World Bank Project Financial Management Guidelines
-
Upload
innocent-aryan -
Category
Documents
-
view
245 -
download
6
Transcript of World Bank Project Financial Management Guidelines
-
8/3/2019 World Bank Project Financial Management Guidelines
1/156
MODULE 1
Unit 1 - Tr. no. 1
WORLD BANK PROJECT FINANCIAL
MANAGEMENT GUIDELINES
ART. III, SEC. 5 (B), OF THE WORLD BANKS
ARTICLES OF AGREEMENT:
The Bank should make arrangements toensure that borrowers use loan proceeds:
Only for the purposes intended With due attention to economy and
efficiency
-
8/3/2019 World Bank Project Financial Management Guidelines
2/156
MODULE 1
Unit 1 - Tr. no. 2
WORLD BANK
PFM GUIDELINES (contd)
SOME POLICIES AND GUIDELINES TOFACILITATE COMPLIANCE WITH ART. III,
SEC. 5 (B): OP/BP 10.02
Guidelines that have issued to borrowers
FARAH LACI Implementation Handbook
The Project Financial Management Manual
Others
-
8/3/2019 World Bank Project Financial Management Guidelines
3/156
MODULE 1
Unit 1 - Tr. no. 3
WORLD BANK
PFM GUIDELINES (contd)
OP 10.02
The definitive bank guideline on project financialmanagement
Describes the minimum fm requirements for everybank financed project
Requires projects to:
maintain adequate financial management
systems provide annual audited financial statements
have the financial statements audited
Describes the remedies available to the Bank in theevent of non-compliance
-
8/3/2019 World Bank Project Financial Management Guidelines
4/156
MODULE 1
Unit 1 - Tr. no. 4
WORLD BANK
PFM GUIDELINES (contd)
Bank Procedures (BP 10.02) Describes application of OP 10.02
in the project cycle
Recognizes the CFAA as a starting
point
-
8/3/2019 World Bank Project Financial Management Guidelines
5/156
MODULE 1
Unit 1 - Tr. no. 5
PHASES OF A TYPICAL
PROJECT CYCLE
Identification
Preparation
Appraisal Negotiations
Board Presentation
Effectiveness
Implementation
CompletionN.B. The focus of this session is on the Financial Management
activities that are performed during all eight stages
-
8/3/2019 World Bank Project Financial Management Guidelines
6/156
MODULE 1
Unit 1 - Tr. no. 6
FM activities before and during
implementation are strongly influenced by: whether the organization (e.g. PIU) that
will Implement the project already exists,or still has to be created
whether or not FM staffhave a trackrecord of managing and accounting for anexternally-funded project
PHASES OF A TYPICAL
PROJECT CYCLE (Contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
7/156
MODULE 1
Unit 1 - Tr. no. 7
There is usually a difference betweenborrower and lender FM requirements
An example of a borrower FM requirementis ensuring availability of enoughcounterpart funds before requesting foreignproject financing
Lender staffhave to ensure that the FMarrangements for the project will facilitatecompliancewith their organizationsfiduciary requirements.
PHASES OF A TYPICAL
PROJECT CYCLE (contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
8/156
MODULE 1
Unit 1 - Tr. no. 8
Typical case of the very first externally-
financed project in a sector
Most pre-implementation activities areconceptual
FM arrangements may not be created andFM staff may not be hired hired until justbefore effectiveness
The FM arrangements for the project need tobe conceptualized and described in detail
CASE 1: NEW PROJECT
WITH A PROPOSED PIU
-
8/3/2019 World Bank Project Financial Management Guidelines
9/156
MODULE 1
Unit 1 - Tr. no. 9
Conceptualization of FM arrangementswould
include:
The structure of the project FM organization
FM activities and functions
The types, numbers, and terms of reference of
needed FM skills
When, how, and where FM staffwill be hired
Remuneration of FM staff
CASE 1: NEW PROJECT WITH
A PROPOSED PIU (contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
10/156
MODULE 1
Unit 1 - Tr. no. 10
A project organization chart incorporating an FM
organization chart is a good starting point for
designing th
e FM structure Some Important Factors to Consider are:
Size and complexity of project
Number of participating/beneficiary institutions
Nature and geographical spread of the project
Number and frequency of project transactions
Sophistication and exigencies of financial reporting
CASE 1: NEW PROJECT WITH
A PROPOSED PIU (contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
11/156
MODULE 1
Unit 1 - Tr. no. 11
This is the easiest FM design situation
PIU is a known entity with a track record
The design and description of FM structureand functioning must still be as completeand detailed as in case 1
Emphasis should be on the modifications to
the existing structure and skills mix that areneeded to cope with new project
Such modifications must be made before thenew project becomes effective
CASE 2: FOLLOW-UP PROJECT
IN AN EXISTING PIU
-
8/3/2019 World Bank Project Financial Management Guidelines
12/156
MODULE 1Unit 1 - Tr. no. 12
A situation where the borrower decides to use an
existing PIU and FM staff and structure to implement
a new project in a completely different sector or field
of activities from that in which the PIU was previously
engaged
This is very rare because of the tendency for PIUs to
be staffed by sector specialists
This case requires greater care than case 2, because of
the likelihood that the new project would involve new
types of transactions, assets and liabilities
CASE 3: BRAND NEW PROJECTIN AN EXISTING PIU
-
8/3/2019 World Bank Project Financial Management Guidelines
13/156
MODULE 1Unit 1 - Tr. no. 13
NEGOTIATIONS STAGE
The Negotiations state is when borrower and lender
Agree on, among other things:
Structure, functioning, staffing of the FMsystems and
Reporting formats
These agreements are recorded in the minutes of
negotiations signed by both parties Whenever practicable, project director and
financial director should be included in the
borrowers negotiating team (easier in cases 2 and
3) than in case 1
-
8/3/2019 World Bank Project Financial Management Guidelines
14/156
MODULE 1Unit 1 - Tr. no. 14
PROJECT LAUNCH
WORKSHOP
To be organized immediately after loan or credit
effectiveness, but before implementation begins, it:
Brings togeth
er everyone likely to be involved inproject implementation
Discusses lender and borrower procurement,accounting, reporting, disbursement, auditingand other FM (and non-FM) arrangements
FM discussions at the workshop are facilitated bythe existence of a Project Financial ManagementManual (PFMM)
Anticipates and resolves problems
-
8/3/2019 World Bank Project Financial Management Guidelines
15/156
MODULE 1Unit 1 - Tr. no. 15
PROJECT PREPARATION
FACILITY (PPF)
Introduces pre-implementation FM problems
as well as the means for providing solutions
Necessitates project accounting which
would have been unnecessary without it
Provides the funds to recruit and pay FM
staff before credit effectiveness Is very useful in case 1 projects by
enabling the creation of good FM capacity
well before implementation begins
-
8/3/2019 World Bank Project Financial Management Guidelines
16/156
MODULE 1Unit 1 - Tr. no. 16
BORROWER ROLE VERSUS
LENDER ROLEPre-implementation FM activities
The borrower has the primary responsibility forimplementing all the FM activities
The lenders primary responsibility is to ensurethat the borrower carries out its responsibilities tothe lenders satisfaction
Borrower and lender share the responsibility forensuring that FM arrangements are accurately
and adequately reflected in the minutes ofnegotiations
Although the lender often request the projectlaunchworkshop, it is usually organized by theborrower
-
8/3/2019 World Bank Project Financial Management Guidelines
17/156
MODULE 1Unit 1 - Tr. no. 17
FM ACTIVITIES DURING
IMPLEMENTATION
Borrower is responsible for
all record keeping, systemsmaintenance, and reporting
activities
Lender requires adequateborrower reporting for
fiduciary purposes
-
8/3/2019 World Bank Project Financial Management Guidelines
18/156
MODULE 1Unit 1 - Tr. no. 18
FM PROJECT
COMPLETION
Overall evaluation of implementation experience includes
a review of FM performance throughout project life: the
reviewwill cover the following aspects of FM
Planning & budgeting
Internal control, including procurement &
internal audit
Book-keeping, accounting, IT, records
management
Financial reporting
Independent audit opinions
-
8/3/2019 World Bank Project Financial Management Guidelines
19/156
MODULE 1Unit 1 - Tr. no. 19
PROJECT FINANCIALMANAGEMENT (PFM) AND ITS
ENVIRONMENT
The organizational structure for
project implementation should
reflect the complexity of the
project.
