Background
Zain is a leading mobile telecommunications provider in the Middle East andNorth Africa. It was started in 1983 in Kuwait, as Mobile TelecommunicationsCompany (MTC), the regions first mobile operator, and commencing with theinitiation of our expansion strategy in 2003, it grew rapidly in both the MiddleEast and Africa through the acquisition of several mobile operators across theregion.
In 2008, Zain became the 4th largest mobile operator in the world in terms ofgeographical presence, with operations in 15 African countries and 7 in theMiddle East with over 6,000 employees providing a comprehensive range ofmarket-leading mobile voice and data services to a base of over 42.7 millionactive customers as of 31 December, 2012
Name : Walid GaddouchEmail Id :[email protected] No : +965 96973338 ; +965 24641432
Number of Employees : 1100+Number of Users : 40+
-
Project Outline
Modules Implemented
Oracle Hyperion Planning &
Budgeting
Oracle Capital Asset Planning
Oracle Workforce Planning
Operating System : Windows
Server 2008R2
Virtual Machines 6 Cores @3
GHz. 3 Node Architecture
Project Kick Off Date : 10-July -
2013
Project Go Live Date : 09-March -
2014
-
Resource Details
Evosys Resource Details
Project Manager : 1
Functional Consultant : 3
Technical Consultant : 1
Client Resource Details
Project Manager : 1
-
Business Needs
Zain is spread over in 8 countries and in an such a larger organization size controlbecomes very critical as well as a difficult task for the management. In order toimplement the control over the organization it has to have an efficient system forplanning.
Inspite of being a good tool for calculations, MS Excel lacks plenty of featureswhich are required by any organization. Some of the examples of these lacking are: a consolidated Database, Security etc. thus Oracle Planning & Budgeting comesin to picture
There was no effective version control in the existing system to manage thenumber of iterations happening before final draft of budget
Zain were having no proper organizational Hierarchy for the purpose of approvalof various budgeting segments like Manpower or Operating expense
-
Standardization is also one of the major hurdles when the organization is
operating in more than one geography.
Different COA structure across Operating Cost - Mapping of these structures is
extremely necessary to derive consolidated view of the financials.
Different Ledger Currency across Opting Cost - Converting figures to single
reporting currency with a rate which is entered manually.
Business Needs Contd
-
Challenges
There were many Models to be developed like Revenue, Cost of Sale, Operating Expense,
Device Budgeting, Business Plan which made the project very complex.
Zain project is the 1st Project in Telecom Sector for Evosys and therefore domain knowledge
was one of the major challenges.
Over and above the routine budgeting of the client needed all the financial statements
including Balance Sheet, Income Statement and Cash Flow Statement not only for Actual
but also for Budget data.
Revenue and Cost of Sale are driver based budgeting which goes very much in detail.
-
Solutions
All the versions which went through the approval cycles are stored in the database
and can be visited at any point of time
Data security can be assured with respect to visibility of data of one entity or
department to the other entity or the department
Approval workflow is taken care of in particular
-
Business Benefits
Security Structure is built in such a way that individual Operating Cost can see
only their data. Consolidated picture is available at the Zain Group level.
The system is integrated with the transaction system so as to remove any
manual intervention while transferring the actual data from ERP to HPB or
transferring the budget data from HPB to ERP.
All the reports made available in the Hyperion financial reporting Studio which
are directly linked with database and refreshable.
Ad Hoc Analysis of Budget and Actual data and management reports with user
friendly interface of MS Excel.
Various Analytical reports can be created very easily and as per the
requirements of the user
-
Value Addition by Evosys
Drastic Reduction in time for Budgeting cycle by 3-4 weeks
Radical reduction in cost of budgeting due to automated Budgeting process
Individual and Consolidated Budget with the actual data along with variance
analysis time readily available at any time
Improved overall profitability through more effective workforce cost
control. Managers can understand how to optimize staffing levels to ensure
satisfactory delivery of service while maintaining the lowest effective
headcount.
Long term Planning of Revenues and Costs can be effectively done keeping
in view the actual data and the trends and the steps for improving
profitability can be taken at the right moment well in advance.
-
Questions?
-
Thank You Global HeadquarterEvolutionary Systems Pvt. Ltd.11th floor, Kataria Arcade,Beside Adani Vidya Mandir School,Behind ADANI CNG Pump,S. G. Highway,Makarba Ahmedabad 380054.Tel : +91 79 30233300, 30233301Fax : +91 79 30233399,
Follow us on -
ME HeadquarterEvolutionary Systems Arabia Fz LLC112, Building 11, Dubai Internet City,PO Box 500830, Dubai, UAEBoard: +9714-4380181Fax: +9714-4380180
Facebook
Twitter
LinkedIn
U.K./ Europe Headquarter400 Thames Valley Park DriveThames Valley ParkReading ,RG6 1PTUnited Kingdom.Tele : +44 (0) 01189 637 586Fax : +44 (0) 0118 9637 585
E-mail us at:
www.evosys.co.in
http://www.facebook.com/Evosys
http://www.linkedin.com/company/evosys
http://twitter.com/evosysoracle