Working of Substation

75
1 SUMMER INTERNSHIP REPORT On Substation Automation using SCADA and Financial Modeling of 5 MW Solar PV Under the Guidance of Ms. Indu Maheshwari Dy. Director (NPTI, Faridabad) & Mr. Anil Vaishy D.G.M SCADA BSES Yamuna At Submitted by ASHISH KUMAR MBA Power Management Roll No: 22 ; Batch 2012-14 Affiliated to MAHARSHI DAYANAND UNIVERSITY, ROHTAK (A State University established under Haryana Act No. XXV of 1975)

description

Working of Substation

Transcript of Working of Substation

  • 1

    SUMMER INTERNSHIP REPORT

    On

    Substation Automation using SCADA and

    Financial Modeling of 5 MW Solar PV

    Under the Guidance of

    Ms. Indu Maheshwari

    Dy. Director (NPTI, Faridabad)

    &

    Mr. Anil Vaishy

    D.G.M SCADA BSES Yamuna

    At

    Submitted by

    ASHISH KUMAR

    MBA Power Management

    Roll No: 22 ; Batch 2012-14

    Affiliated to

    MAHARSHI DAYANAND UNIVERSITY, ROHTAK

    (A State University established under Haryana Act No. XXV of 1975)

  • 2

    CERTIFICATE

  • 3

    DECLARATION

    I, Ankit Singh, Roll No. 16, class 2012-14 of the National Power Training Institute, Faridabad

    hereby declare that the Summer Training Report entitled Substation Automation using

    SCADA and Financial Modelling of 5 megawatt Solar PV plant is an original work and the

    same has not been submitted to any other institute for the award of any other degree.

    A seminar presentation of the Training Report was made on 3rd

    August 2013 and the suggestions

    approved by the faculty were duly incorporated.

    Presentation In charge

    (Faculty)

    Signature of the Candidate

    (Ankit Singh)

    Countersigned

    Director/Principal of the Institute

  • 4

    ACKNOWLEDGEMENT

    I would like to express my sincere gratitude to all the people who had been associated with me in

    some way or the other and helped me avail this opportunity for my summer Internship on the

    topic Substation Automation using SCADA and Financial Modelling of 5 MW Solar PV

    plant.

    I acknowledge with gratitude and humanity my indebtedness to my Summer Internship guide

    Mr. Anil Vaishy D.G.M (SCADA),BSES Yamuna for providing me excellent guidance and

    motivation under whom I completed my summer internship

    I would like to thank my Project In-charge Ms. Indu Maheshwari, Deputy Director, NPTI,

    Faridabad for his support and guidance throughout the course of summer internship.

    A special thanks to Mrs. Indu Maheswari, Dy. Director, NPTI and Dr. Rohit Verma, Dy.

    Director, NPTI for their guidance throughout my summer internship.

    I would like to thank Mr. S.K. Choudhary, Principal Director (NPTI), Mrs. Manju Mam,

    Director, NPTI and all faculty members for arranging my internship at TERI and being a

    constant source of motivation and guidance throughout the course of my internship.

    Ankit Singh

    Summer Interns

    NPTI, Faridabad

  • 5

    TABLE OF CONTENTS

    PROJECT TITLE 1

    CERTIFICATE ......................................................................................................................2

    DECLARATION ....................................................................................................................3

    ACKNOWLEDGEMENT ......................................................................................................4

    TABLE OF CONTENTS ........................................................................................................6

    LIST OF FIGURES ................................................................................................................7

    LIST OF TABLES.8

    COMPANY PROFILE..9

    CHAPTER 1 INTRODUCTION TO SCADA..13

    1.1 NEED FOR SCADA15

    1.2 BENEFITS OF SCADA..17

    CHAPTER 2 DISTRIBUTION SUBSTATIONS19

    2.1 TYPES OF SUBSTATIONS21

    2.2 CLASSIFICATION OF SUBSTATIONS...24

    2.3 MAIN INSTRUMENTS USED IN DISTRIBUTION SUBSTATION.28

    CHAPTER -3 BASICS OF RTU AND SCADA APPLICATIONS..43

    3.1 SCADA APPLICATIONS56

    CHAPTER-4 FINANCIAL MODELLING OF SOLAR PV 1 MW ..63

    CHAPTER-5 CONCLUSION..76

    CHAPTER-6 REFERENCES.77

  • 6

    LIST OF FIGURES

    Figure 1 ....................................................................................................................................................... 11

    Figure 2 ....................................................................................................................................................... 18

    Figure 3 ....................................................................................................................................................... 19

    Figure 4 ....................................................................................................................................................... 21

    Figure 5 ....................................................................................................................................................... 23

    Figure 6 ....................................................................................................................................................... 23

    Figure 7 ....................................................................................................................................................... 23

    Figure 8 ....................................................................................................................................................... 28

    Figure 9 ....................................................................................................................................................... 32

    Figure 10 ..................................................................................................................................................... 35

    Figure 11 ..................................................................................................................................................... 37

    Figure 12 ..................................................................................................................................................... 38

    Figure 13 ..................................................................................................................................................... 40

    Figure 14 ..................................................................................................................................................... 42

    Figure 15 ..................................................................................................................................................... 43

    Figure 17 ..................................................................................................................................................... 44

    Figure 18 ..................................................................................................................................................... 45

    Figure 19 ..................................................................................................................................................... 46

    Figure 20 ..................................................................................................................................................... 47

    Figure 21 ..................................................................................................................................................... 47

    Figure 22 ..................................................................................................................................................... 49

    Figure 23 ..................................................................................................................................................... 50

  • 7

    LIST OF TABLES

    Table 1 ......................................................................................................................................................... 10

    Table 2 ......................................................................................................................................................... 64

    Table 3 ......................................................................................................................................................... 64

    Table 4 ......................................................................................................................................................... 64

    Table 5 ......................................................................................................................................................... 65

    Table 6 ......................................................................................................................................................... 65

    Table 7 ......................................................................................................................................................... 66

    Table 8 ......................................................................................................................................................... 66

  • 8

    COMPANY PROFILE

    BSES Corporate Profile

    BSES, a Reliance Group Company, is the largest, fully integrated private sector Power Utility

    company in the country, engaged in Generation, Transmission and Distribution of electricity

    with an Annual Turnover in excess of Rs.8,000 crore. (US$ 1.2 billion) BSES have over five

    million customers in Mumbai, Delhi and Orissa, the largest in India in the Private Sector. Our

    Power Plants are located in Maharashtra, Kerala and Andhra Pradesh.

    The Reliance Group founded by Mr. Dhirubhai H. Ambani (1932-2002) is India's largest

    business house with total revenues of Rs. 80,000 crore (US$ 16.8 billion), cash profit of over Rs.

    9,800 crore (US$ 2.1 billion), net profit of over Rs. 4,700 crore (US$ 990 million) and exports of

    Rs. 11,900 crore (US$ 2.5 billion). The group's activities span exploration and production

    (E&P) of oil and gas, refining and marketing, petrochemicals (polyester, polymers, and

    intermediates), textiles, financial services and insurance, power, telecom and infocom

    initiatives.

  • 9

    BSES, Delhi Network Overview

    BSES YAMUNA POWER LTD which are a joint venture between Reliance Infra and Govt of

    Delhi distribute power to Central, East, Delhi. As a 1st Milestone in road map towards Network

    Automation, BSES proposes to implement a SCADA/DMS system in the Delhi Distribution

    Network. Brief details of Delhi Distribution Network is given below.

    Delhi draws power from 400kV Northern Grid at 400/220kV Mandola sub-station which is

    interconnected with Bawana and Bamnauli sub-stations, at 220 kV through interconnection at

    Patparganj (with Uttar Pradesh) and Narela (with Haryana) and at 220 KV Indra Prastha

    Extension sub-station to Badarpur Thermal Power Station (BTPS). Delhis transmission system

    at 220 kV consists of twenty-three 220 kV interconnected sub-stations.

