Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and...
-
Upload
thalia-gravitt -
Category
Documents
-
view
234 -
download
2
Transcript of Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and...
![Page 1: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/1.jpg)
Work Breakdown Structures
![Page 2: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/2.jpg)
Define scope of project Identify stakeholders,
decision-makers, and escalation procedures
Develop detailed task list (work breakdown structures)
Estimate time requirements Develop initial project
management flow chart Identify required resources
and budget Evaluate project
requirements
Identify and evaluate risks Prepare contingency plan Identify interdependencies Identify and track critical
milestones Participate in project phase
review Secure needed resources Manage the change control
process Report project status
Fifteen Project Management Job Functions*
![Page 3: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/3.jpg)
Overlap of Process Groups in a Phase (PMBOK® Guide, 2000)
![Page 4: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/4.jpg)
Relationships Among Process Groups and Knowledge Areas (PMBOK® Guide 2000, p. 38)
![Page 5: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/5.jpg)
Relationships Among Process Groups and Knowledge Areas (PMBOK® Guide)
![Page 6: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/6.jpg)
Project Planning
The main purpose of project planning is to guide execution
Every knowledge area includes planning information
Key outputs include: A team contract A scope statement (project charter) A work breakdown structure (WBS) A project schedule, in the form of a Gantt chart with all
dependencies and resources entered A list of prioritized risks
![Page 7: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/7.jpg)
PMI Process Project Gantt Chart
![Page 8: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/8.jpg)
Scope Planning and theScope Statement
A scope statement is a document used to develop and confirm a common understanding of the project scope. It should include a project justification a brief description of the project’s products a summary of all project deliverables a statement of what determines project
success
![Page 9: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/9.jpg)
Scope Planning and the Work Breakdown Structure
After completing scope planning, the next step is to further define the work by breaking it into manageable pieces
Good scope definition helps improve the accuracy of time,
cost, and resource estimates defines a baseline for performance
measurement and project control aids in communicating clear work
responsibilities
![Page 10: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/10.jpg)
List of Prioritized Risks
![Page 11: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/11.jpg)
The Work Breakdown Structure
A work breakdown structure (WBS) is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project
It is a foundation document in project management because it provides the basis for planning and managing project schedules, costs, and changes
![Page 12: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/12.jpg)
Approaches to Developing WBSs
Using guidelines: Some organizations, like the DoD, provide guidelines for preparing WBSs
The analogy approach: Review WBSs of similar projects and tailor to your project
The top-down approach: Start with the largest items of the project and break them down
The bottom-up approach: Start with the detailed tasks and roll them up
Mind-mapping approach: Write down tasks in a non-linear format and then create the WBS structure
![Page 13: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/13.jpg)
Basic Principles for Creating WBSs*
1. A unit of work should appear at only one place in the WBS.2. The work content of a WBS item is the sum of the WBS items
below it.3. A WBS item is the responsibility of only one individual, even
though many people may be working on it.4. The WBS must be consistent with the way in which work is
actually going to be performed; it should serve the project team first and other purposes only if practical.
5. Project team members should be involved in developing the WBS to ensure consistency and buy-in.
6. Each WBS item must be documented to ensure accurate understanding of the scope of work included and not included in that item.
7. The WBS must be a flexible tool to accommodate inevitable changes while properly maintaining control of the work content in the project according to the scope statement.
![Page 14: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/14.jpg)
Sample Intranet WBSOrganized by Product
![Page 15: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/15.jpg)
Sample Intranet Organized by Phase
![Page 16: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/16.jpg)
Intranet WBS in Tabular Form
1.0 Concept1.1 Evaluate current systems1.2 Define Requirements
1.2.1 Define user requirements1.2.2 Define content requirements1.2.3 Define system requirements1.2.4 Define server owner requirements
1.3 Define specific functionality1.4 Define risks and risk management approach1.5 Develop project plan1.6 Brief Web development team
2.0 Web Site Design3.0 Web Site Development4.0 Roll Out5.0 Support
![Page 17: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/17.jpg)
Intranet Project with Gantt Chart
![Page 18: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/18.jpg)
Intranet WBS and Gantt Chart Organized by Project Management Process Groups
![Page 19: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/19.jpg)
Sample Mind-Mapping Approach
![Page 20: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/20.jpg)
Sample Gantt Chart
The WBS is on the left, and each task’s start and finish date are shown on the right using a calendar timescale. Early Gantt Charts, first used in 1917, were drawn by hand.
![Page 21: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/21.jpg)
Sample Network Diagram
Each box is a project task from the WBS. Arrows show dependencies
between tasks. The bolded tasks are on the critical path. If any tasks on thecritical path take longer than planned, the whole project will slip unless something is done. Network diagrams were first used in 1958 on the Navy Polaris project, before project management software was available.
