Development and Third Party Maintenance for the IBM Mainframe (L. De Bruyn)
WP1: Reference design objectives and specifications Didier De Bruyn SCKCEN [email protected]...
-
Upload
stephen-foster -
Category
Documents
-
view
219 -
download
0
Transcript of WP1: Reference design objectives and specifications Didier De Bruyn SCKCEN [email protected]...
WP1: Reference design
objectives and specifications
Didier De BruynSCK•CEN
Fourth PCC meeting FP7 LEADERBologna, 27 October 2011
Copyright © 2011
SCK•CEN
task 3 6 9 12 15 18 21 24 27 30 33 36
T1.1
T1.2
T1.3
T1.4
Recall: Schedule
D29
D01
D02
D30 D30 R1
D29 R1 D29 R2
D01: Updated design options for the LFR referenceD02: Design options for the ETDRD29: Roadmap for LFR developmentD30: Cost estimate for LFR & ETDR
© SCK•CEN2
Task 1.1 Roadmap
The “Rev 1” version is on-going:Include PALLAS together with JHR & MYRRHAInclude ELECTRA in parallel to the other facilities
(from GUINEVERE to the industrial one)Rename the facilities to avoid misunderstandingConsider the current design updates (ALFRED –
D02)Check the schedules with experts for the different
concepts (detailed NRG level global level) some misunderstanding NRG >< experts
(Fukushima) recall the inherent favourable LFR characteristics (but no comparison!)
Include a § on funding opportunities.
© SCK•CEN3
Blue: foreseen & doneRed: foreseen but not doneGreen: not foreseen but done
Renaming the different concepts
ELSY is the design performed in an FP6 project, but also still the name of the FOAK facility, so the risk of misunderstanding is real!
Proposal:100 MWth Technology Pilot Plant: MYRRHA
300 MWth Demonstration: ALFRED
800-1200 MWth Prototype: ELSY PROLFR
Min 600 MWel Industrial plant: ILFR ELFR
DONE !
4 © SCK•CEN
Tasks 1.2 LFR options & 1.3 ETDR options
Del 01 finalized & distributed.Del 02 written, distributed for comments &
finalized (July ‘11).
© SCK•CEN5
Task 1.4 Cost estimate
Methodology proposed by EA after iteration with NRG, but input will be required from all partners (distribution proposed by EA);
Some guidelines to ensure consistency :Costs are expressed in € (Dec 2010);Separate investment costs (engineering, licensing,
construction) from operation costs (O&M, fuel cycle)
Where to put D&D? Proposal: in investmentConsider R&D? Proposal: no, but to be mentionedInterest during construction? Proposal: no (in other
words overnight costs are calculated without escalation)
Contingencies? Proposal: yes, preferably per itemTo allow comparison: recalculate the FP6 ELSY
following those rules. © SCK•CEN6
Decision WP1 meeting 24 october ‘11
Some comments from the WP leader
Good participation from most partners:NRG is interacting in 1.1 & 1.4Good input from WP2 & WP3 partnersGood feedback from reviewers
Less good participation from AGHNot present in 2010 (for good reason)Few feedback since then (mixing with WP2 ?)
Work has been performed so far, but sometimes by other partners than originally foreseenCan we envisage to re-distribute the WP budget?
7 © SCK•CEN
Original distribution of resources
8
partner name t1,1 t1,2 t1,3 t1,4 Total1 Ansaldo 1 5 1 1 82 AGH 6 63 CEA 4 CIRTEN 6 EA 5 57 ENEA 3 1 48 KIT 0,25 0,75 1 29 INR 2 2
10 JRC-Petten 0,5 0,511 KTH 12 NRG 4 3 713 PSI 14 SCK•CEN 1 1 3 515 SRS 16 NRI
17 Uni Bologna Total 11,25 7,25 12 9 39,5
Copyright notice
Copyright © 2011 - SCKCEN
All property rights and copyright are reserved. Any communication or reproduction of this document, and any communication or use of its content without explicit authorization is prohibited. Any infringement to this rule is illegal and entitles to claim damages from the infringer, without prejudice to any other right in case of granting a patent or registration in the field of intellectual property.
SCK•CENStudiecentrum voor KernenergieCentre d'Etude de l'Energie Nucléaire
Stichting van Openbaar Nut Fondation d'Utilité Publique Foundation of Public Utility
Registered Office: Avenue Herrmann-Debrouxlaan 40 – BE-1160 BRUSSELOperational Office: Boeretang 200 – BE-2400 MOL