    The Transmission lines broadly comprise of 122 ckt.-kms of 400 kV and 529 ckt.-kms of 220 kV

    lines. The 220 kV lines having ACSR Zebra conductor form a ring around Delhi region. The

    transmission lines do not belong to BSES and are managed by other transmission company

    (Transco).

    The power from these 220/66 & 220/33 kV substation of Transco is fed to BSES Delhi area by

    various 99 input feeders at 66 & 33 kV voltage level.

    There are 50 grid substation of 66/11 kV, 33/11 kV & 66/33 kV. The Primary distribution

    network operates essentially at 11 kV (except for a few old 6.6 kV feeders) emanating from the

    66 kV and/or 33 kV sub-stations. In many areas the 11 kV feeder network has the facility for

    Ring Connection or interconnection with different zones. There are about 1200 numbers of such

    11 kV feeders. These 11 kV feeders in turn are feeding to about 2500-distribution transformer of

    11/0.4 kV.

    A summary of the system parameters consisting of BSES Yamina Power Ltd (BYPL) areas is

    given in the table below :

  • 10

    Table 1

    Maximum demand 1195 MW

    No of 66/11, 33/11 & 66/33 kV substation 50 nos

    Total capacity at 66 & 33 Kv 2834 MVA

    Power factor 0.85 -0.9

    No. of 11kV Feeders 685 nos.

    11kV OH Lines 250 kms.

    11kV UG Cables 1756 kms.

    Distribution Transformers 3261 nos.

    Total Transformers capacity 2319 MVA

  • 11

    Delhi Network

    Figure 1

    Chapter -1

    Introduction to SCADA:

  • 12

    The SCADA systems in use for Distribution systems like Water & Gas are existent for

    several decades in USA and other developed countries; however the use of these systems

    for electric distribution monitor & control is quite recent. In India also now we can see

    the number of electric distribution projects some are already in the operation and other

    are in the implementation phase. The SCADA technology has been matured enough now

    due to advances that has taken place in semiconductor technologies & telemetric. In the

    document the discussion is limited to Electric SCADA & Distribution Automation

    Systems.

    The early SCADA systems were built on replicating the existing system remote controls,

    lamps, and analog indications at the functional equivalent of pushbuttons, often placed on

    a mimic board for easy operator interface. The SCADA masters simply replicated point-

    for-point, control circuits connected to the remote, or slave, unit. At the same time as

    SCADA systems were developing, a parallel technology on remote teleprinting , or

    Teletype" was taking shape. The invention of the "modem" (Modulator / Demodulator)

    allowed digital information to be sent over wire pairs which had been engineered to only

    carry the electronic equivalent of human voice communication. The introduction of

    digital electronics made it possible use of faster data streams to provide remote indication

    and control of system parameters. The integration of Teletype technology and the digital

    electronics gave birth to "Remote Terminal Units" (RTUs) which were built with solid-

    state electronics which could provide the remote indication and control of both discrete

    events and analog voltage and current quantities of the electric power system.

    The development of Microprocessors gave the required impetus to SCADA industry

    craving for increased functionality & faster speeds. The 1970s and early 1980s saw the

    coming age of integrated microprocessor-based devices which came to be known as

    "Intelligent Electronic Devices", or IEDs. The IEDs are being used increasingly to

    convert data into engineering unit values in the field and to participate in field-based local

    control algorithms. Many IEDs are being built with programmable logic controller

    (PLC) capability and, communication.

  • 13

    1.1Need for SCADA system:

    Following are the main cause for SCADA need.

    Lack of Information Availability

    Poor Visibility

    Long Fault Restoration Times

    Inadequate Information for processing Customer requests

    Need for Real Time data for Network Analysis & Reconfiguration

    Need For Historical Information

    Load Forecasting and capacity planning.

    Asset tracking and management

    All Report generation

    Training and research.

    Earlier methods used to acquire data:

    PLCC Network

    Wireless VHF sets

    P&T.FWP telephones

    Log sheets

  • 14

    Limitations of old method:

    Outage of telephone/PLCC network

    Non-clarity of speech

    Human factor

    No check on improper compliance of instruction

    Huge time require to collect data and pass instructions

    No control on operations

  • 15

    1.2BENEFITS OF SCADA?

    Visibility for the network operation.

    Real-time, accurate and consistent information of the system.

    Flexibility of operational controls.

    Faster fault identification, Isolation & system restoration.

    Extensive reporting & statistical data archiving.

    Central database and history of all system parameters.

    Improve availability of system, Optimized Load Shedding.

    SCADA in distribution system & utilities is used for Distribution Automation, DMS, OMS i.e.

    Distribution Management System and Outage Management respectively. These has been

    implemented by a lot of distribution utilities across the world the achieve better monitoring and

    control and to improve power quality, reliability & customer satisfaction.

    The goal of Advanced Distribution Automation is real-time adjustment to changing loads,

    generation, and failure conditions of the distribution system, usually without operator

    intervention.

    Presently the distribution utilities across the world are either implementing or have implemented

    distribution automation solutions for fulfilling one or more of these business objectives:

    Better monitoring & control of their distribution assets

    To reduce their Aggregate Technical and Commercial (AT&C) losses

    As part of their Smart Grid compliance put by the regulation

    SCADA systems are globally accepted as a means of real-time monitoring and control of electric

    power systems, particularly for generation, transmission and distribution systems. RTUs

    (Remote Terminal Units) are used to collect analog and status telemetry data from field devices,

    as well as communicate control commands to the field devices. Installed at a centralized location,

    such as the utility control center, are front-end data acquisition equipment, SCADA software,

  • 16

    operator GUI (graphical user interface), engineering applications that act on the data, historian

    software, and other components.

    Recent trends in SCADA include providing increased situational awareness through improved

    GUIs and presentation of data and information; intelligent alarm processing; the utilization of

    thin clients and web-based clients; improved integration with other engineering and business

    systems; and enhanced security features.

  • 17

    CHAPTER-2

    DISTRIBUTION SUBSTATION

    A substation is a part of an electrical generation, transmission, and distribution system.

    Substations transform voltage from high to low, or vice-versa, or perform any of several

    other important functions. Electric power may flow through several substations between

    generating plant and consumer, and its voltage may change in several steps.

    A substation that has a step-up transformer increases the voltage while decreasing the

    current while a step-down transformer decreases the voltage while increasing the current

    for domestic and commercial distribution.

    Substations may be on the surface in fenced enclosures, underground, or located in

    special-purpose buildings. High-rise buildings may have several indoor substations.

    Indoor substations are usually found in urban areas to reduce the noise from the

    transformers, for reasons of appearance, or to protecstwitchgear from extreme climate or

    pollution conditions.

    Where a substation has a metallic fence, it must be properly grounded to protect people

    from high voltages that may occur during a fault in the network. Earth faults at a

    substation can cause a ground potential rise. Currents flowing in the Earth's surface

    during a fault can cause metal objects to have a significantly different voltage than the

    ground under a person's feet; this touch potential presents a hazard of electrocution.

  • 18

    Figure 2

  • 19

    2.1 TYPES OF SUBSTATIONS

    Transmission substation: A transmission substation connects two or more transmission

    lines. The simplest case is where all transmission lines have the same voltage. In such

    cases, the substation contains high-voltage switches that allow lines to be connected or

    isolated for fault clearance or maintenance. A transmission station may

    have transformers to convert between two transmission voltages, voltage control devices

    such as capacitors, reactors or static VAr compensator and equipment such as phase

    shifting transformers to control power flow between two adjacent power systems.

    Transmission substations can range from simple to complex. A small "switching station"

    may be little more than a bus plus some circuit breakers. The largest transmission

    substations can cover a large area (several acres/hectares) with multiple voltage levels,

    many circuit breakers and a large amount of protection and control equipment (voltage

    and current transformers, relays and SCADA systems).

    Figure 3

    TRANSMISSION SUBSTATION

  • 20

    Distribution substation

    A distribution substation transfers power from the transmission system to the distribution system

    of an area. It is uneconomical to directly connect electricity consumers to the high-voltage main

    transmission network, unless they use large amounts of power, so the distribution station reduces

    voltage to a value suitable for local distribution.

