World0Bank0Sri1nal0Resources0Group0

download World0Bank0Sri1nal0Resources0Group0

of 104

Transcript of World0Bank0Sri1nal0Resources0Group0

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    1/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    2/104

    i

    Acknowledgements

    This document was prepared for the Asia Alternative Energy Program (ASTAE) of the WorldBank under a contract with International Resources Group (IRG). The principal author of the

    report is Mr. Matthew S. Mendis of IRG. Rohitha Ananda of LGA Consultants (Pvt) Ltd of SriLanka carried out the field data collection and survey work. Sriram Iyer, Mac Cosgrove-Davies,Chandra Govindarajalu and Johannes Exel of the World Bank provided guidance and extensivereview comments. Susan Quinn of IRG provided editorial support for the final report.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    3/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    4/104

    iii

    Contents

    Acknowledgements........................................................................................................................................ i

    Acronyms ...................................................................................................................................................... v

    Executive Summary ................................................................................................................................ES-1

    1. Background for Impacts Assessment and Lessons Learned Document..............................................11.1 Objectives and Scope of Impact Assessment ...........................................................................11.2 Methodology for Conducting Impacts Assessment..................................................................11.3 Structure of the Report .............................................................................................................2

    2. Overview of the ESD Project..............................................................................................................52.1 Objectives and Scope ...............................................................................................................52.2 Objectives of GEF Support ...................................................................................................... 52.3 Major Components...................................................................................................................52.4 Project Cost ..............................................................................................................................6

    2.5 Expected Outputs ..................................................................................................................... 62.6 Institutional Set-Up and Implementation Arrangements..........................................................72.7 Project Stakeholders.................................................................................................................8

    3. Expected Outputs vis--vis Accomplishments .................................................................................113.1 Credit Component ..................................................................................................................113.2 Pilot Grid-Connected Wind Farm Component.......................................................................13

    4. Assessment of Technical Performance/Overall Implementation......................................................214.1 Implementation of the Solar Home System Component........................................................214.2 Off-grid Village Hydro Component ....................................................................................... 224.3 Grid-connected Hydro Component ........................................................................................234.4 Pilot Wind Farm Component..................................................................................................244.5 Capacity Building Component ...............................................................................................24

    5. Addressing Cost Barriers..................................................................................................................27

    6. Assessment of Institutional Effectiveness ........................................................................................296.1 Participating Credit Institutions..............................................................................................296.2 Borrowers of ESD Credit ....................................................................................................... 296.3 Administrative Unit (AU), based at DFCC Bank...................................................................306.4 Ceylon Electricity Board ........................................................................................................ 316.5 GOSL Agencies......................................................................................................................316.6 Effectiveness of Other Relevant GoSL Agencies...................................................................316.7 Effectiveness of Bank Management and Supervision ............................................................32

    7. Assessment of Consumer Satisfaction and Socio-Economic Impacts.............................................. 337.1 Methodology Used in Field Surveys ...................................................................................... 337.2 Summary of Survey Results ................................................................................................... 337.3 Socio-Economic Impacts........................................................................................................36

    8. Lessons Learned ...............................................................................................................................398.1 Institutional.............................................................................................................................39 8.2 Technical/Implementation......................................................................................................40

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    5/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-iv

    8.3 Financial/Economic................................................................................................................42

    Annex. Statistical Results of Field Surveys.........................................................................................A-1

    Tables2-1 ESD Project Financing Plan................................................................................................................6

    2-2 ESD Project Stakeholders...................................................................................................................9

    3-1 Cumulative No. of Households Served by SHS, per district (as of June 2002)................................12

    3-2 Grid-Connected Minihydro Projects Installed.................................................................................. 13

    3-3 Summary of ESD Project Accomplishments....................................................................................15

    3-4 Interventions Carried Out Following Mid-Term Review to Address Project Weaknesses .............. 17

    4-1 Issues Involved in Implementation of SHS Component...................................................................21

    4-2 Issues Involved in Implementation of OGVH Component............................................................... 23

    Figures

    E-1 ESD Project Partnership .................................................................................................. ES-1E-2 Growth in Grid-Connected Minihydro Capacity (19982002) ....................................... ES-2E-3 Growth in SHS Sales (19982002) ................................................................................. ES-3E-4 Growth in No. of Households Served by Off-Grid Village Hydro Systems ................... ES-4

    E-5 Social Impacts of ESD Project on SHS End-users .......................................................... ES-7

    E-6 Social Impacts of ESD Project on Off-Grid Village Hydro End-users ........................... ES-9

    2-1 ESD Project Set-up................................................................................................................ 8

    Boxes

    E-1 Accomplishments Under the CEB DSM Component ..................................................... ES-4E-2 ESD Administrative Unit................................................................................................. ES-5

    E-3 Private Sector Equipment Vendors and Project Developers ........................................... ES-5

    E-4 SEEDS Accomplishments............................................................................................... ES-6

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    6/104

    v

    Acronyms

    AU Administrative Unit based at DFCC BankBII Bureau of Infrastructure Investment

    CAPS Consultancy and Professional Services Pvt. Ltd.CB Capacity BuildingCboC Commercial Bank of CeylonCBSL Central Bank of Sri LankaCEA Central Environmental Authority of Sri LankaCEB Ceylon Electricity BoardDSM Demand-Side Management unit of CEBESD Energy Services Delivery ProjectEVC End-user village cooperativesGCMH Grid-connected mini hydroGCSPDA Grid-connected small power developers association

    GCSHDA Grid-connected small hydro developers associationGEF Global Environment FacilityGoSL Government of Sri LankaHNB Hatton National BankIDA International Development AssociationITDG Intermediate Technology Development GroupLSB Licensed Specialized BanksMFI Micro finance institutionsMoFP Ministry of Finance and PlanningNDB National Development BankNGO Non-governmental organization

    OGVH Off-grid village hydroOOPP Objective-oriented project planningPCI Participating credit institutionsPEU Pre-electrification unit (Ceylon Electricity Board)PGCWF Pilot grid-connected wind farmSHS Solar Home SystemsSIA Solar Industries AssociationSEEDS Sarvodaya Economic Enterprises Development ServicesSELCO Solar Electric Light Company Inc.SLBDC Sri Lanka Business Development CentreSPPA Small Power Purchase Agreement

    SPPT Small Power Purchase TariffTOR Terms of referenceUNDP United Nations Development Programme

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    7/104

    ES-1

    Executive Summary

    Introduction

    The Sri Lanka Energy Services Delivery (ESD) Project, a uniquely designed and implementedproject, can serve as an excellent model for other rural electrification initiatives with renewableenergy and energy efficiency components. In particular, it applies a multi-stakeholder approachin overcoming the financial, institutional and market barriers traditionally associated with theimplementation of small-scale renewable energy and energy efficiency options. Through theestablishment of strategic and working partnerships between the government of Sri Lanka, theCeylon Electricity Board, commercial banks, a microfinancing institution, private developers,equipment vendors, rural electricity cooperatives, and end-users, significant gains have beenmade to commercialize grid-connected minihydro and wind power, off-grid village ormicrohydro power, and wide scale use of solar home systems. Additionally, the ESD Project hasalso helped strengthen the basis for adopting demand side management (DSM) options to helpreduce consumption of grid-based electricity. By successfully achieving its objectives, the ESDProject has laid the foundations for a wider-scale commercialization program for renewableenergy and energy efficiency in Sri Lanka. Technical, financial, policy, and information barriershave been addressed by the project, and many lessons can be learned from how these barrierswere overcome. Figure E-1 provides an overview of how the different project stakeholdersinteract.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    8/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-2

    Figure E-1. ESD Project Partnership

    Project Objective and Components

    The main objectives of the World Bank and Global Environment Facility (GEF) assisted ESDProject are to:

    Promote the provision by the private sector, NGOs and cooperatives of grid-connected and off-gridenergy services using environmentally sustainable renewable energy technologies;

    Strengthen the environment for demand side management (DSM) implementation; and

    Improve public and private sector performance to deliver energy services through renewable energyand DSM.

    The ESD Project has three principal components. They include the following: The ESD Credit Component,which has an estimated cost of $48.9 million, is designed to provide

    support for medium- and long-term financing of private sector firms, NGOs, and cooperatives for off-grid SHS and village hydro projects and grid-connected mini-hydro, wind, and other renewable

    energy investments.

    The Pilot Grid-Connected Wind Farm Component,which has an estimated cost of $3.8 million, isdesigned to demonstrate the commercial viability and long-run economic potential of wind power inSri Lanka and to catalyze future private sector wind farm development.

