WORLD HEALTH ORGANISATION MONDIALE ORGANIZATION DE …€¦ · ORGANISATION MONDIALE DE LA SANTE...
Transcript of WORLD HEALTH ORGANISATION MONDIALE ORGANIZATION DE …€¦ · ORGANISATION MONDIALE DE LA SANTE...
•
-
WORLD HEALTH ORGANIZATION
ORGANISATION MONDIALE DE LA SANTE
REGIONAL OFFICE FOR THE WESTERN PACIFIC
BUREAU REGIONAL DU PACIFIQUE OCCIDENTAL
REGIONAL COMHITTEE
Twenty-first Session Uani1a 1-8 September 1970
Provisional agenda item 17
WPR/RC21/10 26 August 1970
ORIGINAL: ENGLISH
REPORTS BY GOVEmn1ENTS ON THE PROGRESS
1
OF CURRENT PROGRAMMES RECEIVING WHO ASSISTANCE (RESOLUTION WPR/RC20.R5)
QUESTIONNAIRE SENT TO GOVERm!ENTS
The Regional Committee at its twentieth session adopted resolution
WPR/RC20.R5 which requested the Regional Director to include in the
agenda for future meetings of the Committee reports by governments on
the progress of current programmes receiving ~mo assistance. A
questionnaire was sent to governments to obtain the information
required. The questions were framed broadly in the context of this
resolution, so that the completed questionnaires could serve as govern
ment reports on the progress and evaluation of WHO-assisted country
projects currently in operation.
The WHO-assisted country activities are referred to as projects
rather than programmes, as the activities normally undertaken are con
cerned with achieving in particular areas specific objectives within
a limited time-span.
In content, the questionnaire included consideration of the place
and priority of projects in the national health programmes, the aptness
and attainability within a time constraint of their objectives, the
local applicability and effectiveness of the methods (transferable
technology) used, the availability of resources, the flexibility given
Ito planning and •••
WPR/RC2l/10 page 2
to planning and implementation, and their impact on the population.
WHO-assisted activities dealing with fellowships not connected
with projects were not included in the questionnaire because they are
periodically evaluated.
Copies of the questionnaire were sent to fourteen countries in
the Region which had WHO-assisted projects in operation. In these
countries there were currently a total of 130 projects re~eiving WHO
assistance.
2 SUMMARY OF THE REPORTS SUBI1ITTED BY GOVERNl1ENTS
Two of the fourteen countries did not return the questionnaires.
Reports were submitted on 92 of the 130 WHO-assisted projects currently
in operation. The questionnaire was not completed in respect of ten
projects because they were in too early a stage for assessment. The
response rate was therefore 12/14 or 85.7% for countries, and 92/120 or
76.7% for projects, excluding the ten projects recently initiated.
There were two boxes, yes and no, for each question so that either
one or the other could be ticked. The affirmative replies to the
questions are summarized in Table 1 by country and in Table 2 by subject.
The figures in these tables denote the number of projects on which
affirmative replies were received. The difference between 92 and the
totals given in the Tables denotes the number of projects on which
negative replies were received.
The questionnaire included three other points which are not
presented in the above two tables. They are (1) whether the country
has a national socio-economic development plan, (2) whether the country
has a national health plan, and, if so, (3) whether this national health
plan is incorporated as a sector of the national socio-economic develop
ment plan. The twelve countries which sent in completed questionnaires
replied to these three questions in the affirmative.
It will be noted from Tables 1 and 2 that 83.7% of the 92 projects
are based on or are related to national health plans. The ~ajority of
Ithe projects •••
•
-
s
I , . I
"
I I
~ -~
WPR/RC2l/l0 page 3
the projects (95.7%) have objectives clearly related to specific
problems intended to be solved.
The objectives of 56 of the projects can be translated into
quantifiable targets. Thirty-six are without such targets, but have
appropriate criteria \~hich provide a basis for determining if the
objectives have been met. In 62 of the projects it is believed that
the targets can be achieved or the criteria satisfied during their
life span.
