Yarn Manufacture I : Principle of Carding and Drawing Prof. R. … · 2018-10-05 · Yarn...
Transcript of Yarn Manufacture I : Principle of Carding and Drawing Prof. R. … · 2018-10-05 · Yarn...
Yarn Manufacture I : Principle of Carding and DrawingProf. R. Chattopadhyay
Department of Textile EngineeringIndian Institute of Technology, Delhi
Lecture - 18Significance of Process Parameters
So, now we are going to discuss the Significance or the importance of different Process
Parameters.
(Refer Slide Time: 00:28)
Roller setting is one of the very important process parameters in draw frame. So, the
setting depends upon fibre length that is either 2.5 percent span length or 5 percent AFIS
length for cotton or staple length for manmade fibres it also depends upon the linear
density or the bulk of material between the rollers. And it also depends upon the level of
entanglement and parallelization of fibres in the sliver. So, these three are very important
factors that governs this sitting.
(Refer Slide Time: 01:10)
Here is a guideline for draft as well as roller setting on draw frame. So, draft if you look
at the table broad breaker and finish or draw frame the setting guidelines and the break
drafts are shown. Breaker draw frame is the first passage that we give to the card sliver
that is known as breaker draw frame or breaker drawing process. Then the drawn slivers
are again passed once more on second draw frame again. And this is known as the
second passage will be known as finisher drawing passage.
And, if we look at this setting part now, you can see that the back zone setting for carded
cotton as an example we have chosen 2.5 percent span length plus 10 mm the brake draft
could be 1.7 and the front zone the draft could be the rest of the draft, because most of
the draw frames we will have basically two drafting zones, and the setting in the front
zone it is 2.5 percent span length plus 6 mm.
Therefore, if we look at and compare the settings between the front and back zone what
we see is that, in the back zone span length plus 10 millimeter in the front zone it is span
length plus 6 mm. And same is true for the finisher passage also the setting in the back
zone is again 2.5 percent span length plus 12 mm and in the front zone it is 2.5 percent
span length plus 8 mm the setting can be done on the basis of f is 5 percent length as
well.
(Refer Slide Time: 03:25)
So, generally what we have seen from this table is this that the setting in back zone is
little wider than their setting in the front zone.
Now, why it is wider what are the reasons? So, we are discussing right now about the
breaker draft and passage all right. So, what happens that we feed card sliver and there
are lot of entanglements of fibres in the card sliver. So, because of these entanglements
which are present, and fibre also highly crimped and in a hook state the sliver can extend
more. So, a card sliver has the ability to extend more in comparison to the drawn sliver
or combed sliver made from the same fibre. So, because it can extend more before the
sliding action actually starts, hence we need a little wider setting in the back zone.
So, that we make sure that the sliding action commences and before that the sliver has to
extend. So, sufficient space has to be there to accommodate the extended sliver. Other
thing is that there is a high drafting force due to fibre entanglement, and bulk being more
in the back zone. In the back zone always the mass of material is more and because of
the presence of entanglement there will be very high drafting force; the high drafting
force mainly two plucking of fibres from the back roller nip.
So, we will not allow the drafting force to increase too much. And hence what we have to
do; we have to reduce the force and we can achieve it by widening the setting that is why
we have to keep the setting little wider also in the back zone.
(Refer Slide Time: 05:41)
If we compare the setting between breaker and finish a draw frame, you have to
understand what is the difference in the sliver which are fed to the breaker draw frame
and which are fed to the finisher draw frame. What we have seen is this that they are
setting a little wider in the breaker than in the finisher. In the finisher there is also a
chance for the setting to be kept at a higher level because of the reason which is stated
here that once the fibres or the slivers have undergone one draw frame passages there is
increase in the extent of fibre there is lot of straightening out action which has happened.
Because of the straightening out actions and removal of hooks removal of crimps the on
an average the fibres have extended now.
Now, when the fibres are little longer because of being certain out, we have to keep a
little increase setting in the back zone and also in the front zone. Therefore, in the
finisher draw frame we keep a little higher setting in comparison to the breaker because
fibre extent has changed fibres have straightened out. And hence we require little more
setting that is wider distance between the roller nips.
Now, what is the influence of roller setting?