    The Capacity Building Component,which has a total cost of $2.5 million, is designed to providetraining and technical support for renewable energy and energy efficiency initiatives by both the

    World Bank/GEF

    Sri Lanka ESD Project

    Govt of Sri Lanka

    Ceylon Electricity Board Ministry of Finance/Central Bank of Sri Lanka

    $

    $

    $ $

    $

    Participating Credit

    Institutions

    DSM PEUGrid-

    Connected

    SPPA Pilot wind project

    Grid-connectedhydro

    Future commercialwind projects

    Comml Banks& LSBs

    MFI(SEEDS)

    SHS End -UsersOGVH Electricity Coops

    - MinihydroDevelopers

    -SHS Vendors

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    9/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    10/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-4

    in rural homes throughout SriLanka (Figure E-3). In theprocess, at least four major SHSvendors have invested significantsums to established extensive

    sales and distribution networks inSri Lanka and are now installingSHS at the rate of over 1,300systems per month. Additionally,the ESD Project has helped defineand establish a workable micro-finance institution (MFI) modelwith the participation of a keyNGO: Sarvodaya EconomicEnterprise Development Services(SEEDS), which has a rural

    networkand a grassrootsorientation that enables it to reacha greater number of ruralconsumers. This MFI, working in close partnership with the SHS vendors have helped overcome

    the SHS consumer financing barrier that plagued the start-up of this component of the ESD

    Project.1

    Without the support and flexibility demonstrated in the ESD Project, it is unlikely thatthe SHS component would have succeeded. However, as the rate of SHS sales is now increasing,

    there is a clear need to diversify and increase the number of participating MFIs in the project.

    Additionally, the support provided by the GEF grant for this component has also beeninstrumental in supporting the development of the market. It is not immediately clear how a

    reduction in the grant will impact the growth in sales of SHS.

    Village Hydro Systems

    The ESD Project has already supported the installation of 574 kW village hydro systems serving2,897 households. This is far in excess of the original ESD target of developing 250 kW and

    serving 2,000 rural households. This success has been due primarily to the active involvement of

    the ESD project working in partnership with NGOs and community based organizations (CBOs)to identify, organize and develop the village hydro projects. Additionally, the involvement of

    SEEDS as the microfinance institution has recently helped bridge the financing needs of the

    small electricity cooperative societies that are formed to build, own and operate the village hydroprojects. However, like the SHS component, there is a need for the involvement of more MFIs if

    village hydro and other similar small-scale isolated grid/cooperatives are to evolve. With the

    exception of the Hatton National Bank, the approved PCIs did not aggressively pursue financingof these projects.

    1 The ESD Project had an initial SHS target of 30,000 rural households. However, at mid-term (February 2000) less than 1,000 SHS wereinstalled. The mid-term evaluation of the ESD identified the unwillingness of the SHS vendors to borrow from the ESDs approved participatingcredit institutions (PCIs) and provide consumer financing and the constraint faced by most of the PCIs in extending micro-finance directly to SHSconsumers as the principal reasons for failure of this component. As a result, the SHS target was revised to 15,000 and alternate approaches to

    consumer finance were explored.

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    2000 E nd-2001 Mid- 2002

    No.ofhouseholdsserved

    Figure E-4. Growth in Number of Households Servedby Off-Grid Village Hydro Systems

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    11/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-5

    Demand-side Management

    The ESD Project also had the objective of supporting the CEB to promote and implementdemand-side management (DSM) programs. Specifically, the ESD supported the CEB in: (a)developing of code of practice for energy efficient commercial buildings; (b) developing thetechnical capacity to carry out energy audits and provide advice on energy efficiency measures

    for commercial and industrial clients; (c) carrying out a load research study; and (d) institutingan appliance energy labeling program. The CEB continues to work in promoting energyefficiency and DSM. A recent analysis provided by the CEB indicates that its promotionprograms for energy efficiency and DSM should result in savings of approximately 82 GWh/yrof energy and 32.5 MW of demand capacity by the year 2006. While it is not clear if thesetargets will be met, it is evident that the ESD project has assisted the CEB in initiating its energyefficiency and DSM programs.

    Project Organization and Management

    From an institutional perspective, one of the most

    important elements of the ESD Project was theeffective functioning of the Administrative Unit(AU). The AU played a pivotal role in theadministration of the ESD credit, includingprocessing of loan disbursement requests,maintaining of disbursement records and accounts,compiling program-related statistical records, andsubmitting quarterly reports. Establishing the AUwithin one of the PCIs (the DFCC) was a bold yetprudent move. Equally important was the creation ofan effective wall between the AU and it parent

    organization so that the AU was able to operateindependently and without prejudice. By having the

    AU drawn from one of the PCIs, the AU was familiar

    with the prevailing banking rules and procedures and

    was administratively adapt in matters relating to

    the application and disbursement of the credit and

    the GEF grant. However, the AU was initially not

    as effective in matters relating to development and

    promotion of the ESD components it was

    responsible for. To its credit, the AU recognized

    this requirement and has actively worked to meet

    this objective. The success of the ESD Project is in

    part due to the performance of the AU and,

    specifically, the skills and dedication of the AU

    Manager, Mr. Jayantha Nagendran. The AU has

    actively reached out to all ESD Project

    stakeholders and regularly meets with key

    stakeholders to identify issues and resolve

    problems. Equally important was the long-term

    Box E-1. Accomplishments UnderCEB DSM Component

    Development of a code of practice for energyefficient commercial buildings

    Development of technical capacity to carry out

    energy audits and provide advice on energyefficiency measures for commercial andindustrial clients

    Conduct of a load research study

    Institution of an appliance energy labelingprogram

    Projected savings of approximately 82GWh/year of energy and 32.5 MW of demandcapacity by the year 2006

    Box E-2. ESD Administrative Unit

    Established within one of the PCIs (DFCC),making it familiar with prevailing bankingrules and procedures and administrativelyadept in matters relating to credit applicationand disbursement, BUT carried outoperations independently and withoutprejudice

    Overcame initial difficulties in developmentof promotion of ESD components it wasresponsible for

    Identification and solution of issues throughregular interaction and consultation withproject stakeholders

    Broke even financially in 4th year and nowoperating profitably

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    12/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-6

    view taken by the DFCC in operating the AU. The DFCC demonstrated a willingness to initiallysustain losses from AU operations for the first three years as the ESD Project ramped up. TheAU broke even financially in its fourth year and is now reported to be operating profitably. Thismodel of an effective, efficient and proactive AU with a long-term commitment and ableleadership is an important element in the success of the ESD.

    The commercial licensed specialized banks (LSBs) that were approved as PCIs, for their part,proved to be effective partners primarily in the development of grid-connected hydro projects.However, the commercial banks were not well suited to address the financing needs of off-gridSHS and village hydro components and the SHS vendors and village hydro developers wereunwilling or unable to assist their consumers withfinancing. Thus, it became evident at an early stagein the ESD Project that effective rural based micro-finance institutions (MFIs) were needed. Theinvolvement of SEEDS at about the mid-point inthe project and the eventual approval of SEEDS asa PCI/MFI were instrumental in the success of the

    off-grid village hydro and SHS components of theproject. SEEDS capability to function as an MFI, itsestablished rural network and its community basedapproach are all critical elements in addressing thefinancing needs of the SHS and village hydrocomponents.The OGVH developers had their initial share ofstruggles in organizing themselves, meeting therequirements of the commercial banks, and dealingwith members, but overall proved to be effectiveborrowers of credit from the microfinanceinstitution. The SHS vendors did not prove to beeffective providers of credit as shown by theirperformance at the start of the project, but this wasaddressed by accrediting a microfinance institutionso they could concentrate on marketing,distributing, installing and servicing the SHS. Todate, 50 service and distribution centers have beenset up by the SHS vendors throughout the targetareas. It is crucial that this is maintained and evenexpanded to ensure continued reliable operation ofthe SHS systems.It also bears mentioning that the local industryassociation was crucial to the success of the minihydro component of the project as it was able toeffectively voice out the concerns of the hydro project developers concerning the small powerpurchase tariff with the Ceylon Electricity Board.