How a project is organized and
staffed has a very important
bearing on its financial
management arrangements.
-
8/3/2019 World Bank Project Financial Management Guidelines
20/156
MODULE 1Unit 1 - Tr. no. 20
MAIN COMPONENTS OF A
PFM ENVIRONMENT
The organizational structure of the
project implementing unit
Functional relationships between the
various parts of the organization
Clear definition of the responsibilities ofeach functional part and individual
The quality ofhuman resources
-
8/3/2019 World Bank Project Financial Management Guidelines
21/156
MODULE 1Unit 1 - Tr. no. 21
MAIN COMPONENTS OF A
PFM ENVIRONMENT
Vertical and horizontal flows ofinformation, recommendations and decisions
Project actions based on information,recommendations and decisions
The flow of funds to finance project activities
The culture of the entity regarding properfinancial accountability and management
-
8/3/2019 World Bank Project Financial Management Guidelines
22/156
MODULE 1Unit 1 - Tr. no. 22
PROJECT FINANCIALMANAGEMENT (PFM)
ENVIRONMENT (contd)
Elements of good PFM Systems:
Planning and Budgeting
Internal Controls
Records Management and IT
Book-keeping and accounting Financial reporting
Auditing
-
8/3/2019 World Bank Project Financial Management Guidelines
23/156
MODULE 1Unit 1 - Tr. no. 23
INTERNAL CONTROL
Internal control is a process:
effected by an organization,
designed to provide reasonable assurance that
objectives in the following areas are being
achieved:
effectiveness and efficiency of operations
reliability of financial and operational reporting
compliance with applicable laws, and regulations
-
8/3/2019 World Bank Project Financial Management Guidelines
24/156
MODULE 1Unit 1 - Tr. no. 24
CATEGORIES OF
INTERNAL CONTROL
Main categories of Internal Control
Control Environment
Risk Assessment
Control Activity
Information and Communication
Monitoring
-
8/3/2019 World Bank Project Financial Management Guidelines
25/156
MODULE 1Unit 1 - Tr. no. 25
INTERNAL CONTROL (IC)
Internal control is a key component of a goodfinancial management system.
A Weak System: Endangers the security of project assets
Facilitates unauthorized transactions
Facilitates fraud and mistakes
Leads to inaccurate and/or unreliableinformation
Endangers the integrity of project or Businessrecords
-
8/3/2019 World Bank Project Financial Management Guidelines
26/156
MODULE 1Unit 1 - Tr. no. 26
INTERNAL CONTROL (IC)(contd)
The Control System Environment is veryimportant and includes:
Ethical values
Competent staff
Good organization methods
A clear definition of responsibilitiesand reporting relationships
A clear separation of functions
-
8/3/2019 World Bank Project Financial Management Guidelines
27/156
MODULE 1Unit 1 - Tr. no. 27
INTERNAL CONTROL (IC)(contd)
Good internal control requires anexcellent IC culture.
IC culture requires:
Understanding
Acceptance
Involvement of all project staff
-
8/3/2019 World Bank Project Financial Management Guidelines
28/156
MODULE 1Unit 1 - Tr. no. 28
INTERNAL CONTROL (IC)(contd)
Other important aspects of internal controlthat are sometimes overlooked :
Procurement procedures
Internal audit department
Documentation: creation, storage,retrieval and security (i.e., Records
Management)
-
8/3/2019 World Bank Project Financial Management Guidelines
29/156
MODULE 1Unit 1 - Tr. no. 29
INTERNAL CONTROL (IC)(contd)
Designing of IC system can beapproached from viewpoint of:
Organization of function
Transactions
Records/documentation Combination of all above (probably
best)
-
8/3/2019 World Bank Project Financial Management Guidelines
30/156
-
8/3/2019 World Bank Project Financial Management Guidelines
31/156
MODULE 1Unit 1 - Tr. no. 31
IC SYSTEM FOR A MULTI-DONOR-FINANCED PROJECT
By way of example only, a project shouldinclude:
A. Project receipts Special bank account for each donor source
Prompt notification of receipt to PIU by the bank
Regular and prompt month
ly bank statements Monthly and prompt bank reconciliation
statements, prepared by cashier, reviewed by thefinance director, signed by both
-
8/3/2019 World Bank Project Financial Management Guidelines
32/156
MODULE 1Unit 1 - Tr. no. 32
-DONOR-FINANCED PROJECT(contd)
B. Procurements by purchase orderto be signed by everyone responsible
for follow
ing: Initiation of order
Authorization
Placing of order
Receipt and confirmationquantity/quality
Payment
-
8/3/2019 World Bank Project Financial Management Guidelines
33/156
MODULE 1Unit 1 - Tr. no. 33
IC SYSTEM FOR A MULTI-DONOR-FINANCED PROJECT
(contd)C. Salaries
To be carefully compiled,
independently checked, and paid toauthentic recipients
Special procedures for authenticatingpayment to any sick or absent staff
A monthly salary charge to theproject form should be used forsalary IC and accounting
-
8/3/2019 World Bank Project Financial Management Guidelines
34/156
-
8/3/2019 World Bank Project Financial Management Guidelines
35/156
-
8/3/2019 World Bank Project Financial Management Guidelines
36/156
MODULE 1Unit 1 - Tr. no. 36
F. Journal
Record every transaction, includingadjustments, before any entry ismade in the ledger
Access should be restricted to staff in
charge
Entries should be regularly checkedby finance director
-DONOR-FINANCED PROJECT(contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
37/156
MODULE 1Unit 1 - Tr. no. 37
G. Ledger accounts
To be maintained by qualified staff andsecured from everyone else
Posted daily
H. Trial balance
To be prepared by responsible staff and
checked by the finance director monthly
J. Internal auditor
To perform independent reviews and checks
DONOR-FINANCED PROJECT(contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
38/156
-
8/3/2019 World Bank Project Financial Management Guidelines
39/156
-
8/3/2019 World Bank Project Financial Management Guidelines
40/156
-
8/3/2019 World Bank Project Financial Management Guidelines
41/156
MODULE 1
Unit 1 - Tr. no. 41
PRE-IMPLEMENTATION P&B
PRE-IMPLEMENTATION P&B INCLUDE:
Pre-feasibility and/or feasibility study
that contains details of Project justification
Market analysis
Tech
nical analysis Planning of project activities and timing
Critical path analysis
Project cost estimates
-
8/3/2019 World Bank Project Financial Management Guidelines
42/156
MODULE 1
Unit 1 - Tr. no. 42
PRE-IMPLEMENTATIONP&B (contd)
Financial analysis
Economic analysis (including
shadow pricing, where necessary)
Cash flow planning and analysis
Sensitivity analysis
A financing package
