YT-MF-G-06-02061
-
Upload
murali-krishna -
Category
Documents
-
view
61 -
download
0
description
Transcript of YT-MF-G-06-02061
CONTRACTOR'S STAMP:
A FOR APPROVAL KSMU PNAN/HSV JJU 25-07-2011
REV. DESCRIPTION PREPARED CHECKED APPROVED DATE
EMPLOYER:
P.M.C.:
CONTRACTOR:
SAUDI ARCHIRODON LTD
DESIGNER:
PROJECT TITLE:
YANBU II POWER AND WATER PROJECT PACKAGE 2 - MARINE FACILITIES
Project No:
7200018815
DOCUMENT TITLE:
Intake Channel Layout Study (Flow Modelling) Location:
YANBU
No. of Pages 32
Including this page
DOCUMENT NO.:
YT-MF-G-06-02061 REV.: A
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 2 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
Revision History
Rev. Section Description of change
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 3 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
Saudi Archirodon Ltd.
Yanbu II Power and Water Project, Package 2 - Marine Facilities
Intake Channel Layout Study
July 2011
COWI A/S
Parallelvej 2
DK-2800 Kongens Lyngby
Denmark
Tel +45 45 97 22 11
Fax +45 45 97 22 12
www.cowi.com
COWI Project No. A017621 / P-75406
Prepared KSMU
Checked HSV/PNAN
Approved JJU
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 4 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Table of Contents
1 Introduction 5
1.1 Project Location 5
1.2 Proposed Marine Facility 7
1.3 Scope of Work 8
1.4 Intake channel requirements and criteria. 9
2 Intake Channel Modelling 10
2.1 Modelling Approach 10
2.2 Model Description (MIKE 21 HDFM) 11
2.3 Model Bathymetry 11
2.3.1 Reference datum: 11
2.3.2 Bathymetry 11
2.3.3 Tendered Layout and Bathymetry: 13
2.4 Model Set-up 19
2.4.1 Water level Forcing 19
2.4.2 Intake conditions 21
2.4.3 Simulation time 21
2.4.4 Additional model parameters 21
2.5 Results 23
2.5.1 Flow Pattern 23
2.5.2 Maximum Current Velocities 26
3 References 32
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 5 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
1 Introduction
The power and water utility for Jubail and Yanbu (MARAFIQ) will construct a
new 850 MW (net to the grid) power and water plant for Yanbu II Industrial
City (YIC II) which will satisfy a growing demand for power, process / potable
water and seawater cooling. The project will be located at YIC II on a new plot
which is currently vacant other than an existing, operational switch-yard locat-
ed at the Northern end [ref. (COWI, 2011)].
The site will be developed in several phases. The present project includes Phase
1 of the site development only.
Saudi Archirodon has been awarded the engineering procurement and construc-
tion (EPC) contract for the marine facilities and has engaged COWI to carry out
the detailed design of this part of the project. The marine facilities comprise a
seawater intake facility and associated pumping station, tunnels, thrust blocks
and a seawater outfall. The seawater intake facility will draw water from an in-
take basin. Dredging will be required to create this facility, with suitable
dredged material being used for land reclamation and to construct the cause-
way. The pumping station will be located on the reclaimed land. Seawater will
flow in GRP pipes from the pumping station to the battery limits of the P&W
contract, where the Power & Water Contractor takes over.
Return water will be discharged at the reef edge via two GRP pipelines. The
interface between the P&W contract and the MF contract is at the intersection
between the Eastern main site boundary and the P&W discharge channel.
1.1 Project Location
The Yanbu 2 Industrial City is located in Western Province of the Kingdom of
Saudi Arabia, approximately 280 km north of Jeddah, (see Figure 1.1). Figure
1.2 and Figure 1.3, shows the project location in the Admiralty chart no 326
and satellite imagery, dated 21-June-2010, respectively.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 6 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 1.1 Project location in the Red Sea. (courtesy: Google Earth).
Figure 1.2 Yanbu 2 project site in the Admiralty chart No 326.
Jeddah
Yanbu 2 Project
Area
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 7 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 1.3 Yanbu 2 project site in the Satellite image (dated:21-June-2010).
1.2 Proposed Marine Facility
The proposed marine facilities comprise of seawater intake channel and outfall
structures. The seawater intake structure consists of two curved breakwaters.
