Year 1 Progress Report & Cost Statements submitted to EC - 17 March 2004 Receipt acknowledged by EC...
-
Upload
jordan-lyons -
Category
Documents
-
view
216 -
download
0
description
Transcript of Year 1 Progress Report & Cost Statements submitted to EC - 17 March 2004 Receipt acknowledged by EC...
Year 1 Progress Report & Cost Statements submitted to EC - 17 March 2004 Receipt acknowledged by EC but no other feedback
24% of total €1.8m budget spent in Year 1.
Personnel expenditure - 36% of 3 year budget
Travel expenditure – 25% of 3 year budget
Subcontract & ‘Other’ expenditure – 2% of 3 year budget
New Project Officer ‘Ulrich Karock’ assigned to evitherm
No indication yet of when Year 2 advance payment will be made – hopefully in May!
8 New members officially accepted into evitherm project Assotec - WP1 and WP2
SciTe B.V. – WP1 and WP2
Nestle – WP3
Daimler Chrysler – WP3
EADS – WP3
Testo – WP3
Hot Disk – WP4 (in place of TNO)
AIPT – WP6
+ Nutrifreeze – exiting WP3 member – now also in WP2
Air Products (WP 3) requested to resign from project on 5 April
EC agreed remaining budget for Air Products can be reallocated to PTB for activities in WP3
RA chasing Air Products to get formal letter of withdrawal from project. This, together with revised CPFs for Air Products and PTB and updated WP3 text for DoW needed by EC to formalise the change in contract
SP (existing WP4 member) to be given budget to coordinate the Scandinavian and Baltic region in the framework of WP3
Revised CPF sent to EC
Awaiting official approval of this contract change
Budget available for additional new members
WP1 – 1 new member
WP3 – 1 new member
WP6 – 1 new member
Budgets available for ‘invited participants’ (T&S costs only) in all WPs (except WP2) – See DoW for details
The Mid-Term Report should:
Provide a critical overview of the project achievements against planned objectives (milestones, deliverables). It must NOT be a repetition of the 12 month Progress Report
Cover the entire project up to the mid-term assessment
Be 20-25 pages in length
Mid Term Report and Assessment Meeting
Target dates agreed with Ulrich Karock:
Basic draft Mid-Term Report by early August
Mid-Term Assessment meeting (at NPL) early September*
Final Mid-Term Report by end of September
* SG members to advise RA of dates in early September when they are available to attend the M-T meeting
Extension to deadline for Mid-Term Assessment Report/Meting requested because of:
Revised launch date of evitherm ‘Free Access’ website – now planned for end of June 2004 (reported in 12 month Progress Report)
AND
To provide extra time to develop an appropriate constitution and business plan for the ELE
Based on this report and discussions at the Mid-Term Assessment meeting, the Commission will:
Decide on the continuation, modification or termination of the project !
It is therefore essential that we achieve all stated Mid-Term milestones (see DoW and 12 Month Report for details)
In particular we must:
Launch the Free-access website by end of June 2004
Show progress towards the pay for access website
Deliver an ELE constitution and business plan that achieves sign-up by a majority of evitherm project members (Target is 75%) and is acceptable by the EC