In 78.3% of the projects, baseline data are available to measure
project progress. In 59.8% of the projects the results of the activities
are considered satisfactory.
Transferable technology had been introduced before the inception
of 65 projects. In all of these projects it was considered that WHO
assistance would promote the use of the technology in the country; this
expectation has been confirmed during the operation of 60 or 92.3%.
H~ever, in 26 of the remaining 27 projects (96.3%) in which transfer
able technology had not been introduced prior to their inception, it
is believed that the assistance provided by WHO will ensure the conti
nuous use of the technology after international assistance has been
completed.
The efficacy of the methods used has been assessed (a) by employing
performance standards on which to base estimates of target accomplish
ments, (b) by determining the cost-effectiveness of the results obtained,
(c) by using criteria on quality of the results, or (d) by two or all of
these measures. Among these measures, (a) was used in 9.8%, (b) in 1.1%,
(c) in 10.9% and (d) in 33.7% of the projects. Five of the 9 projects
employing (a), the only project using (b), 5 of the 10 projects utilizing
(c) and 23 of the 31 projects using (d) found the results of assessment
satisfactory.
Government commitments covering local resources are being fully
met in 53 of the 92 projects (57.6%). Local resources are being fully
land effectively
WPR/RC21/l0 page 4
and effectively utilized in 47. In 39 projects, government commit
ments are not being fully met. It is believed that this deficiency
may be solved by the more efficient use of the resources! available in
4 projects, by adding resources in 10, and by employing both of these
means in 23.
In the implementation of projects, non-resource constraints have
been encountered due to (a) political and social climate. (b) existing
legislation, (c) physical environment, (d) institutional structure,
(e) supplies system and (f) others, or a combination of two or more of
these causes. Among them, (a) is the cause of non-resource constraints
in 40.2%, (b) in 25.0%, (c) in 30.4%, (d) in 30.4%, (e) in 27.2%, and
(f) in 20.7%. It is believed that from 63.2 to 85.7% of these causes
can be minimized or eliminated.
Non-resource constraints on the part of WHO are also encountered
due to its policies, supplies system or others, or due to two or all of
these causes. l~IO policies were said to be the cause of non-resource
constraints in 10.9%, its supplies system in 9.8%, and others in 10.9%.
The replies indicated that from 70.0 to 90.0% of the causes can be
minimized or eliminated.
The project plan of action is regularly revie'ved in 73.3% of the
projects to conform to budgetary and other resource constraints, in
81.5% to introduce changes required as a result of progress in techno
logy and management, and in 70.7% to incorporate modifications resulting
from substantive changes in the projects' objectives, methods and/or
targets.
A country project can help satisfy the population's needs through:
(a) accomplishment of its specifiC objectives, (b) its clontribution to
the broader objectives of the programme to which it is linked and/or
(c) its relation to the national socio-economic development plan;
(a) is applicable in 83.7%, (b) in 75.0% and (c) in 70.7% of the
projects on which reports were received.
/3 OBSERVATIONS •••
• •
,
~~ .
3 OBSERVATIONS
vIPR/RC21/10 page 5
The questionnaire used in this evaluation had its limitations.
It can only furnish general information on the projects assessed to
indicate trends, problems and progress. In-depth evaluation for each
project would be necessary to determine more precisely the difficulties
encountered, the results of the methods used, and the targets met.
In the present study the rate of response is 76.7% (92 out of 120
projects). which leaves undetermined the situation prevailing in the
remaining 23.3%. The present evaluation is. therefore. based on
information collected on approximately three-fourths of the ~iHO-assisted
projects in the Region. It is hoped that with the co-operation of
I1ember States, coverage can be increased in future evaluation exercises.
Although the importance of collecting baseline data at the
beginning of a project is generally recognized as a basis for future
assessment, such data are not available in 21.7% of the projects.
Steps should, therefore, be taken as soon as possible to obtain the
information needed and, if this is not feasible, to establish new' base
line data corresponding to a fixed time from which further project
progress can be measured. The findings also underscore the necessity
of establishing baseline data in each new project being started.