    The input for a distribution substation is typically at least two transmission or sub transmission

    lines. Input voltage may be, for example, 66 kV, or whatever is common in the area. The output

    is a number of feeders. Distribution voltages are typically medium voltage, between 11 and

    33 kV depending on the size of the area served and the practices of the local utility.

    The feeders will then run overhead, along streets (or under streets, in a city) and eventually

    power the distribution transformers at or near the customer premises.

    Besides changing the voltage, the job of the distribution substation is to isolate faults in either the

    transmission or distribution systems. In a large substation, circuit breakers are used to interrupt

    any short or overload currents that may occur on the network. Distribution substations may also

    be the points of voltage regulation, although on long distribution circuits (several km/miles),

    voltage regulation equipment may also be installed along the line.

    Complicated distribution substations can be found in the downtown areas of large cities, with

    high-voltage switching, and switching and backup systems on the low-voltage side.

  • 21

    Figure 4

    Distribution Substation

  • 22

    2.2 CLASSIFICATION OF SUBSTATION

    1. According to service requirement

    a) Transformer sub-station: Those sub-station which change the voltage level of electrical

    supply is called Transformer sub-station.

    b) Switching sub-station: This sub-station simply perform the switching operation of power

    line.

    c) Power factor correction S/S: This sub-station which improves the p.f. of the system are

    called p.f. correction s/s. these are generally located at receiving end s/s.

    d) Frequency changer S/S: Those sub-stations, which change the supply frequency, are known

    as frequency changer s/s. Such s/s may be required for industrial utilization

    e) Converting sub-station: That sub-station which change A.C power into D.C. power are

    called converting s/s ignition is used to convert AC to dc power for traction, electroplating,

    electrical welding etc.

    f) Industrial sub-station: Those sub-stations, which supply power to individual industrial

    concerns, are known as industrial sub-station.

    2. According to constructional features

    a) Outdoor Sub-Station: For voltage beyond 66KV, equipment is invariably installed

    outdoor. It is because for such Voltage the clearances between conductor and the space

    required for switches, C.B. and other equipment becomes so great that it is not

    economical to install the equipment indoor.

  • 23

    Figure 5

    OUTDOOR SUBSTATION

    b) Indoor Sub-station: For voltage up to 11KV, the

    equipment of the s/s is installed indoor because of economic consideration. However,

    when the atmosphere is contaminated with impurities, these sub-stations can be erected

    for voltage up to 66KV

    Figure 6

    Figure 7

  • 24

    c) Underground sub-station: In thickly populated areas, the space available for equipment

    and building is limited and the cost of the land is high. Under such situations, the sub-

    station is created underground. The design of underground s/s requires more careful

    consideration.

    The size of the s/s should be as small as possible.

    There should be reasonable access for both equipment & personal.

    There should be provision for emergency lighting and protection against fire.

    There should be good ventilation

    3. According to nature of duties

    a) Step-up or Primary Substations- Where from power is transmitted to various load

    centers in the system network and are generally associated with generating stations.

    b) Step-up and Step-down or Secondary Substations- may be located at generating

    points where from power is fed directly to the loads and balance power generated is

    transmitted to the network for transmission to other load centers.

    c) Step-down or Distribution Substations- receives power from secondary substations

    at extra high voltage (above 66 kV) and step down its voltage for secondary

    distribution.

    4. According to operating voltage

    a) High Voltage Substations (HV Substations) - involving voltages between 11

    kV and 66 kV.

  • 25

    b) Extra high voltage substations (EHV Substations) - involving voltages

    between 132 kV and 400 kV and

    c) Ultra high voltage substations (UHV Substations) - operating on voltage above

    400 kV

    5. According to Importance

    a) Grid Substations- These are the substations from where bulk power is transmitted

    from one point to another point in the grid. These are important because any

    disturbance in these substations may cause the failure of the grid.

    b) Town Substations- These substations are EHV substations which step down the

    voltages at 33/11 kV for further distribution in the towns and any failure in such

    substations results in the failure of supply for whole of the town.

  • 26

    2.3 MAIN EQUIPMENTS USED IN A DISTRIBUTION SUBSTATION

    A distribution substation is an assembly of various electrical equipments connected to step down

    electric power at higher voltages i.e. 66kV/33kV to 11kV and to clear faults in the system. The

    various electrical equipments used in the distribution substation are as follows:-

    1. Power Transformers

    2. Instrument Transformers i.e. CT, PT and CVT

    3. Bus Bars

    4. Isolators

    5. Relays

    6. Circuit Breakers

    7. Lightening Arrestors

    8. Battery chargers

    9. Capacitor banks

    10. Earthing equipments

    11. Control and relay (C & R) panels

    12. PLCs or RTU (remote terminal units)

    13. Multi function Meters

  • 27

    POWER TRANSFORMERS

    A transformer is a device that transfers electrical energy from one circuit to another

    through inductively coupled conductorsthe transformer's coils. A varying current in the first

    or primary winding creates a varying magnetic flux in the transformer's core, and thus a

    varying magnetic field through the secondary winding.

    It is the costliest equipment in a substation and important from the view of station layout.

    One of the governing factors affecting the layout of a substation is that weather the transformer is

    a 3 phase transformer or a bank of 3 single phase transformers. The space requirement with bank

    of 3 single phase transformers is much more than a single 3 phase transformer. In case of a 3

    single phase unit it is normal to provide one spare single phase transformer to be used in case of

    a fault or if one of the single phase transformer is under maintenance. On account of large

    dimensions it is very difficult to accommodate two transformers in adjacent bays. In order to

    reduce the risk of spread of fire, large transformers are provided with stone pebble filled soaking

    pits and oil collecting pits.

    With transformers, however, the high cost of repair or replacement, and the possibility of a

    violent failure or fire involving adjacent equipment, may make limiting the damage a major

    objective. The protection aspects of relays should be considered carefully when protecting

    transformers. Faults internal to the transformer quite often involve a few turns. While the

    currents in the shorted turns are large in magnitude, the changes of the currents at the terminals

    of the transformer are low compared to the rating of the transformer.

  • 28

    Figure 8

    Instrument Transformer:

    They are devices used to transform voltage and current in the primary system to values suitable

    for measuring instruments, meters, protective relays etc.

    They are basically the current transformers and voltage transformers.

    a) Current transformers: It may be of bushing or wound type. The bushing types are

    normally accommodated within the transformer bushing and the wound types are

    separately mounted. When current in a circuit is too high to directly apply to measuring

    instruments, a current transformer produces a reduced current accurately proportional to

    the current in the circuit, which can be conveniently connected to measuring and

    recording instruments.The CT is typically described by its current ratio from primary to

    secondary.

  • 29

    b) Voltage transformers: It may be either capacitive type or electromagnetic type. The

    electromagnetic type VTs are more expensive than capacitive type and are used where

    higher accuracy is required. Capacitive type is usually preferred at high voltages due to

    lower cost and secondly because it serves the purpose of coupling capacitor for the power

    line carrier equipment. Voltage transformers are usually connected on the feeder side of

    the circuit breaker. However they are also connected on the bus bar side for

    synchronization. They step down extra high voltage signals and provide a low

    voltage signal, for measurement or to operate a protective relay.

    c) Capacitive Voltage Transformer (CVTs): In combination with wave traps are used for

    filtering high frequency communication signals from power frequency. This forms a

    carrier communication network throughout the transmission network.

    TAP CHANGER

    A device used to increase or decrease a transformer's voltage to alter the level of current it can

    draw (tap) from the circuit supplying electricity. Changing the tap of a transformer or regulator

    serves the same function in an electrical circuit as turning the tap handle of a water faucet serves

    to adjust water flow.

  • 30

    BUS-BARS

    In electrical power distribution, a bus bar is a thick strip of copper or aluminum that

    conducts electricity within a switchboard, distribution board, substation or other electrical

    apparatus. Bus bars are used to carry very large currents, or to distribute current to multiple

    devices within switchgear or equipment. Bus bars are typically either flat strips or hollow tubes

    as these shapes allow heat to dissipate more efficiently due to their high surface area to cross

    sectional area ratio.