![Page 22: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/22.jpg)
Sample Enterprise Project Management Tool
In recent years, organizations have been taking advantage of softwareto help manage their projects throughout the enterprise.
![Page 23: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/23.jpg)
Project Time Management Processes
Project time management involves the processes required to ensure timely completion of a project. Processes include: Activity definition Activity sequencing Activity duration estimating Schedule development Schedule control
![Page 24: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/24.jpg)
Activity Definition
Project schedules grow out of the basic document that initiate a project Project charter includes start and end
dates and budget information Scope statement and WBS help define
what will be done Activity definition involves developing a
more detailed WBS and supporting explanations to understand all the work to be done so you can develop realistic duration estimates
![Page 25: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/25.jpg)
Activity Sequencing
Involves reviewing activities and determining dependencies Mandatory dependencies: inherent in the
nature of the work; hard logic Discretionary dependencies: defined by
the project team; soft logic External dependencies: involve
relationships between project and non-project activities
You must determine dependencies in order to use critical path analysis
![Page 26: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/26.jpg)
Project Network Diagrams
Project network diagrams are the preferred technique for showing activity sequencing
A project network diagram is a schematic display of the logical relationships among, or sequencing of, project activities
![Page 27: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/27.jpg)
Sample Activity-on-Arrow (AOA) Network Diagram for Project X
![Page 28: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/28.jpg)
Precedence Diagramming Method (PDM)
Activities are represented by boxes Arrows show relationships between
activities Better at showing different types of
dependencies
![Page 29: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/29.jpg)
Task Dependency Types
![Page 30: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/30.jpg)
Sample PDM Network Diagram
![Page 31: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/31.jpg)
Activity Duration Estimating
After defining activities and determining their sequence, the next step in time management is duration estimating
Duration includes the actual amount of time worked on an activity plus elapsed time
Effort is the number of workdays or work hours required to complete a task. Effort does not equal duration
People doing the work should help create estimates, and an expert should review them
![Page 32: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/32.jpg)
Schedule Development
Schedule development uses results of the other time management processes to determine the start and end date of the project and its activities
Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project
Important tools and techniques include Gantt charts, PERT analysis, critical path analysis, and critical chain scheduling
![Page 33: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/33.jpg)
Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
Symbols include: A black diamond: milestones or significant
events on a project with zero duration Thick black bars: summary tasks Lighter horizontal bars: tasks Arrows: dependencies between tasks
![Page 34: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/34.jpg)
Gantt Chart for Project X
![Page 35: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/35.jpg)
Gantt Chart for Software Launch Project
![Page 36: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/36.jpg)
Milestones
Milestones are significant events on a project that normally have zero duration
You can follow the SMART criteria in developing milestones that are: Specific Measurable Assignable Realistic Time-framed
![Page 37: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/37.jpg)
Sample Tracking Gantt Chart
![Page 38: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/38.jpg)
Critical Path Method (CPM)
CPM is a project network analysis technique used to predict total project duration
A critical path for a project is the series of activities that determines the earliest time by which the project can be completed
The critical path is the longest path through the network diagram and has the least amount of slack or float
![Page 39: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/39.jpg)
Finding the Critical Path
First develop a good project network diagram
Add the durations for all activities on each path through the project network diagram
The longest path is the critical path
![Page 40: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/40.jpg)
Simple Example of Determining the Critical Path
Consider the following project network diagram. Assume all times are in days.
2 3
4
5
A=2 B=5C=2
D=7
1 6
F=2
E=1
start finish
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?
![Page 41: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/41.jpg)
Determining the Critical Path for Project X
![Page 42: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/42.jpg)
More on the Critical Path
If one or more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken
Misconceptions: The critical path is not the one with all the
critical activities; it only accounts for time. There can be more than one critical path if
the lengths of two or more paths are the same
The critical path can change as the project progresses
![Page 43: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/43.jpg)
Using Critical Path Analysis to Make Schedule Trade-offs
Knowing the critical path helps you make schedule trade-offs
Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities
Total slack or total float is the amount of time an activity may be delayed from its early start without delaying the planned project finish date
A forward pass through the network diagram determines the early start and finish dates
A backward pass determines the late start and finish dates
![Page 44: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/44.jpg)
Calculating Early and Late Start and Finish Dates
![Page 45: Work Breakdown Structures. Define scope of project Identify stakeholders, decision-makers, and escalation procedures Develop detailed task list (work.](https://reader034.fdocuments.in/reader034/viewer/2022051400/551a3f8b550346cb358b559b/html5/thumbnails/45.jpg)
Project Schedule Table View Showing Free and Total Slack