Woolley Hill Wind Farm CMS

135
Woolley Hill Wind Farm CONDITION 31 CONSTRUCTION METHOD STATEMENT FOR WOOLLEY HILL WIND FARM, ELLINGTON Appeal Decision APP/H0520/A/11/ 2158702 1001741FUL Date of Approval 23rd March 2012 Site of Proposed Development: LAND EAST OF WHITLEATHER LODGE, WOOLLEY HILL, ELLINGTON Description of Proposal: ERECTION OF 4 THREE BLADED WIND TURBINES, UP TO A HEIGHT OF 130.5 METRES, AND ASSOCIATED ELECTRICITY TRANSFORMERS, UNDERGROUND CABLING, TWO NEW ACCESSES TO THE SITE AND NEW BRIDGE, TRACKS, HARDSTANDINGS, CONTROL BUILDING, SUBSTATION COMPOUND, MET AND COMMUNICATIONS MAST FOR A PERIOD OF 25 YEARS; TEMPORARY WORKS TO INCLUDE CONSTRUCTION COMPOUNDS LAY DOWN AREA AND 2 ANEMOMETRY MASTS. Applicant: Address: RES UK & Ireland Limited Beaufort Court Egg Farm Lane Kings Langley Herts WD4 8LR

description

Bridge MS

Transcript of Woolley Hill Wind Farm CMS

  • Woolley Hill Wind Farm

    CONDITION 31 CONSTRUCTION METHODSTATEMENT FOR WOOLLEY HILL WIND FARM,

    ELLINGTON

    Appeal Decision APP/H0520/A/11/2158702

    1001741FUL

    Date of Approval 23rd March 2012

    Site of ProposedDevelopment:

    LAND EAST OF WHITLEATHER LODGE, WOOLLEY HILL,ELLINGTON

    Description of Proposal: ERECTION OF 4 THREE BLADED WIND TURBINES, UP TOA HEIGHT OF 130.5 METRES, AND ASSOCIATEDELECTRICITY TRANSFORMERS, UNDERGROUNDCABLING, TWO NEW ACCESSES TO THE SITE AND NEWBRIDGE, TRACKS, HARDSTANDINGS, CONTROLBUILDING, SUBSTATION COMPOUND, MET ANDCOMMUNICATIONS MAST FOR A PERIOD OF 25 YEARS;TEMPORARY WORKS TO INCLUDE CONSTRUCTIONCOMPOUNDS LAY DOWN AREA AND 2 ANEMOMETRYMASTS.

    Applicant:Address:

    RES UK & Ireland LimitedBeaufort CourtEgg Farm LaneKings LangleyHertsWD4 8LR

  • Document Reference: 02341-003667 Issue: 01 - Approved

    CONTENTS

    1.0 INTRODUCTION...............................................................................................1

    2.0 PROJECT DESCRIPTION.....................................................................................1

    3.0 PLANNING CONDITIONS.....................................................................................1

    3.1 Conditions of Consent 1

    3.2 Non-Material Amendment 5

    3.3 Design Basis 5

    4.0 CONSTRUCTION PHILOSOPHY AND GENERAL WORKS.................................................6

    4.1 Timescale 6

    4.2 Environmental Management 7

    4.3 Flood Risk Assessment 9

    4.4 Site Won Materials 9

    4.5 Spoil Management 9

    4.6 Traffic Management 10

    4.7 Reinstatement of Construction Areas 10

    4.8 Community Liaison 10

    4.9 Health and Safety Management 10

    5.0 CONSTRUCTION METHOD ................................................................................ 11

    5.1 Temporary Construction Compounds and Site Fencing 11

    5.2 Site Entrances 11

    5.3 Site Tracks 12

    5.4 Bridge 14

    5.5 Crane Hardstandings 15

    5.6 Turbine Foundations 16

    5.7 Turbine and Turbine Transformer Erection 17

    5.8 Cable Trenching Works 18

    5.9 Substation Compound and RES Control Building 19

    5.10 Grid Connection 20

    5.11 Anemometry & Communication masts 21

    6.0 DECOMMISSIONING METHOD............................................................................. 22

    6.1 Site Access Tracks & Temporary Hardstanding Areas 22

    6.2 Wind turbines 22

    6.3 Turbine Foundations 22

    6.4 Electrical Equipment 23

    7.0 RECORDS .................................................................................................... 23

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.1

    1.0 INTRODUCTION

    This Construction Method Statement (CMS) is submitted by RES UK & Ireland Ltd (RES). The

    principal objective of this document is to provide information on the methodologies to

    construct and decommission Woolley Hill Wind Farm, to assist in discharging the pre-

    construction planning conditions (Appeal Ref: APP/H0520/A/11/2158702).