(Refer Slide Time: 07:42)
If you look at the diagram which is on the right hand side top part what we see here that
as we increase setting, the irregularity of the drafted product is going to decline first and
then is going to increase. So, it passes through a minima and we have already now
discuss this points in some other previous lectures.
So, its almost its going to repeat it again. So, there is always an optimum setting between
the rollers at which the irregularity in the delivered sliver becomes minimum. If the
setting is increased beyond this optimum there is irregularity increases as there will be
inadequate control on the movement of short fibre, because if we increase the setting too
much most of the fibres will behave like short fibres. And therefore, they will move in a
erratic manner within the drafting zone and as a result there will be increase in
irregularity.
When the setting is low, the irregularity may also increase as many fibres will be
simultaneously gripped or nipped by both the nips of the drafting rollers and they will be
pulled out in the form of a bunch from the back roller nip and hence there is a there is an
increase in irregularity. So, that is why we get a minimum too wide setting is bad, too
narrow setting is also bad. Therefore, keeping in mind the length of the fibres and the
proportion of short fibres which are there, we have to find out what is the right setting
that we should keep so that we can minimize the generation of irregularity.
It is not that we will be able to avoid the generation of irregularity any drafting will
always lead to some now some increase in regularity, but we have to try to minimize the
generation by optimally adjusting the setting between the rollers.
(Refer Slide Time: 10:10)
Influence of sliver hank or sliver bulk; now this diagram which is shown here we are
showing here how the with the increase in setting how the irregularity is changing for a
single sliver for a double sliver and for six slivers combined together.
So, there are three different color lines indicating the number of slivers being fed to the
machine with the optimum setting if we feed more slivers to the drafting unit drafting
wave will be visible in the delivered sliver why? With the increase you know sliver bulk,
because as we feed more sliver bulk comity there is going to increase the drafting force
is going to increase which may cause fibres to be plucked from the back roller nip
causing rise in it is regularity.
So, the optimum setting that we get for single sliver, let us say if I keep the setting at that
level and feed two slivers. Then we will find that we are not getting an optimum there
you have to move towards the right hand side, and you will get a new setting where we
will find the optima for double sliver being fed together
similarly at that level of setting which you have obtained for two slivers if I increase the
number of slivers that is from 2 to if we go to 6, then we will find that one is there is a
increase in the irregularity and there the minima the optimum setting is actually shifting
towards the right hand side; is all because there is a increase in bulk there is a increase in
drafting force. So now, the situation is different when I feed more and more sliver, and
again you have to find out where the new optima is.
So, depending upon the number of sliver that you feed, bulb being different we have to
find out where is the new optima. So, as we change the number of sliver that you feed
you have to again find out where the new optimum lies as we move from 5 sliver to 6 6
to 7 7 to 8.
(Refer Slide Time: 12:50)
Other than sitting the next process parameter is delivery rate, at what speed you should
produce this sliver. The delivery rate has to be judicially decided based on type of fibre,
that is whether the fibre is manmade or cotton.
And if it is cotton whether it is carded cotton or combed cotton and it also depends upon
the condition of the machine how old the machine is. What is the recommended speed
suggested by the machine manufacturers. Whenever we buy a machines the machine
manufactures such suggests certain speed for different fibres. So, they already know that
at what speed the machines would run from the engineering point of view.
Going beyond the recommended speed whatever has been suggested by the machine
manufactures may lead to two things, one is roller vibration and noise. The vibration will
introduce irregularity into the draft get sliver, that is why the machine manufacturers
suggest certain speed and one should not try to go beyond their speed in order to enhance
the productivity, because the engineering design of the machine in terms of bearing in
terms of the load that is acting on different parts the dynamic forces which acts on the
machine parts all these are designed for a certain range of speeds only.
If I go beyond that, then there is a chance of vibration there is a chance of noise and
hence any vibration we will lead to generation of irregularity. But typically their speeds
which are used or so, shown on the right hand side one manmade fibre it can vary
between 300 to 500 meters per minute combed cotton 300 to 600 meters per minute
carded cotton, 400 to 800 meters per minute and viscose rayon 400 to 800 meters per
minute.
So, what we see that for carded cotton and viscose rayon the range of speed is little more
than combed cotton or more in comparison to manmade fibres. So, what is the reason for
this? Well possessing manmade fibres other than viscose rayon. Viscose rayon is the only
exceptions right we have seen that the speeds of processing is same or similar to what we
give for carded cotton
But for other fibre like polyesters that is see, which is very popular fibres and processed
the speed is less.