A loan or grant request is based on the
feasibility study
-
8/3/2019 World Bank Project Financial Management Guidelines
43/156
MODULE 1
Unit 1 - Tr. no. 43
P&B DURING PROJECT
IMPLEMENTATIONAt this stage, P&B activities involve
preparation, implementation and
monitoring of: Annual and quarterly physical
activities
Annual and quarterly plans, including:
Procurement Receipts
Expenditures
Cash flow
-
8/3/2019 World Bank Project Financial Management Guidelines
44/156
-
8/3/2019 World Bank Project Financial Management Guidelines
45/156
MODULE 1
Unit 1 - Tr. no. 45
P&B DURING PROJECT IMPLEMENTATION(contd)LINKING REPORTING/ACCOUNTING/BUDGETING FORMAT
PAD Cost Tables
Budget Format & Content
Accounting Systems
Reporting Content & Frequency
Stakeholder Information Needs
-
8/3/2019 World Bank Project Financial Management Guidelines
46/156
MODULE 1
Unit 1 - Tr. no. 46
P&B DURING PROJECTIMPLEMENTATION (contd)
The first quarter in a project life
usually involve minimal activities
One-quarter of annual project
activities and cost may not occur in
the first (or indeed any) quarter of
the year
-
8/3/2019 World Bank Project Financial Management Guidelines
47/156
MODULE 1
Unit 1 - Tr. no. 47
THE IMPACT OF UNCERTAINTY
No guarantee that any project plan or
budget will be implemented as anticipated
Primary reasons:
Imperfect knowledge of future events
Time: over time, even things we know,
ch
ange The longer the project period, the more likely
are project circumstances to change, necessitating
adjustments of plans and budgets
-
8/3/2019 World Bank Project Financial Management Guidelines
48/156
MODULE 1
Unit 1 - Tr. no. 48
Techniques employed to minimize impact of
uncertainty include:
Contingency provisions (physical and price)
Pilot projects
Flexible design of project and loan, matchingcommitments and disbursements to varying
project circumstances during implementation
P&B FOR
UNCERTAINTY AND TIME
-
8/3/2019 World Bank Project Financial Management Guidelines
49/156
MODULE 1
Unit 1 - Tr. no. 49
Post-implementation events/activities that
need to be planned and/or budgeted:
Arrangements for after-life of project
Disposal of project computers, vehicles,
other assets
Future repairs, maintenance, sustainability
(e.g. Roads, railways, industrial forests)
P&B FOR OF UNCERTAINTY ANDTIME (contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
50/156
MODULE 1
Unit 1 - Tr. no. 50
Evaluation of project achievements
The future of project personnel
Continuation of activities not completed during
project period (e.g. 7-year scholarship for 5-year
project life)
Credit closing by lender; Borrower refund of any
balance remaining in special account
Arrangements for final audit
Ensuring availability of funds to pay for final audit
Dispatch of final audit report to lender and government
P&B FOR UNCERTAINTYAND TIME (contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
51/156
-
8/3/2019 World Bank Project Financial Management Guidelines
52/156
MODULE 1
Unit 1 - Tr. no. 52
ACCOUNTING SYSTEM (AS)
(contd)
Project management (PIU)
Government (typical project owner) Beneficiaries
Bilateral donors (e.g. USAID, SIDA,
CIDA, etc.) Lenders (e.g. World Bank)
-
8/3/2019 World Bank Project Financial Management Guidelines
53/156
-
8/3/2019 World Bank Project Financial Management Guidelines
54/156
MODULE 1
Unit 1 - Tr. no. 54
ACCOUNTING SYSTEM (AS)
(contd)
Having ascertained stakeholderrequirements, the third question is:
What do we need to account for?
These are typically project activities andtransactions, including:
Receipts
Commitments
Expenditures Inputs
Outputs
Results
-
8/3/2019 World Bank Project Financial Management Guidelines
55/156
MODULE 1
Unit 1 - Tr. no. 55
ACCOUNTING SYSTEM (AS)
(contd)
Project transactions are either generic or specific.
Generic activities and transactions include:
Receipts of government, lender, or donordisbursement
Payment of salaries
Procurement of vehicles and computers Payment of consultants
Payment for local training workshops
-
8/3/2019 World Bank Project Financial Management Guidelines
56/156
MODULE 1
Unit 1 - Tr. no. 56
ACCOUNTING SYSTEM (AS)
(contd)
Examples of transactions specific to a particular sector include:
In a health project, purchase of medicines
In a rural development project, credit to farmers
In an education project, purchase of textbooks
In a railway rehabilitation project, purchase ofnewwagons
After listing what needs to be accounted for, the fourthquestion is:
What kinds of records are needed to account for them?
-
8/3/2019 World Bank Project Financial Management Guidelines
57/156
MODULE 1
Unit 1 - Tr. no. 57
ACCOUNTING SYSTEM (AS)
(contd)By way of illustration only, a traditional
project accounting system should include:
Purchase orders, receipts, check books andother similar evidence of receipt,commitment or expenditure of funds
Ajournal for primary entry of all items(including adjustments) destined for ledgerposting
A petty cash book (PCB) for very smallpayments, with credit side analysed byproject component
-
8/3/2019 World Bank Project Financial Management Guidelines
58/156
MODULE 1
Unit 1 - Tr. no. 58
ACCOUNTING SYSTEM (AS)
(contd)
A bank cash book for each source of financing,with the credit side analysis columns by
component (like th
e PC
B) A ledger with a separate account for each
component, and the debit side analysed with acolumn for each procurement and disbursementcategory (e.g.Civil works, vehicles, etc.)
A fixed assets register, recording location priceand date of acquisition of each project fixedasset, and divided into sections for buildings,vehicles, computers, etc.
-
8/3/2019 World Bank Project Financial Management Guidelines
59/156
MODULE 1
Unit 1 - Tr. no. 59
The accounting system should help to generate atthe end of eachmonth, at least, the following:
Total project expenditures Total contribution from each financier
Total expenditure on each projectcomponent
Analysis of all project expenditures into civilworks and all other procurement anddisbursement categories
ACCOUNTING SYSTEM
(AS) (contd)
-
8/3/2019 World Bank Project Financial Management Guidelines
60/156
MODULE 1
Unit 1 - Tr. no. 60
ACCOUNTING SYSTEM (AS)
(contd)
Having decided on books and records to keep,the fifth question is:
What entries should be made in these bookson the occurrence of each transaction?
It is useful to record these in the form of
accounting instructionswh
ich
sh
ould be partof the project financial management manual(PFMM) for all project staff.