    At the time of preparing this CMS, RES were yet to appoint a wind turbine manufacturer or

    contractors to undertake the electrical or civil engineering works. The contractor(s) appointed

    to construct the project will prepare detailed method statements to construct the works.

    These detailed method statements will incorporate the details in this outline CMS.

    The construction methodologies described in this CMS have been developed in accordance

    with relevant local and national design standards, guidelines, regulations and publications and

    with due regard to avoiding, minimising and mitigating adverse environmental impacts.

    2.0 PROJECT DESCRIPTION

    The proposed Woolley Hill Wind Farm is made up of the following elements:

    Installation of four wind turbines with a maximum height to blade tip of 130.5 m

    including an external transformer at each turbine;

    Construction of approximately 2.0 km of new access track and the upgrade of

    approximately 1.1 km of existing access track;

    Construction of associated infrastructure including an on-site substation, crane

    hardstandings, electrical connection cables and a permanent met mast;

    Provision of two temporary site calibration and power performance masts; and

    Provision of two temporary construction compounds during the construction period.

    3.0 PLANNING CONDITIONS

    3.1 Conditions of Consent

    Consent was received on the 23rd

    March 2012 to construct and operate the Woolley Hill Wind

    Farm wind powered electricity generating station subject to condition compliance. For ease of

    reference, the sections of this document which relate to specific Planning Conditions are

    included in Table 1.

    RES acknowledges that unless otherwise agreed with Huntingdonshire District Council through

    the CMS approval process, the development shall be carried out strictly in accordance with

    the approved plans and conditions.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.2

    Table 1 - Woolley Hill Wind Farm Planning Conditions and Relevant Supporting Information

    No. Planning Condition Relevant CMS

    Section

    1 The development hereby permitted shall begin not later than 5 years from the date of this decision. (23 March 2012) 4.1.1

    3

    The permission hereby granted shall expire no later than 25 years from the date when electrical power is first exported from

    any of the wind turbines to the electricity grid network, excluding electricity exported during initial testing and

    commissioning (First Export Date). Written confirmation of the First Export Date shall be provided to the Local Planning

    Authority no later than one calendar month after the event.

    4.1.1

    4

    Not later than 12 months before the expiry of this permission, a decommissioning and site restoration scheme shall be

    submitted for the written approval of the Local Planning Authority. The scheme shall make provision for the removal of the

    wind turbines and the associated above ground equipment and foundations to a depth of at least one metre below finished

    ground level. The scheme shall include the management and timing of any works; a traffic management plan to address likely

    traffic impact issues during the decommissioning period; an environmental management plan to include details of measures

    to be taken during the decommissioning period to protect wildlife and habitats; identification of access routes; location of

    material laydown areas; restoration measures; and a programme of implementation. The approved scheme shall be fully

    implemented within 24 months of the expiry of this permission.

    4.1.1

    5

    If any of the turbines hereby permitted fails to produce electricity for supply to the grid for a continuous period of 6 months,

    a scheme shall be submitted to the Local Planning Authority for its written approval within 3 months of the end of that 6

    month period for the repair or removal of the relevant turbine. Where repairs or replacements are required the scheme shall

    include a proposed programme of remedial works. Where removal of the relevant turbine is required the scheme shall include

    a method statement and timetable for the dismantling and removal of the relevant turbine and associated above ground

    works and foundations to a depth of at least one metre below finished ground level; and a method statement and timetable

    for any necessary restoration works following removal of the turbine. The relevant scheme shall thereafter be implemented

    in accordance with the approved details and timetable.

    4.1.1

    6

    Construction work shall only take place between the hours of 07:00 19:00 on Monday to Friday inclusive and 08:00 13:00

    hours on Saturdays, with no construction work on a Sunday or Public Holiday. Outside these hours, works at the site shall be

    limited to emergency works and dust suppression. The Local Planning Authority shall be informed in writing of emergency

    works within 3 working days of occurrence. Where turbine erection has started, emergency work includes any construction

    work necessary to make the turbine safe.

