Work Content Feb 18 2010

7
Work Content - Cycle Time Diagram 2

description

 

Transcript of Work Content Feb 18 2010

Page 1: Work Content Feb 18 2010

Work Content - Cycle Time Diagram2

Page 2: Work Content Feb 18 2010

It is the sum of basic tasks performed at each workstation to obtain a complete and good product.

2

2.1. Work Content

Work Content = 30s + 50s + 40s = 120s

Minimum cycle timesfound in time study :

JOB 1 JOB 2 JOB 3

30s 50s 40s

Finishedpart

Page 3: Work Content Feb 18 2010

It brings out variations between each cycle (variability) and the imbalance among the operators.

3

2.2. Cycle Time Diagram

Time (in s)

0

5

10

15

20

25

30

35

40

45

OP1 OP2 OP3 OP4 OP5

Time (in s)

TAKT TIME TAKT TIME

0

5

10

15

20

25

30

35

40

45

OP1 OP2 OP3 OP4 OP5

Page 4: Work Content Feb 18 2010

4

2.2. Cycle Time Diagram

Page 5: Work Content Feb 18 2010

5

Cycle Time Measurement Form

Page 6: Work Content Feb 18 2010

6

Standardized Work Chart

Page 7: Work Content Feb 18 2010

7

Standardized Work Combination Table