Due to the limitations of the questionnaire it was not possible
to obtain precise and detailed replies; hence the difficulty in
tabulating some of the answers received. Such details may be obtained
in thein-depth evaluation of individual projects which is normally
undertaken by project staff. Further efforts should nevertheless be
undertaken in the future to improve the frame and content of the
questionnaire in order to secure as much information as possible.
4 CONCLUSIONS
It is encouraging to note that every country in the Region
considers that it has a national health plan which is incorporated
las a sector •••
WPR/RC2l/l0 page 6
as a sector of its national socio-economic development plan.
The great majority of WHO-assisted projects in the Region are based
on national health plans and their objectives are clearly related to the
specific problems intended to be solved.
Three-fifths of the projects have objectives w~ich are translated
into quantifiable targets, while the remaining two-fifths have appro
priate criteria which provide a basis for determining whether objectives
have been met. In 67% of the projects, the reports indicate that the
targets can be achieved or the criteria satisfied during their life span.
Since about one-fifth of the projects have no baseline data upon
which to measure project progress, every effort should be made to obtain
or establish them in projects in operation and to ensure that baseline
information is available in all new projects.
The local applicability and effectiveness of the methods used have
been confirmed in tllTo-thirds of the projects.
The findings that government commitments are fully met in only
57.6% of the projects leave a large number for further sqrutiny, since
attainment of the objectives will be jeopardized by the shortage of
available resources and other unsatisfied requirements. Although this
deficiency can be covered fully in some projects, and partly in others,
by making more efficient use of the resources available, it is important
to determine whether the additional resources required can be met by
governments. If not, the targets or plans of action would have to be
revised so that they fit more realistically the resources available.
In more than half of the projects, government commitments covering
local resources are fully met and these resources are fully and effi
ciently utilized. Non-resource constraints on the part of countries are
due to various factors, mostly political and social, about four-fifths
of which can be minimized or eliminated.
Non-resource constraints on the part of WHO are encountered in
a small percentage of projects and it should be possible to explore
/ areas l.,here •••
. -
HPR/RC2l/l0 page 7/8
areas where they can be minimized within the frame of WIlO policy and
regulations. Constraints necessarily arising from WHO policy should
be taken into account in preparing project plans of operation. If l~O
policy changes are felt necessary by governments, representations can
be made by them at the appropriate levels of the Organization.
The plan of action is regularly revievled in about three-fourths
of the projects in order to give flexibility to planning and imple
mentation.
The majority of the projects help directly or indirectly to satisfy
the needs of the population.
This is the first attempt at an overall evaluation of WHO-assisted
activities on the basis of about three-fourths of the projects currently
in operation in the Region. It is believed that with an improved
questionnaire and the co-operation of Hember States more useful informa
tion can be obtained from future evaluations •
+ \ ,;:, ¥ t \
TABLE 1. WHO-ASSISTED PROJECTS IN COUNTRIES FURNISHING AFFmMAl'IVE REPl.lES
1"" ~uery I No. of No. of WHO· NHP Project Project's objec- Objectives No quantifiable
~ I WHO_ ..... , aubted proj8CQ related to based on t1 ves related to translated into targets but with
projects on which rep- project NHP solution of quantifiable criteria for
"-lies were specific problems targets determining
Country '" received accomplishments
~::.-. -.. .-
British Solomon Islands
Protectorate 3 1 1 1 1 1
China (Taiwan) I 17 15 10 10 15 12 3
Gilbert & Ellice Islands 2 2 2 2 2 2
Laos 14 11 10 9 11 3 8 \
Malaysia I 17 16 15 15 16 12 4
I New Hebrides 3 2 2 2 2 2
Philippines 17 15 14 13 14 11 4
! I Republic of Korea 10 10 10 9 10 4 6
. I s.