The breakwaters are approximately 800-1000m long with roundheads located
close to the reef edge. The mouth defines the entrance to the channel, whereas
the pumping station located along the shoreline defines the end of the channel.
The seawater outfall consists of two 4m diameter GRP pipes buried in the sea-
bed. The tendered layout of the proposed cooling water intake and outfall facili-
ty for the Yanbu 2 project is presented in Figure 1.4 [ref. (ARCHIRODON, Sep
2010)].
Yanbu 2 Project
Area
Yanbu 2 Project Area
Comment [ksmu1]: Comment 8.SBAS� sentence to be reframed ??
HGLN?
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 8 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 1.4 Sketch of Tendered layout of Yanbu 2 marine facilities.
1.3 Scope of Work
COWI’s scope of work is structured as follows:
• Task A Project and Interface Management
• Task B Project Definition and Planning
• Task C Data Collection and Desk Studies
• Task D Hydraulic and Coastal Engineering
• Task E Layout Confirmation/Optimization
• Task F Seawater Intake Channel Design
• Task G Pumping Station Design
• Task H Seawater Outfall Design
• Task I Buildings
• Task J Infrastructure
• Task K Hydraulic Tests
The scope of the present study as a part of TASK E [ref. (COWI, 2011)] is to
evaluate the overall layout of the marine facilities. Initially, flow modelling will
be carried out and subsequently wave penetration modelling based on design
wave conditions at the intake mouth will be carried out.
1.4 Intake channel requirements and criteria.
The layout shall comply with the requirements of the Civil/Structural Design
Basis of Marafiq/Jacobs R214-00/C.02a/0001 [ref. (Jacobs/Marafiq, Saudi
Comment [ksmu2]: 9.SBAS� Image changed/Incorporated
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 9 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Arabia: May 2011)] The following requirements are stated in the tender docu-
ments:
1 The intake channel bed level shall be at least -10.0m MYAS and the veloci-
ty must not exceed 0.2m/sec for a distance of 100m from the mouth for a
flow rate as required in document R214-00/P.02a/0002.
2 After this 100m from the mouth point it can become shallower at an incline
of 5% to a level that keeps the velocity at 0.3m/sec or less for the ultimate
development.
3 Seawater intake currents shall not exceed 0.3m/s through the trash screens
of the Phase I pumping stations
The above requirements translate into the following operational criteria:
1 For an intake volume of 1,200,000 m3/hr (Phase IV) during lowest astro-
nomical tide [ref. (COWI, 2011)] the sectional average current velocity
shall not exceed 0.2 m/s for a distance of 100 m from the mouth of the in-
take channel.
2 For an intake volume of 1,200,000 m3/hr (Phase IV) during lowest astro-
nomical tide [ref. (COWI, 2011)] the sectional average current velocity
shall not exceed 0.3 m/s in the part of the intake channel which will be
shared by multiple pumping stations once future phases are implemented.
3 For an intake volume of 280,000 m3/hr during lowest astronomical tide[ref.
(COWI, 2011)] the sectional average current velocity shall not exceed 0.3
m/s at the screening wall of the pumping station.
Compliance with criteria 1 and 2 is demonstrated analytically (Q/A < 0.2 m/s,
Q/A < 0.3 m/s respectively). Criterion 3 will be tested with the numerical mod-
el study, which is described in the subsequent sections of this report. Comment [ksmu3]: Comment 4.TZ & 10.SBAS� HGLN?? How are we going to
include the section?
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 10 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
2 Intake Channel Modelling
The purpose of the intake channel modelling is to study in details the flow in
the intake channel, and to optimese the layout of the channel, so that the flow
into the pumping station is steady and uniform, and meet with the above men-
tioned criteria.
2.1 Modelling Approach
The modelling approach adopted is listed in the following [ref. (COWI, 2011)]:
1. The study is performed numerically with a 2D hydrodynamic flow model
(MIKE 21 HDFM model).
2. Three layouts are tested in the MIKE 21 HD/FM model: (1) The tendered
channel layout, (2) Flow optimized channel layout 1 and (3) Flow opti-
mized layout 2.
3. The model extends approximately 150 m outside the mouth of the channel
and covers the entire intake channel.
4. At the offshore boundaries of the model (at the intake mouth) the water lev-
el is defined as LAT, which is -0.40m MYAS.
