World Bank Project Financial Management Guidelines

download World Bank Project Financial Management Guidelines

of 156

Transcript of World Bank Project Financial Management Guidelines

  • 8/3/2019 World Bank Project Financial Management Guidelines

    1/156

    MODULE 1

    Unit 1 - Tr. no. 1

    WORLD BANK PROJECT FINANCIAL

    MANAGEMENT GUIDELINES

    ART. III, SEC. 5 (B), OF THE WORLD BANKS

    ARTICLES OF AGREEMENT:

    The Bank should make arrangements toensure that borrowers use loan proceeds:

    Only for the purposes intended With due attention to economy and

    efficiency

  • 8/3/2019 World Bank Project Financial Management Guidelines

    2/156

    MODULE 1

    Unit 1 - Tr. no. 2

    WORLD BANK

    PFM GUIDELINES (contd)

    SOME POLICIES AND GUIDELINES TOFACILITATE COMPLIANCE WITH ART. III,

    SEC. 5 (B): OP/BP 10.02

    Guidelines that have issued to borrowers

    FARAH LACI Implementation Handbook

    The Project Financial Management Manual

    Others

  • 8/3/2019 World Bank Project Financial Management Guidelines

    3/156

    MODULE 1

    Unit 1 - Tr. no. 3

    WORLD BANK

    PFM GUIDELINES (contd)

    OP 10.02

    The definitive bank guideline on project financialmanagement

    Describes the minimum fm requirements for everybank financed project

    Requires projects to:

    maintain adequate financial management

    systems provide annual audited financial statements

    have the financial statements audited

    Describes the remedies available to the Bank in theevent of non-compliance

  • 8/3/2019 World Bank Project Financial Management Guidelines

    4/156

    MODULE 1

    Unit 1 - Tr. no. 4

    WORLD BANK

    PFM GUIDELINES (contd)

    Bank Procedures (BP 10.02) Describes application of OP 10.02

    in the project cycle

    Recognizes the CFAA as a starting

    point

  • 8/3/2019 World Bank Project Financial Management Guidelines

    5/156

    MODULE 1

    Unit 1 - Tr. no. 5

    PHASES OF A TYPICAL

    PROJECT CYCLE

    Identification

    Preparation

    Appraisal Negotiations

    Board Presentation

    Effectiveness

    Implementation

    CompletionN.B. The focus of this session is on the Financial Management

    activities that are performed during all eight stages

  • 8/3/2019 World Bank Project Financial Management Guidelines

    6/156

    MODULE 1

    Unit 1 - Tr. no. 6

    FM activities before and during

    implementation are strongly influenced by: whether the organization (e.g. PIU) that

    will Implement the project already exists,or still has to be created

    whether or not FM staffhave a trackrecord of managing and accounting for anexternally-funded project

    PHASES OF A TYPICAL

    PROJECT CYCLE (Contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    7/156

    MODULE 1

    Unit 1 - Tr. no. 7

    There is usually a difference betweenborrower and lender FM requirements

    An example of a borrower FM requirementis ensuring availability of enoughcounterpart funds before requesting foreignproject financing

    Lender staffhave to ensure that the FMarrangements for the project will facilitatecompliancewith their organizationsfiduciary requirements.

    PHASES OF A TYPICAL

    PROJECT CYCLE (contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    8/156

    MODULE 1

    Unit 1 - Tr. no. 8

    Typical case of the very first externally-

    financed project in a sector

    Most pre-implementation activities areconceptual

    FM arrangements may not be created andFM staff may not be hired hired until justbefore effectiveness

    The FM arrangements for the project need tobe conceptualized and described in detail

    CASE 1: NEW PROJECT

    WITH A PROPOSED PIU

  • 8/3/2019 World Bank Project Financial Management Guidelines

    9/156

    MODULE 1

    Unit 1 - Tr. no. 9

    Conceptualization of FM arrangementswould

    include:

    The structure of the project FM organization

    FM activities and functions

    The types, numbers, and terms of reference of

    needed FM skills

    When, how, and where FM staffwill be hired

    Remuneration of FM staff

    CASE 1: NEW PROJECT WITH

    A PROPOSED PIU (contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    10/156

    MODULE 1

    Unit 1 - Tr. no. 10

    A project organization chart incorporating an FM

    organization chart is a good starting point for

    designing th

    e FM structure Some Important Factors to Consider are:

    Size and complexity of project

    Number of participating/beneficiary institutions

    Nature and geographical spread of the project

    Number and frequency of project transactions

    Sophistication and exigencies of financial reporting

    CASE 1: NEW PROJECT WITH

    A PROPOSED PIU (contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    11/156

    MODULE 1

    Unit 1 - Tr. no. 11

    This is the easiest FM design situation

    PIU is a known entity with a track record

    The design and description of FM structureand functioning must still be as completeand detailed as in case 1

    Emphasis should be on the modifications to

    the existing structure and skills mix that areneeded to cope with new project

    Such modifications must be made before thenew project becomes effective

    CASE 2: FOLLOW-UP PROJECT

    IN AN EXISTING PIU

  • 8/3/2019 World Bank Project Financial Management Guidelines

    12/156

    MODULE 1Unit 1 - Tr. no. 12

    A situation where the borrower decides to use an

    existing PIU and FM staff and structure to implement

    a new project in a completely different sector or field

    of activities from that in which the PIU was previously

    engaged

    This is very rare because of the tendency for PIUs to

    be staffed by sector specialists

    This case requires greater care than case 2, because of

    the likelihood that the new project would involve new

    types of transactions, assets and liabilities

    CASE 3: BRAND NEW PROJECTIN AN EXISTING PIU

  • 8/3/2019 World Bank Project Financial Management Guidelines

    13/156

    MODULE 1Unit 1 - Tr. no. 13

    NEGOTIATIONS STAGE

    The Negotiations state is when borrower and lender

    Agree on, among other things:

    Structure, functioning, staffing of the FMsystems and

    Reporting formats

    These agreements are recorded in the minutes of

    negotiations signed by both parties Whenever practicable, project director and

    financial director should be included in the

    borrowers negotiating team (easier in cases 2 and

    3) than in case 1

  • 8/3/2019 World Bank Project Financial Management Guidelines

    14/156

    MODULE 1Unit 1 - Tr. no. 14

    PROJECT LAUNCH

    WORKSHOP

    To be organized immediately after loan or credit

    effectiveness, but before implementation begins, it:

    Brings togeth

    er everyone likely to be involved inproject implementation

    Discusses lender and borrower procurement,accounting, reporting, disbursement, auditingand other FM (and non-FM) arrangements

    FM discussions at the workshop are facilitated bythe existence of a Project Financial ManagementManual (PFMM)

    Anticipates and resolves problems

  • 8/3/2019 World Bank Project Financial Management Guidelines

    15/156

    MODULE 1Unit 1 - Tr. no. 15

    PROJECT PREPARATION

    FACILITY (PPF)

    Introduces pre-implementation FM problems

    as well as the means for providing solutions

    Necessitates project accounting which

    would have been unnecessary without it

    Provides the funds to recruit and pay FM

    staff before credit effectiveness Is very useful in case 1 projects by

    enabling the creation of good FM capacity

    well before implementation begins

  • 8/3/2019 World Bank Project Financial Management Guidelines

    16/156

    MODULE 1Unit 1 - Tr. no. 16

    BORROWER ROLE VERSUS

    LENDER ROLEPre-implementation FM activities

    The borrower has the primary responsibility forimplementing all the FM activities