-
8/3/2019 World Bank Project Financial Management Guidelines
61/156
-
8/3/2019 World Bank Project Financial Management Guidelines
62/156
-
8/3/2019 World Bank Project Financial Management Guidelines
63/156
MODULE 1
Unit 1 - Tr. no. 63
COMPUTERIZATION
Computerization of accounting
systems does not tell uswh
atinformation we need, or what to do
It merely helps us to obtain faster or
more easily the information we havealready decided should be prepared
-
8/3/2019 World Bank Project Financial Management Guidelines
64/156
MODULE 1
Unit 1 - Tr. no. 64
SPECIAL ACCOUNTING ISSUES
Certain types of project raise special
issues requiring attention during the
design of an accounting system:
Multiple institutional participants or
implementing agencies
One agency implementing a project in
several locations
-
8/3/2019 World Bank Project Financial Management Guidelines
65/156
-
8/3/2019 World Bank Project Financial Management Guidelines
66/156
-
8/3/2019 World Bank Project Financial Management Guidelines
67/156
-
8/3/2019 World Bank Project Financial Management Guidelines
68/156
-
8/3/2019 World Bank Project Financial Management Guidelines
69/156
-
8/3/2019 World Bank Project Financial Management Guidelines
70/156
MODULE 1
Unit 1 - Tr. no. 70
COMPUTERIZATION
STRATEGY (contd)
CASE 1
PIU already has knowledge and experienceof computerized system
Staff may be able to modify the existing
softwarewith or without outside help
New software is desirable
This would involve many of theconsiderations applicable to a case 2 or 3scenario
-
8/3/2019 World Bank Project Financial Management Guidelines
71/156
-
8/3/2019 World Bank Project Financial Management Guidelines
72/156
MODULE 1
Unit 1 - Tr. no. 72
COMPUTERIZATION
COMMITTEE
Set up a computerization committee to
meet regularly to review the advisers
progress reports and provide advice and
input
The committee should:
Define the precise computerization
needs of the project
Invite proposals from a few pre-
selected suppliers
-
8/3/2019 World Bank Project Financial Management Guidelines
73/156
MODULE 1
Unit 1 - Tr. no. 73
COMPUTERIZATION
COMMITTEE (contd)
Manage the rest of process:
Decide appropriate time scales and phasing
Decide the impact on the project staff
Brief project staff regularly during the process
Decide the staff needs and training requirements
Decide technological needs and how they will be met Decide the required documentation and support
organization and how they will be provided
-
8/3/2019 World Bank Project Financial Management Guidelines
74/156
MODULE 1
Unit 1 - Tr. no. 74
OTHER DESIRABLE MEASURES
Put project needs in writing and requirevendors to state in writing how they
would respond to all needs Review all responses in detail and
match them up
Seek independent views, particularlyfrom persons who have used the samepackage in implementing multi-donorfinanced projects
-
8/3/2019 World Bank Project Financial Management Guidelines
75/156
MODULE 1
Unit 1 - Tr. no. 75
OTHER DESIRABLE
MEASURES (contd)
Require each vendor to give a
demonstration, showing howhis/her
package responds to all project needs
Before inviting vendor proposals it is
important to distinguish between
mandatory and optionalrequirements.
The mandatory requirements should be
clearly communicated to vendors
-
8/3/2019 World Bank Project Financial Management Guidelines
76/156
MODULE 1
Unit 1 - Tr. no. 76
MANDATORY
REQUIREMENTS
The system must be:
Capable ofhandling provincial district aswell as headquarters transactions
Multi-currency
User friendly (e.g. Windows driven)
Not prohibitively expensive
Able to account under different bases (e.g. Cash,accrual, modified cash, modified accrual)
Able to produce the PMR for the financialmanagement initiative (formerly LACI)
-
8/3/2019 World Bank Project Financial Management Guidelines
77/156
MODULE 1
Unit 1 - Tr. no. 77
MANDATORY
REQUIREMENTS(contd)
Capable of providing clear audit trails
Able to track actual, budget, forecast andproject life per the pad
Able to link financial figures to physicalperformance indicators as required by
project
Equipped with user manual or documentation
Able to track and search by specific references(e.g. The journal number allocated to eachtransaction or by cheque number)
-
8/3/2019 World Bank Project Financial Management Guidelines
78/156
A A O Q S
-
8/3/2019 World Bank Project Financial Management Guidelines
79/156
MODULE 1
Unit 1 - Tr. no. 79
MANDATORY REQUIREMENTS
(contd)
Able to track and report by:
Flexible reporting cycles, e.g. Month, quarter,calendar year, fiscal year, etc.
Source of program funds
Loan agreement category
Project components
Able to generate reports for previous periods(e.g. Lost reports)
Able to customize reports within reasonablelimits
MANDATORY REQUIREMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
80/156
MODULE 1
Unit 1 - Tr. no. 80
MANDATORY REQUIREMENTS
(contd)
Equipped with:
Adequate security features (e.g. Cannot delete
posted transactions, controlled access,password protection)
Back-up and system maintenance procedures
Self diagnostic tests to ensure integrity
Adequate training facilities
Adequate after sale support for resolvingtechnical issues
-
8/3/2019 World Bank Project Financial Management Guidelines
81/156
-
8/3/2019 World Bank Project Financial Management Guidelines
82/156
MODULE 1
Unit 1 - Tr. no. 82
SOFTWARE SELECTION PROCESS
SOME TIPS
The committee should assess:
Technical and functional quality of solution
Overall quality of proposed relations
h
ip Reliability of company
Quality of support staff
Training facilities
Help desk service Documentation available
Future development plans
Policy for upgrades of previous version
-
8/3/2019 World Bank Project Financial Management Guidelines
83/156
MODULE 1
Unit 1 - Tr. no. 83
COMPUTERIZATION
It may be prudent to run a manual and
computerized system in parallel for some
time, before finally abandoning manual
system
Even after that, there should be back up of
all information and systems in electronic
form
PERIODIC PROGRESS
-
8/3/2019 World Bank Project Financial Management Guidelines
84/156
MODULE 1
Unit 1 - Tr. no. 84
PERIODIC PROGRESSREPORTS
Projects typically produce 3 types of reports:
(i) ad hoc
(ii) regular periodical progress reports(iii) annual reports
Bank-financed projects are required to submit
to the bank at regular intervals, not more than
6 months, periodic progress reports, FMR
FMR stands for Financial Monitoring Reports
-
8/3/2019 World Bank Project Financial Management Guidelines
85/156
MODULE 1
Unit 1 - Tr. no. 85
CHARACTERISTICS OF FMR
FMR replaces theProject Management Reports (PMR),introduced by the World Bank on July 1, 1998, under
th
e loan administration ch
ange initiative (LAC
I)The distinguishing characteristics of FMR are:
Distinction between project management (byBorrower) and project monitoring (by lender)
New emphasis on maximum reliance on borrowersAccounting/reporting systems/format Format, content, and frequency more flexible
Reflecting project size, sector, and complexity
GUIDING PRINCIPLESGUIDING PRINCIPLES
-
8/3/2019 World Bank Project Financial Management Guidelines
86/156
MODULE 1
Unit 1 - Tr. no. 86
GUIDING PRINCIPLESGUIDING PRINCIPLESOF FMROF FMR
The overall objective is to provide regularinformation that gives necessary fiduciaryassurance to the Bank
FMRwill be less detailed than the reportprepared for project management
Borro
wers o
wn system s
hould be used asfar as possible in producing FMRs
GUIDING PRINCIPLES OF FMR
-
8/3/2019 World Bank Project Financial Management Guidelines
87/156
MODULE 1
Unit 1 - Tr. no. 87
GUIDING PRINCIPLES OF FMR(Contd)