I I lngapore 14 9 7 7 7 4 5
, . I 2 2 2 2 1 1 I Tonga 2 , i
Viet-Nam 15 6 4 4 6 4 2
Western 5 amoa 4 3 3 3 2 2 1
TOTAL 118 92 80 77 88 56 36 --~ ----1------1----- -- I---- -:
Per cent, 100.0 87,0 83.7 95.7 l 60.9 39.1
,------------------------ -.. -------'---.. _._-------- ."- - -.. ---------------- '--- -- . _. __ . __ ._-._--_. --------- -- ._------_.-
Targets and 1 criteria to be achieved during life of project
--
13
1
6
7
2
14 !
8
5
2
3
1
62 __ -1 67.4 I
! -------j
>-
'g ~ CJ<I ::tI CD ....... \Q~
N .... ....... S
T ;tile 1. (continued)
Query No. of WHO No. of WHO- Baseline data Results of assisted assisted projects available to project activi-projects on which measure project ties satisfac-
replies were progress tory Country received
I
SHtish Solomon Islands I Protectorate 3
I 1 1 I
I China (Taiwan) 17 15 12 12
I G libert & Ellice Islands Z 2 2 2
Laos 14 11 7 8
Malaysia 17 16 12 7
New Hebrides 3 2
Philippines 17 15 14 9
Republlc of Korea 10 10 8 3
I Singapore 14 9 7 7
Tonga Z 2 2 2
Viet-Nam 15 6 4 2
Western Samoa 4 3 3 3
TOTAL 118 92 I 72 55 ,
Per cent. 100.0 78.3 69,8
• I -I -"
Transferable WHO assistance technology would promote introduced use of techno-previously logy In the
country
1 1
14 14
1 1
4 4
10 10
2 2
12 12
7 7
7 7
2 2
4 4
1 1
65 66
70.6 (lOO.W
-65/65
~
This expectatlol
confumed
during operation of project
1
14
1
4
7
2
11
6
7
2
4
1
60
92.S-
-60/65
--WHO assistance would ensure con-tinuous use of
technOlogy after end of project
1
1
7
6
3
3
1
2
2
26
92.9* "26/(92-64)
i
I
'2 ~ OQ ~ ~ .... .... ~ ON .... .... ....
o
~-, ('
Table 1. (continued)
Efficacy of the methods Query I No. of WHO- \ No. of WHO- 1 ________ ~~~:~~---
assisted assisted projects. Target _ Cost- : QUality
projects \ on which repli~ accomplish- ! effectiveness i of the I I were received ! ment i of the i results _ Countrv , 'i results t---~,,------ ----===1- t== -,-!-_____ - I I ".
British Solomon Islands \ 1 : Protectorate 3! I I
17 I 15 I China (Taiwan)
Gilbert & Ellice Islands
Laos
Malaysia
New Hebrides
philippines
Republic of Korea
Singapore
Tonga
Viet-Nam
Western Samoa
TOTAL
Per cent
2 \ 2 \
I 11 14
17
3
17
10
14
2
15
4
118
I I 16
! 1
I
I \ I j !
2
15
10
9
2
6
3
92
100.0
1
1
1
I 1 i I
I \
1
3
i
1
\ 9
I
! 9.8
2
1
4
1
1
1
1
1 10
1.1 10.9
• ... • Results of assessments satisfactory
as regards:
'"
2 Target Cost- Quality 2 :::1 ---- ~
or all accomplish-, effectiveness I of the or all of these ment I of the results of these'
iI~~= I . I I I I i I
5
5 I 3 1
10
2
4 1
1 I
) 2
1 1
31 5
33.7
2
1
1
1
1 5
_---L--_~ --r=--
5
3
2
7
2
2
1
1
23
'g ~ OQ I'Q III ......
I-'~ I-' N
I-' ...... b
J..., I I~ I;. .. , '....... ~ I, .... i , ~ Query No. of WHO- No. ci WHO- Government
C-, -~ assisted projects assisted projects commitments on
on which replies local resources
were received fully met
British Solomon Islands Protectorate 3 1
China (Taiwan) 17 15 10
Gilbert & Ellice Islands 2 2 2
Laos 14 11 5
Malaysia 17 16 10
New Hebrides 3 2 2
Phlllppines 17 15 9
Republic of Korea 10 10 2
Singapore 14 9 6 .
