Page 1: Work-packages CLIC 2011-2016 for the Drive Beam BJ, 23 feb 2010 Beam Dyn Meeting 2/23/11Beam Dyn meeting1.

Beam Dyn meeting 1

Work-packages CLIC 2011-2016for the Drive Beam

BJ, 23 feb 2010Beam Dyn Meeting

2/23/11

Page 2: Work-packages CLIC 2011-2016 for the Drive Beam BJ, 23 feb 2010 Beam Dyn Meeting 2/23/11Beam Dyn meeting1.

Beam Dyn meeting 2

Sources

Thermo-ionic source Study of the bunching system. Explore removal of satellite bunch population, establish a floor limit.

Photoinjector Explore feasibility, stability & reliability w.r.t. intensity and pulse length

DB Linac

New E_CM energy Adapt the linac to the new CLIC top energy (one or two linacs, length)

Linac RF and operation Stable operation with missing klystrons. Qualification of the RF phase requirements. Collaboration with the RF team for klystron and modulator studies. Participation to studies for alternative power sources.

Collective and beam loading effects

Off-crest acceleration vs. beam loading. Wake-field studies.

2/23/11

Page 3: Work-packages CLIC 2011-2016 for the Drive Beam BJ, 23 feb 2010 Beam Dyn Meeting 2/23/11Beam Dyn meeting1.

Beam Dyn meeting 3

DB Formation

RF deflectors Beam loading and collective effects. Their impact on field quality.

SR & CSR studies Impact of the SR on the vacuum system (vacuum quality, thermal & mechanical issues, fatigue, implications on magnet design). Impact of CSR on beam quality. Combined minimization of SR & CSR impact on beam quality.

Phase synchronization of DB & MB

Specify and quantify the issue. Collaboration with the Timing and RF teams for the design of the phase correction system.

DB dumps Study of the optics line between the end of a decelerator and the dump.Specify the impact map of the beam on the dump. Collaborate to the design of the dump with the EN/STI team.

Turn-arounds Study options for magnets (normal conducting, super-ferric, permanent). Optimize for power consumption, taking into account high SR power deposition.

2/23/11

Page 4: Work-packages CLIC 2011-2016 for the Drive Beam BJ, 23 feb 2010 Beam Dyn Meeting 2/23/11Beam Dyn meeting1.

Beam Dyn meeting 4

Overall DB complex

Beam lines description Further studies and consolidation of the optics.Build an overall description of the beam lines and rings, in order to allow for the definition of a detailed layout, in coordination with the Main Beam

Overall DB

Fast Timing Definition of the fast timing network. Specification of accuracy and stability for the different sub-systems