(Refer Slide Time: 16:10)
We will discuss why the speed is less the other factors which can affect the speeds are
fineness of the fibre. The fibres are very fine even for cotton fibre to the fibres are fine
then we have to reduce the speed because the incidence of frequent lapping that we have
to remember that the rollers get lapped. The drafted wave has a tendency to follow the
curvature of the roller and at times they follow it and get wrapped around it. And, that
leads to basically breakage of the sliver or it may lead to theme players getting generated
in this sliver. So, these lapping incidence has to be reduced and this is more with fine
fibres because fine fibres are they have less bending rigidity, they are flexible and
compression to coarse fibres. So, we find incidents of lapping more on fine fibres.
So, for the same type of fibre if it is cotton or if it is polyester if we go from coarse to
finer side then also you have to reduce the speed fibres with considerable crimp leads to
drafting problem, because the crimpy fibre behave like springs within the drafting zone.
So, they extend and when they are suddenly released they retract.
So, this extension and retraction is a source of irregularity generation in the drafting
zone. So, fibres which are too crimpy also lead to different types of drafting problem.
And therefore, we have to reduce the speed when we have too much of crimp in fibres.
Fibers with spore spin finish a synthetic fibres this spin finish is not correct then there is
a possibility of static electricity generation.
Static electricity generation is a big problem with fibres like polyester, acrylic nylon.
And hence, whenever we try to process these fibres, we have to reduce the speed the
production speed in comparison to what we can keep for cotton or for viscose rayon.
Because viscose rayon and cotton do not have this problem of generation of static
viscosity, because their hygroscopic fibre they can absorb moisture and hence the
possibilities of static equisetic generation is not there with viscose rayon and cotton.
Too long a fibres means, very high dynamic drafting force drafting force will increase
because the fibres being long there is a lot of contact between the this fibre and its
neighbors the surface area is more. And therefore, drafting force is going to increase
phenomenally with long fibres. And that could be chance of uncontrolled drafting and
also possibilities of roller lapping. So, when we processed long fibres we have to reduce
the speed or production.
So, its synthetic fibres chances of static generation is there and that is why reduce speed
and the other issue for between if we compared between card sliver and the combed
sliver with combed sliver we reduce speed, because combed sliver what is the difference
between combed sliver and carded sliver the difference is the combed sliver the short
fibres are not there, and because of the comb being actions all the fibres are very straight
and parallel. So, fibres are highly parallel they have been separated by the combing
needles which you learn later. And therefore, combed slivers are very very weak as well
because of removal of crimps from fibre and paralyzation between the fibre.
There is no interlocking between the fibres too much parallelization is there, and these
combed sliver or comb sliver yes the fibres in combed slivers are also prone to lapping
around the rollers. So, to avoid this lapping tendency, we have to also reduce speed while
processing cone material.
(Refer Slide Time: 21:03)
Now, from the speed we move to the next parameter which is roller pressure. Top rollers
as we all know are pressed against the bottom roller. So, that the fibres are held by the
rollers firmly and move it at its speed. So, all these rollers are pressed against each other
there is a pressure, the pressure is to the order of 60 to 80 kg force very high level of
pressures we generally apply and we make sure that the top one which is friction driven
gets its drive from the bottom ones though in between there is a layer of fibres which is
lying.
The back roller pressure is little more than the front roller pressure it is any simple the
bulk or material is more between the back rollers. Because as if the material comes to the
front roller side there is a draft which is acting the sliver is thinning. So, as the material is
thin down the mass of material is less, and hence we can have less force on the rollers.
So, the back roller more force or more pressure and the front rollers less force because
fibre bulk is less there. The other thing is manmade fibres are very very smooth and
slippery, and in the manmade fibre there is no short fibres as we have found them in the
case of cotton.
So, being very long most of the fibres are long, and the surface area of the contact is also
more hence what happens? Higher force is required to grip them effectively between the
rollers and transmit motion to them, this is the reason see cotton has convolutions the
surface of viscose rayon have solutions. So, the surface of cotton or viscose rayon is little
rough in comparison to the cylindrical fibres like let us say polyester or nylon, actually
even though it actually cross section is not really circular, but the surface of the fibre is
very very slippery.