The same structure of financial information
should normally be used for project planning,
monitoring reports and annual audited financial
statements, and implementation completionreports (ICRs)
As far as possible, borrowers should not berequired to provide the Bankwith information
already available to the Bank The requirements for financial and procurement
monitoring should, as far as possible, be alignedwith other bank requirements for projectprogress reporting and monitoring
GUIDING PRINCIPLES OF
-
8/3/2019 World Bank Project Financial Management Guidelines
88/156
MODULE 1
Unit 1 - Tr. no. 88
GUIDING PRINCIPLES OFFMR (contd)
While the reports to be submitted to the Banksshould meet certain minimum requirements,they should be flexible and customized to each
project or where possible, to each countryand/or sector
Monitoring expenditures in relation to physicalprogress is a key aspect of ensuring that the
project is under proper financial control
Wherever possible, common reporting andmonitoring arrangements should be agreedwith other donors involved in the project
-
8/3/2019 World Bank Project Financial Management Guidelines
89/156
MODULE 1
Unit 1 - Tr. no. 89
STRUCTURE OF THE FMR
The FMR should normally include:
Financial reports Physical progress reports, and
Procurement reports
-
8/3/2019 World Bank Project Financial Management Guidelines
90/156
MODULE 1
Unit 1 - Tr. no. 90
FMR FINANCIAL REPORTS
Financial reports should show:
Cash inflows and outflows for the period
(e.g., quarter), and cumulatively for the
project life
Expenditures should be reported according
to project activities, not according toprocurement/disbursement categories
(although this may be reported as an
addition)
PHYSICAL PROGRESS
-
8/3/2019 World Bank Project Financial Management Guidelines
91/156
MODULE 1
Unit 1 - Tr. no. 91
PHYSICAL PROGRESSREPORT
Physical progress reports should link
physical outputs or implementation
progress to costs of achieving them
Indicators of physical progress andoutputs should be selected during project
preparation, stated in the ProjectImplementation Plan (PIP)
-
8/3/2019 World Bank Project Financial Management Guidelines
92/156
MODULE 1
Unit 1 - Tr. no. 92
PROCUREMENT REPORT
The procurement report:
shows the status of procurement of goods,
works, services, and consultants compares the actual procurement
performance with the plan agreed with
Bank at negotiations or in a subsequent
review
highlights specific problems (e.g., staffing
or training needs)
MATTERS TO BE AGREED AT
-
8/3/2019 World Bank Project Financial Management Guidelines
93/156
MODULE 1
Unit 1 - Tr. no. 93
MATTERS TO BE AGREED ATNEGOTIATIONS
Explains deviations from plan, and proposes
solutions to problems identified
Format, content, frequency, and currency ofreports
Project outputs and other indicators formonitoring physical or other progress towardachieving project results
How to deal with multiple implementationagencies, scattered project locations, andcommunity-based project activities
-
8/3/2019 World Bank Project Financial Management Guidelines
94/156
-
8/3/2019 World Bank Project Financial Management Guidelines
95/156
ANNUAL FINANCIAL
-
8/3/2019 World Bank Project Financial Management Guidelines
96/156
MODULE 1
Unit 1 - Tr. no. 96
ANNUAL FINANCIAL
REPORTING (contd)
FARAH discusses extensively in
chapter iv how to meet the need for
annual financial reporting.
FARAH also presents two basic models
of financial reporting:
One for revenue-earning
One for non-revenue-earning
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
97/156
MODULE 1
Unit 1 - Tr. no. 97
PROJECTS IMPLEMENTED BY
REVENUE-EARNING ENTITIES
Projects implemented by revenue-
earning entities typically involve on-lending Bank/IDA funds from
government to the implementing agency
through a subsidiary loan agreement
between government and agency.
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
98/156
MODULE 1
Unit 1 - Tr. no. 98
REVENUE-EARNING ENTITIES
(contd)
They also usually involve the Bank requiring,
not only annual financial statements of the
project, but also those of the implementingagency, because:
The success and viability of the project
depend on the financial health of the
agency
Capacity building within the agency is
one of the project objectives
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
99/156
MODULE 1
Unit 1 - Tr. no. 99
Entity financial statements required from such
projects generally include:
A balance sheet - financial snapshot taken
at the year end - showing assets, liabilities
and equity
An income statement showing income,
expenses, and results of operations for the
covered period
REVENUE-EARNING ENTITIES
(contd)
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
100/156
MODULE 1
Unit 1 - Tr. no. 100
A cash flow statement showing the cash
provided by and used in operations and
activities during the covered period
Notes on the financial statements explaining
the main accounting disclosures, including
risks and uncertainties affecting theorganization, and any resources or
obligations not recognized in the financial
statement
REVENUE-EARNING ENTITIES
(contd)
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
101/156
MODULE 1
Unit 1 - Tr. no. 101
Sometimes the project financial statements
are integrated in the entity financial
statements.
In other cases they are shown as a separateattachment to the entity financial statements.
Whichever solution is adopted, the Bankalways requires, through the DCA, thatproject expenditures be accounted separatelyfrom other entity expenditures.
REVENUE-EARNING ENTITIES
(contd)
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
102/156
MODULE 1
Unit 1 - Tr. no. 102
NON-REVENUE-EARNING
ENTITIES
It is likely that the majority Bank financed
projects are implemented by government
ministries (or PIUs), or other entities.
Regardless of the type of implementing
agency, the Bank requires financial
statements to monitor project performance
and utilization of the loan.
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
103/156
MODULE 1
Unit 1 - Tr. no. 103
NON-REVENUE-EARNING
ENTITIES (contd)
For non-revenue-earning agencies, the
main feature of the annual financial
statements is the statement of sources andapplication of funds for the current year
and cumulatively since the start of the
project.
Actual project expenditures should be
compared with the original (PAD) or
amended projections.
PROJECTS IMPLEMENTED BY
-
8/3/2019 World Bank Project Financial Management Guidelines
104/156
MODULE 1
Unit 1 - Tr. no. 104
The reporting should include the total project,
regardless of funding sources for particular
activities.
The Bank still receives financial project
statements showing only world Bank-financed
activities and excluding others.
This is unacceptable and contrary to OP/BP
10.02.
NON-REVENUE-EARNING
ENTITIES (contd)
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
105/156
MODULE 1
Unit 1 - Tr. no. 105
SOME ISSUES IN PROJECT
ANNUAL FINANCING REPORTING
Application of IAS to projects in agencies that do not apply
IAS
This requests project reporting standards that differ fromthose applying to:
The ministrys other business
Projects reports to, say, ministry of finance Since all
governments report differently, applying IAS to all
projects ensures their financial statements information
would be more directly comparable than if government
reporting standards were applied
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
106/156
MODULE 1
Unit 1 - Tr. no. 106
SOME ISSUES IN PROJECTANNUAL FINANCING
REPORTING (contd)Even within the private sector, reporting practices vary
across countries.