    The size of the bus bar is important in determining the maximum amount of current that can be

    safely carried.

    Bus bar may either be supported on insulators, or else insulation may completely surround it.

    Bus bars are protected from accidental contact either by a metal enclosure or by elevation out of

    normal reach. Bus bars may be connected to each other and to electrical apparatus by bolted or

    clamp connections.

    Various Bus bar Schemes

    Single Bus

    Single Bus with Bus Section

    Main & Transfer Bus.

    Double Bus.

    Main 1, Main 2 & Transfer Bus

    CIRCUIT BREAKER

    A circuit breaker is an automatically operated electricalswitch designed to protect an electrical

    circuit from damage caused by overload or short circuit. Its basic function is to detect a fault

    condition and, by interrupting continuity, to immediately discontinue electrical flow. Unlike a

    fuse, which operates once and then has to be replaced, a circuit breaker can be reset (either

  • 31

    manually or automatically) to resume normal operation. Circuit breakers are made in varying

    sizes, from small devices that protect an individual household appliance up to large switchgear

    designed to protect high voltage circuits feeding an entire city.

    The type of the Circuit Breaker is usually identified according to the medium of arc extinction.

    The classification of the Circuit Breakers based on the medium of arc extinction is as follows:

    Air break Circuit Breaker. (Miniature Circuit Breaker).

    Oil Circuit Breaker (tank type of bulk oil)

    Minimum oil Circuit Breaker.

    Air blast Circuit Breaker.

    Vacuum Circuit Breaker.

    Sulphur hexafluoride Circuit Breaker. (Single pressure or Double Pressure).

  • 32

    ISOLATOR

    In electrical systems, an isolator switch is used to make sure that an electrical circuit is

    completely de-energized for service or maintenance. Such switches are often found in electrical

    distribution and industrial applications where machinery must have its source of driving power

    removed for adjustment or repair. High-voltage isolation switches are used in electrical

    substations to allow isolation of apparatus such as circuit breakers and transformers, and

    transmission lines, for maintenance.

    An isolator can open or close the circuit when either a negligible current has to be broken or

    made or when no significant voltage change across the terminals of each pole of isolator occurs.

    It can carry current under normal conditions and can carry short circuit current for a specified

    time. They can transfer load from one bus to another and also isolate equipments for

    maintenance. Isolators guarantee safety for the people working on the high voltage network,

    providing visible and reliable air gap isolation of line sections and equipment. They are basically

    motorized i.e. motor does the closing and opening of the isolator.

    Isolators are distinguished as off load and on load isolator

    Figure 9

    ISOLATORS IN A SUBSTATION

  • 33

    EARTHING

    The function of an earthing system is to provide an earthing system connection to which

    transformer neutrals or earthing impedances may be connected in order to pass the

    maximum fault current. The earthing system also ensures that no thermal or mechanical

    damage occurs on the equipment within the substation, thereby resulting in safety to

    operation and maintenance personnel. The earthing system also guarantees equipotential

    bonding such that there are no dangerous potential gradients developed in the substation.

    In designing the substation, three voltages have to be considered.

    1. Touch Voltage: This is the difference in potential between the surface potential and

    the potential at an earthed equipment whilst a man is standing and touching the earthed

    structure.

    2. Step Voltage: This is the potential difference developed when a man bridges a

    distance of 1m with his feet while not touching any other earthed equipment.

    3. Mesh Voltage: This is the maximum touch voltage that is developed in the mesh of

    the earthing grid.

    RELAYS

    A relay is an electrically operated switch. Many relays use an electromagnet to operate a

    switching mechanism mechanically, but other operating principles are also used. Relays

    are used where it is necessary to control a circuit by a low-power signal (with complete

    electrical isolation between control and controlled circuits), or where several circuits

    must be controlled by one signal.

    Relays with calibrated operating characteristics and sometimes multiple operating coils

    are used to protect electrical circuits from overload or faults; in modern electric power

    systems these functions are performed by digital instruments still called "protective

    relays".

    Types of relays:

  • 34

    Electromagnetic attraction relay

    Electromagnetic induction relay

    Thermal relay

    Buchholz relay

    Numerical relay

    Over current relay

    Control and relay panel

    Control and relay panel of a grid substation has all controls, indications, meters and

    protective relays mounted on the front. These panels are free-standing, floor mounting

    type suitable chambers for indoor installation. Panels are rigid structural frames enclosed

    completely with smooth finished rolled sheet steel. In every grid of BYPL the

    instruments operate at 220V DC supply. The standard voltages of a grid are 220V DC

    and 48V DC.

    Thus, to supply 220V DC separate battery charger rooms are set up in the grid. DC is

    supplied to avoid the failure of instruments in the absence of AC supply. Thus for

    continuous operation of the grid DC is supplied to all instruments in a C & R panel.

  • 35

    Figure 10

    Multifunction meters

    The MFM is an IED that can calculate values once the inputs from the secondary of the

    CTs and PTs have been given. Each MFM is dedicated to a particular panel, be it,

    outgoing or incoming. The MFM calculates and displays values on a hand held

    programming and display unit. These values depend on the programmed primary value

    corresponding to the CT and PT ratio, pertaining to that feeder.

    There is a communication port available for each MFM. It uses the RS 485 connection

    scheme. The communication ports of five MFMs are looped. It is extended to the front

    face of an SLI card through a cable. A maximum of 32 MFMS can be connected to one

    single cable. The cable is then terminated at the A and B ports of the SLI cards, using an

    RJ45 jack. In order to terminate the cable in port 1 and 2 of the SLI card, we have to

    make use of a converter, which converts the RS 485 into a RS232 scheme.

  • 36

    The various values given by MFM (Multi Function Meter) which is the IED in this case

    are:

    R phase Current (A)

    Y phase Current (A)

    B phase Current (A)

    R-Y phase Voltage (V)

    B-R phase Voltage (V)

    Y-B phase Voltage (V)

    Active Power (W)

    Reactive Power (VA)

    Power Factor

    Maximum Demand (W)

    Capacitor Banks

    A capacitor (originally known as condenser) is a passivetwo-terminalelectrical

    component used to store energy in an electric field. The forms of practical capacitors vary

    widely, but all contain at least two electrical conductors separated by a dielectric

    (insulator); for example, one common construction consists of metal foils separated by a

    thin layer of insulating film. Capacitors are widely used as parts of electrical circuits in

    many common electrical devices.

    When there is a potential difference (voltage) across the conductors, a static electric field

    develops across the dielectric, causing positive charge to collect on one plate and

    negative charge on the other plate. Energy is stored in the electrostatic field. An ideal

    capacitor is characterized by a single constant value, capacitance, measured in farads.

    This is the ratio of the electric charge on each conductor to the potential difference

    between them.

  • 37

    The capacitance is greatest when there is a narrow separation between large areas of

    conductor, hence capacitor conductors are often called "plates," referring to an early

    means of construction. In practice, the dielectric between the plates passes a small

    amount of leakage current and also has an electric field strength limit, resulting in a

    breakdown voltage, while the conductors and leads introduce an undesired inductance

    and resistance.

    Capacitors are widely used in electronic circuits for blocking direct current while

    allowing alternating current to pass, in filter networks, for smoothing the output of power

    supplies, in the resonant circuits that tune radios to particular frequencies, in electric

    power transmission systems for stabilizing voltage and power flow, and for many other

    purposes.

    Figure 11

    capacitor bank

  • 38

    Battery Charger

    In a protection system it is necessary that control DC voltage shall remain always

    constant for as much time as possible, so that system works without interruptions. The

    charger is a rectifier which whichproduces slightly higher voltage compared to the

    nominal cell voltage of a battery. The main source is derived from the normally available

    AC source which is rectified by the charger.

    Here the battery is combination of multiple cells connected ion series to get the nominal

    DC tripping/control voltage required for the operation of relays and breakers and could

    be from 24V to 220 V depending on loads and capacity requirements

    Figure 12

    Lightening arrestors

    A lightning arrester is a device used on electrical power systems and telecommunications

    systems to protect the insulation and conductors of the system from the damaging effects

  • 39

    of lightning. The typical lightning arrester has a high-voltage terminal and a ground

    terminal. When a lightning surge (or switching surge, which is very similar) travels along

    the power line to the arrester, the current from the surge is diverted through the arrestor,

    in most cases to earth.