    The lenders primary responsibility is to ensurethat the borrower carries out its responsibilities tothe lenders satisfaction

    Borrower and lender share the responsibility forensuring that FM arrangements are accurately

    and adequately reflected in the minutes ofnegotiations

    Although the lender often request the projectlaunchworkshop, it is usually organized by theborrower

  • 8/3/2019 World Bank Project Financial Management Guidelines

    17/156

    MODULE 1Unit 1 - Tr. no. 17

    FM ACTIVITIES DURING

    IMPLEMENTATION

    Borrower is responsible for

    all record keeping, systemsmaintenance, and reporting

    activities

    Lender requires adequateborrower reporting for

    fiduciary purposes

  • 8/3/2019 World Bank Project Financial Management Guidelines

    18/156

    MODULE 1Unit 1 - Tr. no. 18

    FM PROJECT

    COMPLETION

    Overall evaluation of implementation experience includes

    a review of FM performance throughout project life: the

    reviewwill cover the following aspects of FM

    Planning & budgeting

    Internal control, including procurement &

    internal audit

    Book-keeping, accounting, IT, records

    management

    Financial reporting

    Independent audit opinions

  • 8/3/2019 World Bank Project Financial Management Guidelines

    19/156

    MODULE 1Unit 1 - Tr. no. 19

    PROJECT FINANCIALMANAGEMENT (PFM) AND ITS

    ENVIRONMENT

    The organizational structure for

    project implementation should

    reflect the complexity of the

    project.

    How a project is organized and

    staffed has a very important

    bearing on its financial

    management arrangements.

  • 8/3/2019 World Bank Project Financial Management Guidelines

    20/156

    MODULE 1Unit 1 - Tr. no. 20

    MAIN COMPONENTS OF A

    PFM ENVIRONMENT

    The organizational structure of the

    project implementing unit

    Functional relationships between the

    various parts of the organization

    Clear definition of the responsibilities ofeach functional part and individual

    The quality ofhuman resources

  • 8/3/2019 World Bank Project Financial Management Guidelines

    21/156

    MODULE 1Unit 1 - Tr. no. 21

    MAIN COMPONENTS OF A

    PFM ENVIRONMENT

    Vertical and horizontal flows ofinformation, recommendations and decisions

    Project actions based on information,recommendations and decisions

    The flow of funds to finance project activities

    The culture of the entity regarding properfinancial accountability and management

  • 8/3/2019 World Bank Project Financial Management Guidelines

    22/156

    MODULE 1Unit 1 - Tr. no. 22

    PROJECT FINANCIALMANAGEMENT (PFM)

    ENVIRONMENT (contd)

    Elements of good PFM Systems:

    Planning and Budgeting

    Internal Controls

    Records Management and IT

    Book-keeping and accounting Financial reporting

    Auditing

  • 8/3/2019 World Bank Project Financial Management Guidelines

    23/156

    MODULE 1Unit 1 - Tr. no. 23

    INTERNAL CONTROL

    Internal control is a process:

    effected by an organization,

    designed to provide reasonable assurance that

    objectives in the following areas are being

    achieved:

    effectiveness and efficiency of operations

    reliability of financial and operational reporting

    compliance with applicable laws, and regulations

  • 8/3/2019 World Bank Project Financial Management Guidelines

    24/156

    MODULE 1Unit 1 - Tr. no. 24

    CATEGORIES OF

    INTERNAL CONTROL

    Main categories of Internal Control

    Control Environment

    Risk Assessment

    Control Activity

    Information and Communication

    Monitoring

  • 8/3/2019 World Bank Project Financial Management Guidelines

    25/156

    MODULE 1Unit 1 - Tr. no. 25

    INTERNAL CONTROL (IC)

    Internal control is a key component of a goodfinancial management system.

    A Weak System: Endangers the security of project assets

    Facilitates unauthorized transactions

    Facilitates fraud and mistakes

    Leads to inaccurate and/or unreliableinformation

    Endangers the integrity of project or Businessrecords

  • 8/3/2019 World Bank Project Financial Management Guidelines

    26/156

    MODULE 1Unit 1 - Tr. no. 26

    INTERNAL CONTROL (IC)(contd)

    The Control System Environment is veryimportant and includes:

    Ethical values

    Competent staff

    Good organization methods

    A clear definition of responsibilitiesand reporting relationships

    A clear separation of functions

  • 8/3/2019 World Bank Project Financial Management Guidelines

    27/156

    MODULE 1Unit 1 - Tr. no. 27

    INTERNAL CONTROL (IC)(contd)

    Good internal control requires anexcellent IC culture.

    IC culture requires:

    Understanding

    Acceptance

    Involvement of all project staff

  • 8/3/2019 World Bank Project Financial Management Guidelines

    28/156

    MODULE 1Unit 1 - Tr. no. 28

    INTERNAL CONTROL (IC)(contd)

    Other important aspects of internal controlthat are sometimes overlooked :

    Procurement procedures

    Internal audit department

    Documentation: creation, storage,retrieval and security (i.e., Records

    Management)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    29/156

    MODULE 1Unit 1 - Tr. no. 29

    INTERNAL CONTROL (IC)(contd)

    Designing of IC system can beapproached from viewpoint of:

    Organization of function

    Transactions

    Records/documentation Combination of all above (probably

    best)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    30/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    31/156

    MODULE 1Unit 1 - Tr. no. 31

    IC SYSTEM FOR A MULTI-DONOR-FINANCED PROJECT

    By way of example only, a project shouldinclude:

    A. Project receipts Special bank account for each donor source

    Prompt notification of receipt to PIU by the bank

    Regular and prompt month

    ly bank statements Monthly and prompt bank reconciliation

    statements, prepared by cashier, reviewed by thefinance director, signed by both

  • 8/3/2019 World Bank Project Financial Management Guidelines

    32/156

    MODULE 1Unit 1 - Tr. no. 32

    -DONOR-FINANCED PROJECT(contd)

    B. Procurements by purchase orderto be signed by everyone responsible

    for follow

    ing: Initiation of order

    Authorization

    Placing of order

    Receipt and confirmationquantity/quality

    Payment

  • 8/3/2019 World Bank Project Financial Management Guidelines

    33/156

    MODULE 1Unit 1 - Tr. no. 33

    IC SYSTEM FOR A MULTI-DONOR-FINANCED PROJECT

    (contd)C. Salaries

    To be carefully compiled,

    independently checked, and paid toauthentic recipients

    Special procedures for authenticatingpayment to any sick or absent staff

    A monthly salary charge to theproject form should be used forsalary IC and accounting

  • 8/3/2019 World Bank Project Financial Management Guidelines

    34/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    35/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    36/156

    MODULE 1Unit 1 - Tr. no. 36

    F. Journal

    Record every transaction, includingadjustments, before any entry ismade in the ledger

    Access should be restricted to staff in

    charge

    Entries should be regularly checkedby finance director

    -DONOR-FINANCED PROJECT(contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    37/156

    MODULE 1Unit 1 - Tr. no. 37

    G. Ledger accounts

    To be maintained by qualified staff andsecured from everyone else

    Posted daily

    H. Trial balance

    To be prepared by responsible staff and

    checked by the finance director monthly

    J. Internal auditor

    To perform independent reviews and checks

    DONOR-FINANCED PROJECT(contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    38/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    39/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    40/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    41/156

