YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

18
YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS June 2017 Greetings from Facilities! The June issue of this newsletter contains the latest information related to Facilities Management programs and projects, along with general information concerning the campus master plan and subsequent capital improvements. If you have questions about any of the items listed, please e-mail me at [email protected]. The newsletter will also be posted on the Facilities web site. College Wide Campus Master Plan Phase 1b Allied Health/EMS/JTED Health Occupation Programs At the new Prescott Valley Center addition, framing is underway along with the installation of fire sprinklers, HVAC duct work and electrical rough-in. Framing has started on the second floor along with waterproofing, the setting of mechanical components, a stairwell and an elevator shaft. The exterior of the building is receiving windows and architectural panels along with the roof and exterior stairway. The building is expected to be “dried in” by June. The east side of the site has been graded for the additional parking and storm water detention pond. Panther Path is being widened and repaved by the Town of Prescott Valley, and the College is constructing a new side walk, curb and gutter. The Town is making major improvements to Glassford Hill and Long Look Roads, which has significantly increased construction traffic around and at the Prescott Valley Center, so please use extra caution when traveling to and entering the site. Demolition has begun in preparation for the EMS labs on the second floor of Building 2 on the Prescott Campus. Demolition will continue the first week of June followed by framing, electrical and plumbing rough-in. The EMS garage is nearing completion as interior and exterior trim work continues, along with final site grading, paving and dumpster enclosure construction. Dumpsters will be moved to this location from the service area at the rear entrance of Building 3.

Transcript of YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Page 1: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

YAVAPAI COLLEGE FACILITIES

MANAGEMENT NEWS

June 2017

Greetings from Facilities!

The June issue of this newsletter contains the latest information related to Facilities

Management programs and projects, along with general information concerning the

campus master plan and subsequent capital improvements. If you have questions about

any of the items listed, please e-mail me at [email protected]. The newsletter will

also be posted on the Facilities web site.

College Wide Campus Master Plan Phase 1b

Allied Health/EMS/JTED Health Occupation Programs

At the new Prescott Valley Center addition, framing is underway along with the

installation of fire sprinklers, HVAC duct work and electrical rough-in. Framing has

started on the second floor along with waterproofing, the setting of mechanical

components, a stairwell and an elevator shaft.

The exterior of the building is receiving windows and architectural panels along with the

roof and exterior stairway. The building is expected to be “dried in” by June.

The east side of the site has been graded for the additional parking and storm water

detention pond. Panther Path is being widened and repaved by the Town of Prescott

Valley, and the College is constructing a new side walk, curb and gutter.

The Town is making major improvements to Glassford Hill and Long Look Roads, which

has significantly increased construction traffic around and at the Prescott Valley Center,

so please use extra caution when traveling to and entering the site.

Demolition has begun in preparation for the EMS labs on the second floor of Building 2

on the Prescott Campus. Demolition will continue the first week of June followed by

framing, electrical and plumbing rough-in.

The EMS garage is nearing completion as interior and exterior trim work continues,

along with final site grading, paving and dumpster enclosure construction. Dumpsters

will be moved to this location from the service area at the rear entrance of Building 3.

Page 2: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

The updated construction schedule is as follows:

1. Construct EMS Garage for Ambulance Parking at Prescott – March through

June 16, 2017

2. Prescott Valley Center Parking Expansion – December 2016 through June 30,

2017

3. Prescott Valley Center Addition – January 2017 through August 2017

4. Prescott Valley Center Addition Floor 2 Completion - December 2017

5. Building 2 Interior Remodel – May through August 2017

6. Prescott Valley Center Existing Space Remodel – June through August 2017

7. Move JTED from Centre Pointe to Prescott Valley – July/August 2017

8. Move Allied Health to Prescott Valley Center – July/August 2017

9. Move EMS from Prescott Valley Center to Building 2 – July/August 2017

The goal of the construction and design team is to ensure that classroom and lab

spaces are ready for students at the start of the Fall 2017 semester.

Parking Lot Grading with the Building Addition in the Background

Page 3: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

New Curb and Gutter and Sidewalk Preparation at Panther Path

First Floor Framing HVAC Install and Fire Sprinklers

Page 4: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Second Floor Window Installation/Weather Proofing and Framing for Drywall

New Sidewalk at EMS Garage

Page 5: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

EMS Garage

Building 2 Second Floor Demolition for EMS

Page 6: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Buildings 1 and 15 Renovation

Demolition of the second floor of Building 1 in preparation for Visual Arts is complete.

Framing is complete and plumbing, electrical and mechanical rough-in continues.

During the month of June, drywall will be installed and floor preparation will occur.

In Building 15 the demolition of the first floor is complete and framing is underway.

Exterior windows are cut and plumbing is being roughed-in.

Demolition of the second floor is nearing completion.