    In telegraphy and telephony, a lightning arrestor is placed where wires enter a structure,

    preventing damage to electronic instruments within and ensuring the safety of individuals

    near them. Smaller versions of lightning arresters, also called surge protectors, are

    devices that are connected between each electrical conductor in power and

    communications systems and the Earth. These prevent the flow of the normal power or

    signal currents to ground, but provide a path over which high-voltage lightning current

    flows, bypassing the connected equipment. Their purpose is to limit the rise in voltage

    when a communications or power line is struck by lightning or is near to a lightning

    strike.

    If protection fails or is absent, lightning that strikes the electrical system introduces

    thousands of kilovolts that may damage the transmission lines, and can also cause severe

    damage to transformers and other electrical or electronic devices. Lightning-produced

    extreme voltage spikes in incoming power lines can damage electrical home appliances.

  • 40

    Figure 13

  • 41

    CHAPTER-3

    Basics of RTU &

    SCADA Adaptation

    Remote Terminal Unit

    The RTU or the Remote Terminal Unit is one of the components that comprise the

    SCADA system. It gathers information that is present in the field or substation and sends it to the

    Master Control Center (MCC). Similarly, it executes the command that come from the MCC. So,

    we can say it is a two-way communication device that keeps updating the status of the field

    continually and simultaneously executing the commands from the MCC.

    RTU panels are divided into three parts one is RTU panel, 2nd

    is MFM panel and 3rd

    is

    marshalling panel. Housing a stack of racks with electronic cards is called the RTU Panel.

    Housing of only the MFMS or Multifunction Meters, called the MFM panel. The marshalling

    panel is a junction which provides the connections of field signals to RTU .

  • 42

    Figure 14

    The RTU panel consists of a Basic Rack&Extension Racks

  • 43

    Figure 15

    Basic Rack: - The Basic rack or the Communication Rack houses the brain of the RTU. It

    consists of nine slots. Into these slots are inserted a set of Cards. The Cards are the CPUs of

    the RTU. They help in coordinating the flow of data from and into the RTU. These CPUs are

    basically of two types.

    1. SLI (Serial Line Interface) Cards

    2. ETH (Ethernet) Cards

    Figure 16

    SLI (Serial Line

    Interface) Card

  • 44

    Figure 17

    Ethernet Card

    The SLI Card acts as an interface between the RTU and the IEDs (Intelligent Electronic Devices)

    like protection relays, multifunction meters, digital RTCC and battery charger.

    SLI continually reads data from the IEDs. These IEDs could either be Numerical Relays

    mounted on the CR Panel or an MFM placed on the MFM panel of the RTU It is generally

    placed in a slot of the Basic Rack. The SLI card has got a provision for communicating with the

    IEDs through four ports, A, B, 1 and 2. The port A and B are of the RS485 type where 1 and 2

    are of the RS232. The SLI card has an serial MMI port for communicating with PC.

    The ETH card controls the process events and communications with the Control Centers. It

    continually reads the data from the Extension Racks, the SLI cards and sends it to the control

    center. The ETH card has a port marked by E used by the RTU to communicate to the Master

    control center. The either ports marked by A & B may use to connect the communication

    from extension rack. Generally in our configuration port B using for this purpose. Similar as

  • 45

    SLI card It also has an serial MMI port for communication with PC or Lap-Top for

    configuration and diagnosis purpose.

    The ETH and the SLI cards communicate with each other through a dedicated communication

    channel present on the back plane of the Basic Rack.

    Figure 18

    Extension Racks: - The Extension rack is a place, where Input/output Modules are placed.

    Similar to the structure of the Basic Rack, the Extension rack has 19 slots into which the I/O

    modules can be inserted. The extension rack communicates only with the ETH card of the Basic

    Rack.

    In cases where there are more than one extension rack, each communication port of the extension

    rack is looped with the one succeeding it.

    As mentioned before, the extension rack is connected to the ETH Card through port A or B,

    called COM A and COM B.

  • 46

    The function of the Input Modules is to send the status of the equipment present in the grid

    station to the MCC. Where as the function of the output modules is to control the status of the

    equipment from the MCC. Thus, we see that the flow of data, in the case of input modules, is

    from RTU to MCC and from MCC to RTU in the case of Output modules.

    The different type of I/O modules used are the

    DI cards 23BE21

    AI cards 23AE21

    DO cards. 23BA20

    Figure 19

  • 47

    Figure 20

    Figure 21

    The DI cards have 16 channels, which can be used for connecting the status of field devices as an

    indication to MCC. If one takes a look at the front face of the DI card, who can see 16 LEDs,

    Each LED indicates ON/OFF status of a input connected to particular channel of the DI card.

  • 48

    The AI card on the other hand gives the analog value of the signal. It has 8 channels on which

    eight signals can be configured. The input to a channel in the AI card is a 4-20ma dc current,

    which is proportional to the range of the analog value.

    The DO card is used to execute commands that are sent from the MCC. As soon as the DO card

    gets a command from the MCC, it sends a pulse of 48v dc to the exciting terminals of the

    contactor(CMR). As soon as the contactor gets this pulse it closes its contacts and the command

    gets executed.

  • 49

    Figure 22

    *

  • 50

    Communication Equipment:

    Figure 23

    The way the SCADA system network (topology) is set up can vary with each system but

    there must be uninterrupted, bidirectional communication between the MTU and the RTU

    for a SCADA or Data Acquisition system to function properly. This can be accomplished

    in various ways, i.e. private wire lines, buried cable, telephone, radios, modems,

    microwave dishes, satellites, or other atmospheric means, and many times, systems

    employ more than one means of communicating to the remote site. This may include

    dial-up or dedicated voice grade telephone lines, DSL (Digital Subscriber Line),

    Integrated Service Digital Network (ISDN), cable, fiber optics, WiFi, or other broadband

    services.

    There are many options to consider when selecting the appropriate communication

    equipment and can include either a public and/or private medium. Public medium is a

    communication service that the customer pays for on a monthly or per time or volume

    use. Private mediums are owned, licensed, operated and serviced by the user. If you

    choose to use a private medium, consider the staffing requirements necessary to support

    the technical and maintenance aspects of the system.

  • 51

    Private Media Types:

    Private Wire

    This type of media usually is limited to low bandwidth modems.

    Wireless

    (Spread Spectrum Radio)

    This media type is license-free and available to the public in the 900 MHz and 5.8GHz

    bands. The higher the frequency used in the system, the more "line of sight" it becomes.

    Microwave Radio

    Microwave radio transmits at high frequencies through parabolic dishes mounted on

    towers or on top of buildings. This media uses point-to-point, line-of-sight technology

    and communications may become interrupted at times due to misalignment and/or

    atmospheric conditions.

    VHF/UHF Radio

    Good for up to 30 miles, VHF/UHF radio is an electromagnetic transmission with

    frequencies of 175MHz-450MGz-900MHz received by special antennas. A license from

    the FCC must be obtained and coverage is limited to special geographical boundaries.

    Public Media Types:

    (Telephone Company)

    There are different services that your local telephone company can provide including:

    Switched Lines, Private Leased Lines, Digital Data Service, Cellular and PCS/CDPD.

  • 52

    Switched Lines: Public Switch Telephone Network (PSTN) and Generally Switched

    Telephone network (GSTN) are dial-up voice and data transmission networks furnished

    by your local telephone company.

    Private Leased Lines: Private Leased Lines (PLL) are permanently connected 24 hours a

    day between two or more locations and used for analog (continuously varying signal)

    data transmission.

    Digital Data Service: Digital Data Service (DDS) is a private leased line with a special

    bandwidth used to transfer data at a higher speed and lower error rate. This service is

    applicable for computer-to-computer links.

    Cellular: This service is equivalent to Switched Line services over landlines.

    PCS/CDPD: This service is provided by cellular companies on a monthly fee or traffic

    volume basis and is used when continuous communication is needed.