    MODULE 1

    Unit 1 - Tr. no. 41

    PRE-IMPLEMENTATION P&B

    PRE-IMPLEMENTATION P&B INCLUDE:

    Pre-feasibility and/or feasibility study

    that contains details of Project justification

    Market analysis

    Tech

    nical analysis Planning of project activities and timing

    Critical path analysis

    Project cost estimates

  • 8/3/2019 World Bank Project Financial Management Guidelines

    42/156

    MODULE 1

    Unit 1 - Tr. no. 42

    PRE-IMPLEMENTATIONP&B (contd)

    Financial analysis

    Economic analysis (including

    shadow pricing, where necessary)

    Cash flow planning and analysis

    Sensitivity analysis

    A financing package

    A loan or grant request is based on the

    feasibility study

  • 8/3/2019 World Bank Project Financial Management Guidelines

    43/156

    MODULE 1

    Unit 1 - Tr. no. 43

    P&B DURING PROJECT

    IMPLEMENTATIONAt this stage, P&B activities involve

    preparation, implementation and

    monitoring of: Annual and quarterly physical

    activities

    Annual and quarterly plans, including:

    Procurement Receipts

    Expenditures

    Cash flow

  • 8/3/2019 World Bank Project Financial Management Guidelines

    44/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    45/156

    MODULE 1

    Unit 1 - Tr. no. 45

    P&B DURING PROJECT IMPLEMENTATION(contd)LINKING REPORTING/ACCOUNTING/BUDGETING FORMAT

    PAD Cost Tables

    Budget Format & Content

    Accounting Systems

    Reporting Content & Frequency

    Stakeholder Information Needs

  • 8/3/2019 World Bank Project Financial Management Guidelines

    46/156

    MODULE 1

    Unit 1 - Tr. no. 46

    P&B DURING PROJECTIMPLEMENTATION (contd)

    The first quarter in a project life

    usually involve minimal activities

    One-quarter of annual project

    activities and cost may not occur in

    the first (or indeed any) quarter of

    the year

  • 8/3/2019 World Bank Project Financial Management Guidelines

    47/156

    MODULE 1

    Unit 1 - Tr. no. 47

    THE IMPACT OF UNCERTAINTY

    No guarantee that any project plan or

    budget will be implemented as anticipated

    Primary reasons:

    Imperfect knowledge of future events

    Time: over time, even things we know,

    ch

    ange The longer the project period, the more likely

    are project circumstances to change, necessitating

    adjustments of plans and budgets

  • 8/3/2019 World Bank Project Financial Management Guidelines

    48/156

    MODULE 1

    Unit 1 - Tr. no. 48

    Techniques employed to minimize impact of

    uncertainty include:

    Contingency provisions (physical and price)

    Pilot projects

    Flexible design of project and loan, matchingcommitments and disbursements to varying

    project circumstances during implementation

    P&B FOR

    UNCERTAINTY AND TIME

  • 8/3/2019 World Bank Project Financial Management Guidelines

    49/156

    MODULE 1

    Unit 1 - Tr. no. 49

    Post-implementation events/activities that

    need to be planned and/or budgeted:

    Arrangements for after-life of project

    Disposal of project computers, vehicles,

    other assets

    Future repairs, maintenance, sustainability

    (e.g. Roads, railways, industrial forests)

    P&B FOR OF UNCERTAINTY ANDTIME (contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    50/156

    MODULE 1

    Unit 1 - Tr. no. 50

    Evaluation of project achievements

    The future of project personnel

    Continuation of activities not completed during

    project period (e.g. 7-year scholarship for 5-year

    project life)

    Credit closing by lender; Borrower refund of any

    balance remaining in special account

    Arrangements for final audit

    Ensuring availability of funds to pay for final audit

    Dispatch of final audit report to lender and government

    P&B FOR UNCERTAINTYAND TIME (contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    51/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    52/156

    MODULE 1

    Unit 1 - Tr. no. 52

    ACCOUNTING SYSTEM (AS)

    (contd)

    Project management (PIU)

    Government (typical project owner) Beneficiaries

    Bilateral donors (e.g. USAID, SIDA,

    CIDA, etc.) Lenders (e.g. World Bank)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    53/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    54/156

    MODULE 1

    Unit 1 - Tr. no. 54

    ACCOUNTING SYSTEM (AS)

    (contd)

    Having ascertained stakeholderrequirements, the third question is:

    What do we need to account for?

    These are typically project activities andtransactions, including:

    Receipts

    Commitments

    Expenditures Inputs

    Outputs

    Results

  • 8/3/2019 World Bank Project Financial Management Guidelines

    55/156

    MODULE 1

    Unit 1 - Tr. no. 55

    ACCOUNTING SYSTEM (AS)

    (contd)

    Project transactions are either generic or specific.

    Generic activities and transactions include:

    Receipts of government, lender, or donordisbursement

    Payment of salaries

    Procurement of vehicles and computers Payment of consultants

    Payment for local training workshops

  • 8/3/2019 World Bank Project Financial Management Guidelines

    56/156

    MODULE 1

    Unit 1 - Tr. no. 56

    ACCOUNTING SYSTEM (AS)

    (contd)

    Examples of transactions specific to a particular sector include:

    In a health project, purchase of medicines

    In a rural development project, credit to farmers

    In an education project, purchase of textbooks

    In a railway rehabilitation project, purchase ofnewwagons

    After listing what needs to be accounted for, the fourthquestion is:

    What kinds of records are needed to account for them?

  • 8/3/2019 World Bank Project Financial Management Guidelines

    57/156

    MODULE 1

    Unit 1 - Tr. no. 57

    ACCOUNTING SYSTEM (AS)

    (contd)By way of illustration only, a traditional

    project accounting system should include:

    Purchase orders, receipts, check books andother similar evidence of receipt,commitment or expenditure of funds

    Ajournal for primary entry of all items(including adjustments) destined for ledgerposting

    A petty cash book (PCB) for very smallpayments, with credit side analysed byproject component

  • 8/3/2019 World Bank Project Financial Management Guidelines

    58/156

    MODULE 1

    Unit 1 - Tr. no. 58

    ACCOUNTING SYSTEM (AS)

    (contd)

    A bank cash book for each source of financing,with the credit side analysis columns by

    component (like th

    e PC

    B) A ledger with a separate account for each

    component, and the debit side analysed with acolumn for each procurement and disbursementcategory (e.g.Civil works, vehicles, etc.)

    A fixed assets register, recording location priceand date of acquisition of each project fixedasset, and divided into sections for buildings,vehicles, computers, etc.

  • 8/3/2019 World Bank Project Financial Management Guidelines

    59/156

    MODULE 1

    Unit 1 - Tr. no. 59

    The accounting system should help to generate atthe end of eachmonth, at least, the following:

    Total project expenditures Total contribution from each financier

    Total expenditure on each projectcomponent

    Analysis of all project expenditures into civilworks and all other procurement anddisbursement categories

    ACCOUNTING SYSTEM

    (AS) (contd)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    60/156

    MODULE 1

    Unit 1 - Tr. no. 60

    ACCOUNTING SYSTEM (AS)

    (contd)

    Having decided on books and records to keep,the fifth question is:

    What entries should be made in these bookson the occurrence of each transaction?