    Box E-3. Private Sector EquipmentVendors and Project Developers

    OGVH developers had their initial share ofstruggles in organizing themselves, meetingthe requirements of the commercial banks,and dealing with members, but overall proved

    to be effective borrowers of credit SHS vendors did NOT prove to be effective

    providers of credit as shown by theirperformance during the start of the project, butthis was addressed by the accreditation of amicrofinance institution so that they couldconcentrate on marketing, distribution,installation, and servicing of SHS systems

    Hydro industry association effectively voicedout concerns of project developers duringnegotiations with CEB concerning small powerpurchase tariff issue

    Box E-4. SEEDS Accomplishments

    Enabled SHS and OGVH components to takeoff with its accreditation as a participatingcredit institution in the project

    Approved a total of Rs 199 million worth ofSHS loans as of June 2002

    Approved a total of Rs 0.7 million worth ofOGVH loans as of June 2002

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    13/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-7

    Project Impacts

    Macro Level

    The ESD project was conceived at a time of lagging public sector investments in powergeneration vis--vis growing demand. Investments in core infrastructure had been increasing

    only marginally since 1990 to about 4.5% of GDP while demand for power was increasing at arate of 8% or more annually. Daily power cuts in 1996 underscored the urgent need for newgenerating capacity and improved efficiency. In order to address the situation, the government of

    Sri Lanka (GOSL) adopted two strategies: (1) creation of a regulatory and policy environment

    which encourages private investments to supplement public resources; and (2) improving theefficiency of energy services delivery. The ESD project was aimed at addressing the serious

    issues of capacity and efficiency in the sector by fostering private provision of energy services.The ESD project enhanced the enabling environment for (1) private investments inrenewable energy services through the application of a standardized small power purchase

    agreement and non-negotiable tariff (the lack of which effectively impeded development of

    small grid-connected power projects; and (2) implementation of DSM by building capacitywithin the CEB.

    End-Users

    A detailed survey of 100 SHS customers and 50 off-grid village hydro (OGVH) consumers was

    carried out to determine the social, economic and quality of life impacts of receiving off-gridelectric services. When interviewed about the impact of the ESD project on their lives, SHS and

    OGVH customers all acknowledged the improvement in their quality of life as a result of having

    a cleaner, more reliable source of electricity (see Figure E-5). All were pleased about theextended entertainment hours and improved family interaction. Women in particular, highlighted

    the usefulness of having lights to continue their household work at night. Parents indicated that

    their children have also been able to study better at night and perceive improvements in the

    educational performance of their children. There is also increased feeling of safety and betterhealth conditions with the elimination of the fumes from their old kerosene lamps. However,

    there appears to be little evidence that access to SHS or OGVH has significantly increasedeconomic or income generating activities. Interestingly, SHS consumers surveyed indicated an

    expected increase of discretionary income once their SHS payments were completed. However,

    OGVH consumers did not appear to have the same perception. In the case of SHS, the amount ofenergy available is barely sufficient to meet basic household lighting and entertainment serviceneeds. There appears to be more potential for income generating activities with OGVH.

    An important impact that the project has also had on end-users, but which they did not

    specifically identify during the surveys was improvement in local capabilities to organizethemselves and to collectively manage and monitor projects. This was especially true for the

    OGVH component wherein residents had to form rural electricity cooperatives/societies and thenassume responsibility for the day-to-day operation of the project.

    Local Business

    The ESD project has also had a significant impact on local business. For vendors of solar home

    systems, the project has made it possible for existing ones to expand their current market, and

    new ones to be established to respond to growing demand. The same is true for local hydroconsultants who have grown in number as a result of growing demand for their services. For

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    14/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-8

    private developers, the project has made hydro project development more attractive, especiallywith the implementation of an SPPA and the resolution of the tariff issue.

    Financial Community

    The ESD project has given member of the Sri Lanka financial community a better appreciation

    of and actual exposure to renewable energy and rural electrification projects. The experienceunder the project has enabled financial institutions to better appreciate the importance ofinnovative financing mechanisms for such projects, and the fact that not all renewable energyprojects fall under the high-risk category.

    Figure E-5. Social Impacts of ESD Project on SHS End-users

    0 10 20 30 40 50 60 70 80 90 100

    Increased Income

    Longer Entertainment Hours

    More Time for Schoolwork

    Other Activities at Night

    Increased Safety

    Better Informed

    Better Quality of Life

    Income-Generating Activities

    % of Households Surveyed

    Lessons Learned

    Implementation of the ESD project has brought to light several lessons in the sustainableprovision of rural energy services.

    Institutional

    On the institutional aspect, it has shown that local or community participation is crucial toproject successas it ensures project ownership on the part of the communities involved and also

    promotes improvement of local capabilities, strengthening of community relations and aids incost recovery. The involvement of a wide range of stakeholdersin the implementation of thedifferent components of the project (e.g. both commercial banks and microfinance institutionsaccredited as participating credit institutions in order to reach a broader group of customers) alsoresulted in project targets being attained and even exceeded. On a macro-level, the institutionalstructures should be in place, and the general policy framework should be conducive for thegrowth of the industry. Government commitment is crucial, and this should be reflected inconsistency of national and sectoral objectives. Two elements that facilitated the growth of the

    Increased Discretionary Income

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    15/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-9

    grid-connected hydro market are the standardized power purchase agreement and the tariffceiling, which significantly lessened transaction costs and risk on the part of investors, and gavethem a more defined framework within which to operate. The ESD project has also shown thatthe administration of a project, especially one with a credit component, is best handled by agroup that is highly familiar with the financial sector, has the administrative capabilities, and

    possesses sufficient experience dealing with the private sector. This was demonstrated by the AUexperience.

    Implementation/Technical

    On the implementation/technical aspect, some ofthe key elements of a successful project includea viable distribution and servicing infrastructureand sufficient market development activities.Flexibility on the part of project implementersisalso very important. One of the major reasons forthe current success of the ESD is that project

    implementers were flexible enough to makesome significant changes in project design whenit was determined during mid-term that someissues were preventing the attainment of specifictargets. Experience under the project has alsoshown that the most common technical problemsresult from system overuse. This points to theneed to better educate end-users on thelimitations of their systems and on the basics of

    proper operation. In terms ofmarketing/information dissemination, the ESD

    project has demonstrated that word-of-mouthseems to be the most effective mediuminattracting potential customers.

    Financial/Economic

    On the financial/economic aspect, theinvolvement of micro-finance institutionsinfinancing solar home systems and village hydroprojects has been crucial in the expansion ofboth markets. Unlike the common perception that rural customers represent high-risk, the projecthas demonstrated that end-users are willing to pay more than they usually do for energy

    expenditures, as long as the energy supply is reliable and safe. End-users place a higher premiumon the reliability and safety offered by sources like hydro and solar energy. However, it shouldbe noted that even with the current credit facilities extended by the ESD project, it is still themiddle to upper rural class who are benefiting from the project. How the needs of the lowerincome rural groups thus remains an issue that has to be resolved. The project also demonstratesthat economic development is not guaranteed by providing access to energy alone . For ruraldevelopment to take place the necessary supporting infrastructure needs to be developed andthere should be a focused effort on the development and promotion of specific income-

    Key Lessons Learned

    Policy and regulatory framework should beestablished and clear;

    Institutional framework should be in place;

    Involve key stakeholders in project design,development and review;

    Include local and community participation to

    support project implementation; Ensure viable distribution and servicing

    infrastructure;

    Encourage flexibility and adaptability ofproject implementers to changing conditions;

    Educate end-users on the operation andlimits of their energy systems;

    Communal communications is effectivemarketing medium;

    Good micro-finance institutions are critical tosuccess of solar home and village hydrosystems;

    Rural households in Sri Lanka are willing topay a premium for clean and reliable energyservices;

    Economic development is not guaranteed byonly providing access to energy.

    Energy services improve the quality of life butnot necessarily income generation.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    16/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    ES-10

    generating activities. The ESD project has shown that although the general lifestyle of thebeneficiaries has improved, there are no clear and concrete economic benefits that can be linkedto the project. This is an area being addressed by the follow-on RERED project.