5. Along the pumping station an open discharge boundary is generated with a
constant flux of 280,000 m3/hr.
6. A bottom friction of M=32 m1/3/s (Manning Number) is applied in the open
channel and along dredged sloped. A bottom friction of M=25 m1/3/s is ap-
plied on rock slopes to simulate higher roughness on rock armoured slopes.
7. The results are presented in terms of 2D colour plots with flow vectors.
Furthermore, the flow is extracted along cross sections in the channel 10 m
and 50 m from the pumping station and compared with criteria 3 in terms of
velocity sections and directional sections for the various layouts.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 11 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
In the present report the results of channel modeling for the tendered channel
layout and the flow optimized layout 1 are presented.
2.2 Model Description (MIKE 21 HDFM)
The numerical flow model applied in the present study is the MIKE 21 HDFM
(Hydrodynamic Flexible Mesh) module of the comprehensive 2-dimensional
MIKE 21 modelling system from DHI, Denmark. MIKE 21 HDFM is a model-
ling system for 2D free-surface flows. It can be applied to a wide range of hy-
draulic and related phenomena. This includes modelling of tidal hydraulics,
wind and wave generated currents, storm surges and flood waves. The HDFM
module is the basic module of the system and is used in the simulation of hy-
draulics and related phenomena in lakes, estuaries, bays, coastal areas and seas
where the flexibility inherited in the unstructured meshes can be utilized.
The applied MIKE 21 HDFM model requires the following main input for flow
simulations:
• Bathymetry of the area
• Hydrographic boundary conditions (water levels and/or fluxes)
• Wind and/or barometric pressure of the area
• Eddy Viscosity and Bed Resistance (Manning number)
2.3 Model Bathymetry
2.3.1 Reference datum:
The horizontal [ref. (Marafiq, Minutes of Meeting, 25.06.2011)] and vertical
[ref. (Jacobs/Marafiq, Saudi Arabia: May 2011)] datum are in MYAS
(YANBU) datum, [ref. (Jacobs, 2009)].
2.3.2 Bathymetry
Flexible mesh model bathymetries are prepared based on the drawings of the
intake channel for tendered layout and of the flow optimized channel layout 1
and 2, and the data from the bathymetric survey by Saudi Archirodon Ltd in
June 2011. The survey data is utilised from the reef edge upto a distance of ap-
proximately 150m from the mouth of the channel. The extent of the survey is
show in Figure 2.1, and the data from AREA A is used in the present study.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 12 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.3 shows the tendered layout, where as Figure 2.4 show the flow opti-
mised layout 1 and 2, respectively, and corresponding flexible mesh bathyme-
try used for the channel modelling simulations in the MIKE 21 HDFM model.
The area of the triangular meshes have been decreased from 50m² at boundaries
to 25m² near the study region to have a sufficiently resolved bathymetry close
to the breakwaters and in the dredged channel. To resolve the breakwater slopes
adequately a quadrangular mesh has been applied on the slopes of the breakwa-
ters.
The intake channel is protected by two curved breakwaters on each side ap-
proximately 800-1000m long as shown in Figure 2.2. The natural water depth
outside the channel mouth is deeper than -10m.
Fot the tendered layout and optimised layout , the inner channel is dredged to a
depth of -10 m MYAS from mouth to the pumping station as shown in the Fig-
ure 2.3 and Figure 2.4. where as for flow optimised layout 2 the depth of the
intake channel is varying between 6.5m to 10m. The width of the dredged
channel is varying from 130-150m and the breakwaters slopes are of varying
width. The width of the pumping station is approximately 60m for tendered
layout and ~70m for both the flow optimised layout 1 and 2.
Figure 2.1 Survey areas for Yanbu 2 project.
Comment [ksmu4]: 11.SBAS� sen-
tence to be reframed ?? HGLN?
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 13 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.2 Survey data overlayed on the tendered plan layout of Yanbu 2 project.
2.3.3 Tendered Layout and Bathymetry:
The tendered layout is based on the drawing 0132.TD.CAT.0004 dated Sep,
2010. Figure 2.3 shows the tendered layout and flexible mesh bathymetry for
tendered layout used in the modelling.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 14 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.3 Tendered Layout drawing (above) and corresponding Flexible mesh
bathymetry used for the Channel modelling (depths relative to MYAS).