    It is useful to record these in the form of

    accounting instructionswh

    ich

    sh

    ould be partof the project financial management manual(PFMM) for all project staff.

  • 8/3/2019 World Bank Project Financial Management Guidelines

    61/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    62/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    63/156

    MODULE 1

    Unit 1 - Tr. no. 63

    COMPUTERIZATION

    Computerization of accounting

    systems does not tell uswh

    atinformation we need, or what to do

    It merely helps us to obtain faster or

    more easily the information we havealready decided should be prepared

  • 8/3/2019 World Bank Project Financial Management Guidelines

    64/156

    MODULE 1

    Unit 1 - Tr. no. 64

    SPECIAL ACCOUNTING ISSUES

    Certain types of project raise special

    issues requiring attention during the

    design of an accounting system:

    Multiple institutional participants or

    implementing agencies

    One agency implementing a project in

    several locations

  • 8/3/2019 World Bank Project Financial Management Guidelines

    65/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    66/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    67/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    68/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    69/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    70/156

    MODULE 1

    Unit 1 - Tr. no. 70

    COMPUTERIZATION

    STRATEGY (contd)

    CASE 1

    PIU already has knowledge and experienceof computerized system

    Staff may be able to modify the existing

    softwarewith or without outside help

    New software is desirable

    This would involve many of theconsiderations applicable to a case 2 or 3scenario

  • 8/3/2019 World Bank Project Financial Management Guidelines

    71/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    72/156

    MODULE 1

    Unit 1 - Tr. no. 72

    COMPUTERIZATION

    COMMITTEE

    Set up a computerization committee to

    meet regularly to review the advisers

    progress reports and provide advice and

    input

    The committee should:

    Define the precise computerization

    needs of the project

    Invite proposals from a few pre-

    selected suppliers

  • 8/3/2019 World Bank Project Financial Management Guidelines

    73/156

    MODULE 1

    Unit 1 - Tr. no. 73

    COMPUTERIZATION

    COMMITTEE (contd)

    Manage the rest of process:

    Decide appropriate time scales and phasing

    Decide the impact on the project staff

    Brief project staff regularly during the process

    Decide the staff needs and training requirements

    Decide technological needs and how they will be met Decide the required documentation and support

    organization and how they will be provided

  • 8/3/2019 World Bank Project Financial Management Guidelines

    74/156

    MODULE 1

    Unit 1 - Tr. no. 74

    OTHER DESIRABLE MEASURES

    Put project needs in writing and requirevendors to state in writing how they

    would respond to all needs Review all responses in detail and

    match them up

    Seek independent views, particularlyfrom persons who have used the samepackage in implementing multi-donorfinanced projects

  • 8/3/2019 World Bank Project Financial Management Guidelines

    75/156

    MODULE 1

    Unit 1 - Tr. no. 75

    OTHER DESIRABLE

    MEASURES (contd)

    Require each vendor to give a

    demonstration, showing howhis/her

    package responds to all project needs

    Before inviting vendor proposals it is

    important to distinguish between

    mandatory and optionalrequirements.

    The mandatory requirements should be

    clearly communicated to vendors

  • 8/3/2019 World Bank Project Financial Management Guidelines

    76/156

    MODULE 1

    Unit 1 - Tr. no. 76

    MANDATORY

    REQUIREMENTS

    The system must be:

    Capable ofhandling provincial district aswell as headquarters transactions

    Multi-currency

    User friendly (e.g. Windows driven)

    Not prohibitively expensive

    Able to account under different bases (e.g. Cash,accrual, modified cash, modified accrual)

    Able to produce the PMR for the financialmanagement initiative (formerly LACI)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    77/156

    MODULE 1

    Unit 1 - Tr. no. 77

    MANDATORY

    REQUIREMENTS(contd)

    Capable of providing clear audit trails

    Able to track actual, budget, forecast andproject life per the pad

    Able to link financial figures to physicalperformance indicators as required by

    project

    Equipped with user manual or documentation

    Able to track and search by specific references(e.g. The journal number allocated to eachtransaction or by cheque number)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    78/156

    A A O Q S

  • 8/3/2019 World Bank Project Financial Management Guidelines

    79/156

    MODULE 1

    Unit 1 - Tr. no. 79

    MANDATORY REQUIREMENTS

    (contd)

    Able to track and report by:

    Flexible reporting cycles, e.g. Month, quarter,calendar year, fiscal year, etc.

    Source of program funds

    Loan agreement category

    Project components

    Able to generate reports for previous periods(e.g. Lost reports)

    Able to customize reports within reasonablelimits

    MANDATORY REQUIREMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    80/156

    MODULE 1

    Unit 1 - Tr. no. 80

    MANDATORY REQUIREMENTS

    (contd)

    Equipped with:

    Adequate security features (e.g. Cannot delete

    posted transactions, controlled access,password protection)

    Back-up and system maintenance procedures

    Self diagnostic tests to ensure integrity

    Adequate training facilities

    Adequate after sale support for resolvingtechnical issues

  • 8/3/2019 World Bank Project Financial Management Guidelines

    81/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    82/156

    MODULE 1

    Unit 1 - Tr. no. 82

    SOFTWARE SELECTION PROCESS

    SOME TIPS

    The committee should assess:

    Technical and functional quality of solution

    Overall quality of proposed relations

    h

    ip Reliability of company

    Quality of support staff

    Training facilities

    Help desk service Documentation available

    Future development plans

    Policy for upgrades of previous version

  • 8/3/2019 World Bank Project Financial Management Guidelines

    83/156

    MODULE 1

    Unit 1 - Tr. no. 83

    COMPUTERIZATION

    It may be prudent to run a manual and

    computerized system in parallel for some

    time, before finally abandoning manual

    system

    Even after that, there should be back up of

    all information and systems in electronic

    form

    PERIODIC PROGRESS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    84/156

    MODULE 1

    Unit 1 - Tr. no. 84

    PERIODIC PROGRESSREPORTS

    Projects typically produce 3 types of reports:

    (i) ad hoc

    (ii) regular periodical progress reports(iii) annual reports

    Bank-financed projects are required to submit

    to the bank at regular intervals, not more than

    6 months, periodic progress reports, FMR

    FMR stands for Financial Monitoring Reports

  • 8/3/2019 World Bank Project Financial Management Guidelines

    85/156

    MODULE 1

    Unit 1 - Tr. no. 85

    CHARACTERISTICS OF FMR

    FMR replaces theProject Management Reports (PMR),introduced by the World Bank on July 1, 1998, under

    th

    e loan administration ch

    ange initiative (LAC

    I)The distinguishing characteristics of FMR are:

    Distinction between project management (byBorrower) and project monitoring (by lender)

    New emphasis on maximum reliance on borrowersAccounting/reporting systems/format Format, content, and frequency more flexible

    Reflecting project size, sector, and complexity

    GUIDING PRINCIPLESGUIDING PRINCIPLES

  • 8/3/2019 World Bank Project Financial Management Guidelines

    86/156

    MODULE 1

    Unit 1 - Tr. no. 86

    GUIDING PRINCIPLESGUIDING PRINCIPLESOF FMROF FMR

    The overall objective is to provide regularinformation that gives necessary fiduciaryassurance to the Bank