    4.1.2

    7

    The delivery of any construction materials or equipment for the construction of the development, other than turbine blades,

    nacelles and towers, shall be restricted to the hours of 07:00 19:00 on Monday to Friday inclusive and 08:00 13:00 hours on

    Saturdays with no such deliveries on a Sunday or Public Holiday unless otherwise approved in writing by the Local Planning

    Authority having been given a minimum of 7 working days written notice of the proposed delivery.

    4.1.2

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.3

    8

    The turbines shall have a semi matt finish and be a pale grey colour. Prior to the erection of any turbine, its exact

    specification of finish and colour along with details of dimensions, finish and colour of any external transformer units and the

    proposed meteorological and communications masts shall be submitted to and approved in writing by the Local Planning

    Authority. No name, sign, symbol or logo shall be displayed on any external surfaces of the turbines or any external

    transformer units or the masts other than those required to meet statutory requirements. The development shall be carried

    out as approved and thereafter be retained in accordance with the approved details.

    5.7.1

    9

    The overall height of the wind turbines shall not exceed 130.5 metres to the tip of the blades when the turbine blade is in the

    vertical position as measured from natural ground conditions immediately adjacent to the turbine base. The hub height of the

    wind turbines shall be between 77 metres and 87 metres.

    5.7.1

    10 All wind turbine blades shall rotate in the same direction. 5.7.1

    11

    There shall be no permanent illumination on the site other than a passive infra-red-operated external door light for the

    substation building door to allow safe access; temporary lighting required during the construction period or during

    maintenance; or emergency lighting; and infra-red lighting required by Condition 23.

    4.2.3 and 5.7.1

    12

    Construction of the substation building and the associated substation compound and parking area shall not commence until

    details of the external appearance and materials to be used, together with details of surface and foul water drainage, have

    been submitted to and approved in writing by the Local Planning Authority. The development shall be constructed in

    accordance with the approved details.

    5.9.1

    13 All cabling between turbines and between the turbines and substation shall be laid underground. 5.8.1

    30The development shall only be carried out in accordance with the approved Flood Risk Assessment (February 2011) submitted

    in Appendix 3.1 of the Supplementary Environmental Information.4.3

    31

    Development shall not be begun until a construction method statement has been submitted to and approved in writing by the

    Local Planning Authority. The construction method statement shall set out details of all on-site construction works; post-

    construction reinstatement; drainage; mitigation; and other restoration, together with details of their timetabling. It shall

    include details of, and measures to secure:-

    -

    (a) the phasing of construction works; 4.1

    (b)the formation of the temporary construction compound and the temporary enabling works construction compound; the

    temporary laydown area; and the temporary anemometry masts;5.1

    (c) dust management and suppression; 4.2.4

    (d) cleaning of site entrances, facilities for wheel washing and cleaning the adjacent public highway; 5.2

    (e)pollution control, including the protection of water courses and ground water; subsoil surface water drainage; bunding of fuel

    storage areas; sewage and foul water drainage and disposal; and emergency procedures and pollution response plans;4.2.2 and 5.9.1

    (f) temporary site illumination during the construction period; 4.2.3

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.4

    (g)the methods to be adopted to reduce the effects of noise occurring during the construction period to the lowest practicable

    levels and in accordance with BS 5228: Noise control on construction and open sites;4.2.1

    (h) storage of materials and disposal of surplus materials; 4.5

    (i)the construction of the access into the site, the erection of any entrance gates and the creation and maintenance of

    associated visibility splays;5.2

    (j) access tracks and other areas of hardstanding; 5.3 and 5.5

    (k) the construction of the crane pads; 5.5

    (l) the carrying out of foundation works; 5.6

    (m) method of working cable trenches; 5.8

    (n) the erection of the meteorological and communications masts; 5.11

    (o) watercourse crossings; 4.2.1

    (p) soils storage and handling; 4.5

    (q) post-construction restoration/reinstatement of the working areas; 6.0

    (r)the sheeting of all heavy goods vehicles construction materials to, or spoil from, the site to prevent spillage or deposit of any

    materials on the highway;4.2.1

    (s) any works to the public highway including temporary widening and/or replacement of street furniture; 4.6