    Figure E-6. Social Impacts of ESD Project on Off-Grid Village Hydro End-users

    0 0.2 0.4 0.6 0.8 1

    Increased Income

    Longer Entertainment Hours

    More Time for Schoolwork

    Other Activities at Night

    Increased Safety

    Better Informed

    Better Quality of Life

    Income-Generating Activities

    SocialImpacts

    % of Households Surveyed

    Increased Discretionary Income

    20 40 60 80 100

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    17/104

    1

    Background for Impacts Assessmentand Lessons Learned DocumentSri Lanka has a population of 19 million people with a per capita GNP of US$900 per annum.Approximately 75 percent of the population lives in the rural areas. It is estimated that only 54

    percent of the population has access to electricity resulting in approximately 2 millionhouseholds that do not have access to electricity from the grid. Power demand in Sri Lanka isgrowing at over 8 percent per annum and the CEB is unlikely to be able to keep up with thisrapid growth. Currently, the CEB has had to institute load shedding to cope with its increasingdemand. Given the relatively high costs associated with the expansion of rural electric services, itis unlikely that the CEB will be able to significantly increase its rural electric service coverage inthe coming decade and beyond. The government of Sri Lanka places high priority on ruralelectrification as a component of its overall economic, social, and regional development strategy.The basic premise is that by providing reliable energy access to rural populations, economicgrowth will increase and general social well-being will improve.The Energy Services Delivery (ESD) project was conceived to support the government of Sri

    Lankas energy strategy. The basic objectives of the ESD Project include the development ofenergy sources in an economically least-cost and environmentally sound manner, improving

    institutional capacity to manage the energy sector, promoting rational energy pricing, promoting

    energy conservation, and diversifying energy sources and reducing dependence on imported

    energy sources. As part of its basic approach, the project promotes active involvement by

    community organizations and the private sector in rural energy service provision and

    management.

    Objectives and Scope of Impact Assessment

    The ESD Project is scheduled to officially close by 31 December 2002. The project has been

    consistently rated satisfactory and has made impressive progress towards the achievement of theproject development objectives. After the last supervision mission the project was upgraded to

    highly satisfactory. In view of the innovative project design and limited renewable energy

    experience within Sri Lanka at the start of this project, this achievement is commendable. Recent

    Bank/GEF renewable energy projects have in fact already begun incorporating elements of the

    ESD project design. In order for wider dissemination among the donor community and clients, it

    is important that an independent, comprehensive assessment be undertaken to document the

    impacts, implementation experience and lessons learned under this project. Also, the independent

    review can support the design of the follow on project in minimizing the risk of replication of

    sub-optimal features in the ESD project.

    The main objective of the impacts assessment is to comprehensively assess the results achieved.

    The report also seeks to identify key lessons learned during implementation and map out bestpractices for cost-effective and sustainable delivery of energy services to rural populations.

    Methodology for Conducting Impacts Assessment

    This report builds on an independent evaluation report of the ESD Projectcompleted in April

    2002 and the results of a field study conducted in May 2002. The field study included interviews

    with the different stakeholder groups, including equipment vendors and industry associations,

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    18/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    2

    participating credit institutions, government institutions involved, the ESD Administrative Unit,and the end-users at the village level.Discussions with the equipment vendors and industry associations were carried out to get someinsights on the technical performance of the systems installed, problems encountered in the field,and issues pertaining to the credit component of the project, particularly any problems

    encountered with the participating credit institutions as well as matters involving policy, such asthe small power purchase agreement (SPPA) and the tariff ceiling, which was one of the keyissues during the earlier parts of the project.The participating credit institutions were a good source of insights on how the project has faredfrom a financial point of view by discussing issues such as adequacy of IDA credits as well asaffordability of the OGVH and SHS projects on the basis of repayment performance. Theinterviews also provided a look into how financial institutions perceive renewable energyprojects, i.e. which ones were viewed as risky, viable/sustainable, etc.Discussions with the government institutions focused on the effectiveness of the capacitybuilding component and obtaining general insights on how the project has fared. Interviews withthe ESD administrative unit (AU) were likewise a good source of general insights on the

    projects performance.A local (Sri Lanka) consultant, LGA Consultants Private Ltd, was hired to assist with the field

    study at the village level. Standard questionnaires were provided for the interviews conducted(attached as Annex 1). The data collected included

    Background information on each household

    Information on purchasing decisions, consumer financing

    Economic impact of new energy service on household, e.g. new employment generated by the project

    Social impact of new energy service on household, e.g. improvements in lifestyle

    This information was obtained mainly from end-users(to get a close look at how the project has

    affected individual lives). Key informants from concerned rural electric cooperativeswere alsoa source of information. In the conduct of the interviews, emphasis was given to identifying

    specific benefits from the project, such as employment generation, income generation, and anyother factors that directly contribute to the development of the rural economy. The key results of

    this survey are discussed in Chapter 7. Annex 2 contains the full text of the field report results.

    Structure of the Report

    The report is structured to present the results of the stakeholder consultations on the projectsimpacts and then identify lessons learned and best practices that will promote replication on a

    larger scale in other projects and countries.

    Chapter 2 gives an overview of the ESD project.Chapter 3 outlines the main accomplishments vis--vis expected outputs.

    Chapter 4 is an assessment of the projects implementation/technical performance.

    Chapter 5 is an assessment of how the project addressed the cost barriers typically associatedwith rural electrification projects.

    Chapter 6 is an assessment of the projects institutional effectiveness and impacts on the various

    stakeholders.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    19/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    3

    Chapter 7 is a more focused assessment of consumer satisfaction and socio-economic impacts,using as a basis the results of the household surveys conducted.Chapter 8 outlines lessons learned and best practices.The main conclusions and recommendations of the evaluation are presented in the ExecutiveSummary of the report.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    20/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    21/104

    5

    Overview of the ESD Project

    Objectives and Scope

    The World Bank and Global Environmental Facility (GEF)-assisted Sri Lanka Energy ServicesDelivery (ESD) Project commenced on 22 July 1997 with the Ministry of Finance and Planning(MOFP) and Ceylon Electricity Board (CEB) named as the executing agencies.The principal objectives of the project include: Promoting the provision by the private sector, NGOs and cooperatives of grid-connected and off-grid

    energy services using environmentally sustainable renewable energy technologies;

    Strengthening the environment for demand side management (DSM) implementation; and,

    Improving public and private sector performance to deliver energy services through renewable energyand demand side management (DSM).

    The Project was expected to result in the addition of about 26 MW of environmentallysustainable generating capacity, including a Pilot Wind Farm, grid-connected mini-hydro, andelectricity services to up to 32,000 rural customers through solar home systems and village hydroschemes. Another key objective of the project was to strengthen demand side management andenergy conservation capabilities within the CEB and the Sri Lankan architecture/ engineeringcommunity.

    Objectives of GEF Support

    Global Environment Facility (GEF) grant funds have been made available to off-grid (i.e. solarhome systems and village hydro) sub-project developers who signed a sub-loan agreement with a

    participating credit institution (PCI). The grant funds have been used to co-finance the initial costof equipment installed through the project and are available to sub-loan beneficiaries. They arereleased on a reimbursement basis, after installation of the off-grid system.Part of the GEF grant is also allocated to providing technical assistance for the preparation ofoff-grid subprojects. Specifically, it finances consultant services to help project developersprepare feasibility studies, business plans, and bank loan documentation. The GEF grant is alsoavailable to PCIs to supervise off-grid village hydro and solar home system subprojects.

    Major Components

    The ESD Project has three principal components, namely:

    ESD Credit Component. This provides support for medium and long-term financing of privatesector firms, NGOs and cooperatives for off-grid solar home systems (SHS) and village hydro(OGVH) projects, grid-connected mini-hydro (CGMH), wind and other renewable energyinvestments. It makes funds available for energy subprojects up to 5 megawatts (MW) through PCIs.Support for the ESD credit program and associated technical assistance is available under IDA creditas well as the GEF grant.

    Pilot Grid-Connected Wind Farm Component. This component has an estimated cost of $3.8million and is co-financed by $2.23 million of IDA credit and a GEF grant of $0.88 million. The 3-

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    22/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    6

    MW pilot wind farm project is designed to demonstrate the commercial viability and long-runeconomic potential of wind power in Sri Lanka and to catalyze future private sector wind farmdevelopment.

    Capacity Building Component. This component has a total estimated cost of $2.5 million and is co-financed with $1.0 million of IDA credit and $1.05 million of GEF grant. This component is to

    provide training and technical support for renewable energy and energy efficiency initiatives by boththe public and private sector.

    Project Cost

    The total project cost is US$55.3 million. The project financing includes US$24.2 million fromIDA and $5.9 million from the GEF. The remaining project financing includes $13.7 millionfrom private sector Participating Credit Institutions (PCIs), $9.6 million from renewable energyproject developers/entrepreneurs/energy end-users and $1.9 million from the Ceylon ElectricityBoard/Government of Sri Lanka. A summary of the projects financing plan is presented in

    Table 2-1.