So, these fibres are slippery in nature the surface, fibres purpose of these fibres and
hence. So, if you want to grip them we need more force on them. And that is why the
pressure on the roller will be more if we are processing synthetic fibres other than
viscose rayon. And not only that viscose rayon also we increase pressure to the extent of
20 to 30 percent because viscose rayon even though surface is selected still the surface is
smooth in comparison to cotton.
So, with viscose rayon also the pressure is increased by 20 to 30 percent whereas, for
polyester it can increase by 30 to 40 percents. So, remember this that whenever you
process manmade fibres pressure needs to be raised, because the surface is slippery
within synthetic fibres that could be different types of cross sections; but even then the
surface of these fibres are much slippery in nature in comparison to what we see in the
case of cotton.
We can find out how much pressure is acting.
(Refer Slide Time: 25:17)
.
If n slivers each of width w are pressed together by a force F on them, then the normal
force per unit width of the sliver is going to be F by N w, here there is a assumption.
Assumption is that if we have n number of slivers in between two rollers and the contact
is only established between the fibre and the roller. The rollers are quite long enough so,
that they can accommodate 6 or 8 sliver side by side.
So, we are assuming that beyond the width of the n number of sliver that you are feeding
the rollers are not in contact with each other. So, entire pressure that we keep on the top
roller is getting transmitted through the fibres to the bottom roller only. And therefore,
we can say the force on them is going to be F by N w inadequate roller pressure may lead
to roller slippage on the contrary too excessive pressure may bend the bottom rollers and
would require more energy to run them.
So, between these two contrary requirements, we have to find out what is the optimum
pressure that we need. So, a typical pressure suppose say of 70 kg force with the typical
sliver in a compressed state is going to be around 2.5 centimeter almost an inch. And if I
feed 8 slivers then the pressure per unit width is shown here is around 34.3 Newton per
centimeter or 3.5 kg per centimeter that much pressure we require to grip the material
effectively between the rollers.
(Refer Slide Time: 27:20)
Another parameter these tension draft, these tension draft generally does not get much
attention or much importance, but it is sometimes become very very significant its
influence. Tension draft is employed to ensure that is sliver or the fibrous wave remain in
a top state while being possessed with there are regions where tension draft is applied
what are those regions let us first try to look at. The locations are between the front
drafting roller and coiler calendar roller front drafting roller that is the delivery rollers of
the machine, and the calendar rollers with it they are in the coiler between these two
there is certain distance the material has to travel. And we do not allow the material to
accumulate.
So, there has to be little tension and the small tension is known as tension draft. So, that
draft is generally little more than 1 little more than 1, but we will see that it could be less
than 1 also why it is we will discuss this the other location is between sliver guiding
roller and back roller of the drafting system that is the creel draft. That in the creel as you
leave the sliver from this from the can and the sliver has directed or guided to us the
drafting unit. There is a little tension that we keep on the sliver and there is a tension
draft there is also known as creel draft.
So, the magnitude of draft is always close to one it is generally little more than 1. So, the
table shows here the kind of creel draft we keep 1.01 1.02 that is the typical; that means,
the speed of the guiding roller is little less than the surface speed of the back roller of the
drawing system. If we look at the tension draft in the breaker and finisher stage one
important difference is for the breaker machine the tension draft with the web tension
draft is little less than 1. The draft being less than 1 what does it mean it basically means
that there is a feeding is more than the delivery that is I am feeding more length and
taking out less. So, there is a chance of accumulation still we keep a draft which is less
than 1.
But the finisher we keep a draft more than 1 as usual about not too much you have
remember as a draft have 1.05 1.06 we should not keep to keep the material and that
taught state, because that will lead to irregularity into the drafted product. Because, such
a long distance they are traveling there is no guidance to them this stretch is too much,
then there is going to be sliding action between fibres, and it is any sliding means
drafting actions and drafting action basically means that the chance of development of
irregularity. And therefore, we have to ensure that the tension draft should not be high
enough which can lead to sliding between the fibres.
Now, why tension draft it less than 1 that we need to discuss?
(Refer Slide Time: 31:26)
.
The tension draft depends upon the elasticity of the sliver or the drafted wave which in
turn is affected by the nature of fibre, the crimp in the fibre, the degree of fibre
entanglement within the sliver, these are the important factors which decides the
elasticity of the sliver. The drafted wave that moves out from the delivery roller when
released from the front roller nip it detracts while the fibres are being processed they are
under tension from back zone to front zone as soon as they are released from the front
roller nip. Before they reach the coiler calendar roller there is a sudden go for relaxation
and the fibre drafted wave can retract retractions.