One of the most striking international differences is
between:
Anglo-Saxon practice, allowing freedom inreporting format, and
Napoleonic law (practised in most western Europe,
French, Portuguese and Spanish speaking countries)
where financial statement format must conform to a
standard.
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
107/156
MODULE 1
Unit 1 - Tr. no. 107
Even within the Anglo-Saxon countries, the typical UK
format is different from the typical U.S.A. Format.
So, in the private as well as the public sector,
application of IAS facilitates matters by introducing a
degree of uniformity and comparability of project
financial reporting whichwould not exist otherwise.
How to report on a project with multiple implementing
agencies
SOME ISSUES IN PROJECTANNUAL FINANCING
REPORTING (contd)
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
108/156
MODULE 1
Unit 1 - Tr. no. 108
Example: a capacity building project benefiting 10
different institutions, each implementing its own
project component/s independently of all other.
Usually, the best solution to this case is to create
one small umbrella PIU, consolidate the project
financial statements of all th
e 10 agencies in th
atumbrella and send only one consolidated annual
financial statement to the Bank.
SOME ISSUES IN PROJECTANNUAL FINANCING
REPORTING (contd)
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
109/156
MODULE 1
Unit 1 - Tr. no. 109
In practice, apart from entity financial
statements, a typical world Bank-financed
project produces the following annual financialstatements:
A statement of sources and application of
funds, or A receipts and payments account, showing
cash received and paid by the project
SOME ISSUES IN PROJECTANNUAL FINANCING
REPORTING (contd)
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
110/156
MODULE 1
Unit 1 - Tr. no. 110
A balance sheet, always required when
accounts are prepared on an accrual basis
A summary of special account transactions
and balance for the year, sometimes
combined with, or in the form of:
A special account reconciliation
statement
SOME ISSUES IN PROJECTANNUAL FINANCING
REPORTING (contd)
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
111/156
MODULE 1
Unit 1 - Tr. no. 111
ANNUAL FINANCING
REPORTING (contd)
A summary of statements of expenditure(SOEs) issued during the year, where the
project is using SOEs A summary of the financial monitoring
reports (FMR) issued during the year,where the project is disbursing through
FMR
A list of project fixed assets and, whereapplicable
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
112/156
MODULE 1
Unit 1 - Tr. no. 112
ANNUAL FINANCING
REPORTING (contd)
A list of important financial commitmentswhich,although they are not yet payable, will definitely
become payable in the future, showing whenpayments will become due (e.g. Scholarshippayments during the next 7 years).
Specific financial reporting requirements vary
from project to project, even th
ough
generalrequirements in article iv of the DCA arestandard. The specific requirements are alsoincluded in financial covenants in the DCA.
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
113/156
MODULE 1
Unit 1 - Tr. no. 113
ANNUAL FINANCING
REPORTING (contd)For most projects, relevant grouping for
annual financial reporting are determined by:
Project components as presented in t
he
PAD
Procurement/disbursement categories in
the DCA
Under a good PFM system, projectscomponents in the pad and disbursement
categories determine:
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
114/156
MODULE 1
Unit 1 - Tr. no. 114
ANNUAL FINANCING
REPORTING (contd)
The ledger and other accounts tomaintained by the project
The FMR reporting format
The annual project financial statementformat
It is important to this bear in mind whenpreparing the PAD and the DCA
SOME ISSUES IN PROJECT
-
8/3/2019 World Bank Project Financial Management Guidelines
115/156
MODULE 1
Unit 1 - Tr. no. 115
ANNUAL FINANCING
REPORTING (contd)
Note also that having the same format
for both the FMR and the annual
financial statements, particularly thestatement of sources and application of
funds, means that last annual FMR is
effectively th
e annual financialstatement.
AUDITING ARRANGEMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
116/156
MODULE 1
Unit 1 - Tr. no. 116
AUDITING ARRANGEMENTS
The Bank requires borrower and implementing
entity to have annual financial statements audited
in accordance with standards on auditing
acceptable to the Bank (OP 10.02).
The audit includes:
Assessment of adequacy of accounting andinternal control systems
Determination of maintenance of adequatedocumentation of all transactions
Verification of eligibility of transactions
AUDITING ARRANGEMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
117/156
MODULE 1
Unit 1 - Tr. no. 117
AUDITING ARRANGEMENTS
The three most common types of audit are:
Financial statement audit,
verification/confirmation
Compliance audit, usually by internal audit, to
confirm compliance with rules and regulations
Operational audit, to assess performance,efficiency and effectiveness, requiring more than
accounting skills
AUDITING ARRANGEMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
118/156
MODULE 1
Unit 1 - Tr. no. 118
(contd)
Normally Bank-financed projects require onlyfinancial statement audits. Any other type of
audit sh
all be specifically indicated in th
eTO
RS.Distinguish between:
Revenue-earning projects requiring audits ofboth entities and project financial statements
Non-revenue-earning projects requiringaudits only of project financial statements
AUDITING ARRANGEMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
119/156
MODULE 1
Unit 1 - Tr. no. 119
(contd)
The overall audit objective is to express an
opinion on:
Fair presentation of financial statement in
conformity to IAS and GAAP
Basis consistent with preceding year
Such audits must be in accordance withinternational standard on auditing (ISA)
promulgated by IFAC.
AUDITING ARRANGEMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
120/156
MODULE 1
Unit 1 - Tr. no. 120
(contd)
Professional and ethical principles, requiredby ISA from all auditing firms andindividuals, include:
Independence
Integrity
Objectivity
Professional competence Confidentiality
Professional behaviour
Technical standards
AUDITING ARRANGEMENTS
-
8/3/2019 World Bank Project Financial Management Guidelines
121/156
MODULE 1
Unit 1 - Tr. no. 121
(contd)
Auditors, members of IFAC institutions or
associations, generally adhere to these principles.
NON-REVENUE-EARNING
-
8/3/2019 World Bank Project Financial Management Guidelines
122/156
MODULE 1
Unit 1 - Tr. no. 122
ORGANIZATIONS
The Bank may accept audit of financial
statements of non-revenue-earningorganizations and projects by SAI,
provided they apply auditing standards
of international organisation of supreme
audit institutions (INTOSAI) to auditaccounts of revenue-earning entities.
NON-REVENUE-EARNING
-
8/3/2019 World Bank Project Financial Management Guidelines
123/156
MODULE 1
Unit 1 - Tr. no. 123
ORGANIZATIONS (contd)
INTOSAI standards promote:
Independence
Competence
Due care Field standards are based on:
Planning, supervision and review
Study and evaluation of internal control
Compliance with applicable law andregulations
Audit evidence
Analysis of financial statement
NON-REVENUE-EARNING
-
8/3/2019 World Bank Project Financial Management Guidelines
124/156
MODULE 1
Unit 1 - Tr. no. 124
ORGANIZATIONS (contd)
Constitution of most countries creates SAI and
mandates it to audit all government revenues and
expenditures, including projects.