Tonga 2 2 2
Viet-Nam 15 6 . 4
Western Samoa 4 3 1
TOTAL 118 92 53
I Per cent. 100.0 57.6 I i \
~ Local resources
fully and effectively
utilized
10
2
5
9
2
7
1
6
2
3
47
51.1
•
Deficienc~ i\8over~ent commitments n met y:
Efficient use Adding Both of these
of resources more means
provided ~lOUICes
1
1 1 1
1 1 4
1 1 4
6
6 2
1 2
1 1
2
4 10 23
(l0.3)- (25.6)- (59.0)-
Decominator '" 92 - 53 = 39
'g~ 0<1 l:'d 1Il_
.... ~ "., N .... -.... o
'x." • ,~. Table 1. (continued)
--------TN'~ of Il!!!l of ~ Noo_ ._ .... """""" .... In Query' 0- country due to:
WHO- ass ted __ _ .. _._ . d groJegI~lt Po~tical ~xi'ting Pltlflcal l!JStitu-~PPlies I h asSlste n if an e§: a- n ron- tional Ot ers . reg, es ~ yCial tl ment structure system
Country prOjects ~lJived i mate
f Bri",' Solomon ''''''& ~
3 1 1 1 1 I Protectorate
I China (Taiwan) 17 15 3 4 1 4 1
I I I
: Gilbert & Ellice Islands 2 2 1 1
Laos 14 11 9 3 4 1 5 5
Malaysia 1'1 16 3 1 4 5 1 4
New, Hebrides 3 2 2 2 2 2
Phili ppines 17 15 'f 4 8 '1 9 1
Republic of Korea 10 10 '1 2 3 4 1 3
Singapore 14 9 1 1 1 2 1 2
Tonga 2 2 2
Viet-Nam 15 6 6 5 1 1 2 3
Western Samoa 4 3 1 2 1 1
TOT A L U8 92 3'1 23 28 28 25 19
Per cent. 100.0 40.2 25.0 30.4 30.4 27.2 20.'1
~ '!-'{ ,~
Non-resource c~trl!inU An country can be minimized or mIDate from:
Poatical Existing ~cal Institu- Supplies an ~~sla- ron- tlonal Others sYfal !ment structure system C mate
1 1 ! 1 ! I
3 4 1 4 I 1 i I
1 . I 1
I 6 1 3 1 ! 4
3 1 3 3 1 4
2 2 2 2
5 4 6 7 I 9 1
7 2 3 3 2
1 1 1 2 1 2
2
3 3 2
1 2 1 1
28 19 23 24 21 12
- - • (85. '1)- (84.0)- (63.2)-('15.7) (89.,6) (82.1)
* 28/37 *19/23 *23/28 *24/28 ~26 *12/19
("'I
'2 ~ aq l>:I II> .......
~~ "" N ~ ....... ~ o
Query
~ountry
~tish Solomon ~ds Prorectorate
:biaa (T*,wan)
;Ubert & ElUce Islands
AlII
falaylia
'ewHebddef
ldUpplDel
"public of Korea
<rIgapore
0118·
iet-Nam
'estern Samoa
TOTAL .
Per cent,
~ ,
No, of WHO_bted
projecu
3
17
2
14.
17
3
I'!