If there is retract tension will develop in the wave and which will lead to uncontrolled
sliding between fibres, and that may result in irregularity. Therefore, to counter this is the
web tension draft we have to keep less than 1. See the possibilities of retraction is there
because the fibres are retractable in nature then we must keep a draft which is less than 1
so, that even if there is try to contract we are taking out less feeding mode. So therefore,
the possibilities of sliding action will not be there. But by the time the sliver goes to the
finisher drawing stage there is not much crimp and entanglement left in the finisher
sliver and hence tension draft more than 1 is to be maintained.
This is the tension draft the web tension draft which we maintain less than 1 is in the
breaker stage while possessing cotton, whether by that time the material goes to the next
draw frame stage as a finisher drawing stage the crimps are no more they are in the fibre,
they have all lost most of it. And because, there is another passage of drawing the fibres
are passing through and entanglement also less the retraction possibilities it goes down.
And therefore, we keep a tension draft which is more than 1, when you go to the fresher
drawing stage.
(Refer Slide Time: 34:09)
Influence of drawing on fibre configurations. Now what is the purpose of drawing? If
you go back to the original objectives or drawing you will find that one of the purpose of
drawing is to realize the fibres, to unhook the fibres to improve their orientations and all.
So, this particular table gives you an idea it is trying to quantify what happens to the
hooked fibre that we see in the card sliver.
So, if we look at this table then what we find? In the last row percentage of reduction in
hook ok. So, what we see here that, if I go by the column number one trailing hooks
reduction in 68.4 percent, leading who reduction is 442.1 percent. So, these values if we
see there is a tremendous improvement in the hooked fibres and we have categorized the
fibre terms of trailing hook leading hook both and hook you hook in trailing direction
and you hook in leading directions all types of hooks are here and that is straight fibres s
and o means others different categories of fibres are there and.
What we see here is that there is a in each category there is a improvement hooks are
going down and down and straight fibres are also increasing what all there is
improvement that is what happens. That is as we process the material that is from on the
breaker draw frame and finisher draw frame stage there is a tremendous improvement in
the overall configuration of the fibre.
That is the fibres are becoming more and more straight more and more parallel and the
hooked part of the fibres hooks are basically vanishing. So, in the end there were little
hooks which will be left.
(Refer Slide Time: 36:28)
There is always a in this question comes to our mind that why do you need two draft in
passages or three passages. So, we will see that one of the reason why do you need two
draft in passages, is to ensure that most of the hooks which we see in card slivers are
remove to the maximum extent.
Now, if we study this particular diagram carefully, and we see that the two types of
hooked fibre that we find in the card wave or in the card sliver they are represented by
two different colors. So, trailing hooks they represented by the orange color and the
leading hooks by the blue color. So, in the card can you see from the wave as it enters,
and you have seen already that in a card wave or in a card sliver with reference to the
direction of delivery trailing hooks are more in number than leading hooks.
So, let us concentrate on these two types of hook trailing hook and leading hook. So, in
the card sliver trailing hooks are more and this trailing and leading hook definition is
with respect to the direction of delivery from the carding machine. Now when this sliver
is packed in a can and then withdrawn there is a reversal that what goes in first that
moves out last from the can. So, the part of the sliver that goes first there remains at the
bottom and the part that goes last this withdrawal first. So, there is a reversal because the
reversal there is a direction change of the hooked ends also. So, when he remove sliver
from the card can there is a change in direction.
So, what we see here? In the first draw frame passage the trailing hooks are being fed in
the leading directions and leading hooks are being fed in the trailing directions. If we
look at the diagram the trailing hooks this is in orange color it is being fed in the leading
direction because there is a reversal be because, the sliver has impact into a the can of the
can we are removing this sliver.
So, there is a reversal now in a draw frame the drafting operation helps in removing
trailing hooks more than leading hooks. Because of the sliding action between the two
group of fibres within drafting zone the any fibre with the hook at the trailing end will be
straightened out easily whereas, if a fibre same fibre is fed with a leading and hook it is
not going to be removed preferentially. So, in any drafting zone trailing hook removal
will be more in number in comparison to leading hooks.