    (t)

    a traffic management plan including access and egress arrangements for abnormal loads and heavy goods vehicles; pre and

    post construction surveys of the slip road at junction 20 of the A14 (T) and Maltings Lane, from the east bound on-road at

    junction 20 to the site entrance, and a programme and methodology for any repairs as a consequence of any damage caused

    by construction traffic following the completion of construction; and a local signage scheme; and

    4.6

    (u) restricted access to the skew bridge by way of a removable barrier. 5.4

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.5

    3.2 Non-Material Amendment

    During the development of detailed designs for the construction of the wind farm it became

    apparent that improvements could be made through small changes in the layout of

    infrastructure, to help minimise the quantities of earthworks required and improve health and

    safety during construction. A Non-Material Amendment (NMA) was thus applied for and

    approved in February 2013, refer to Annex 1 for details of the approval and description of

    changes to the design incorporated in the NMA.

    3.3 Design Basis

    RES has employed a mix of internal specialists and external consultants to develop and

    validate an appropriate design associated with the site specific conditions for Woolley Hill

    Wind Farm.

    The following parties were used in the preparation of this method statement:

    McCloy Consulting (Drainage design)

    Waterman Transport & Development Ltd (Site Access and Bridge design)

    Mott MacDonald (Substation design)

    RSK Environment Ltd (Geotechnical Investigations)

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.6

    4.0 CONSTRUCTION PHILOSOPHY AND GENERAL WORKS

    Woolley Hill Wind Farm will be constructed in accordance with the Environmental Statement

    2010, the Supplementary Environmental Information 2011 and the Non-material Amendment

    2013 prepared during the development stage of the project.

    Throughout the development of project, the overarching design philosophy has been to ensure

    the design:

    minimises extent of infrastructure;

    avoids sensitive habitats;

    minimises environmental impacts; and

    maximises health and safety.

    Where appropriate and practicable, local plant and materials will be used in order to

    maximise the benefit of the wind farm project to the local community.

    4.1 Timescale

    4.1.1 Wind Farm Operation

    In accordance with Planning Condition 1, the development will commence before the

    expiration of 5 years from the date of the consent.

    In accordance with Planning Condition 3, the permission for the operation of the Wind Farm is

    for a period not exceeding 25 years from the date when electrical power is first exported from

    any of the wind turbines to the electricity grid network, excluding electricity exported during

    initial testing and commissioning.

    In accordance with Planning Condition 4, within 24 months of the end of the period of

    consent pursuant to Planning Condition 3, those parts of the Development requiring

    decommissioning and restoration in accordance with the conditions of the consent will be

    removed and the land restored, in accordance with the decommissioning of the scheme and

    detailed restoration and aftercare required by Planning Condition 4.

    In accordance with Planning Condition 5, if an installed and commissioned turbine fails to

    produce electricity for supply to the grid for a continuous period of 6 months, a scheme will be

    submitted to Huntingdonshire District Council for its written approval within 3 months of the

    end of that 6 month period for the repair or removal of the relevant turbine.

    4.1.2 Wind Farm Construction Hours

    In accordance with Planning Condition 6, construction work will only take place between the

    hours of 07:00 19:00 on Monday to Friday inclusive and 08:00 13:00 hours on

    Saturdays. No construction work will take place on a Sunday or Public Holiday. Outside these

    hours, works at the site will be limited to emergency works and dust suppression. The Local

    Planning Authority will be informed in writing of emergency works within 3 working days of

    occurrence. Where turbine erection has started, emergency work includes any construction

    work necessary to make the turbine safe.

    In accordance with Planning Condition 7, the delivery of any construction materials or

    equipment for the construction of the development, other than turbine blades, nacelles and

    towers, will be restricted to the hours of 07:00 19:00 on Monday to Friday inclusive and 08:00

    13:00 hours on Saturdays with no deliveries on Sundays or Public Holidays.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.7

    If any works are required outside these times, written details will be provided and agreed with

    the Local Planning Authority prior to commencing.

    Table 2 highlights the projected key dates and timescale for construction activities.