NON-REVENUE-EARNING
-
8/3/2019 World Bank Project Financial Management Guidelines
125/156
MODULE 1
Unit 1 - Tr. no. 125
ORGANIZATIONS (contd)
Overall objective of audit project financial
statements is to confirm that:
Financial statements, particularly sourcesand application of funds, are fairly presented
Disbursement is in accordancewith loanagreement and PAD
Balance sheet (if any) fairly presents assetsand liabilities
NON-REVENUE-EARNING
-
8/3/2019 World Bank Project Financial Management Guidelines
126/156
MODULE 1
Unit 1 - Tr. no. 126
ORGANIZATIONS (contd)
Audit procedures are similar to those of auditfinancial statements of revenue-earning projects.
They involve: Evaluation of internal controls
Tests of transactions with supportingdocuments
Other procedures, including physicalobservation of significant assets, third partyconfirmation of balances, etc.
AUDIT SOE AND PMR
-
8/3/2019 World Bank Project Financial Management Guidelines
127/156
MODULE 1
Unit 1 - Tr. no. 127
AUDIT SOEs AND PMRs
Audit of statements of expenditure
(SOE) and project management reports(PMR) involve more compliance
checking, since their supporting
documents are not sent to the Bank, but
retained in PIUS.
AUDIT OF SA
-
8/3/2019 World Bank Project Financial Management Guidelines
128/156
MODULE 1
Unit 1 - Tr. no. 128
AUDIT OF SA
Audit of the special account (SA) statement
verify that:
SA transaction have been fairly presented
Are in accordance with the loan
agreement
Funds have been used solely for project
purposes
SELECTION OF AUDITORS
-
8/3/2019 World Bank Project Financial Management Guidelines
129/156
MODULE 1
Unit 1 - Tr. no. 129
SELECTION OF AUDITORS
Auditor are selected according to Bankguidelines for the selection of consultants.
Terms of reference (TORS) are necessary,to cover auditor responsibilities peculiar toBank-funded projects (e.g. SOES and SAS).
TORs must be clear, specific and
comprehensive, without in any way limitingauditor obligation to apply ISAS or GAAS.
Samples ofTORS are in FARAH.
SELECTION OF AUDITORS
-
8/3/2019 World Bank Project Financial Management Guidelines
130/156
MODULE 1
Unit 1 - Tr. no. 130
(contd)
Many auditors provide their letter of engagement,
containing:
Acceptance of appointment,w
ith
reference toTO
Rs Auditor responsibilities
Access to clients premises, staff and records
Form of audit reports
Involvement of internal or other external auditors Report timing
Fees: computation, mode of payment
SELECTION OF AUDITORS
-
8/3/2019 World Bank Project Financial Management Guidelines
131/156
MODULE 1
Unit 1 - Tr. no. 131
(contd)
Three things are generally required by the auditor:
Opinions on:
Annual financial statement of entire project(sources and application of funds, balancesheet, etc.)
SOE/PMR summary
SA statement
A management letter
Coverage of all project expenditures, not justthose financed by the Bank
AUDIT REPORTING
-
8/3/2019 World Bank Project Financial Management Guidelines
132/156
MODULE 1
Unit 1 - Tr. no. 132
COMPLIANCE SYSTEM (ARCS)
The Bankhas an audit reporting compliance system(ARCS) for monitoring borrower compliance with theaudit covenants.
Bankhas also remedies in event that:
Audited financial statements are not receivedwhen due
Opinion indicates deficiency in accounting, internalcontrol or reliability of financial statements
The Bank considers scope or quality of auditunacceptable
AUDIT REPORTING
COMPLIANCE SYSTEM (ARCS)
-
8/3/2019 World Bank Project Financial Management Guidelines
133/156
MODULE 1
Unit 1 - Tr. no. 133
COMPLIANCE SYSTEM (ARCS)
(contd)
In any of these events, normally the Bank:
Will not extend loan closing date
Delays negotiations or board presentation ofany new loan benefiting defaulting entityuntil:
Acceptable audited financial statementsare received
A remedial action plan is agreed
AUDIT REPORTING COMPLIANCE
-
8/3/2019 World Bank Project Financial Management Guidelines
134/156
MODULE 1
Unit 1 - Tr. no. 134
SYSTEM (ARCS) (contd)
In addition, if audited financial statementsare not receivedwithin 4 months, the Bankdiscontinues use of SOE procedure.
In addition, if acceptable audited SAfinancial statements are not receivedwithin4 months, the Bank normally withholds SAreplenishments.
In addition, after 9 months following duedate, the Bank may suspend alldisbursements on the loan.
AUDIT REPORTING
COMPLIANCE SYSTEM (ARCS)
-
8/3/2019 World Bank Project Financial Management Guidelines
135/156
MODULE 1
Unit 1 - Tr. no. 135
COMPLIANCE SYSTEM (ARCS)
(contd)
In addition, if audited financial
statements reveal major deficiencies in
internal control, or inadequate evidence
that funds have been used for only
eligible expenditures, Bank may suspend
all disbursements on th
at loan untilsatisfied that adequate remedial actions
have been taken.
,ACCOUNTING AND
-
8/3/2019 World Bank Project Financial Management Guidelines
136/156
MODULE 1
Unit 1 - Tr. no. 136
AUDITING
Scope and definition
Project fixed assets comprise mainly civil works,vehicles and equipment.
International accounting standards (IAS16)defines as property, plant and equipment,those assets which are:
Used in production or supply of goods or
services, rental to others, or foradministrative purposes
Expected to be used during more than oneaccounting period (typically one year)
FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING
-
8/3/2019 World Bank Project Financial Management Guidelines
137/156
MODULE 1
Unit 1 - Tr. no. 137
ACCOUNTING AND AUDITING
(contd)Section 5 (b) of Article III of the IBRD articles
of agreement states that the Bank shall make
arrangements to ensure that the proceeds of
any loan are used only for the purposes for
which the loan was granted, with due attention
to economy and efficiency and regardless to
political or other non-economic influences or
considerations.
Similar provisions are included in IDA articles
of agreement.
FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING
-
8/3/2019 World Bank Project Financial Management Guidelines
138/156
MODULE 1
Unit 1 - Tr. no. 138
ACCOUNTING AND AUDITING
(contd)Fiduciary and accountability obligations require to:
Ensure delivery of project assets to right place and
Monitor use of assets
Not jeopardize achievement of project objectives byallowing assets to be diverted to non-project use
Therefore, concern for project fixed asset management hastwo main objectives:
Protecting project implementation and objectives
Satisfying the Bank fiduciary and accountabilityobligations under article iii
FIXED ASSET MANAGEMENT,ACCOUNTING AND
-
8/3/2019 World Bank Project Financial Management Guidelines
139/156
MODULE 1
Unit 1 - Tr. no. 139
ACCOUNTING AND
AUDITING (contd)
Therefore, concern for project fixed assetmanagement has two main objectives:
Protecting project implementation andobjectives
Satisfying the Bank fiduciary andaccountability obligations under article iii
FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING
-
8/3/2019 World Bank Project Financial Management Guidelines
140/156
MODULE 1
Unit 1 - Tr. no. 140
ACCOUNTING AND AUDITING
(contd)Some issues in fixed asset management
Tying expenditures to actual fixed assets
Identification of project fixed assets andtheir separation from other fixed assets of
the implementing agency
Accurate valuation of fixed assets,especially in civil works
FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING
-
8/3/2019 World Bank Project Financial Management Guidelines
141/156
MODULE 1
Unit 1 - Tr. no. 141
ACCOUNTING AND AUDITING
(contd) Condition and fitness for intended purpose at
time of purchase
Repair and maintenance program to protect
value and fitness Ownership versus control: interference between
one and the other or with use of asset forintended purposes
Incidence of non-project use Insurance: protecting value until end of
economic life, or end of project, whichevercomes first
FIXED ASSET MANAGEMENT,ACCOUNTING AND
-
8/3/2019 World Bank Project Financial Management Guidelines
142/156
MODULE 1
Unit 1 - Tr. no. 142
ACCOUNTING AND
AUDITING (contd) Arrangements for disposal of fixed asset at:
End of useful life
End of project period Accounting records maintained for fixed
assets (register, ledger, etc.)