And therefore when I pass the material to the first draw frame passage most of the
leading hooks, which are there in the card sliver they are being fed as trailing hooks now
and therefore, most of them will get removed. However, the trailing hooks in the card
sliver which are more in number they are being fed in leading direction. So, their
removal will be less in the first passage. And then the material moves in to the draw
frame can after the first passage and then again we lift it and fit to the second machine
that is the finish or draw frame.
So, there if we see now direction of presentation of the hooked fibre the orange fibres are
being presented in the trailing directions and the leading hook fibres is presented as blue
fibres in the leading directions. Now again, a drafting is going on the breaker draw frame
and now what will happen that most of the trailing hooks with reference to carding
machine or card sliver labor are now being presented in the trailing direction in the
drafting zone of the breaker draw frame. So, they will all get removed preferentially.
So, second draw frame passage will be more effective in removing the trailing hooks
than the leading hooks. Training hooks means these are trailing hooks with respect to the
carding machine delivery directions. And hence, what we need with the earliest two draw
frame passage to take care of removal of trailing and leading hooks.
(Refer Slide Time: 41:55)
So, whatever I have told the same thing is being stated here that in the first drawing
passage all trailing hooks in card sliver would expect to card delivery are presented in
trailing directions. And they do not get removed preferentially in compassion to leading
hook presented in the trailing directions.
Exactly this is what was stated and the second drawing passage majority trailing hooks
with respect to card are now presented in trailing directions and are preferentially
removed. Therefore, two passages are bare necessary to remove both type of hook fibres
and hence from the point of view of removal of hooked fibres two passages are required,
and we the practice in the industries also what going for two passages. Why the trailing
hooks are more removed or preferentially removed?
Now if we imagine that the fibre with a trailing which is trailing and hooked is moving
to the drafting zone the hooked end is short. So, the leading end as is as soon as it is
gripped by the front pair of rollers this end is being pulled at a faster speed. The hooked
end is now brushing against these slow moving fibres. And now there is a friction
between the hooked end and the slow moving fibres. And therefore, the hooked end will
be easily unhooked, if I now focus on the orange fibre with a hooked end and the leading
part of the fibre.
Now, when this fibre moves through the machine, the hooked end itself will get caught.
So, both limbs or the hooked will be caught by the front roller nip and now the fibre
suddenly gets accelerated, but there is nothing left in the trailing part of the fibre trailing
end of the fibre. So, the hooked end remains hooked end and their chances of removal is
very very low.
So, leading hook removal is actually less in any draw frame passage if the fibre and
trailing end of the fibre is has being hooked, that we will get unhooked very easily. But
one can still feel that does not mean the leading whose will never get removed still they
get removed while they are passing to the drafting zone we could, because before they
reach the front roller nib the faster moving fibres are brushing against the hooked part
this fibre. Let us say a fibre with a leading and hooked is gradually approaching the
drafting zone, and being delivered slowly and slowly into the drafting zone, but still
moving at the speed of back roller.
So, when the hooked part is has gone middle of the drafting zone, now what is
happening, but this hooked part is in contact with many other fibres moving at a faster
speed. Those fibres are going to now unhook this end therefore, some reading hooks also
we will get removed, whenever we you know go for a drawing passage. So, both type of
hook has a chance to be removed, but fibres with trailing and hook has a better chance of
removal than the other one.
(Refer Slide Time: 45:33)
In the drawing what happens therefore, there is a removal of hook 10 there is a
straightening of fibres there is improvement in homogeneity because there is a doubling
actions. And there is improvement in mass uniformity all are achieved the number of
passages; however, are restricted to two usually why? More drawing passages make this
sliver very weak progressively due to over privatization of fibres without any further
significant improvement in uniformity. So, you do not go for the third passage in general
because you do not gain much by giving one more passage on the contrary this sliver
becomes very weak because fibres becomes two parallel with each other.