10
14
2
15
4
U8
Table I, (continued)
Non-resource constrainU on Non-resource COIIIUatlllS Cll'I I
No, of WHO- the pan of WHO due to: the pan of WHO can be mini-! Project plaa of action reviewed regularly to:
IIIiIted pro mlzed or eUm1nated as r~ds: I _---on whlch WHO Supplies Othen WHO i Supplies Othen 1 j,orm ~nd Introduce Incorporate 11 ~ replies were policies IY'tem policfes j.ystem I ~ relevant mod1ficatiollS III ;;
constraUlU I n received innovations , ~ N
1
15 1 1 1 1
2 1
11 2 3 1
16 2 1 2
2 2 2
15 3 1 3
10 6 5
9 1 1 1
2
6 1 3
3
92 I 10 I 9 I 10 I 9 I 7 I
100,0 10,9 9.8 10.9 (90.0)", (1'1.8)",
• linn - 'f /9 .,. • ~
1
12
1 2
1 9
1 11
2
1 13
'I
1 6
1
2 6
2
'I I 72 I
'10.0-1 78.3 I - 1flll. I I
1
10
2
9
13
2
13
9
'I
1
5
3
75
81.5
10
2
6
13
2
12
5
7
1
5
2
65
70,7
I-' ..... b
~ i ,\.' Table 1. (continued)
,f 1', " .
""---~-~~-rl No. of WHO"_' I No. ~f WHO-_.:;! Pro"'" bd""" ""'" ......... tioo· ....... ""oo;;-~ projects projecu on which
repUes were received
Accomplishment of l iu specific object! ves I lU contribution to
broader objecti vel of lu relation to the
national socia-economic
development plan , the programme to
which it is linked \- Caun~ =-~:.-=-'=""=' "====i=======jFr===== I _
British Solomon Islands
Protectorate
China (Taiwan)
Gilbert & Ellice Islands
Laos
Malaysia
New Hebrides
Phill ppines
Republic of Korea
Singapore
Tonga
Vier-Nam
Western Samoa
TOTAL
Pel cent,
3
17
2
14
17
3
17
10
14
2
15
4
U6
1 1 1
15 12 12
2 2 1
u 9 8
16 13 11
2 2
15 13 12
10 8 6
9 9 8
2 1 1
6 6 1
3 3 2
92 77 69
100,0 83.7 75.0
1
10
1
8
14
2
13
8
7
1
65
70.7
...
1~ OQ~ (1)_
f-'~ VI N _f-' f-'-"'E;
'1\ l , "
, ,\ 't(
TABLE 2. WHO-ASSISTED PROJECTS ACCORDING TO SUBJECT FURNISHING AFFIRMATIVE REPLIES
~~ No. of WHO- No. of WHO- I Project's ob-I
NHP Project Objectives No quantifiable Targets and assisted assisted projects related based on I jeeti ves rela- translated targets but with criteria to bE projects on which replies to project NHP ted to solutim into criteria for achieved
. "~ were received of specific quantifiable determining during life of ,Project problems targets accomplishments project
al Communicable Diseases- 12 9 9 9 9 6 3 7
Tuberculosis and Leprosy 8 8 8 8 8 6 2 8
Malaria and Filariasis 9 7 7 5 7 5 2 4
Environmental H~alth 17 9 7 7 9 7 2 7
bl Public Health Services- 42 34 29 28 31 16 18 19
Maternal and Child Health and
Nutrition 10 8 5 5 7 4 4 5
cl Health Protection aIld Promotion- 11 10 8 8 10 8 2 8
Education and Training 9 7 7 7 7 4 3 4
TOTAL 118 92 80 77 88 56 36 62 .
I Per cent. 100.0 87.0 83.7 95.7 60.9 39.1 67.4 I t ._-_. --
!I Includes: Venereal Diseases, Tracheima and Epidemiological Surveill ance, International Quarantine
ty Includes: National Health Planning, Health Laboratory Servic~ Medical Care, Nursing, Health Education. Rehabilitation, and Vital and Health S tatlstles
Sl Includes : Occuptaional Health, Mental Health. Dental Health, Radiation Health, Cancer and Goitre
'g ~ O<I~ ~ ..... ..... ~ " N ..... ..... ..... o
Table 2. (continued)
--.--Query No. of WHO- No. of WHO- Baseline data Results of
assisted assisted projects available to project projects on which replies measure activities
were received project satisfactory Project progress
-
al Communicable Diseaser 12 9 '/ '/
Tuberculosis and Leprosy 8 8 8 5
Malaria and Filariasis 9 '/ 6 3
Environmentai Health 1,/ 9 6 6
Public Health Servicel-I 42 34 25 19
Maternal and Child, and Nutrition 10 8 5 3
Health Protection and Promotiog.1
11 10 9 6
Education and Training 9 '/ 6 6
TOT A L 118 92 ,/2 55
:
Per cent. 100.0 '/8.3 59.8
. --
• 1
Transferable WHO assistanc'!