    Other Media Types:

    (WiFi-SMR)

    Sometimes it makes sense to use the infrastructure of another company. WiFi equipment

    utilizes broadband with high data rates and is used in a "time-share" basis to

    communicate between sites of the system. This media type generally requires advanced

    protocols like TCP/IP and network type connections.

    (Satellite-Geosychronous/LEO)

    Geosynchronous satellite's orbits are synchronous with the earth's orbit and remain in the

    same position with respect to the earth. These satellites use high frequency transmissions

    received by parabolic dish antennas. Low Earth Orbit (LEO) satellites hand off signals to

  • 53

    other satellites for continuous coverage and latency times are less than geosynchronous

    satellites due to the lower orbit.

  • 54

    3.1 SCADA Applications:

    Following are the main application commonly used.

    Network Connectivity Analysis (NCA)

    State Estimation (SE)

    Load Flow Application (LFA)

    Voltage VAR control (VVC)

    Load Shed Application (LSA)

    Fault Management and System Restoration (FMSR)

    Loss Minimization via Feeder Reconfiguration (LMFR)

    Load Balancing via Feeder Reconfiguration (LBFR)

    Operation Monitor (OM)

    Distribution Load forecasting (DLF)

    Network Connectivity Analysis (NCA):

    The network connectivity analysis function provides the connectivity between various

    network elements. The prevailing network topology will be determined from the status of

    all the switching devices such as circuit breaker, isolators etc. that affects the topology of

    the network modeled.

    NCA runs in real time as well as in study mode. Real-time mode of operation uses data

    acquired by SCADA. Study mode of operation will use either a snapshot of the real-time

    data or save cases. NCA can run in real time on event-driven basis.

    The network topology of the distribution system will be based on

    Tele-metered switching device statuses

    Manually entered switching device statuses.

  • 55

    Modeled element statuses from DMS applications.

    The NCA will be useful in determining the network topology for the following status of

    the network.

    Bus connectivity (Live/ dead status)

    Feeder connectivity

    Network connectivity representing S/S bus as node

    Energized /de-energized state of network equipment

    Representation of Loops (Possible alternate routes)

    Representation of parallels

    Abnormal/off-normal state of CB/Isolators

    The NCA also assists the power system operator to know the operating state of the

    distribution network indicating radial mode, loops and parallels in the network.

    Distribution networks which are normally operated in radial mode; loops and/or parallel

    may be intentionally or inadvertently formed.

    State Estimation (SE)

    The State Estimation (SE) is used for assessing (estimating) the distribution network

    state. It shall assess loads of all network nodes, and, consequently, assessment of all other

    state variables (voltage and current phasors of all buses, sections and transformers, active

    and reactive power losses in all sections and transformers, etc.) in the Distribution

    network.

  • 56

    Load Flow Application (LFA)

    In Power system the quantities of electrical real & reactive power and Voltages are

    complex quantities and the equations linking them are non-linear. At the load centres

    (buses) the quantities of power both real & reactive will be known and at the power

    generating points the real power and Voltage magnitudes will be available. The Load

    flow analysis helps to evaluate the unknown quantities at all the buses for a given

    network topology.

    The Load Flow function shall provide real/active and reactive losses on:

    Station power transformers , Feeders, sections, Distribution circuits including feeder

    regulators and distribution transformers, as well as the total circuit loss, Phase voltage

    magnitudes and angles at each node. Phase and neutral currents for each feeder ,

    transformers, section.

    Total three phases and per phase KW and KVAR losses in each feeder, section,

    transformer, DT substation & for project area

    Active & reactive power flows in all sections, transformers List of overloaded feeder,

    lines, bus bars, transformers loads etc. including the actual current magnitudes, the

    overload limits and the feeder name, substation name

    List of limit violations of voltage magnitudes, overloading. Voltage drops and The LFA

    utilizes information including real-time measurements, manually entered data, and

    estimated data together with the network model supplied by the topology function, in

    order to determine the best estimate of the current network state.

    The Load Flow Application (LFA) determines the operating status of the distribution

    system including buses and nodes. The LFA shall take the following into consideration

    the following information:

    Real time data

  • 57

    Manual entered data

    Estimated data

    Power source injections

    Loops and parallels

    Unbalanced & balanced loads

    Manually replaced values

    Temporary jumpers/ cut/ grounds

    Electrical connectivity information from the real-time distribution network model

    Transformer tap settings

    Generator voltages, real and reactive generations.

    Capacitor/reactor bank ON/OFF status value.

    The LFA function can be executed at pre-defined events that affect the distribution

    system. Some of the events the dispatcher may choose for triggers shall include:

    Power system Topology Change i.e. Alteration in distribution system configuration.

    Transformer Tap Position Change / Capacitive/reactor MVAR Change.

    Feeder Over loadings.

    Sudden change in feeder load beyond a set dead band

    Volt VAR control (VVC)

    In electrical power system the reactive power can be generated at source generators or

    can be injected at the substations through Volt-var systems. It is more appropriate to

    inject at substations rather than producing then at generator points and transporting them

    over long distances. Any power system always tries to optimize on the reactive power

    flow over their networks.

  • 58

    The coordination of voltages and reactive power flows control requires coordination of

    VOLT and the VAR function. This function shall provide high-quality voltage profiles,

    minimal losses, controlling reactive power flows, minimal reactive power demands from

    the supply network.

    The following resources should be taken into account in any voltage and reactive power

    flow control:

    TAP Changer for voltage control

    VAR control devices: switchable and fixed type capacitor banks.

    Load Shed Application (LSA)

    The power delivery to the consumers is also bogged down with the Demand-Supply

    problems, with demand being always higher than supply. The reasons for less Supply are

    several including the faults, tripping of lines. In these situations the power system

    operator tries to Distribute available power

    through Shedding of loads to consumers over small definite periods till he tides over the

    situation of loss of power.

    The load-shed application helps to automate and optimize the process of selecting the

    best combination of switches to be opened and controlling in order to shed the desired

    amount of load. Given a total amount of load to be shed, the load shed application shall

    recommend different possible combinations of switches to be opened, in order to meet

    the requirement. The dispatcher is presented with various combinations of switching

    operations, which shall result in a total amount of load shed, which closely resembles the

    specified total. The dispatcher can then choose any of the recommended actions and

    execute them.

    In case of failure of supervisory control for few breakers, the total desired load

    shed/restore will not be met. Under such conditions, the application will inform the

    dispatcher the balance amount of load to be shed /restore. The load-shed application runs

    again to complete the desired load shed /restore process.

  • 59

    Fault Management & System Restoration (FMSR) Application

    The availability of data related to the breakers/ switches and the level of The Fault

    current flowing in the networks helps one to Manage & Restore the System in an event of

    fault. This application helps to provide the assistance to the power system dispatcher for

    detection, localization, isolation and restoration of distribution system after a fault in the

    system has occurred with the help of operating through the supervisory control available

    on SCADA. The devices which help in localization & isolation of the fault include Auto

    Reclosures (AR), Sectionalisers, Fault Passage Indicators etc. The operation &

    characteristics of these devices are separately addressed in the SCADA section.

    Loss Minimization via Feeder Reconfiguration (LMFR)

    The switching operation during fault and requirement to supply power through alternate

    feeders in the distribution network modifies the feeder configuration topology. The

    information of network topology and availability of adjacent feeder networks can be

    useful in right selection of feeders with overall aim of reducing the line losses and

    maximum power delivery to consumers.

    This function identifies the opportunities to minimize technical losses in the distribution

    system by reconfiguration of feeders in the network for a given load scenario. The

    technical losses are the losses created by characteristic of equipment & cable such as

    efficiency, impedance etc.

    The function helps in calculation of the current losses based on the loading of all

    elements of the network. The Telemeter values, which are not updated due to telemetry

    failure, can also be considered by LMFR application based on arriving at the

    recommendations of LF Application. The LMFR application can be utilized to have the

    various scenarios for a given planned & unplanned outages, equipment operating limits,

    tags placed in the SCADA system while recommending the switching operations.