Flow Optimized Channel Layout 1 and Bathymetry:
Based on the results of flow pattern in the tendered layout, a revised flow opti-
mised intake channel layout 1 drawing was prepared on 08 july 2011. Figure
2.4 shows the layout plan and flexible mesh bathymetry for flow optimised lay-
out 1.
Figure
2.8
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 15 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.4 Flow optimised layout 1 drawing and corresponding Flexible mesh ba-
thymetry used for the Channel modelling (depths relative to MYAS).
Flow Optimized Channel Layout 2 and Bathymetry:
Based on the results of flow pattern in the flow optimised layout 1, a revised
flow optimised layout 2 drawing was prepared on 25 August 2011. The depths
near the channel entrance and at the pumping station dredged to 10m and rest
of the channel is dredged to 6.5m. The width of the channel slopes depends on
Figure
2.9
Formatted: Font: (Default) Arial, 10pt, Bold, Complex Script Font: Arial,Highlight
Formatted: Highlight
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 16 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
the channel depth. Figure 2.5, shows the layout plan and flexible mesh bathym-
etry for flow optimised layout 2.
Figure 2.5 Flow optimised layout 2 drawing and corresponding Flexible mesh ba-
thymetry used for the Channel modelling (depths relative to MYAS).
Fig-
ure
2.10
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 17 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
The intake channel basin is protected by breakwaters of dredged material, quar-
ry rock and concrete armour units if required by the final design. Tentative
cross sections of the intake breakwaters roundheads and of the breakwater
trunks are shown in Figure 2.6 and Figure 2.7.
The roundheads of the breakwaters are located near the reef edge at a water
depth of approximately -0.5m MYAS. The slopes of the breakwaters are well
resolved in the bathymetry as shown in the Figure 2.8 to Figure 2.8Figure 2.10
Figure 2.6 Intake Breakwater, tentative section at roundhead.
Figure 2.7 Intake Breakwater, tentative section at breakwater bend.
Field Code Changed
Comment [PNAN5]: Tese are the fig-ures in the latest design basis. However, we
now have new c/s which bhaskar is making
without accropodes
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 18 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.8 Fleximesh bathymetry at the breakwater bend in the Tendered Layout.
Figure 2.9 Fleximesh bathymetry at the breakwater bend in the Flow optimised
layout 1.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 19 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.10 Fleximesh bathymetry at the breakwater bend in the Flow optimised
layout 2.
2.4 Model Set-up
The model is driven by the intake flux at the pump station end and tides at the
mouth of the channel. The tide are applied as water level boundary condition.
Furthermore, the model is influenced by friction in the model in terms of bed
friction and eddy viscosity. Each of these parameters used for the HDFM simu-
lations are described below.
2.4.1 Water level Forcing
The most critical condition is assumed to arise when the pump station is func-
tioning at its full capacity during the Lowest Astronomical Tide(LAT). Accor-
ing to Admiralty Tide Tables, the combined effect of seasonal variations and
tide defines LAT as being 0.56 m below MSL [ref. (Office, 2009)] (i.e., -0.40
m MYAS). A constant water levels of LAT is applied on the open east, west
and south boundaries outside the channel, as shown in the Figure 2.11. The
boundary to the south is located at a distance of approximately 150m from the
mouth of the channel, to minimise boundary instabilities in the model.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 20 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.11 Boundaries defined in the channel modeling for the Tendered layout
(abovetop),Flow optimised layout 1 (middle)) and Flow optimised lay-
out 2 (bottom)..
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 21 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
2.4.2 Intake conditions
The inflow and discharge rates at the pumping station are summarised in Table
2.1 [ref. (COWI, 2011)]. The intake sinks are modelled as discharge boundary
near the pumping station, the discharge boundary acts as line sinks with con-
stant flow out of the model. The line sink boundary near the pumping station
for tendered layout and flow optimised layouts 1 & 2 are shown in the Figure
2.11.
Table 2.1 Yanbu 2 Power and desalination plant cooling water systems intake
operating conditions.