    FMRwill be less detailed than the reportprepared for project management

    Borro

    wers o

    wn system s

    hould be used asfar as possible in producing FMRs

    GUIDING PRINCIPLES OF FMR

  • 8/3/2019 World Bank Project Financial Management Guidelines

    87/156

    MODULE 1

    Unit 1 - Tr. no. 87

    GUIDING PRINCIPLES OF FMR(Contd)

    The same structure of financial information

    should normally be used for project planning,

    monitoring reports and annual audited financial

    statements, and implementation completionreports (ICRs)

    As far as possible, borrowers should not berequired to provide the Bankwith information

    already available to the Bank The requirements for financial and procurement

    monitoring should, as far as possible, be alignedwith other bank requirements for projectprogress reporting and monitoring

    GUIDING PRINCIPLES OF

  • 8/3/2019 World Bank Project Financial Management Guidelines

    88/156

    MODULE 1

    Unit 1 - Tr. no. 88

    GUIDING PRINCIPLES OFFMR (contd)

    While the reports to be submitted to the Banksshould meet certain minimum requirements,they should be flexible and customized to each

    project or where possible, to each countryand/or sector

    Monitoring expenditures in relation to physicalprogress is a key aspect of ensuring that the

    project is under proper financial control

    Wherever possible, common reporting andmonitoring arrangements should be agreedwith other donors involved in the project

  • 8/3/2019 World Bank Project Financial Management Guidelines

    89/156

    MODULE 1

    Unit 1 - Tr. no. 89

    STRUCTURE OF THE FMR

    The FMR should normally include:

    Financial reports Physical progress reports, and

    Procurement reports

  • 8/3/2019 World Bank Project Financial Management Guidelines

    90/156

    MODULE 1

    Unit 1 - Tr. no. 90

    FMR FINANCIAL REPORTS

    Financial reports should show:

    Cash inflows and outflows for the period

    (e.g., quarter), and cumulatively for the

    project life

    Expenditures should be reported according

    to project activities, not according toprocurement/disbursement categories

    (although this may be reported as an

    addition)

    PHYSICAL PROGRESS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    91/156

    MODULE 1

    Unit 1 - Tr. no. 91

    PHYSICAL PROGRESSREPORT

    Physical progress reports should link

    physical outputs or implementation

    progress to costs of achieving them

    Indicators of physical progress andoutputs should be selected during project

    preparation, stated in the ProjectImplementation Plan (PIP)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    92/156

    MODULE 1

    Unit 1 - Tr. no. 92

    PROCUREMENT REPORT

    The procurement report:

    shows the status of procurement of goods,

    works, services, and consultants compares the actual procurement

    performance with the plan agreed with

    Bank at negotiations or in a subsequent

    review

    highlights specific problems (e.g., staffing

    or training needs)

    MATTERS TO BE AGREED AT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    93/156

    MODULE 1

    Unit 1 - Tr. no. 93

    MATTERS TO BE AGREED ATNEGOTIATIONS

    Explains deviations from plan, and proposes

    solutions to problems identified

    Format, content, frequency, and currency ofreports

    Project outputs and other indicators formonitoring physical or other progress towardachieving project results

    How to deal with multiple implementationagencies, scattered project locations, andcommunity-based project activities

  • 8/3/2019 World Bank Project Financial Management Guidelines

    94/156

  • 8/3/2019 World Bank Project Financial Management Guidelines

    95/156

    ANNUAL FINANCIAL

  • 8/3/2019 World Bank Project Financial Management Guidelines

    96/156

    MODULE 1

    Unit 1 - Tr. no. 96

    ANNUAL FINANCIAL

    REPORTING (contd)

    FARAH discusses extensively in

    chapter iv how to meet the need for

    annual financial reporting.

    FARAH also presents two basic models

    of financial reporting:

    One for revenue-earning

    One for non-revenue-earning

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    97/156

    MODULE 1

    Unit 1 - Tr. no. 97

    PROJECTS IMPLEMENTED BY

    REVENUE-EARNING ENTITIES

    Projects implemented by revenue-

    earning entities typically involve on-lending Bank/IDA funds from

    government to the implementing agency

    through a subsidiary loan agreement

    between government and agency.

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    98/156

    MODULE 1

    Unit 1 - Tr. no. 98

    REVENUE-EARNING ENTITIES

    (contd)

    They also usually involve the Bank requiring,

    not only annual financial statements of the

    project, but also those of the implementingagency, because:

    The success and viability of the project

    depend on the financial health of the

    agency

    Capacity building within the agency is

    one of the project objectives

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    99/156

    MODULE 1

    Unit 1 - Tr. no. 99

    Entity financial statements required from such

    projects generally include:

    A balance sheet - financial snapshot taken

    at the year end - showing assets, liabilities

    and equity

    An income statement showing income,

    expenses, and results of operations for the

    covered period

    REVENUE-EARNING ENTITIES

    (contd)

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    100/156

    MODULE 1

    Unit 1 - Tr. no. 100

    A cash flow statement showing the cash

    provided by and used in operations and

    activities during the covered period

    Notes on the financial statements explaining

    the main accounting disclosures, including

    risks and uncertainties affecting theorganization, and any resources or

    obligations not recognized in the financial

    statement

    REVENUE-EARNING ENTITIES

    (contd)

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    101/156

    MODULE 1

    Unit 1 - Tr. no. 101

    Sometimes the project financial statements

    are integrated in the entity financial

    statements.

    In other cases they are shown as a separateattachment to the entity financial statements.

    Whichever solution is adopted, the Bankalways requires, through the DCA, thatproject expenditures be accounted separatelyfrom other entity expenditures.

    REVENUE-EARNING ENTITIES

    (contd)

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    102/156

    MODULE 1

    Unit 1 - Tr. no. 102

    NON-REVENUE-EARNING

    ENTITIES

    It is likely that the majority Bank financed

    projects are implemented by government

    ministries (or PIUs), or other entities.

    Regardless of the type of implementing

    agency, the Bank requires financial

    statements to monitor project performance

    and utilization of the loan.

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    103/156

    MODULE 1

    Unit 1 - Tr. no. 103

    NON-REVENUE-EARNING

    ENTITIES (contd)

    For non-revenue-earning agencies, the

    main feature of the annual financial

    statements is the statement of sources andapplication of funds for the current year

    and cumulatively since the start of the

    project.

    Actual project expenditures should be

    compared with the original (PAD) or

    amended projections.

    PROJECTS IMPLEMENTED BY

  • 8/3/2019 World Bank Project Financial Management Guidelines

    104/156

    MODULE 1

    Unit 1 - Tr. no. 104

    The reporting should include the total project,

    regardless of funding sources for particular

    activities.

    The Bank still receives financial project

    statements showing only world Bank-financed

    activities and excluding others.

    This is unacceptable and contrary to OP/BP

    10.02.

    NON-REVENUE-EARNING

    ENTITIES (contd)

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    105/156

    MODULE 1

    Unit 1 - Tr. no. 105

    SOME ISSUES IN PROJECT

    ANNUAL FINANCING REPORTING

    Application of IAS to projects in agencies that do not apply

    IAS

    This requests project reporting standards that differ fromthose applying to:

    The ministrys other business

    Projects reports to, say, ministry of finance Since all

    governments report differently, applying IAS to all

    projects ensures their financial statements information

    would be more directly comparable than if government

    reporting standards were applied

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    106/156

    MODULE 1

    Unit 1 - Tr. no. 106

    SOME ISSUES IN PROJECTANNUAL FINANCING

    REPORTING (contd)Even within the private sector, reporting practices vary

    across countries.