    Load Balancing via Feeder Reconfiguration (LBFR)

  • 60

    The discussions had on previous topic can be used for the Load Balancing via Feeder

    Reconfiguration for the optimal balance of the segments of the network that are over &

    under loaded. This helps in better utilization of the capacities of distribution facilities

    such as transformer and feeder ratings.

    The Feeder Reconfiguration Function can be used also to have a scenario on an overload

    condition, unequal loadings of the parallel feeders and transformers, periodically or on

    demand in the network by the dispatcher. The system will help generate the

    switchingsequence to reconfigure the distribution network for transferring load from

    some sections to other sections. The LBFR application can even consider the planned &

    unplanned outages, equipment operating limits, tags placed in the SCADA system while

    recommending the switching operations.

    The function helps in distributing the total load of the system among the available

    transformers and the feeders in proportion to their operating capacities, considering the

    discreteness of the loads, available switching options between the feeder and permissible

    intermediate overloads during switching. The dispatcher can have the options to simulate

    switching operations and visualize the effect on the distribution network by comparisons

    based on line loadings, voltage profiles, load restored, system losses, number of affected

    customers.

    Load Forecast (LF)

    The Distribution Automation system keeps logging data periodically of the network. This

    historical database and weather conditions data collected over a period can be used for

    prediction and to have forecasting of the requirement of consumer loads. Generally there

    are two types of forecasting that are resorted too.

    Short-Term Load Forecasting (STLF) will be used for assessment of the sequence of

    average electrical loads in equal time intervals, from 1 to 7 days ahead. The Long term

    forecasting is used for forecasting load growths over longer durations. The fore casting

    techniques are based on different forecasting methods such as Autoregressive, Least

    Squares Method, Time Series Method, Neural, Kalman filter and Weighted Combination.

  • 61

    CHAPTER 4:

    FINANCIAL MODELING (SOLAR PV PLANT)

    5.1 Introduction

    Renewable power generation capacity in India has been set up largely through private sector

    investments. New investment is the most potent indicator of growth of the sector. As per an

    estimate, in 2009 the total financial investment in clean energy in India was at INR 135 billion.

    India ranked the ninth most attractive country for renewable energy investment in the world,

    behind the United States, China, and Germany.35

    But highly aggressive bidding by developers in

    increasing fierce competitive environment and uncertainty regarding the various costs incurred;

    increases the risk associated with making an investment in setting up solar power plant.

    A financial model helps the developer to explore in detail the financial benefits and costs

    associated with the investment. This facilitates the identification of key variables affecting the

    project value and enables financing decisions.The following section describe the key items and

    assumptions that are included in the financial modeling of a typical Indian solar PV project, and

    discusses the conclusions based on the calculation of various financial parameters.

    5.2 Assumptions

    Capital Costs

    The normative capital cost for setting up Solar Photovoltaic Power Project shall be 1000

    Lakh/MW for FY 2012-13 as per CERC (Terms and Conditions for Tariff determination from

    Renewable Energy Sources) Regulations, 2012. But the recent drop in module cost accompanied

    by increase in level of competition has dragged down the overall project cost quite substantially.

  • 62

    Operations and Maintenance (O&M) Cost

    One of the major benefits of Solar PV power plants is less O&M costs as compared to other

    renewable energy technologies. In the financial model O&M has been taken as per prevailing in

    the industry.

    Annual Energy Yield

    There are a number of factors (e.g. Air pollution, shading, soiling, ambient temperature, module

    quality, DC cable resistance, invertor performance, AC losses, downtime etc.) which affect the

    annual energy yield of a solar PV project. The confidence level of the yield forecast is important,

    as the annual energy yield directly affects the annual revenue. The energy yield prediction

    provides the basis for calculating project revenue. The aim of an energy yield analysis is to

    predict the average annual energy output for the lifetime of the proposed power plant. Typically,

    a 25 to 30 year lifetime is assumed. Energy yield prediction reports should consider and (ideally)

    quantify each of these losses. In the financial model energy yield prediction for 25 years is made

    taking into account annual deration.

    Energy Price

    Besides the power generated, the solar PV project revenue is dependent upon the power price.

    This may be fixed or variable according to the time of day or year, and must be clearly stipulated

    in the power purchase agreement. Economic return has historically been the key limiting factor

    for development of large scale grid-connected solar PV projects. PV has a high initial capital

    cost. High energy prices are required for projects to be economic. Currently, grid-connected solar

    projects are highly dependent on policy support initiatives such as grants, feed-in tariffs,

    concessional project funding and mandatory purchase obligations.

  • 63

    The financial model has been made with flexibility to know various financial indicators with 3

    power selling options:

    1. Selling to State Discom at APPC.

    2. Selling through open access to HT consumer.

    3. Selling to power exchange at a market determined price.

    Certified Emission Reductions (CERs)

    As India is a non-Annex 1 party under the UN Clean Development Mechanism (CDM),

    qualifying Indian solar projects could generate Certified Emission Reductions (CERs). These

    CERs can then be sold to Annex 1 parties and help them comply with their emission reduction

    targets. This effectively causes transference of wealth from Annex 1 parties such as the UK and

    Germany to Indian developers.

    Each CER is equivalent to the prevention of one tonne of carbon dioxide emissions. The income

    from CERs can be substantial. However, this revenue source cannot be predicted as it is

    uncertain whether the project will be accredited. Moreover, CER values fluctuate considerably.

    The National CDM Authority under the Ministry of Environment and Forests (MoEF) is the

    designated authority in India for approving CDM projects. The model has the flexibility of

    taking into account approximate revenue from sale of CERs

    Financing Assumptions

    The project financing structure generally comprises of debt and equity.The general financial

    assumptions for a project in India are as follows:

  • 64

    Financing structure equity 30% and debt 70% as assumed in CERC tariff order.

    Debt repayment period 10-12 years (approx.).

    The following table shows assumptions taken for calculation in financial model.

    Table 2

    Plant Details

    Installed Capacity MW 5

    CUF % 17.12%

    Annual Deration % 0.75%

    AUX % 0.25%

    Useful Life Years 25

    Table 3

    Capital Structure

    Debt % 70%

    Equity % 30%

    Total Debt Amount Mn 325.7062147

    Total Equity Amount MN 139.5883777

    Project Cost INR Mn/MW INR Mn

    EPC 80 400

    Land 5 25

    Development Cost 3.5 17.5

    IDC 22.79459241

    Total project Cost 465.2945924

    Table 4

  • 65

    Table 5

    CDM Benefits No Yes

    CERs per MU 950

    Rate per CER Euro 4

    1 Euro INR 66.16

    Rate per CER INR 264.64

    Estimated Period of Availability Years 10

    80 IA Benefit (1="Yes", 2="No") 1

    UNFCCC Adaptation Fee 2.00%

    Revenue Retained (in 1st year) 100%

    Incremental Share of Beneficiary (p.a.) 10%

    Min. Retained Revenue 50%

    Table 6

    Taxes

    Basic Tax 30%

    Add: Surcharge 5.00%

    Add: Cess 3%

    Net Corporate Tax 32.45%

    0.00%

    Min. Alternate Tax 18.50%

    Add: Surcharge 5.00%

    Add: Cess 3.00%

    Net MAT 20.01%

    Start Year Year

    Tax Exemption u/s 80 IA 8 10 100.00%

  • 66

    Table 7

    Debt Schedule

    Loan Amount Mn 325.71

    Moratorium Period No. Of Quarters 0

    Repayment Period Years 7

    Repayment Period (Incl Moratorium) Years 7

    Repayment Style Quaterly

    Interest on Term Loan 13%

    Interest on WC 12%

    Table 8

    Const. Time Table

    Construction Start Date 1-Apr-12

    Time in

    Construction Months 12

    COD 1-Apr-13

    Misc.