    Table 2 - Outline Project Programme

    TaskJul-

    12

    Aug-

    13

    Sep-

    13

    Oct-

    13

    Nov-

    13

    Dec-

    13

    Jan-

    14

    Feb-

    14

    Mar-

    14

    Apr-

    14

    Mobilise to site and set up main

    construction compound

    Site Entrance and on-site tracks

    Crane Hardstandings

    Abnormal Load Site Entrance

    Turbine Foundations

    Control Building & Substation

    MV Cable Installation

    Turbine Deliveries

    Turbine Erection

    Operational Take Over

    4.2 Environmental Management

    Monitoring will be carried out throughout the construction of the wind farm. Specific

    documents relating to this are:

    1. Environmental Requirements of Contractors Annex 3

    2. Emergency Procedure in the Event of a Contaminant Spill Annex 4

    3. SuDS Design Statement Annex 5

    4. Water Quality Monitoring Procedure Annex 6

    4.2.1 Contractors Requirements

    Specific details of the environmental management and emergency procedures to be adopted

    during the construction phase by Contractors are detailed in the Environmental Requirements

    of Contractors document.

    RES specific environmental management requirements and compliance of the Contractors to

    their environmental responsibilities are managed through our Environmental Management

    System Procedures and Policies which are certified to ISO 14001.

    The appointed Contractors will be required to adopt methods of working on site which reduce

    the effects of noise occurring during the construction period in accordance with BS 5228:

    Noise control on construction and open sites. The following mitigation measures will be

    implemented where necessary:

    For any particular job where construction noise may be an issue, the quietest plant

    and/or machinery will be used where reasonably practical;

    All equipment will be maintained in good working order and fitted with the

    appropriate silencers, mufflers or acoustic covers where applicable;

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.8

    Stationary noise sources will be sited as far away as reasonably possible from

    residential properties and where necessary acoustic barriers will be used to shield

    them; and

    The movement of vehicles to and from the site will be controlled and employees

    supervised to ensure compliance with the noise control measures adopted.

    The appointed Contractors will be required to sheet all heavy goods vehicles when

    transporting loose construction materials to, or spoil from the site, to prevent spillage or

    deposit of any materials on the highway.

    4.2.2 Management of Surface and Ground Water and Water Quality Monitoring

    Any incident that may impact on water quality will be dealt with in accordance with the

    Emergency Procedure in the Event of a Contaminant Spill.

    Detailed measures to address surface water management during the construction of the wind

    farm will be based upon the SuDS Design Statement prepared by McCloy Consulting.

    Water quality monitoring in accordance with the Water Quality Monitoring Procedure will be

    undertaken on discharge waters prior to, during and following the construction phase to assess

    and manage the performance of the drainage system, making adjustments as necessary to

    ensure that site drainage does not impact on local watercourses.

    4.2.3 Temporary Lighting

    Temporary lighting will be required at the temporary construction compounds for security

    purposes and to ensure that a safe working environment is provided to construction staff. In

    addition, temporary lighting may be required to ensure safe working conditions during

    construction. Any works will be undertaken within the working hours defined by Planning

    Condition 6 of the planning permission, unless otherwise agreed with the Planning Authority.

    All lighting rigs will be downward facing and all lights will be switched off during daylight

    hours.

    4.2.4 Dust Management

    Typical construction operations such as the excavation and deposition of materials, vehicle

    movements around site and site cutting works may result in dust arising during the works. The

    potential issue of dust creation during the works will be weather and season dependant,

    therefore detailed dust management methods will be subject to the works programme and

    contractor working methods.

    Dust management will be carried out at all times in accordance with industry best practice

    measures to ensure that any local sensitive receptors are not affected by nuisance levels of

    dust from the works. The following methods of dust suppression will be implemented during

    the construction phase of the wind farm:

    Site tracks to be damped down using bowser or other suitable system;

    Road sweeper to be used to remove loose material from highways during construction;

    Cleaning vehicles including wheel washing facilities;

    Soil erosion control measures;

    Speed limits to be put in place to ensure low vehicle speeds;

    Vehicle loads to be covered;

    Damping of dry excavations and cutting activities which generate dust; and

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.9

    Programming of works to minimise the time that soils are exposed.

    4.3 Flood Risk Assessment

    Planning Condition 30 states that the development shall only be carried out in accordance

    with the approved Flood Risk Assessment (FRA) (February 2011) submitted in Appendix 3.1 of

    the Supplementary Environmental Information.

