation of
tunnel settlement can be observed from other soil profiles, but
debonding may not always reduce settlement of tunnel as it does
in profile 1. Detailed comparison is given in the next section.
5.2 Comparison of debonding effects
The maximum settlements of pile and tunnel in different soil
profiles are summarized in Table 4. Z/L is the ratio of tunnel
depth to pile length, and l is the length of debonding determined
following the code of LTA (refer to Fig 2). t W ∆ , is the differ-
ence of tunnel settlement caused by a normal pile and a debonded
pile )( tntd W W − divided by normal pile induced tunnel settle-
ment tnW (refer to Eq. 1):
%100×
−
=∆tn
tntd t
W
W W
W (1)
It is useful to provide a means of describing the effects of
debonding, e.g. a negative t W ∆ means reduction occurs in the
settlement of tunnel if the pile is debonded; while a positive
t W ∆ implies an increase in tunnel settlement due to debonding.
As expected, the settlement of a debonded pile pd W is larger
than that of a pile without debonding pnW in all the profiles.
Fig. 3. Settlement of tunnel along longitudinal direction.
Fig. 4. Settlement of tunnel in transversal section closest to pile
(θ is counter clockwise).
As far as settlement of tunnel is concerned, two types of re-
sults can be observed: (i) settlement of tunnel induced by a
debonded pile is smaller than that induced by a normal pile,
i.e. t W ∆ is negative, as is shown in profiles 1 and 3; (ii) settle-
ment of tunnel by a debonded pile is unchanged or even larger than that by a normal pile, i.e. t W ∆ is greater than or equal to
zero, as is in profiles 2 and 4.
Case 1 Case 2Pf.
L1 (m) Wt1 (mm) L2 (m) Wt2 (mm)(Wt2-Wt1)/Wt1
1 66 1.904 70 1.886 -0.9%
2 40 1.133 42 1.116 -1.5%
0 10 20 30 40 50
2.0
1.6
1.2
0.8
0.4
0.0
X (m)
W t
( m m )
Debonded
Normal
Tunnel in profile 1
longitudinal plot
0x
0 90 180 270 360
2.0
1.6
1.2
0.8
0.4
0.0
(o
)
W t
( m m )
Debonded
Normal
Tunnel in profile 1
transversal plot
0
z
y
θ
θ
8/3/2019 Zou_12ARC
http://slidepdf.com/reader/full/zou12arc 4/4
4
Table 4. Settlement of tunnel and pile during single pile-tunnel
interaction
As is well known, total load on the pile is supported by shaft
friction and base resistance. In a pile-soil-tunnel interaction prob-
lem, as a pile is loaded, the tunnel will be affected by the part of
the load taken by pile shaft (shaft load), as well as the part of the
load taken by base (base load). If total load is not changed, the
behavior of tunnel will depend on (i) the soil profile; (ii) the ratio
of tunnel depth to pile length Z/L, which has been mentioned be-
fore; and (iii) the variation of proportions of load taken by shaft
and base, which is induced by changes of working conditions of
the pile, e.g. from a normal pile to a debonded pile.
If the pile toe is relatively far from the tunnel centre, as is in
profiles 1 and 3 with a small Z/L ratio of 0.3, the tunnel will be
more affected by shaft load, i.e. main proportion of tunnel settle-
ment is induced by shaft friction. In such circumstance, if the pile
is debonded, shaft friction decreases and it will take a smaller
proportion in the total load. As a result, settlement of tunnel re-
duced by 4% and 3% in profile 1 and 3, respectively ( t W ∆ is
negative).
On the contrary, when the pile toe is closer to tunnel centre, as
is in profile 2 with a large Z/L ratio of 0.6, base load becomes
more dominant and its influence on the tunnel settlement may be
more significant. In such a situation, if the pile is debonded, base
load will increase its proportion in total load with the decrease of shaft friction. Therefore in this case, settlement of tunnel in-
creases by 2% ( t W ∆ is positive).
The soil profile plays an important role in the effect of
debonding in pile-soil-tunnel interaction. In any case for the soil
profiles studied, the effect of debonding is small, as t W ∆ is no
more than 5%.
6 CONCLUSIONS
Numerical modeling via 3-D finite element analysis enables
the estimation of the settlement of tunnel due to loads acting on
nearby piles. In this paper, single pile-soil-tunnel interaction in
some realistic layered soil profiles, was studied; the effect of
debonding was also investigated.
The results of the analysis indicate that behavior of debonding
is greatly influenced by Z/L ratio, and soil profile and properties.
While the results show some trend, the number of cases studied is
too few to generalize the explicit impact of each of these factors.
For the cases considered, the effect of debonding is small.This paper is a preliminary attempt to study only one aspect of
the pile-soil-tunnel interaction problem, namely the induced set-
tlement of tunnel. It is noted that soil is a nonlinear material; the
assumption of linear elastic soil behavior has a tendency to over-
estimate the interaction effects. These results presented will,
however, need to be verified by well-controlled laboratory centri-
fuge experiments and field studies. Another aspect of the interac-
tion behavior, namely the effect on stresses in the tunnel lining
will also need to be investigated.
REFERENCES
ABAQUS, 2002. ABAQUS User’s and Theory Manuals, Version
6.3. Rhode Island: Hibbitt, Karlsson & Sorensen, Inc.
Benton, L. J. & Phillips, A., 1991. The behavior of two tunnels
beneath a building on piled foundations. Proc. 10th
European
Conference on Soil Mechanics and Foundation Engineering:
665-668. Florence.
Calabrese, M. & Monaco, P. 2001. Analysis of stresses induced
in an old deep tunnel by pile driving from the surface. FLAC
and Numerical Modeling in Geomechanics: 199-204. France.
Chen, L. T., Poulos, H. G. & Loganathan, N. 1999. Pile Re-
sponses Caused by Tunneling. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE Vol. 125 (3): 207-215.
Cheng, C. Y., Dasari, G. R., Leung, C. F. & Chow, Y. K. 2002.
A novel FE technique to predict tunneling induced ground
movement in clays. The 15th KKCNN Symposium on Civil
Engineering: 43-48. Singapore.
Higgins, K.G., John, H. D. St., Chudleigh, I. L. J. & Potts, D. M.
2000. An example of a pile-tunnel interaction problem. Geo-
technical Aspects of Underground Construction in Soft
Ground : 99-103. Rotterdam.
Loganathan, N. & Poulos, H. G. 1998. Analytical prediction for
tunneling-induced ground movements in clays. Journal of
Geotechnical and Geoenvironmental Engineering, ASCE
Vol. 124 (9): 846 -856.
Land Transport Authority, 1996. Code of practice for railway
protection. Singapore.
Mair R. J. & Taylor R. N. 1997. Bored tunneling in the urban en-
vironment. Theme lecture to the 14th
international conference
on soil mechanics and geotechnical engineering: 2353-2385.
Hamberg.
(1) normal (2) debonded profile
W pn (mm) Wtn (mm) W pd (mm) Wtd (mm)
1 11.01 1.886 11.88 1.816
2 9.54 1.116 10.74 1.138
3 13.27 2.071 13.74 2.012
4 6.89 1.054 6.95 1.054
l (m) Z/L ∆Wt
1 14 0.3 -4%
2 18 0.6 2%
3 12 0.3 -3%
4 6 0.5 0%