    Table 2-1. ESD Project Financing Plan (in US$MM)

    Project Component IDA GEF PCIs Entrepreneurs CEB/GOSL Total

    ESD Credit Program

    Mini Hydro 14.4 - 10.1 6.3 0.1 30.8

    Village Hydro 0.3 0.1 0.1 0.1 0.1 0.7

    SHS 5.0 2.9 3.5 3.0 - 14.4

    Business Devt - 0.3 - 0.2 - 0.5

    Off-grid Support - 0.5 - - 0.7 1.2

    Subtotal 19.7 3.8 13.7 9.6 0.9 47.7

    Wind Farm 2.1 0.8 - - 0.6 3.5Capacity Building

    PE Unit - 0.3 - - 0.2 0.5

    DSM Unit 1.0 0.7 - - 0.2 1.9

    Subtotal 1.0 1.0 - - 0.4 2.4

    PPF* 0.3 0.3

    Unallocated 1.1 0.3 1.4

    Total Project Cost 24.2 5.9 13.7 9.6 1.9 55.3

    *The PPF is US$340,000.

    Expected Outputs

    The principal performance indicators for the Project include:

    Installation of at least 26 MW of grid and off-grid renewable energy capacity including service to upto 32,000 off-grid rural customers through solar home systems (SHS) and village hydro schemes;

    Development of a 3 MW pilot grid-connected wind farm project;

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    23/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    7

    Issuance by the Ceylon Electricity Board (CEB) of a comprehensive Energy Efficient CommercialBuilding Code of Practice (EECB); and

    Support by the CEB for the development of small-scale grid connected renewable energy projects by:

    Annually updating the Small Power Purchase Tariff (SPPT);

    Signing of least 5 SPPA contracts by mid-term evaluation, and 12 by project completion; and

    Incorporating intermittent, non-dispatchable renewable energy generating sources in the generationplanning models prepared by the CEB.

    Institutional Set-Up and Implementation Arrangements

    Credit Program

    For the ESD Credit Program Component, the Ministry of Finance and Planning on-lends theproceeds of the credit component to eligible PCIs, which would in turn on-lend these proceeds,

    along with complementary financing from their own resources to eligible sub-borrowers. Theseinclude project developers, SHS equipment vendors, electricity cooperatives, and SHS end-users.An Administrative Unit (from the Development Finance Corporation of Ceylon (DFCC))manages the other credit program. Its other responsibilities include: administration of the GEFgrants and technical assistance related to off-grid subprojects. The GEF grants are used to (1)support off-grid subproject preparation activities; (2) co-finance off-grid subprojects; and (3)provide support through promotion activities, provision of grant funding for verification of solarhome systems; and consumer education and protection. The technical assistance is available tohelp project developers prepare feasibility studies, business plans, and bank loan documentationfor off-grid sub-projects.Grid Connected Pilot Wind Farm Component

    The Ceylon Electricity Board is responsible for implementing the pilot grid connected wind farmcomponent on an engineering, procurement, and Construction (EPC) basis. The CEB isresponsible for monitoring, operation and maintenance of this facility.Capacity-Building Component

    The Ceylon Electricity Board is also responsible for overseeing the capacity-building activitiesof the Pre-Electrification Unit and the DSM unit. In the PEU, this includes procurement ofequipment as well as retaining local consultants to develop and conduct training courses for CEBstaff as well as private sector and NGO personnel, and assist CEB staff in feasibility studypreparation and other services related to off-grid project support. In the DSM Unit, this includesthe issuance of an Energy Efficient Building Code of Practice, development of institutional

    capacity in the energy-related public and private sectors to incorporate the Code of Practice intobuilding design and operations and to monitor the energy savings, demonstration of energyefficiency building design through design competition incentives, and implementation of a DSMstrategy and load research program.Figure 2-1 is a diagram of the basic project set-up.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    24/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    25/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    9

    Table 2-2. ESD Project Stakeholders

    Suppliers/Developers/Consultants

    Participating CreditInstitutions

    IndustryAssociations

    Government/Otherinstitutions

    SHS Suppliers

    Access International Ltd

    Alpha Thermal Systems (Pvt) Ltd.SELCO Solar Lanka Ltd.

    Shell Renewables Lanka Ltd.

    Solar Project Developers/Consultants

    Energy Forum

    ITDG South Asia

    LLGA Consultants Ltd

    Natl Engg Research andDevelopment Centre (NERD)

    Resource Management AssociatesLtd

    Village Hydro Project Developers/

    Consultants/ SuppliersAmanda S P R K

    Consultancy and ProfessionalServices (Pvt) Ltd

    Enexe (Pvt) Ltd

    ENCO (Pvt) Ltd

    ETC Lanka (Pvt) Ltd

    Integrated Development Association(IDEA)

    Infotechs-I/D/E/A/S (Pvt) Ltd

    ITDG South Asia

    Redco Ltd

    Sarvodaya Rural Tech Services

    Sri Lanka Business Devt CentreUdayaratne Hydro Power Engg

    Grid-connected Mini-hydroDevelopers

    Ecopower Ltd.

    Zyrex

    Wind

    NEG Micron A/S Denmark

    Development FinanceCorporation of Ceylon(DFCC)

    Sarvodaya EconomicEnterprisesDevelopmentServices (SEEDS)

    National DevelopmentBank

    Sampath Bank

    Commercial Bank ofCeylon

    Hatton National Bank

    Grid-Connected SmallPower DevelopersAssociation

    Solar IndustriesAssociation (SIA-SL)

    Village HydropowerDevelopersAssociation

    Sri Lanka BusinessDevelopmentCentre

    ESD Administrative Unit

    Central Environment

    AuthorityCeylon Electricity Board

    Dept of ExternalResources

    Energy ConservationFund

    Energy Forum

    Ministry of Power andEnergy

    Ministry of Science andTechnology

    Pre-electrification Unit,Ministry of Financeand Planning

    Board of Investments(BOI) and Bureau ofInfrastructureInvestment

    Local governmentinstitutionsprovincialcouncils and divisionalsecretariats

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    26/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    27/104

    11

    Expected Outputs vis--vis AccomplishmentsBy December 2001, it was apparent that the ESD project had already achieved success inmeeting its original targets, with the installation of 30 MW grid-connected minihydro capacity,287 kW from off-grid village hydros, and some 13,300 solar home systems (at a monthly rate of

    1,300 systems), and that it was going to exceed targets by the time the project was finished. Thiscontrasted greatly with the status at mid-term wherein the project was being bogged down withmany issues concerning off-grid components. With the implementation of key interventions,weak areas in the project design were successfully addressed and appropriate adjustments weremade. This chapter discusses the projects accomplishments vis--vis the targets set out in the

    original project design. It includes a discussion of the problems encountered in the different

    components and the interventions made mid-term in order to improve project performance.

    Credit Component

    Solar Home Systems (SHS)

    As of mid-term, sub-loans approved by the PCIs were expected to support the installation of a

    little more than 6,000 SHSs. However, by February 2000, the total number of approvals totaled

    only 723 systems. The poor performance of the SHS sub-component of the project was being

    inhibited by a number of technical and implementation issues. From the point of view of the

    PCIs, the SHS sub-loans were too small to justify the costs involved in loan processing, and SHS

    borrowers were also perceived as being high-risk. From the perspective of the SHS vendors and

    MFIs (intermediate borrowers of SHS sub-loans), the costs involved in securing SHS sub-loans

    with PCIs and administering micro-loans to SHS end-users were too high, and there was no

    dealer network to speak of, which made it difficult to market the product to the rural areas. For

    SHS end-users, the difficulty was in accessing affordable loans, given the high initial costs of

    SHS installation. They also had limited awareness of the SHS option, and had misguided notionsas to its reliability.

    In order to address the above issues, it was recommended that microfinance institutions be

    encouraged to participate in the project in order to increase the number of SHS customers. This

    resulted in the accreditation of the SEDS as a PCI and the introduction of a private partnership

    model for market development financing. The job of financing SHS was left to the MFIs, while

    vendors were encouraged to concentrate on selling systems.