technology would promote
introduced use of techno-
previously logy in the country
5 5
'/ '/
5 5
'/ '/
25 25
3 3
.
8 8
5 5
~5 65
'/0.6 100.0·
°65/65
•
This expectation
confirmed during operation
of project
5
'/
5
6
23
2
'1
5
60
(92.3)·
·60/65
WHO assistance would ensure continuous use
of technology after end of the Dlolect
4
1
2
2
9
5
2
1
26
92.9·
"26/(92-64)
'2 ~ 00 ~ 11>-
.... ~ OON .... -b
'~ • ~
No. of WHO-QUery
No. of WHO- assisted (11'0:'
assisted eets on wbid
pIo;ects epUee were
Project Ireceived
al Communicable Diseases- 12 9
Tuberculosis and Leprosy 8 8
Malaria and Filariasis 9 'I
Environmental Health 1'1 9
bl Public Health ServiCes- 42 34
Maternal and Child Health and
Nutrition 10 8
c Health Protection and PromotiOir 11 10
Education and Training 9 'I
TOT A L 118 92
I Per cent. 100.0
" Table 2. (continued)
Efficacy of the methods assessed by:
Target Cost- Quality 2
accomplishments effectiveness of the or all of
of the results results these
2 3
2 6
2 1 3
I 3
8 8
1 1 2
2 5 I ,
1 1
9 1 10 31
9.8 1.1 10.9 33.'1
,), 'r,
Results of assessment satisfactory as regards:
Target Cost- Quality 2 accomplish- effective- of the or all of
ment ness of the results these results
2 2
5
2 1 2
1
4 5
1 2
1 5
1
5 1 :; 23
I
,
"d :I III ~
00 1'1 II> "'
~~ t 8
Query No. of WHO- No, of WHO-
assisted assisted project
projects on which rep-
liea were Project tecei~
h al ~ommunicable Diseaser 12 9
TubereubUacd ~ 8 8
!Malaria and Filariasis 9 7
!Environmental Health 17 9
bl Public Health Services- 42 34
tvtaternal and Child Health and t-Iutrition 10 8
~I _ cl ealth Protection and PromotioJl 11 10
ducation and Training 9 7
-~----- -,,,.- ~- _.. - -~.- -~-- "- - --- - ---_._ ... _---
TOTAL 118 92
-- --
Per cern:. 100.0
.~ j
Table 2. (continued)
Government Local resources
commitments on fully and
local resources effectively
fully met utilized
6 5
6 5
5 5
5 4
17 16
2 1
6 5
6 6
53 47
57.6 51.1
Deficiency in government commitments can be met by:
Efficient use of Adding more Both of
resources provided resources these means
3
1 1
1 1
1 2
5 11
1 5
1 3
1 ----
4 10 23
(10.3)· (25.6)" (59.0)·
"Denominator = 92 ~ 53 = 39
l. , ,
-
1 ~ G~ ::a (1)_
N~ ON .... ...... ....