    Mitigation measures outlined in the FRA have been incorporated in the design of the new

    bridge, access tracks, drainage and other site infrastructure and the positioning of temporary

    and permanent buildings on site. The following consents will be obtained from the relevant

    drainage authority (Environment Agency and Alconbury and Ellington Internal Drainage Board

    (IDB)) to satisfy compliance with Planning Condition 30:

    Environment Agency

    Flood Defence Consents (separate consents for both the Permanent and Temporary works):

    Construction of the new bridge across Ellington Brook; and

    Construction of access tracks, associated extension of drainage pipe and connection of

    new drainage to existing outfall within 9m of the top of bank for Ellington Brook.

    Alconbury and Ellington IDB

    Application for Consent for Works Affecting Watercourses:

    Works affecting tributaries of an IDB controlled watercourse; and

    Extension of drainage pipe.

    4.4 Site Won Materials

    Analysis of geotechnical site investigation results has determined that material won from the

    lower strata is unsuitable for construction use within the development. Therefore all stone for

    tracks, compounds, sub-station and crane hardstandings will be imported from appropriate

    local sources, where possible.

    Soil mixing, strengthening and compacting may occur with materials available in the upper soil

    strata on site and will be performed in-situ to the extent possible. Suitable material at

    locations specific to excavations such as turbine foundations, crane hard standings and

    building platforms may be excavated and treated such that they are suitable as engineering

    fill within the site.

    4.5 Spoil Management

    In line with construction best practice and to suit the ground conditions anticipated on site,

    the track and crane hardstanding design has endeavoured to minimise spoil created during

    construction.

    Topsoil and spoil excavated during the works will generally be stockpiled close to the

    excavation to limit vehicle movements on site. There will be no permanent storage of

    excavated materials within a 10m buffer of any watercourse, stream or river on site to

    prevent possible wash-out of fine soils or risk of instability of the watercourse banks. There

    will be no permanent spoil stockpiled within the floodplain as identified in the Environment

    Agencys flood mapping. The locations for the permanent placement of excavated spoil are

    shown on Drawing 02341D3503-01 in Annex 2.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.10

    4.6 Traffic Management

    In accordance with Planning Condition 30(t), details of the proposed traffic management for

    the site have been developed and are included in the Woolley Hill Wind Farm Traffic

    Management Plan (TMP) (Reference: 02341-004519).

    4.7 Reinstatement of Construction Areas

    4.7.1 General

    Reinstatement will be undertaken as work progresses using the turf and or topsoil removed

    during the construction activities detailed in Section 5.

    In addition, following the completion of the works a final inspection of the wind farm site will

    be undertaken and in circumstances where reinstatement using turf and or topsoil is

    unsuccessful alternative methods will be considered.

    4.7.2 Temporary Construction Compounds

    The temporary construction compounds will be reinstated to the approximate pre-construction

    condition and the following shall take place:

    all temporary structures, construction equipment and fencing will be removed;

    the granular material which was placed to form the hardstanding areas will be taken

    up and removed to areas agreed with the landowner; and

    the areas will be backfilled with material stripped and stored during the construction

    of the compounds, covered with topsoil and reseeded as required.

    4.8 Community Liaison

    Throughout the construction period of the project, RES will maintain an open dialogue with

    local residents and all other interested parties. Regular progress meetings will be held within

    the local communities and updates on progress and forthcoming activities will be

    communicated by a dedicated website and regular newsletters.

    A dedicated Community Liaison Officer will be appointed to provide a key contact between

    RES and the community through a Community Liaison Group (CLG). Details of this CLG are

    provided in Annex 7.

    4.9 Health and Safety Management

    The Principal Contractor will be responsible for ensuring that a construction phase health and

    safety plan is implemented and followed on site. All work will be carried out in accordance

    with:

    the Health and Safety at Work etc. Act 1974;

    the Construction (Design and Management) Regulations 2007; and

    all applicable third party safety guidelines.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.11

    5.0 CONSTRUCTION METHOD

    5.1 Temporary Construction Compounds and Site Fencing

    5.1.1 General

    Temporary construction compounds are required for the provision of site offices, welfare

    facilities and storage arrangements for materials, plant and equipment. There are two

    temporary construction compounds required for different areas and stages of the project.

    The temporary construction compounds will be constructed at the locations indicated on

    Drawing 02341D1001-06 in Annex 2. Details of the construction compounds are shown on

    Drawings 02341D2220-02, 02341D2239-02 and 02341D2229-02 in Annex 2.