    As a result of this intervention, sales followed a nearly exponential projection, from less than 30

    systems per month in 1998 to about 1,000 systems per month in June 2002, with an accumulated

    number of systems installed of more than 18,000. The three main companies in the Sri Lankan

    SHS market have reported monthly sales in the range of 400 to 800 systems, while a fourth

    company has reported sales of about 100-120 per month. A commercial distribution and servicenetwork including fifty centers is also in place.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    28/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    12

    Off-Grid Village Hydro (OGVH)

    As of June 2002, a total of 56 off-gridvillage hydro projects have beenapproved. The mini-grids range from 4-45 kW and serve 2,897 households with

    a total installed capacity of 574 kW andare under implementation with creditand grant support from ESD project.This blend of financing has led to areduction in grant funds per project ofnearly 50% or serving twice as manyhouseholds with the same amount ofgrant funds. In terms of capacity, thisalready exceeds the project target of 250kW.This contrasts greatly with the situation

    during mid-term, wherein there wereonly 7 projects approved, servicing 400households and representing around 58kW capacity. There was very littleincentive for developers to participate,given the very high costs of coordinatingand organizing village cooperatives todevelop, own, and operate OGVHsystems.From the perspective of the PCIs, theOGVH project loans were small and

    entailed high costs and thus not veryattractive. There was also some questionas to the reliability of OGVH borrowers.From the point of view of projectconsultants/organizers, the barriersincluded the long lead-time required to

    organize OGVH cooperatives and obtain approvals, coupled with the risks involved in projectorganization and development work. The timing of the GEF grant release to compensate forproject development and organization work was also unsatisfactory, and sustainability of theproject organization and development work without the ESD Project remained unclear. For thecooperatives and end-users, the biggest problem was accessing project financing. Other issues

    included O& M of the OGVH projects, and finding productive uses for the OGVH power duringthe daytime when demand was not as much.To address the situation, the CEB initiated an open solicitation process where consultants wereasked to submit proposals on how to address the existing technical, financial, and sustainabilityissues pertaining to this particular component. To ensure that the process would lead to concreteachievements, the consulting contracts were tied to actual deliverablesa set-up that workedwell and resulted in increased participation and more funding to OVGH projects by commercial

    banks.

    Table 3-1. Cumulative No. of HouseholdsServed by SHS, per district (as of June 2002)

    District No. of Households

    1. Ampara 699

    2. Anuradhapura 1,473

    3. Badulla 2,284

    4. Batticaloa 24

    5. Colombo 114

    6. Galle 473

    7. Gampaha 60

    8. Hambantota 421

    9. Jaffna 15

    10. Kalutara 103

    11. Kandy 225

    12. Kegalle 236

    13. Kurunegala 2,311

    14. Mannar 11

    15. Matale 633

    16. Matara 487

    17. Moneragala 4,854

    18. Mullaitivu 4

    19. N-Eliya 278

    20. Polonnaruwa 746

    21. Puttlam 693

    22. Ratnapura 2,215

    23. Trincomalee 203

    24. Vavuniya 57

    Total 18,619

    Source: ESD Project Quarterly Statistical Report (June 2002)

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    29/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    13

    Grid-Connected Mini-Hydro (GCMH)

    Sri Lankas minihydro capacity hasrisen from about 1 MW in 1997 to 31MW in June 2002. At mid-term, theprogress of this component was on-

    schedule, but the tariff-setting issuebetween the CEB and projectdevelopers remained unsettled. Themain issue from the perspective of theproject developers was providingadequate compensation for the actualcapacity value of the GCMH systemsin setting the SPPT.To address the situation, thegovernment employed the services ofan independent consultant to review

    and report on the tariffs set by the CEBfor the purchase of power from smallpower producers. Based on hisfindings, a tariff ceiling that wasacceptable to both the CEB and privatedevelopers was set, and the issue isnow considered resolved. Table 3-2 isa list of GCMH projects (andcorresponding capacity) as of June2002.

    Pilot Grid-Connected Wind Farm Component

    The pilot grid-connected wind farm component required that the CEB build a 3-MW pilot windfarm on an Engineer, Procure and Construct (EPC) basis in the Hambantota district by May1998. This component was completed not too far off the original schedule, with commissioningtaking place in February 1999 and certification in May 2000. The plant consists of five 46-metertowers with 600 kW turbines designed to supply a total annual capacity of about 4.5 GWh. Totalproject cost amounted to US$1,200/kW, which is acceptable for a first grid-connected wind farmoperation in a country. Wind speeds have also been found to be as projected during projectdesign. The CEB continues to monitor and record operational data from the wind farm and learnfrom this experience the issues that must be addressed for integrating non-dispatchable and

    intermittent renewable power.At mid-term, there was concern that the CEB had not undertaken any measures to attract privatesector development of wind power in Sri Lanka. To address this, regional wind resourcemeasurements supported by UNDP/GEF and specific evaluations of sites were conducted by acommercial company in order to facilitate project identification by private developers.Consequently, there is now a favorable regime in Sri Lanka to develop and implement windprojects. Several private companies, with international backing, are actively pursuing plans forwindpower development and projects as high as a 30 MW wind farm have been proposed. As a

    Table 3-2. Grid Connected Minihydro (GCMH)Projects Installed as of June 2002

    Name of Project Capacity

    1 Bambara Batu Oya-Ratnapura 3200

    2 Erapura Ganga-Kolonna 750

    3 Carolina Estate-Watawala 2500

    4 Panakura Oya-Minuwanella 320

    480

    5 Ellapita Ella - Maliboda Estate 550

    6 Delgoda 2400

    7 Glassaugh 2526

    8 Mandagal Oya - Maliboda Estate 1271

    9 Galaththa Oya-Pussellawa 1200

    10 Medapiti Oya Deegalahinna 1500

    11 Rat ganga Hapugastenne 1 46502150

    12 Nividu 2000

    13 Naya Ganga Mini Hydro Power Project cancelled

    14 Upper Watawala 1300

    15 Niriella 3000

    16 Deiyanwala, Gantelgoda Ela 1400

    TOTAL 31,197

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    30/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    14

    result, the CEB has recently issued an open tender for windpower electricity to stimulate thisdevelopment. Additionally, some of the windpower developers are exploring the possibilities ofaccessing the financial support of the Clean Development Mechanism (CDM) to enhance thefinancial viability of their proposed projects.

    Capacity-Building Component

    The capacity-building component was programmed to be carried out in the Pre-ElectrificationUnit (PEU), and in the Demand-side Management (DSM) unit of the CEB.In the CEB Pre-electrification unit (PEU), the program was aimed at enhancing in-houseexpertise in off-grid project preparation and to facilitate and promote technically andeconomically viable renewable energy subprojects as part of the ESD credit and the pilot windfarm components. It was also targeted at enhancing the ability of PEU staff to train staff fromCEB, the private sector, and NGOs in the areas of renewable energy project design anddevelopment.This broad objective was met by the PEU by actively engaging in:

    Improved rural electrification coordination;

    Preparation of materials describing off-grid electrification options

    Training of CEB area staff in disseminating information and promotion of off-grid electrificationoptions

    Coordination between CEB and off-grid project developers on CEB rural electrification plansincluding indication of areas not likely to receive grid service in the near term

    Preparation and dissemination of a guide for practical implementation of grid interconnection/integration requirements;

    Off-grid renewable energy project development training;

    Non-dispatch able power source modeling and planning; and

    Mini and village hydro project development assistance.

    Meanwhile, capacity building in the CEBDemand-Side Management (DSM)Unit consisted of: Design and implementation of a Code of Practice for Energy Efficient Commercial Buildings;

    Development of institutional capacity in the energy related public and private sectors to incorporatethe Code of Practice into building design and operations and to monitor the energy savings;

    Demonstration of energy efficiency building design through design competition incentives; and

    Support CEB in implementation of a DSM Strategy and Load Research Program.

    The concepts of energy efficiency/demand side management and renewables have been acceptedwithin the CEB and the capacity to design and execute DSM programs is firmly in place. Energyefficient building codes have been developed and are in use and several energy servicecompanies (ESCOs) are now operating in Sri Lanka, in part due to efforts by the CEB. Theframework for power purchase from grid-connected small hydropower is likewise in place, and

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    31/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    15

    training and awareness generation program for renewables has been conducted internally amongutility staff.At mid-term, the observation was that the CEB was carrying out the capacity-building activitiesin isolation of its general activities, i.e. there was little real coordination between the activities ofthe ESD capacity building components and the normal day-to-day activities of the CEB.