Disclosure of fixed assets in annual financial
statements, particularly if accounting on cash
basis
Auditor verification of asset existence, value
and use
OTHER PFM PROBLEMS:
-
8/3/2019 World Bank Project Financial Management Guidelines
143/156
MODULE 1
Unit 1 - Tr. no. 143
STAFFING
Staff for PFM presents problems of:
How to find and pay qualified staff
to operate double entry project
accounting system in a PIU
How to hire staff
What will happen to project staff at
the end of project
-
8/3/2019 World Bank Project Financial Management Guidelines
144/156
OTHER PFM PROBLEMS:( d)
-
8/3/2019 World Bank Project Financial Management Guidelines
145/156
MODULE 1
Unit 1 - Tr. no. 145
STAFFING (contd)
A typical efficient solution is to hire
temporary staff or consultants on fixed
term, with renewal option, paid by
project, provided that expenditures
were included in project cost estimates.
OTHER PFM PROBLEMS:PROJECT PREPARATION
-
8/3/2019 World Bank Project Financial Management Guidelines
146/156
MODULE 1
Unit 1 - Tr. no. 146
PROJECT PREPARATION
FACILITIES (PPF)PPF presents a challenge and an opportunity:
Challenge: how to ensure proper FM or
funds and activities for a project which isnot effective and may never materialize
Opportunity: PPF provides funds to hire
appropriate staff for its management,provided this was included in the PPF request
OTHER PFM PROBLEMS:PROJECT PREPARATION
-
8/3/2019 World Bank Project Financial Management Guidelines
147/156
MODULE 1
Unit 1 - Tr. no. 147
PROJECT PREPARATION
FACILITIES (PPF) (contd)One of the best ways to look at PPF is to
consider it as a pilot project or a
preliminary part of the project. Thisapproach ensures that:
All PPF funds are properly accounted for
There is a viable and tested fm system inplace at loan/credit effectiveness
OTHER PFM PROBLEMS:PROJECT PREPARATION
-
8/3/2019 World Bank Project Financial Management Guidelines
148/156
MODULE 1
Unit 1 - Tr. no. 148
PROJECT PREPARATION
FACILITIES (PPF) (contd)Substantial (e.g. US$1 million and more)
PPF should send the Bank a simple audited
financial statement, if it remains active formore than one year.
No PPF request should be considered
complete unless it includes arrangementsand financing for proper accounting, and
for audit if active for more than one year.
OTHER PFM PROBLEMS:
-
8/3/2019 World Bank Project Financial Management Guidelines
149/156
MODULE 1
Unit 1 - Tr. no. 149
SMALL OPERATIONS
Article iii of the Banks articles of agreement
andOP/BP apply to all projects financed by the
Bank, no matter how small.
This means that even small grants require:
Satisfactory fm system before Board
Agreed reporting formats and audit terms of
reference at Negotiations Periodic Financial Monitoring Reports
Audited financial statements within 6 months
following end of fiscal year
OTHER PFM PROBLEMS:( d)
-
8/3/2019 World Bank Project Financial Management Guidelines
150/156
MODULE 1
Unit 1 - Tr. no. 150
SMALL OPERATIONS (contd)
How does one manage all this in a small grant
of, say, US$500,000, without using a sledge
hammer to crack a peanut?:
Planning, budgeting, internal controls,accounting and reporting should be kept
simple, reflecting small amount involved, but
without compromising basic principles
Audit could be part of a larger auditcontract for a bigger operation, ensuring
appropriate audit expertise at reasonable cost
OTHER PFM PROBLEMS:GOVERNMENT COUNTERPART
-
8/3/2019 World Bank Project Financial Management Guidelines
151/156
MODULE 1
Unit 1 - Tr. no. 151
GOVERNMENT COUNTERPART
FUNDSMany Bank-financed projects have problemsobtaining governments financial contribution tothe project.
Bank insists on, at least, minimal governmentfinancial participation, to ensure governmentinterest and commitment.
Difficulty of counterpart funding arises, despite
ministry of finance participation in negotiationsand being named government representative inpractically all loan agreements.
OTHER PFM PROBLEMS:GOVERNMENT COUNTERPART
-
8/3/2019 World Bank Project Financial Management Guidelines
152/156
MODULE 1
Unit 1 - Tr. no. 152
GOVERNMENT COUNTERPART
FUNDS (contd)Problems have more to do with government
planning and budgeting system, than with
absolute lack of funds.
Lack of co-ordination of numerous entities in
some projects may also be a problem.
It may happen that there are communication
problems among some ministries responsiblefor projects and ministry of finance.
GOVERNMENTCOUNTERPART FUNDS
-
8/3/2019 World Bank Project Financial Management Guidelines
153/156
MODULE 1
Unit 1 - Tr. no. 153
(contd)
Furthermore, government typically
budgets once a year, but enters
project commitments all year.
Another common practice is to
commit funds only when they
become available, regardless ofbudgetary provision.
OTHER PFM PROBLEMS:GOVERNMENT COUNTERPART
-
8/3/2019 World Bank Project Financial Management Guidelines
154/156
MODULE 1
Unit 1 - Tr. no. 154
GO COU
FUNDS (contd)The possible solutions are: Those responsible for project preparation and
implementation should constantly remind ministryof finance to provide for government commitmentsin budget
For many projects, funds would need to bebudgeted by government up to 12 months beforethey are actually needed
Dealing with cash-based allocations requiresspecific knowledge ofhow things work and how toget the necessary cash allocations in a particularcountry and in particular circumstances
OTHER PFM PROBLEMS:ORGANIZING AND FINANCING
-
8/3/2019 World Bank Project Financial Management Guidelines
155/156
MODULE 1
Unit 1 - Tr. no. 155
THE FINAL AUDITOrganizing and paying for a final auditcan pose a problem, particularly when theproject is expected to pay for the audit.
The Bank expects to receive auditedfinancial statements of the fiscal year inwhich the last disbursement is made.
Project managers need to ensure that thefinal audit is completed and paid for,before the loan or credit closes.
OTHER PFM PROBLEMS:ORGANIZING AND FINANCING
-
8/3/2019 World Bank Project Financial Management Guidelines
156/156
THE FINAL AUDIT (contd)This needs to be planned, discussed with the
task leader and disbursement officer and all
detailed steps agreed, at least one yearbefore the closing date.
Failure to plan for this well in advance of
th
e closing date could result in borrow
erhaving to finance the audit from its own