    One of the most striking international differences is

    between:

    Anglo-Saxon practice, allowing freedom inreporting format, and

    Napoleonic law (practised in most western Europe,

    French, Portuguese and Spanish speaking countries)

    where financial statement format must conform to a

    standard.

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    107/156

    MODULE 1

    Unit 1 - Tr. no. 107

    Even within the Anglo-Saxon countries, the typical UK

    format is different from the typical U.S.A. Format.

    So, in the private as well as the public sector,

    application of IAS facilitates matters by introducing a

    degree of uniformity and comparability of project

    financial reporting whichwould not exist otherwise.

    How to report on a project with multiple implementing

    agencies

    SOME ISSUES IN PROJECTANNUAL FINANCING

    REPORTING (contd)

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    108/156

    MODULE 1

    Unit 1 - Tr. no. 108

    Example: a capacity building project benefiting 10

    different institutions, each implementing its own

    project component/s independently of all other.

    Usually, the best solution to this case is to create

    one small umbrella PIU, consolidate the project

    financial statements of all th

    e 10 agencies in th

    atumbrella and send only one consolidated annual

    financial statement to the Bank.

    SOME ISSUES IN PROJECTANNUAL FINANCING

    REPORTING (contd)

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    109/156

    MODULE 1

    Unit 1 - Tr. no. 109

    In practice, apart from entity financial

    statements, a typical world Bank-financed

    project produces the following annual financialstatements:

    A statement of sources and application of

    funds, or A receipts and payments account, showing

    cash received and paid by the project

    SOME ISSUES IN PROJECTANNUAL FINANCING

    REPORTING (contd)

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    110/156

    MODULE 1

    Unit 1 - Tr. no. 110

    A balance sheet, always required when

    accounts are prepared on an accrual basis

    A summary of special account transactions

    and balance for the year, sometimes

    combined with, or in the form of:

    A special account reconciliation

    statement

    SOME ISSUES IN PROJECTANNUAL FINANCING

    REPORTING (contd)

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    111/156

    MODULE 1

    Unit 1 - Tr. no. 111

    ANNUAL FINANCING

    REPORTING (contd)

    A summary of statements of expenditure(SOEs) issued during the year, where the

    project is using SOEs A summary of the financial monitoring

    reports (FMR) issued during the year,where the project is disbursing through

    FMR

    A list of project fixed assets and, whereapplicable

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    112/156

    MODULE 1

    Unit 1 - Tr. no. 112

    ANNUAL FINANCING

    REPORTING (contd)

    A list of important financial commitmentswhich,although they are not yet payable, will definitely

    become payable in the future, showing whenpayments will become due (e.g. Scholarshippayments during the next 7 years).

    Specific financial reporting requirements vary

    from project to project, even th

    ough

    generalrequirements in article iv of the DCA arestandard. The specific requirements are alsoincluded in financial covenants in the DCA.

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    113/156

    MODULE 1

    Unit 1 - Tr. no. 113

    ANNUAL FINANCING

    REPORTING (contd)For most projects, relevant grouping for

    annual financial reporting are determined by:

    Project components as presented in t

    he

    PAD

    Procurement/disbursement categories in

    the DCA

    Under a good PFM system, projectscomponents in the pad and disbursement

    categories determine:

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    114/156

    MODULE 1

    Unit 1 - Tr. no. 114

    ANNUAL FINANCING

    REPORTING (contd)

    The ledger and other accounts tomaintained by the project

    The FMR reporting format

    The annual project financial statementformat

    It is important to this bear in mind whenpreparing the PAD and the DCA

    SOME ISSUES IN PROJECT

  • 8/3/2019 World Bank Project Financial Management Guidelines

    115/156

    MODULE 1

    Unit 1 - Tr. no. 115

    ANNUAL FINANCING

    REPORTING (contd)

    Note also that having the same format

    for both the FMR and the annual

    financial statements, particularly thestatement of sources and application of

    funds, means that last annual FMR is

    effectively th

    e annual financialstatement.

    AUDITING ARRANGEMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    116/156

    MODULE 1

    Unit 1 - Tr. no. 116

    AUDITING ARRANGEMENTS

    The Bank requires borrower and implementing

    entity to have annual financial statements audited

    in accordance with standards on auditing

    acceptable to the Bank (OP 10.02).

    The audit includes:

    Assessment of adequacy of accounting andinternal control systems

    Determination of maintenance of adequatedocumentation of all transactions

    Verification of eligibility of transactions

    AUDITING ARRANGEMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    117/156

    MODULE 1

    Unit 1 - Tr. no. 117

    AUDITING ARRANGEMENTS

    The three most common types of audit are:

    Financial statement audit,

    verification/confirmation

    Compliance audit, usually by internal audit, to

    confirm compliance with rules and regulations

    Operational audit, to assess performance,efficiency and effectiveness, requiring more than

    accounting skills

    AUDITING ARRANGEMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    118/156

    MODULE 1

    Unit 1 - Tr. no. 118

    (contd)

    Normally Bank-financed projects require onlyfinancial statement audits. Any other type of

    audit sh

    all be specifically indicated in th

    eTO

    RS.Distinguish between:

    Revenue-earning projects requiring audits ofboth entities and project financial statements

    Non-revenue-earning projects requiringaudits only of project financial statements

    AUDITING ARRANGEMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    119/156

    MODULE 1

    Unit 1 - Tr. no. 119

    (contd)

    The overall audit objective is to express an

    opinion on:

    Fair presentation of financial statement in

    conformity to IAS and GAAP

    Basis consistent with preceding year

    Such audits must be in accordance withinternational standard on auditing (ISA)

    promulgated by IFAC.

    AUDITING ARRANGEMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    120/156

    MODULE 1

    Unit 1 - Tr. no. 120

    (contd)

    Professional and ethical principles, requiredby ISA from all auditing firms andindividuals, include:

    Independence

    Integrity

    Objectivity

    Professional competence Confidentiality

    Professional behaviour

    Technical standards

    AUDITING ARRANGEMENTS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    121/156

    MODULE 1

    Unit 1 - Tr. no. 121

    (contd)

    Auditors, members of IFAC institutions or

    associations, generally adhere to these principles.

    NON-REVENUE-EARNING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    122/156

    MODULE 1

    Unit 1 - Tr. no. 122

    ORGANIZATIONS

    The Bank may accept audit of financial

    statements of non-revenue-earningorganizations and projects by SAI,

    provided they apply auditing standards

    of international organisation of supreme

    audit institutions (INTOSAI) to auditaccounts of revenue-earning entities.

    NON-REVENUE-EARNING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    123/156

    MODULE 1

    Unit 1 - Tr. no. 123

    ORGANIZATIONS (contd)

    INTOSAI standards promote:

    Independence

    Competence

    Due care Field standards are based on:

    Planning, supervision and review

    Study and evaluation of internal control

    Compliance with applicable law andregulations

    Audit evidence

    Analysis of financial statement

    NON-REVENUE-EARNING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    124/156

    MODULE 1

    Unit 1 - Tr. no. 124

    ORGANIZATIONS (contd)

    Constitution of most countries creates SAI and

    mandates it to audit all government revenues and

    expenditures, including projects.