    Clearly, there is a stark contrast between the current project situation compared to the status atmid-term wherein the project was basically on schedule with the grid-connected activities, butwas bogged down with many issues concerning off-grid components. With the implementationof key interventions aimed at addressing weak areas in the project design, targets for the off-gridcomponents are being accomplished, and even exceededIt has been estimated, in fact, that by project closure in December 2002, the following shall havebeen accomplished: Additional 22 MW from private sector mini-hydro projects

    Additional 765 kW through village hydro projects

    Additional 10,000 solar home systems (with current monthly sales at 1,300 units per month)

    These are expected to translate into a shortfall of US$1.2 million to maintain credit off-take atthe current level, and to maintain the current SHS sales of 1,300 units per month. For the GEFco-financing grants on the other hand, there is an estimated shortfall of US$400,000.Table 3-3 traces the accomplishments of the ESD project both at mid-term and as of June 30,2002. Table 3-4 lists in greater detail the status of the various projects as of mid-term, thedifferent recommendations made after the mid-term review, interventions carried out, andcorresponding results as of June 2002.

    Table 3-3. Summary of ESD Project Accomplishments

    Objectives Key PerformanceIndicators/Expected

    Outputs

    Accomplishments/ Statusas of Mid-term (Dec 1999)

    Accomplishments as ofJune 30, 2002

    1.1 Installation of at least26 MW of grid and off-gridrenewable energy capacityby end of 2002, includingservice to 32,000 off-gridcustomers by end ofproject

    Grid-connected: 14.7 MWminihydro capacity

    Off-grid: 682 SHS unitsinstalled; seven (7) OGVHprojects amounting to 58 kWcapacity, 2000 households

    Grid-connected: 31 MWminihydro capacity

    Off-grid: 18,619 SHS unitsand 56 approved OGVHprojects (equivalent to 574kW installed capacity, 2,897households) for village hydrosystems

    1. Promote theprovision by theprivate sector, NGOsand cooperatives ofgrid-connected andoff-grid energyservices usingenvironmentallysustainablerenewable energytechnologies

    1.2 At least one powerpurchase agreement for aprivate wind power projectsigned by CEB

    Pilot wind farm completed;awaiting final certification inMay 2000.

    No power purchase

    agreement for a commercialproject yet.

    As a result of successful 3-MW demonstration projectand wind resourceassessment studies

    conducted, a number ofinvestors have entered thepicture, with one alreadyinvesting in on-site windmeasurement and feasibilitystudies, and in seekingfinancing from carbon tradingmechanisms and investors.

    2. Strengthen theenvironment for DSM

    2.1 CEB issuance ofEner Eff icient

    Code already drafted;ex ected to be read b

    EECB codes developed andin use althou h still rather

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    32/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    16

    Objectives Key PerformanceIndicators/Expected

    Outputs

    Accomplishments/ Statusas of Mid-term (Dec 1999)

    Accomplishments as ofJune 30, 2002

    implementation Commercial Building(EECB) Code of Practice

    March 2000 and implementedby July 2000.

    limited; to be expanded underRERED Project

    3.1 CEB annual update of

    Small Power PurchaseTariff

    Annual updates being carried

    out. Tariff issue between CEBand small power producersconsidered resolved with thesetting of a tariff ceiling.

    3.2 Signing by CEB of atleast 5 SPPA contracts bymid-term evaluation; 12 byproject completion

    Ongoing discussions between

    private developers and CEBre: small power purchasetariff

    16 minihydro refinanceapprovals, and 15 more underconsideration

    3. Improve public and

    private sectorperformance todeliver energyservices throughrenewable energyand DSM

    3.3 Generation planningmodels prepared by CEBwhich incorporateintermittent, non-dispatchable renewableenergy generating sources

    Preparation of generationplanning models ongoing.

    CEB continues to monitor andrecord data from wind farmand grid-connected minihydroprojects to become morefamiliar with issues that mustbe addressed for integrating

    non-dispatchable renewableenergy generating sources.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    33/104

    WB Sri Lanka Energy Services Delivery Project Im

    Table 3-4. Interventions Carried Out Following Mid-Term Review To Address Project Wea

    Mid-Term Status Recommendations Interventions

    Off-grid SHS As of end-Dec 99, only 682 SHSapproved for GEF grantdisbursement (vis--vis 30,000

    target); only 9% of IDA creditdisbursed; 2.4% for related GEFgrant approvals disbursed

    SHS vendors reluctant to serveas consumer financinginstitutions due to the necessaryinstitutional network, high costsand risks associated withadministering micro-loans tolow-income isolated ruralhouseholds.

    Interest rates paid by the end-users in excess of 24 percentper annum and in some cases

    as high as 33 percent perannum

    Participation of more MFIs that canservice potential isolated rural SHScustomers should be increased. This

    can be achieved by: assisting potential MFIs in

    qualifying as PCIs for the ESDProject;

    considering less stringent criteriafor MFIs to qualify as PCIs; and

    encouraging existing PCIs towork with and provide loans toMFIs that have proven outreachcapabilities in the targeted ruralareas.

    ESD Project also needs toinvestigate the possibility of using theGEF grant to provide loan insurance

    coverage to enhance MFI financialsecurity thereby allowing MFI toaccess the available ESD credit.

    Microfinance (with theaccreditation of SEEDS as a Pand private partnership mode

    market development and finanintroduced and actively promo

    The job of financing was left toMFIs, while vendors wereencouraged to concentrate onselling systems.

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    34/104

    WB Sri Lanka Energy Services Delivery Project Im

    Mid-Term Status Recommendations Interventions

    Off-gridvillage hydro(OGVH)

    Costs of coordinating andorganizing village cooperatives todevelop, own and operate theOGVH systems very high

    The option to allow private sectoror NGO developers who build,own and operate OGVH systemsand sell the electricity service toconsumers should be considered

    within the ESD Project. GEF grant could be used to

    attract the participation of theprivate sector through competitivebidding for specific franchiseareas

    Open solicitation process was initto get proposals from consultantshow to address policy, technical, sustainability issues pertaining toOGVH component. To ensure thaprocess would yield actualaccomplishments, consulting conwere tied to deliverables.

    GridConnectedMini-hydro(GCMH)

    Progress generally good, withapprovals/ disbursements as of mid-term exceeding targets. Specifically,disbursements are at US$6.0MM

    (out of the total 14.4 million IDAcredit)

    ESD Project should work with theCEB and GCMH developers toensure that tariff-setting issue issettled, i.e. the actual capacity value

    of the GCMH systems areadequately compensated for in thesetting of the SPPT

    Independent consultant hired toreview and report on the tariffs sethe CEB for purchase of power frsmall power producers. Based on

    consultants findings, a ceiling thawas acceptable to both the CEB aprivate developers was set on tarfor minihydro projects

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    35/104

    WB Sri Lanka Energy Services Delivery Project Im

    Mid-Term Status Recommendations Interventions

    Pilot windfarmcomponent

    3MW pilot wind farmcommissioned in February 1999and certified May 2000.

    CEB monitoring and recordingthe operational data from the

    wind farm and learning from thisexperience the issues that mustbe addressed for integratingnon-dispatchable andintermittent renewable power.

    CEB has not undertaken anymeasures to attract privatesector devt of wind power in SriLanka.

    CEB should undertake detailedstudy of energy and capacityvalue of wind electricity for theCEB grid and actively developand disseminate wind resource

    data to help attract private sectordevelopers for Sri Lankas windenergy resources.

    Regional wind resourceassessment (supported by UNand specific evaluations of sitecarried out.

    Potential projects identified to

    facilitate increased private secparticipation in this area.

    Capacity-BuildingComponent

    Implementation of capacity-building activities proceedingwithout any major problems

    However, CEB appears to becarrying out these activities in

    isolation of its general activities,i.e. there is little realcoordination between theactivities of the ESD capacitybuilding components and thenormal day-to-day activities ofthe CEB

    CEB should more activelyintegrate the results of the DSMand PEU activities into itsmainstream activities, i.e.

    clearly define an implementation

    program for the results of theDSM studies and building energyefficiency standards; and

    have the PEU actively identifyand promote off-grid ruralelectrification options in areasthat are clearly not going toreceive grid electricity in the nextfive years

    CEB drafted implementation pfor energy efficient building co

    CEB actively pushed for andassisted in the actual developof ESCOs

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    36/104

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    37/104

    21

    Assessment of Technical Performance/Overall Implementation

    Implementation of the Solar Home System Component

    As of the end of June 2002, a total of 18,619 solar home systems had been installed, with anaverage of 1000 systems being installed per month. This contrasted greatly with the situation atmid-term when only 682 applications had been approved for GEF grant disbursement (vis--vis30,000 target). The main issues that cropped up in the implementation of this component

    (categorized according to stakeholder) were as follows:

    Table 4-1. Issues Involved in Implementation of SHS Component

    Participating CreditInstitutions

    Limited rural network

    High transactions costs

    High risks associated with low-income, isolated households

    SHS Vendors High costs of securing SHS sub-loans with PCIs High cost of administering micro-loans to SHS end-users

    High risks posed by SHS end-users

    Lack of developed dealer network

    Distraction from principal functions (i.e. selling systems)

    End-Users Limited access to affordable loans

    Initial high costs of SHS installation

    Lack of awareness of SHS option

    Perceived lack of credibility of SHS vendors

    Participating Credit Institutions

    A number of the commercial banks reiterated a long-standing and commonly shared view among

    traditional lending institutions that lending to solar home systems was high-risk and unprofitable.