Few hooked fibres which are still left after second drawing passage, get removed by the
drafting processes on speed frame and ring spinning. It is not that we will be able to
remove all hooked ends by giving two draw frame passages to the material. However,
that at some more passages which are left like combing passage is there if not combing
speed frame is there ring frame is there. So, they are still drafting left on speed frame and
not only in spinning machine and on these two machine again there is a chance or there
is scope for the removal of hooked fibre
(Refer Slide Time: 47:05)
Over parallelization on the contrary leads to frequent sliver breaks, if I go for three
passages. When the slivers are lifted from the can and fed to the speed frame this also
you have to remember there is no point in going for three draft and passage because
slivers becomes two weak and frequent bricks would not be expected, when spinning is
performed directly from slave sliver using high speed apron drafting system. Let us,
since vertex spinning more than two passages become necessary to make the fibres
thoroughly homogenized straightened and parallel.
In some specific instances where we are spinning a yarn directly from sliver as an
example vortex spinning; the drafting system is an apron drafting system there and we
feed sliver there. Now in this case the draft is there is very high and the speed of drafting
is also very high. So, in a situation like this the input material that is the sliver has to be
very very uniform homogenized and the fibre has to be very very parallel because the
draft in the machine is very very high.
So, in this kind of situation we have to go for three draw frame passages, but knowing
that there is a chance of over parallelization and sliver may be weak. So, to compensate
that what we do? The sliver strength is maintained by compacting it by passing it to a
very narrow trumpet. So, you have to pass the material or the sliver through a narrow
trumpet there we try to compact it and we want to enhance the strength of the sliver that
is what we generally do.
(Refer Slide Time: 49:05)
This particular table is giving you an idea about the influence of draw frame passage on
certain property that is uniformity tenacity and strength of the sliver.
So, card sliver first passage drawn sliver and second passage drawn slivers are shown
here it is a mixing of J 34 cotton and S 6 cotton the ratio of three fifty. So, what we seen
here is that, as you go from card to first draft and passage the uniformity improves,
second passage also uniformity improves. Tenacity part if we see card sliver is stronger
or strength if we compare card sliver is stronger in comparison to first draw frame
passage sliver. And that is little stronger than the second passage drawn sliver. So, this is
the actual data which also supports the fact that with parallelization this sliver is
becoming weak strength goes down uniformity improves.
(Refer Slide Time: 50:29)
Now, we discuss another important concept called blending delay. On the draw frame
there is a scope of blending or mixing 6 to 8 slivers.
(Refer Slide Time: 50:58)
So, we can quantify the mixing capability of the machine by a term known as blending
delay blending delay time is defined as the production time difference between the first
and the last sliver can being doubled together on a draw frame that is what is the
definition of blending delay is.
The here if we look at the diagram see that the can one can two goes up to can n and all
these cans are then brought. So, these cans are being produced by one carding machine
let us say and they are being fed to the draw frame. So, I am pressing the cans as shown
here 1 up to n. Generally n could be 6 or 7 or 8 and they are being pressed here one after
the other and then they are all drawn and we in produce one sliver. So, material from n
cans have an opportunity to get mixed together.
So, the time difference in the production of the first can to the last, can ease and you
know gives us an idea about the mixing of the material.
(Refer Slide Time: 52:19)
Now to find out the blending delay time we have the following in the set of equations we
can derive easily very very simple, let that be n number of sliver cans which are getting
doubled m is the sliver weight in each can there is a can capacity b there a what is speed
of the carding machine.
They are all coming from the same carding machine at time t equal to 0 we start putting
the sliver cans alright. Time required to produce a full to sliver can is m by v where m is
the weight that is there and v is the delivery speed in terms of not meters per minute, it
should be actually kg per minute. Therefore, time required to feed one can is m by v
minute. The first full can is produced at time t which is t one is m by v minute in a sliver
can be produced at time t equal to n n into m by v minute
Therefore, blending delay time will be t n minus t 1 and that is equal to n into m by v
minus m by v and that becomes gives you if I m by v takes common it become m by v
into n minus 1. So, that is the time difference of filling or producing the first can and the
last can which are getting doubled together on the draw frame.
(Refer Slide Time: 54:11)
Let us say this sliver from 8 cans are being doubled together and draw frame the can
capacity is 30 kg, the card production rate is 54 kg per hour what would be the blending
delay time? So, time taken to produce first can is 54 by 60 into 30 that is 27 minute time
taken to produce 8 can is going to be 27 into 8 is 2016 minute.
Therefore, blending time is going to be the difference between these two that is 189
minutes; that means, whatever the machine is producing over one at 189 minutes this
material. Now are getting a chance to get mixed again on the draw frame.
So, that is end of today’s discussion.
Thank you.