The tentative schedule for the renovation of both buildings is as follows:

Building 1 Rooms 200, 203, 204, 205 and 206 May 15 – August 15, 2017

Building 15 Floor One May 15 – August 15, 2017

Building 15 Floor Two August 15 – January 15, 2018

Building 1 Second Floor Framing for Visual Arts Programs

Page 7: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Building 15 Second Floor Demolition

Building 15 First Floor Framing

Page 8: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

SmithGroup/JJR McCarthy Building Companies

Project Manager: David Laurence

Logistics/Moving: Chris Larson

Sedona Center Renovation

Interior work in the west wing consists of setting kitchen equipment in the cullinary and

pastry kitchens. Office and wash room are being fit with millwork and sinks. Walk-in

coolers and freezers are installed in basement level store room.

East wing storefront windows are installed as well as in the new café area. Remaining

east wing spaces are being prepped for flooring.

The exterior space over the café is painted and clerestory installed along with

architectural lighting.

The exterior walkway leading to the new front entrance has new colored concrete and a

shade structure added. Project substantial completion is scheduled for July 1.

Setting Equipment in Pastry Kitchen

Page 9: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Setting Kitchen Equipment in Culinary

Kitchen Equipment in Culinary

Page 10: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Shade Structure

Enclosing Café Space with Storefront Glass

Page 11: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Preparing New Front Entrance for Colored Concrete

SPS+ McCarthy Building Companies

Project Manager: David Laurence

Logistics/Moving: Chris Larson

If you would like more information about the campus master plan or implementation

schedule, please go to http://masterplan.yc.edu/ . This site is updated on a regular basis

as new information concerning project progress becomes available.

LANDSCAPE PROJECTS

Building 29 Improvements

Work is completed for the Building 29 Landscape and Improvements project.

Page 12: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Building 29 Landscape Project

Buildings 29, 30 and 31 Commons

Project Manager: Mike Kervin

Page 13: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

PREVENTIVE MAINTENANCE PROJECTS

As part of the budget, preventive maintenance projects are scheduled each year to

ensure that College facilities are maintained at a level to support optimum performance

in building systems, infrastructure, life safety, roadways and parking, along with College

grounds. These projects are the result of a recent Facilities Condition Assessment

(FCA) which identifies when repairs, modifications or replacement of components

should occur.

Future FCA Projects: Building 15 Roof – July 2017 Building 3 Breezeway Decking Leaks – TBD/FY18 Building 4 Breezeway Decking Leaks – TBD/FY18 Phase 1 Baseball Field Drainage – TBD/FYFY18 Phase 2 Prescott Waterline Replacement - TBD/ FY18 Phase 1 CTEC Parking Lot Drainage and Expansion – TBD/FY18 For more information, please see the Prescott site map below for a list of summer preventive maintenance and capital improvement projects.

Page 14: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Summer Schedule at the Prescott Campus

Page 15: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Building 7 Parking Lot and Water Line Replacement

Verde Valley Campus Parking Lot Fogging

Page 16: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Risk and Emergency Management

In the 1987 film Planes, Trains and Automobiles, stars John Candy and Steve Martin foolishly

ignore the warnings of passing motorists.

Most will agree that the above movie scene was very funny, but driving

the wrong way in real life is deadly serious. According to the NTSB, 300-

400 people die each year as the result of wrong way driving (“WWD”). In

Arizona alone, there were 1,600 WWD incidents reported to police in

2016. Many more are thought to have occurred, but were resolved

without a collision and not reported. WWD accidents have a much higher

fatality rate because many result in head-on collisions, which can be severe even at slow

speeds.

The Prescott campus is no exception. Yavapai College Police report that motorists are observed

travelling the wrong way on campus roads on a daily basis! Fortunately, there have been no

serious accidents – yet.

Page 17: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Most of these incidents happen when drivers heading east on Sheldon St. turn

left onto Marston Ave. at the main entrance. Drivers mistakenly stay left of the

median heading into the three lanes of traffic exiting the campus. Other areas

include the rotary (aka roundabout or circle) and vehicles leaving the parking

lot at building 28 (right turn only).

In an effort to reduce the amount of WWD, certain curbs have been painted

with high visibility yellow paint and in the next couple of weeks additional signage, road

markings and reflectors will be installed. In addition, the City has agreed to paint turn guide

lines at the Sheldon St. and Marston St. intersection.

Current Entrance

Page 18: YAVAPAI COLLEGE FACILITIES MANAGEMENT NEWS

Future Entrance

Please take care driving on campus, obey the 15 mph speed limit, follow the signs and watch

for pedestrians! Together we can keep each other safe!

FACILITIES MANAGEMENT NEW TEAM MEMBERS

No new Facilities team members this month, but we are still looking to fill the vacated

HVAC Technician position at the Prescott Campus and recently vacated Lead custodian

at Clarkdale.

Well that’s all for this edition of Yavapai College Facilities Management News. Please

stay tuned for the next edition containing the latest information related to projects and

programs around the College.