    They expressed preference for the grid-connected hydro projects, which they perceived to be

    significantly less risky. SEEDS, for its part, recognized the need for it to expand its operations to

    keep up with the growing demand. It also acknowledged the need to streamline the process so

    that the release of funds could be carried out faster.SHS Vendors

    Since the start of the project, SHS vendors had been reluctant to serve as consumer financing

    institutions due to the required institutional network, high costs and risks associated with

    administering micro-loans to low-income isolated rural households. High interest rates were also

    an issue as end-users had to pay in excess of 24 percent per annum and in some cases as high as33 percent per annum.

    In order to address these issues, microfinance and private partnership model for market

    development and financing were introduced and actively promoted. The job of financing was left

    to the MFIs and vendors were encouraged to concentrate on selling systems. As a result of these

    interventions, sales increased at an exponential rate.

    During consultations in May 2002, most of the equipment vendors acknowledged that the entry

    of SEEDS, the lone microfinance institution accredited as a PCI, was highly instrumental in

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    38/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    22

    increasing access of consumers to financing, and as a result, expanding the SHS market. Asidefrom relieving the vendors of the role of financier, SEEDS also has a rural network, whichenabled it to reach a greater number of end-users in remote areas. Most vendors expressed theneed for more MFIs to be accredited as PCIs in the future as SEEDS has been unable to keep upwith the growth in demand for SHS loans, resulting in a growing backlog and delays in the

    release of funds to vendors.End-users

    During the surveys conducted among end-users, majority expressed satisfaction with the energyservice they were receiving under the SHS component (more details in Chapter 7). The mostcommon technical problem cited involved battery failure stemming from over-use of the system.Defective lamps have also been identified as an issue. Other problems stem from wiring defects,loose connections, and incorrect placing of the PV module. Some expressed strong concernabout the future when the warranty period ends and field offices of the vendors are closed.Others also mentioned incidents of parts supply shortages and the lack of enough knowledgeablefield personnel. In terms of overall level of service for repair/maintenance, however, eighty (80)percent of those surveyed indicated satisfaction.

    The success of the SHS component was clearly facilitated by the entry of a microfinanceinstitution that had a rural network and had a grassroots orientation that enabled it to reach andbe more responsive to a greater number of rural customers. In order to sustain the gains madeunder this component, it is essential that more MFIs participate in the program, especially as theexperience under ESD showed that commercial banks are not inclined to go into micro-lending.

    Off-grid Village Hydro Component

    The off-grid village hydro installations are built, owned, and operated by the communitiesthrough electricity cooperative societies that were set up specifically for that purpose. Assistanceis provided by the ESD project in retaining consultants to prepare these installations. Project

    preparation assistance usually includes social mobilization, society formation, preparation offeasibility studies that cover both technical and socio-economic aspects, submission of businessplans, and other documentation for bank loan negotiations and some amount of projectimplementation support (Gamata Light Electricity for Villages, 2002).The main issues that cropped up in the implementation of this component (categorized accordingto stakeholder) were as follows:

    Table 4-2. Issues Involved in Implementation of OGVH Component

    Participating CreditInstitutions

    Small size of OGVH project loans

    High transactions costs

    High risks associated with OGVH borrowers

    OGVH ProjectConsultants/Organizers

    Long lead times required to organize cooperatives and obtain approvals

    Risks associated with project organization and development work

    Timing of GEF grant release to compensate for project developers work

    Sustainability of project organization and development work without the ESDproject

    OGVH Cooperatives/

    Societies/End-users

    Limited access to affordable loans

    Timing of release of GEF grant

    Operation and maintenance of OGVH project

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    39/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    23

    Productive use of OGVH power

    Participating Credit Institutions

    The commercial banksparticipating in the project generally view off-grid village hydro projectsas high-risk, and prefer the grid-connected hydro projects. The principal borrowers for theOGVH projects are village societies or cooperatives specifically formed to undertake the project.As such, they do not have an established banking record. The commercial banks also admitted tonot having the rural network to serve small end-users who make up the electricity cooperatives.As in the case of the SHS component, it was the entry of a microfinance institution that enabledthe OGVH component to take off. SEEDS had a better understanding of the rural situation, awider rural network, and was able to respond more effectively to the needs of rural electricitycooperatives.OGVH Project Consultants/Organizers

    The most important catalysts for the development of the OGVH projects have been the OGVHconsultants/organizers. Their main responsibility is to identify and develop potential village

    hydro sites, a role they have been performing long in various rural areas in Sri Lanka before theESD project. The project, therefore, only served to assist them in their development efforts andexpand the applications of village hydro in the country. The main concern of this group has beenthe long lead time and tremendous effort required to organize target households to a functioningvillage society that is capable of qualifying for a loan.OGVH Cooperatives/Societies/End-users

    Most of the end-users expressed satisfaction over the energy service provided under this scheme(see Sec 7 for more details) and expressed desire to expand their current usage and acquire moreappliances. This contrasted greatly to the situation at the start of the project when there was apervasive lack of awareness about the potential of the proposed OGV projects (as well as theirlimitations). The most common technical problems faced by customers were power failurescaused by over usage. Normally this occurs between 6pm to 10pm. Those consumers who are atthe end of the distribution line also face the problem of low voltage on occasion.

    Grid-connected Hydro Component

    The implementation of the grid-connected minihydro component has been progressing well sincethe start of the project. As of June 30, 2002, 16 loans representing a total of 31 MW installedcapacity had been approved. An additional 15 loans are currently under appraisal, representingan additional 53 MW. The original target at project inception was 26 MW of both grid and off-grid renewable energy capacity.

    A meeting with the ESD Administrative Unit and representatives of the Grid Connected SmallPower Developers Association in May 2002 revealed that private developers are generallysatisfied with the way the grid-connected hydro component of the project has been implemented.The small power purchase agreement and the resolution of the tariff issue were both identified asbeing crucial in attracting more developers to enter the market. The SPPA, in particular, meantreduced transaction costs, risks, and a clearer framework for investors to operate in.Prior to this, there had been long-running debates/discussions between the CEB and the grid-connected small hydro developers association (GCSHDA) regarding the level of the tariff, the

  • 8/11/2019 World0Bank0Sri1nal0Resources0Group0

    40/104

    WB Sri Lanka Energy Services Delivery Project Impacts Assessment and Lessons Learned

    24

    provision of a capacity credit to small power producers, etc. The eventual resolution of theseissues made it possible for turning the situation around.ECOPOWER, one of the private companies that have played a major role in setting up gridconnected hydro projects, cited the resolution of the SPPT and the long-term money madeavailable under the ESD project, as crucial factors in their decision to pursue several projects.

    Prior to ESD, terms offered by financial institutions were for considerably shorter periods.Commercial banks participating under the project perceive this component to be the least risky,largely because of the small power purchase agreement (SPPA).Clearly the success of this component was due largely to the resolution of the SPPA and tariffceiling issues. This serves as an example of how crucial it is to have a conducive institutional andpolicy framework in place to attract private sector participation.

    Pilot Wind Farm Component

    The implementation of the 3-MW pilot wind farm component has proceeded with no majorbarriers to implementation. The pilot project was commissioned in February 1999 and certified

    in May 2000. The plant consists of five 46-meter towers with 600 kW turbines designed tosupply a total annual capacity of about 4.5 GWh. Total project cost amounted to US$1,200/kW,which is acceptable for a first grid-connected wind farm operation in a country. Wind speedshave also been found to be as projected during project design.The success of any pilot project is determined by its ability to stimulate a commercial market. Asof mid-term, there were no prospects for commercial wind farm projects, largely because of theexpected high costs of electricity to be generated from. The prevailing sentiment was that thelevel of the SPPT was not sufficient to support the commercial wind developmen