o
« , \ Table 2. (continued) ~ _1. ~\
•
No. of ~~8! Non-resource constraints encountered in country due to: Non-resource constraints in country can be minimized or eliminated trOIT
~ WHO- nss~ted- political ExIsting Physical - lnst1tu- Supplies
~ eets assisted ;\'lhich and legisla- environ- tional system
re~ iR.5 projects "'''' e social tion ment structure
_ receilred climate
eet - .. ~ -- -
'lm~rble ~ 12 9 3 4 1 4 2
<ereulosis and 8 8 5 4 1 3
.rosy
'aria and Filariasis 9 7 2 1 3 2 1
ironmental-Health 17 9 4 5 3 3 2
~I 42 34 15 9 11 10 10 .lie Health ServiceS'
temal and Child
lIlth and Nutrition 10 8 3 1 3 4 3
dth Pt,::tFtion and ,motiorr" 11 10 4 3 3 4 4
lClItion and Training 9 7 1
rOT A L 118 92 37 23 28 28 25
'er cent. lOO.O 40.2 25.0 30.4 30.4 27.2
. ~ ________ --________ . ____ . ____ .. ______________ 1--____ ._._~ __ •• --. ________ --\---
Political Existing Physical
Othen and legisla- environ-. !OCial tion ment
~mate
3 2 3 1
2 4 2
1 2 1 2
1 3 5 3
10 11 6 11
1 2 1 3
3 3 1
1 1
19 28 19 23
20.7 (75.7)" • (82.6) (82.1)'
*28/37 *19/23 *23/28
Institu- Supplies
tional .yttem
structure
3 1
1 2
1 1
2 2
10 9
4 2
3 4
24 2l
(85.7)' (84.0)*
*24/28 *21/25
Othen
2
1
1
7
1
1
l2
(63.2)*
*i2/19
'2 ~ 00 :>:t
11> ......
N~ .... N .... ...... ....
o
I
Table 2. (continued)
~ QUery-, I Non-resource constraints on
""'- No. of WHO- No. of WHO- the part of WHO due to :
c-~~~ assisted assisted projec '-projects on which WHO I Supplies Others
replies were poliCies 1 system received
i
al Communicable Diseaser 12 9 I 1 1
TuberculoSis and Leprqsy 8 8
Malaria and Filariasis 9, 7 2
Environmental Health 17 9 1 1. bl
Public Health Services- 42 34 5 5 6
Maternal and Child Health and NUtrition 10 8 1 1
Health Pr~ru'Oll and· Promotion- l.l 10 1 2
Education and Training 9 7 1 1.
TOT A L 1.18 92 10 9 10
Per cent. 100.0 10.9 9.8 10.9
I 1~~_,-
.4
Non-resource constraints on I the part of WHO can be mini-mized or eliminated as regards:
WHO Supplies Others
poUcies system
--1
1
1 1.
5 4 4
1 1.
1 2
1
9 7 7
(90.0)" (77.8)' • (70.0)
"9/10 "719 '7/10
:S ~
...--.
Project plan of action
reviewed regularly 10:
Conform to Introduce Incorporate budgetary and
relevant modifica-other resource constramts
innovations tions .- -
6 7 7
7 8 6
6 7 7
7 8 6
28 26 24
3 4 3
9 9 9
6 6 3
72 75 65
78.3 81.5 70.7
.. ~
~~ OQ 1:0 (I) .....
N~ NN ..... ..... .....
o
-----------~------~--~~ ----------I, r
Table 2. (continued)
~ Query
No, of \"HO- No.. of WHO-assisted
assisted pro jeets projects on which
...... '-...... ............... replies were I received I Project ~
al Communicable Diseases-" 12 9
Tuberculosis and ~y 8 8
Malaria and Filatiasis 9 7
Environmental Health 17 9
bl 42 34 Public Health ServiceS
Maternal and Child Health and
Nuttltion 10 8
. c/ ~ealth Protection and Promotiorr 11 10
Education and Training 9 7
TOT A L 118 92
.
Per cent, 100.0
---,;--............... ---
i~ ,', ','
..
------ --------
Project helping satisfy the population's needs through:
Accomplishment Its conttlbution to Its relation to of specific broader objectives the national objectives of the programme to socio-economic
which il is ll.oked develo!Klleot plan
8 6 6
8 6 6
6 6 4
9 7 8
25 23 22
5 7 6
9 9 7
7 5 6
77 69 65
83.7 75.0 70.7
I ,
,
L.
'2 ~ OQ ~ III .....
N~ WN ....
'" b