    Land

    appreciating @ p.a. 5%

    Discount Rate 20.00%

  • 67

    Working

    Capital

    O&M Charges Months 1

    Receivables for Debtors Months 1

    Maintenance

    Spare (% O&M Exp.) 15%

    WC Loan 100%

    Depreciation

    Companies Act

    Depreciation Rate for first

    10 years per annum 5%

    Aggregate Dep. in first 10

    years % 50%

    Total allowed Depreciable

    Value % 100%

    Depreciation Rate from 11 year

    onwards

    %

    p.a. 3.33%

    Income Tax

    Act

    Depreciation

    Rate

    on

    WDV 80%

  • 68

    REC

    Control Period Ending

    on -->

    1-Apr-

    12 1-Apr-17 1-Apr-22

    1-Apr-

    27 1-Apr-32

    1-Apr-37 1-Apr-

    42

    % Reduction in Price 20% 100% 25% 25% 25%

    Forbearance

    Price

    (Rs/KWh

    ) 17 13.4 10.72 0 0 0 0

    Floor Price

    (Rs/KWh

    ) 12 9.3 7.44 0 0 0 0

    Note: The model is developed with flexibility to change the input field in cells with back ground

    color

    5.3 Project Economics and Financial Indicators

    Project financial model calculates a range of project value indicators in order to allow

    developers, lenders, investors and relevant government bodies to assess the project economics

    from several perspectives.

    From an investors point of view, a project is generally considered to be a reasonable investment

    only if the internal rate of return (IRR) is higher than the weighted average cost of capital

    (WACC). Investors will have access to capital at a range of costs; the return arising from

    investment of that capital must be sufficient to meet the costs of that capital. Moreover, the

    investment should generate a premium associated with the perceived risk levels of the project.

  • 69

    Solar projects are usually financed with equity and debt components. As a result, the IRR for the

    equity component can be calculated separately from the IRR for the project as a whole. The

    developers decision to implement the project or not, will be based on the equity IRR.

    As returns generated in the future are worth less than returns generated today, a discount can be

    applied to future cash flows to present them at their present value. The sum of discounted future

    cash flows is termed the net present value (NPV). Investors will seek a positive NPV, assessed

    using a discount rate that reflects the WACC and perceived risk levels of the project.

    Lenders will be primarily concerned with the ability of the project to meet debt service

    requirements. This can be measured by means of the debt service coverage ratio (DSCR), which

    is the cash flow available to service debt divided by the debt service requirements. The Average

    DSCR represents the average debt serviceability of the project over the debt term. A higher

    DSCR results in a higher capacity of the project to service the debt. Minimum DSCR represents

    the minimum repayment ability of the project over the debt term. A Minimum DSCR value of

    less than one indicates the project is unable to service the debt in at least one year.

    Based on assumptions taken and calculations36

    done in financial model following are values of

    various financial indicators.

    Project Economics

    Project IRR 18.03%

    Equity IRR 21.56%

    Min DSCR 1.027023

    Avg. DSCR 1.2971679

  • 70

    5.4 Sensitivity Analysis

    Sensitivity analysis involves changing the inputs in the financial model (such as power tariff,

    capital cost, interest rate etc.) to analyze how the value of the project changes (measured using

    Net Present Value, Internal Rate of Return, or the Debt Service Cover Ratio).

    Sensitivity analysis gives lenders and investors a greater understanding of the effects of changes

    in inputs on the projects profitability and bankability. It helps them understand the key risks

    associated with the project. Lenders will conduct sensitivity analysis around the key variables in

    order to determine whether the project will be able to service the debt in a bad year, for example

    if energy yield is lower than expected, or operational expenditure is higher than expected.

    Following sensitivity analysis was done

    1. Effect of Time Taken in Construction on financial parameters viz. Project IRR, Equity

    IRR,Minimum DSCR and Average DSCR. The effect can be seen in table below.

    Time in Project Equity Min. Avg.

    IRR IRR DSCR DSCR Const.

    (Months)

    4 18.20% 21.87% 1.0367 1.3039

    5 18.13% 21.74% 1.0327 1.3011

    6 18.03% 21.56% 1.0270 1.2972

    7 17.94% 21.39% 1.0215 1.2933

    8 17.84% 21.22% 1.0161 1.2896

    9 17.75% 21.05% 1.0108 1.2859

    10 17.66% 20.89% 1.0055 1.2823

    11 17.57% 20.73% 1.0004 1.2787

    12 17.49% 20.57% 0.9954 1.2752

  • 71

    16.00% 14.40%

    15.50%

    14.20%

    14.00%

    Pro

    ject

    IR

    R

    Eq

    uit

    y I

    RR

    15.00%

    13.80%

    14.50% 13.60%

    14.00% 13.40%

    13.20%

    13.50%

    13.00%

    13.00% 12.80%

    4 5 6 7 8 9 10 11 12

    Months of Construction

    Equity IRR

    Project

    IRR

    2. Effect of REC trade price on Financial Parameters

    CERC has given Forbearance Price and Floor Price for REC. RECs are traded in power

    exchanges between these two price ranges. But the current Floor and Forbearance price

    is applicable till March 2017. After that REC price is expected to go down.

    Some developers are of the view that once grid parity is achieved the government may with

    draw the mechanism. Though, these are just speculations.

  • 72

    The following table shows the how financial indicators viz. Project IRR, Equity IRR and

    Average DSCR will vary with change in price at which REC would be traded post 2017. It

    is evident that if RECs are traded below a certain level then the projects viability will be

    jeopardized.

    Period From COD 1-Apr-17 1-Apr-22 1-Apr-27 1-Apr-32 1-Apr-37 Project

    IRR

    Equity

    IRR Avg DSCR

    Till 1-Apr-17 1-Apr-22 1-Apr-27 1-Apr-32 1-Apr-37 -

    9.3 7.44 - - - - 18.03% 21.56% 1.29

    REC Trade 9.3 5.58 - - - - 17.42% 20.47% 1.24

    Price 9.3 4.65 - - - - 17.05% 19.80% 1.19

    (Rs/KWh) 9.3 4.65 2.325 - - - 17.45% 20.43% 1.19

    9.3 - - - - - 15.16% 16.59% 0.98

  • 73

    5.5 Limitations of Financial Model

    The financial model (attached) is developed with the solely objective of learning the

    intricacies of financial modeling. Values in various input fields (like Tax Rate, EPC Cost

    etc.) may not be correct.

    The financial model developed is not perfectly flexible. It has some constraints while

    entering the input fields like

    Moratorium Period can be either 0 or 1 or 2 years

    Date of commissioning is hard fixed to be April 1, 2013

    Debt service to bank is done quarterly. Etc.

  • 74

    CHAPTER-5

    CONCLUSION

    All the above implementations are one of their kinds, both plays a very important role in

    increasing the efficiency of the distribution company. The sub clustering of distribution

    transformers provide a greater accuracy in pin pointing the affected area, the area which have to

    be considered more for loss correction method.

    This can result into few goods and beneficial aspect for the auditing division, such as:

    1. It will increase the efficiency of the auditing division.

    2. It will generate a sort of accuracy in data collection.

    3. It can also pin point the area of maximum losses and take the corrective measures to reduce

    these losses.

    The DT automation process provides the complete safeguard from irregularities of DT health

    reports and correction and monitoring of all the distribution transformers. It shall provide

    unparalleled capabilities in monitoring, controlling, optimizing the efficiencies of the energy

    meter. Implementation of an MDMS (Meter Data Management System) and integration of real

    time Transformer data, distribution automation systems provide the information and intelligent

    control necessary to facilitate the field operation remotely. It is an enabler that would foster

    energy efficiency, interaction, proactive decisions and innovative practices to optimize power

    usage. DT reports are very crucial and informative tool in reduction of AT&C losses.

    Though total Payback Period is very high around 30 years, but the system will lead to substantial

    improvement in Quality of supply, reduction of O&M expenses and increased customer

    satisfaction. Energy Audit on real time basis will help in substantial reduction of AT & C Losses.

  • 75

    CHAPTER-7

    REFERENCES

    1. Detail Project Reports of BSES Yamuna

    2. www.indianbusiness.nic.in

    3. www.energywatch.org.in

    4. www.projectmonitor.com

    5. www.investopedia.com

    6. www.cea.nic.in

    7. www.sari-energy.org

    8. www.google.com