Properties Tendered Layout Flow Optimised Lay-
out-1
Flow Optimised Lay-
out-2
Flow rate
(inflow/outflow)
77.778 m3/s
(280,000 m3/h)
77.778 m3/s
(280,000 m3/h)
77.778 m3/s
(280,000 m3/h)
Location E 32900, N 27555 E 32875, N 27579 E 32875, N 27579
Pumping Station
Width
~60m ~70m ~70m
Water Depth -10m (MYAS) -10m (MYAS) -6.5 to -10m (MYAS)
2.4.3 Simulation time
Initial trail runs showed that the flow stabilized after 1hour of the simulation
period and attaining a steady state condition approximately after 3 hours. To
make the model more conservative the simulations for tendered layout and flow
optimised layout 1 were carried out for 24 hours.
2.4.4 Additional model parameters
The bed resistance in the model varies in the channel. Along the natural seabed
and dredged channel a normal friction of 32m⅓/s (Manning number) is used.
On the breakwater rock slopes a friction of 25 m⅓/s is used and near the bound-
aries to attain the stability a friction of 5-10 m⅓/s is used. Figure 2.12 shows the
bed resistance maps for tendered layout and for both flow optimised layouts 1
& 2.
A constant eddy viscosity based on the Smagorinsky formulation with a propor-
tionality constant of 0.28m2/s is used in the simulation (model default). A sensi-
tivity test has been carried out with and without eddy viscosity forcing to check
the formation of eddies in the model. The results showed no effect on the for-
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 22 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
mation of eddies in the tendered layout, hence a default value of 0.28m2/s is
used in the simulations.
Figure 2.12 Bed Resistance Map of Intake channel for Tendered Layout (abovetop),
flow optimised layout 1(middle) and flow optimised layout 2 (belowbot-
tom) showing various manning numbers used in MIKE 21 HDFM model
Various input parameters are summarised in Table 2.2.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 23 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Table 2.2 MIKE 21 HDFM model parameters used in calibrated local flow model.
Parameter Value
Start date 12/12/2008
End date 12/13/2008
Timestep 5s
Drying and flooding, drying depth 0.1m
Drying and flooding, flooding depth 0.2m
Drying and flooding, wetting depth 0.3m
Eddy viscosity, Smagorinsky coefficient 0.28 m2/s (default)
Bed friction, Manning number M = 32 m1/3
/s(natural seabed )
M = 25 m1/3
/s(Breakwater Armour)
2.5 Results
2.5.1 Flow Pattern
The flow patterns and the current velocities in the channel during the LAT for
the tendered layout and for flow optimised layouts 1 & 2 are shown in Figure
2.13 and Figure 2.12, respectively. The simulations show that for both tendered
layout and for both flow optimised layouts 1& 2 the highest current velocities
occur near the pumping station mouth end of the intake channel. In the tendered
layout, formation of vortices/eddies is seen at the west breakwater slope near
the pumping station, while the flow is smooth in the flow optimised layouts 1 &
2 (see Figure 2.14 & Figure 2.15). In most parts of the channel the current ve-
locity does not exceed 0.1 m/s in the case of tendered layout and 0.12m/s for
flow optimised layouts 1 & 2.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 24 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.13 Flow pattern and current velocity during LAT in the tendered layout
(abovetop), and Flow optimised layout 1(middle) and Flow optimised
layout 2 (bottom)(below).
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 25 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.14 Flow vectors near the pumping station during LAT in the tendered Lay-
out (abovetop) and Flow optimised layout 1(belowbottom).
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 26 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.15 Flow vectors near the pumping station during LAT in the tendered Lay-
out (above) and Flow optimised layout 12(below).
2.5.2 Maximum Current Velocities
Figure 2.16 and Figure 2.14 shows the simulated maximum current velocity
during the 1day simulation period for tendered layout and for flow optimised
layouts 1 & 2, respectively. In the tendered layout the maximum current veloci-
ties of 0.14-0.16m/s are observed near the pumping station and 0.08-0.10m/s in
some areas inside the channel. In the flow optimised layouts 1& 2, the maxi-
mum current velocities are of the order of 0.10-0.12m/s near the pumping sta-
tion and near the west breakwater bend. These higher velocities are observed
across the rock armoured slopes and are thus not expected to stir up sediments.