    NON-REVENUE-EARNING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    125/156

    MODULE 1

    Unit 1 - Tr. no. 125

    ORGANIZATIONS (contd)

    Overall objective of audit project financial

    statements is to confirm that:

    Financial statements, particularly sourcesand application of funds, are fairly presented

    Disbursement is in accordancewith loanagreement and PAD

    Balance sheet (if any) fairly presents assetsand liabilities

    NON-REVENUE-EARNING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    126/156

    MODULE 1

    Unit 1 - Tr. no. 126

    ORGANIZATIONS (contd)

    Audit procedures are similar to those of auditfinancial statements of revenue-earning projects.

    They involve: Evaluation of internal controls

    Tests of transactions with supportingdocuments

    Other procedures, including physicalobservation of significant assets, third partyconfirmation of balances, etc.

    AUDIT SOE AND PMR

  • 8/3/2019 World Bank Project Financial Management Guidelines

    127/156

    MODULE 1

    Unit 1 - Tr. no. 127

    AUDIT SOEs AND PMRs

    Audit of statements of expenditure

    (SOE) and project management reports(PMR) involve more compliance

    checking, since their supporting

    documents are not sent to the Bank, but

    retained in PIUS.

    AUDIT OF SA

  • 8/3/2019 World Bank Project Financial Management Guidelines

    128/156

    MODULE 1

    Unit 1 - Tr. no. 128

    AUDIT OF SA

    Audit of the special account (SA) statement

    verify that:

    SA transaction have been fairly presented

    Are in accordance with the loan

    agreement

    Funds have been used solely for project

    purposes

    SELECTION OF AUDITORS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    129/156

    MODULE 1

    Unit 1 - Tr. no. 129

    SELECTION OF AUDITORS

    Auditor are selected according to Bankguidelines for the selection of consultants.

    Terms of reference (TORS) are necessary,to cover auditor responsibilities peculiar toBank-funded projects (e.g. SOES and SAS).

    TORs must be clear, specific and

    comprehensive, without in any way limitingauditor obligation to apply ISAS or GAAS.

    Samples ofTORS are in FARAH.

    SELECTION OF AUDITORS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    130/156

    MODULE 1

    Unit 1 - Tr. no. 130

    (contd)

    Many auditors provide their letter of engagement,

    containing:

    Acceptance of appointment,w

    ith

    reference toTO

    Rs Auditor responsibilities

    Access to clients premises, staff and records

    Form of audit reports

    Involvement of internal or other external auditors Report timing

    Fees: computation, mode of payment

    SELECTION OF AUDITORS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    131/156

    MODULE 1

    Unit 1 - Tr. no. 131

    (contd)

    Three things are generally required by the auditor:

    Opinions on:

    Annual financial statement of entire project(sources and application of funds, balancesheet, etc.)

    SOE/PMR summary

    SA statement

    A management letter

    Coverage of all project expenditures, not justthose financed by the Bank

    AUDIT REPORTING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    132/156

    MODULE 1

    Unit 1 - Tr. no. 132

    COMPLIANCE SYSTEM (ARCS)

    The Bankhas an audit reporting compliance system(ARCS) for monitoring borrower compliance with theaudit covenants.

    Bankhas also remedies in event that:

    Audited financial statements are not receivedwhen due

    Opinion indicates deficiency in accounting, internalcontrol or reliability of financial statements

    The Bank considers scope or quality of auditunacceptable

    AUDIT REPORTING

    COMPLIANCE SYSTEM (ARCS)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    133/156

    MODULE 1

    Unit 1 - Tr. no. 133

    COMPLIANCE SYSTEM (ARCS)

    (contd)

    In any of these events, normally the Bank:

    Will not extend loan closing date

    Delays negotiations or board presentation ofany new loan benefiting defaulting entityuntil:

    Acceptable audited financial statementsare received

    A remedial action plan is agreed

    AUDIT REPORTING COMPLIANCE

  • 8/3/2019 World Bank Project Financial Management Guidelines

    134/156

    MODULE 1

    Unit 1 - Tr. no. 134

    SYSTEM (ARCS) (contd)

    In addition, if audited financial statementsare not receivedwithin 4 months, the Bankdiscontinues use of SOE procedure.

    In addition, if acceptable audited SAfinancial statements are not receivedwithin4 months, the Bank normally withholds SAreplenishments.

    In addition, after 9 months following duedate, the Bank may suspend alldisbursements on the loan.

    AUDIT REPORTING

    COMPLIANCE SYSTEM (ARCS)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    135/156

    MODULE 1

    Unit 1 - Tr. no. 135

    COMPLIANCE SYSTEM (ARCS)

    (contd)

    In addition, if audited financial

    statements reveal major deficiencies in

    internal control, or inadequate evidence

    that funds have been used for only

    eligible expenditures, Bank may suspend

    all disbursements on th

    at loan untilsatisfied that adequate remedial actions

    have been taken.

    ,ACCOUNTING AND

  • 8/3/2019 World Bank Project Financial Management Guidelines

    136/156

    MODULE 1

    Unit 1 - Tr. no. 136

    AUDITING

    Scope and definition

    Project fixed assets comprise mainly civil works,vehicles and equipment.

    International accounting standards (IAS16)defines as property, plant and equipment,those assets which are:

    Used in production or supply of goods or

    services, rental to others, or foradministrative purposes

    Expected to be used during more than oneaccounting period (typically one year)

    FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    137/156

    MODULE 1

    Unit 1 - Tr. no. 137

    ACCOUNTING AND AUDITING

    (contd)Section 5 (b) of Article III of the IBRD articles

    of agreement states that the Bank shall make

    arrangements to ensure that the proceeds of

    any loan are used only for the purposes for

    which the loan was granted, with due attention

    to economy and efficiency and regardless to

    political or other non-economic influences or

    considerations.

    Similar provisions are included in IDA articles

    of agreement.

    FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    138/156

    MODULE 1

    Unit 1 - Tr. no. 138

    ACCOUNTING AND AUDITING

    (contd)Fiduciary and accountability obligations require to:

    Ensure delivery of project assets to right place and

    Monitor use of assets

    Not jeopardize achievement of project objectives byallowing assets to be diverted to non-project use

    Therefore, concern for project fixed asset management hastwo main objectives:

    Protecting project implementation and objectives

    Satisfying the Bank fiduciary and accountabilityobligations under article iii

    FIXED ASSET MANAGEMENT,ACCOUNTING AND

  • 8/3/2019 World Bank Project Financial Management Guidelines

    139/156

    MODULE 1

    Unit 1 - Tr. no. 139

    ACCOUNTING AND

    AUDITING (contd)

    Therefore, concern for project fixed assetmanagement has two main objectives:

    Protecting project implementation andobjectives

    Satisfying the Bank fiduciary andaccountability obligations under article iii

    FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    140/156

    MODULE 1

    Unit 1 - Tr. no. 140

    ACCOUNTING AND AUDITING

    (contd)Some issues in fixed asset management

    Tying expenditures to actual fixed assets

    Identification of project fixed assets andtheir separation from other fixed assets of

    the implementing agency

    Accurate valuation of fixed assets,especially in civil works

    FIXED ASSET MANAGEMENT,ACCOUNTING AND AUDITING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    141/156

    MODULE 1

    Unit 1 - Tr. no. 141

    ACCOUNTING AND AUDITING

    (contd) Condition and fitness for intended purpose at

    time of purchase

    Repair and maintenance program to protect

    value and fitness Ownership versus control: interference between

    one and the other or with use of asset forintended purposes

    Incidence of non-project use Insurance: protecting value until end of

    economic life, or end of project, whichevercomes first

    FIXED ASSET MANAGEMENT,ACCOUNTING AND

  • 8/3/2019 World Bank Project Financial Management Guidelines

    142/156

    MODULE 1

    Unit 1 - Tr. no. 142

    ACCOUNTING AND

    AUDITING (contd) Arrangements for disposal of fixed asset at:

    End of useful life

    End of project period Accounting records maintained for fixed

    assets (register, ledger, etc.)