However, for most areas in the middle and outer parts of the channel, the intake
velocities does not exceed 0.1m/s in both layouts. The inflow velocities close to
the mouth of the channel are about 0.02m/s for both tendered layout and also
for both flow optimised layout 1 & 2. The velocities in the flow optimised lay-
out 2 are slightly higher than that of flow optimised layout 1, due to reduced
depth in the middle of the channel and less cross sectional area of the channel
in flow optimised layout 2.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 27 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.16 Maximum current velocities in the Tendered layout (top), flow opti-
mised layout 1 (middle) and flow optimised layout 2 (bottom) during the
simulation period.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 28 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
The flow across the channel has been extracted along cross sections in the
channel at a distance of 10m and 50 m away from the pumping station as
shown in the Figure 2.17, for both the tendered layout and also for flow opti-
mised layout 1 & 2. The cross sectional flow velocities and directions of simu-
lation after a steady state condition attained in the model are presented in Fig-
ure 2.18 and to Figure 2.20Figure 2.17.
Figure 2.17 10m and 50m cross section lines extracted in the channel layouts.
Figure 2.18 Cross section flow velocities and direction at 10m and 50m from the
pumping station in tendered layout during the simulation.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 29 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.19 Cross section flow velocities and directions at 10m(Top) and
50m(Bottom) from the pumping station in flow optimised layout
1(below)& 2 during the simulation.
Formatted: Font: 10.5 pt, Italic,Complex Script Font: 10.5 pt
Formatted: Font: 10.5 pt, Italic,Complex Script Font: 10.5 pt
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 30 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
Figure 2.20 Cross section flow directions at 10m(Top) and 50m(Bottom) from the
pumping station in flow optimised layout 1& 2 during the simulation.
Formatted: Font: 10.5 pt, Italic,Complex Script Font: 10.5 pt
Formatted: Font: 10.5 pt, Italic,
Complex Script Font: 10.5 pt
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 31 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
The results of the cross section flow velocities shows that:
1. Speed 10m from the pumping station is higher than the speed 50m from
the pumping station, for both the tendered layout and for both the flow
optimised layouts 1 & 2. The tendered layout shows a flow velocity of
0.14m/s and 0.09m/s at 10m and 50m cross section, respectively.
Whereas the flow optimised layout 1 & 2, shows slightly lower veloci-
ties of 0.11m/s and 0.09m/s at 10m and 50m cross sections, respective-
ly, though the velocities in the later beingare slightly higher. in the flow
optimised layout 2.
2. The flow velocities are more symmetrical in the flow optimised layouts
1& 2 compared to the tendered layout.
3. The flow in the tendered layout is spread over a wider area compared to
the flowthat in the optimised layouts 1 & 2, due to the reduced channel
width close to the pump house in the two flow optimised layouts 1&2.
4. Flow directions close to the pump house are nearly the same in both the
flow optimised layouts, though they are more variable in the tendered
layout.
5. The flow criteria 3 (Section 1.4), i.e. the cross section flow velocities
should be less than 0.3m/s during LAT for a flow volume of 280,000
m3/s, is met by both the tendered layout and flow optimised layouts 1
and 2.
5. The flow pattern of the flow optimised layout 2 are considerably good
with reduced channel depths of 6.5m in middle of the channel and with
narrow channel and breakwater slopes.
SAUDI ARCHIRODON LTD
Intake Channel Layout Study
Doc. No.: YT-MF-G-06-02061
Revision: A
Date: 25 July 2011
Page: 32 of 32
CONTRACT Nº. 7200018815
YANBU II POWER AND WATER PROJECT - PACKAGE 2 - MARINE FACILITIES
YT-MF-G-06-02061 - Intake Channel Layout Study - Rev B.docx .
3 References
ARCHIRODON. (Sep 2010). Marine Facilities Plan View.
COWI. (2010). Rabigh Power Plant No. 2 - Design Sheet.
COWI. (2011). Preliminary Design Basis, Marine Structures. Doc No: YT-
MF-G-06-02023, YANBU II POWER AND WATER PROJECT
PACKAGE 2 - MARINE FACILITIES.
Jacobs. (2009). Yanbu 2 Power And Water Project - Overall Site Datum Plan
(Rev. E).
Jacobs/Marafiq. (Saudi Arabia: May 2011). Drawing No: R214-00/C.02a/0001
Civil/ Structural Basis of Design, 0th edition.
Marafiq. (17.05.2011). Agreement between Saudi Archirodon and Marafiq:
Confirmation of Water Quantities.
Marafiq. (25.06.2011). Minutes of Meeting.
Office, U. K. (2009). Admiralty Tide Tables (vol 3) - Indian Ocean and South
China Sea.