    Disclosure of fixed assets in annual financial

    statements, particularly if accounting on cash

    basis

    Auditor verification of asset existence, value

    and use

    OTHER PFM PROBLEMS:

  • 8/3/2019 World Bank Project Financial Management Guidelines

    143/156

    MODULE 1

    Unit 1 - Tr. no. 143

    STAFFING

    Staff for PFM presents problems of:

    How to find and pay qualified staff

    to operate double entry project

    accounting system in a PIU

    How to hire staff

    What will happen to project staff at

    the end of project

  • 8/3/2019 World Bank Project Financial Management Guidelines

    144/156

    OTHER PFM PROBLEMS:( d)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    145/156

    MODULE 1

    Unit 1 - Tr. no. 145

    STAFFING (contd)

    A typical efficient solution is to hire

    temporary staff or consultants on fixed

    term, with renewal option, paid by

    project, provided that expenditures

    were included in project cost estimates.

    OTHER PFM PROBLEMS:PROJECT PREPARATION

  • 8/3/2019 World Bank Project Financial Management Guidelines

    146/156

    MODULE 1

    Unit 1 - Tr. no. 146

    PROJECT PREPARATION

    FACILITIES (PPF)PPF presents a challenge and an opportunity:

    Challenge: how to ensure proper FM or

    funds and activities for a project which isnot effective and may never materialize

    Opportunity: PPF provides funds to hire

    appropriate staff for its management,provided this was included in the PPF request

    OTHER PFM PROBLEMS:PROJECT PREPARATION

  • 8/3/2019 World Bank Project Financial Management Guidelines

    147/156

    MODULE 1

    Unit 1 - Tr. no. 147

    PROJECT PREPARATION

    FACILITIES (PPF) (contd)One of the best ways to look at PPF is to

    consider it as a pilot project or a

    preliminary part of the project. Thisapproach ensures that:

    All PPF funds are properly accounted for

    There is a viable and tested fm system inplace at loan/credit effectiveness

    OTHER PFM PROBLEMS:PROJECT PREPARATION

  • 8/3/2019 World Bank Project Financial Management Guidelines

    148/156

    MODULE 1

    Unit 1 - Tr. no. 148

    PROJECT PREPARATION

    FACILITIES (PPF) (contd)Substantial (e.g. US$1 million and more)

    PPF should send the Bank a simple audited

    financial statement, if it remains active formore than one year.

    No PPF request should be considered

    complete unless it includes arrangementsand financing for proper accounting, and

    for audit if active for more than one year.

    OTHER PFM PROBLEMS:

  • 8/3/2019 World Bank Project Financial Management Guidelines

    149/156

    MODULE 1

    Unit 1 - Tr. no. 149

    SMALL OPERATIONS

    Article iii of the Banks articles of agreement

    andOP/BP apply to all projects financed by the

    Bank, no matter how small.

    This means that even small grants require:

    Satisfactory fm system before Board

    Agreed reporting formats and audit terms of

    reference at Negotiations Periodic Financial Monitoring Reports

    Audited financial statements within 6 months

    following end of fiscal year

    OTHER PFM PROBLEMS:( d)

  • 8/3/2019 World Bank Project Financial Management Guidelines

    150/156

    MODULE 1

    Unit 1 - Tr. no. 150

    SMALL OPERATIONS (contd)

    How does one manage all this in a small grant

    of, say, US$500,000, without using a sledge

    hammer to crack a peanut?:

    Planning, budgeting, internal controls,accounting and reporting should be kept

    simple, reflecting small amount involved, but

    without compromising basic principles

    Audit could be part of a larger auditcontract for a bigger operation, ensuring

    appropriate audit expertise at reasonable cost

    OTHER PFM PROBLEMS:GOVERNMENT COUNTERPART

  • 8/3/2019 World Bank Project Financial Management Guidelines

    151/156

    MODULE 1

    Unit 1 - Tr. no. 151

    GOVERNMENT COUNTERPART

    FUNDSMany Bank-financed projects have problemsobtaining governments financial contribution tothe project.

    Bank insists on, at least, minimal governmentfinancial participation, to ensure governmentinterest and commitment.

    Difficulty of counterpart funding arises, despite

    ministry of finance participation in negotiationsand being named government representative inpractically all loan agreements.

    OTHER PFM PROBLEMS:GOVERNMENT COUNTERPART

  • 8/3/2019 World Bank Project Financial Management Guidelines

    152/156

    MODULE 1

    Unit 1 - Tr. no. 152

    GOVERNMENT COUNTERPART

    FUNDS (contd)Problems have more to do with government

    planning and budgeting system, than with

    absolute lack of funds.

    Lack of co-ordination of numerous entities in

    some projects may also be a problem.

    It may happen that there are communication

    problems among some ministries responsiblefor projects and ministry of finance.

    GOVERNMENTCOUNTERPART FUNDS

  • 8/3/2019 World Bank Project Financial Management Guidelines

    153/156

    MODULE 1

    Unit 1 - Tr. no. 153

    (contd)

    Furthermore, government typically

    budgets once a year, but enters

    project commitments all year.

    Another common practice is to

    commit funds only when they

    become available, regardless ofbudgetary provision.

    OTHER PFM PROBLEMS:GOVERNMENT COUNTERPART

  • 8/3/2019 World Bank Project Financial Management Guidelines

    154/156

    MODULE 1

    Unit 1 - Tr. no. 154

    GO COU

    FUNDS (contd)The possible solutions are: Those responsible for project preparation and

    implementation should constantly remind ministryof finance to provide for government commitmentsin budget

    For many projects, funds would need to bebudgeted by government up to 12 months beforethey are actually needed

    Dealing with cash-based allocations requiresspecific knowledge ofhow things work and how toget the necessary cash allocations in a particularcountry and in particular circumstances

    OTHER PFM PROBLEMS:ORGANIZING AND FINANCING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    155/156

    MODULE 1

    Unit 1 - Tr. no. 155

    THE FINAL AUDITOrganizing and paying for a final auditcan pose a problem, particularly when theproject is expected to pay for the audit.

    The Bank expects to receive auditedfinancial statements of the fiscal year inwhich the last disbursement is made.

    Project managers need to ensure that thefinal audit is completed and paid for,before the loan or credit closes.

    OTHER PFM PROBLEMS:ORGANIZING AND FINANCING

  • 8/3/2019 World Bank Project Financial Management Guidelines

    156/156

    THE FINAL AUDIT (contd)This needs to be planned, discussed with the

    task leader and disbursement officer and all

    detailed steps agreed, at least one yearbefore the closing date.

    Failure to plan for this well in advance of

    th

    e closing date could result in borrow

    erhaving to finance the audit from its own