    The Main Construction Compound shown in Drawing 02341D2220-02 and 02341D2239-02 in

    Annex 2 will be built for use during construction of the access tracks and as the main

    compound for the site, with welfare facilities provided at this location.

    The Enabling Works Construction Compound shown in Drawing 02341D2229-02 in Annex 2 will

    be used solely for the temporary setting down of materials during the construction of the

    Ellington Brook Bridge. As the compound is located within the floodplain identified within the

    EA flood mapping, it will not be fenced and no temporary construction buildings will be

    erected.

    5.1.2 General Construction Method

    The typical construction activities associated with the temporary construction compounds are:

    the areas to be used as compounds will be set out;

    topsoil shall be removed and carefully stockpiled;

    granular material will be spread and compacted to provide an area suitable for the

    siting of offices, storage containers, parking (where required) and to enable offloading

    of materials;

    a covered, impermeable bunded area will be provided within the Main Construction

    Compound for the storage of fuel oils. Refuelling will be undertaken in line with the

    requirements as outlined in Annex 4;

    the Main Construction Compound will be fenced around the perimeter and secured

    with locked gates outside working hours.

    5.2 Site Entrances

    5.2.1 General Method

    All traffic associated with construction of the wind farm (except for some larger turbine

    components) will be required to access the site via Grove Lane using the newly constructed

    General Site Entrance in accordance with the TMP. Grove Lane is a Cambridgeshire County

    Council (CCC) adopted highway, therefore technical approval for the new entrance will be

    sought from CCC.

    Turbine component deliveries will be made via both the newly constructed General Site

    Entrance and the Abnormal Load Site Entrance from the eastbound off-slip at Junction 20 of

    the A14. The A14 off-slip is a Highways Agency (HA) adopted highway, therefore technical

    approval for the new entrance will be sought from the HA.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.12

    The site entrances will be constructed at the locations indicated on Drawing 02341D1001-06 in

    Annex 2. Details of the site entrances are provided in the Woolley Hill Wind Farm Traffic

    Management Plan (TMP) (Reference: 02341-004519).

    All works to be carried out within the public highway will be designed in accordance with the

    relevant Highway Authoritys standards. Technical approval for the works will be obtained

    from the relevant Highway Authority prior to the works commencing. The technical approval

    will address:

    construction of the access into the site;

    erection of entrance gates;

    creation of visibility splays;

    installation of a removable barrier for restricting access to the new bridge (Abnormal

    Loads Site Entrance only); and

    cleaning of site entrances, facilities for wheel washing and cleaning the adjacent

    public highway.

    Prior to public road works being undertaken, a Section 278 Agreement in accordance with the

    Highways Act 1980 will be entered into with the relevant Highway Authorities. All works to

    public roads will be carried out in accordance with details of the Section 278 Agreement. A

    detailed programme of all works and any required traffic management proposals will be

    submitted to and agreed with the Highway Authorities

    5.2.2 General Construction Methodology

    The site entrances will be constructed in accordance with the approved technical drawings as

    follows:

    obtain necessary permits and approvals from Cambridge County Council, Highways

    Agency and the Environment Agency;

    inform statutory services & identify any assets to be protected or diverted;

    install appropriate traffic management;

    topsoil shall be removed and carefully stockpiled;

    new drainage will be installed taking care to ensure that existing drainage will not be

    compromised;

    edge restraints where required in the design will be installed;

    road pavement works at the site entrance will be completed to the design

    requirements of the relevant Highway Authority; and

    line marking, signage, fencing and vehicle restraint systems required as part of the

    design will be completed.

    5.3 Site Tracks

    5.3.1 Design Philosophy

    The general approach to road construction is to provide an alignment that minimises

    environmental impact whilst providing an access track that meets the requirements for the

    safe delivery of wind turbine components and other vehicles.

    The running width of the tracks shall be in accordance with the requirements of the chosen

    turbine supplier. Typically this is 4.5 - 5.5 metres wide on straight sections, increasing at

    corners and passing places to accommodate the swept path of turbine delivery vehicles. The

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.13

    track working area will be kept to the minimum required allowing for working area, safe

    access, drainage and electrical works.

    All site tracks have been designed taking account of the loadings provided by the turbine

    manufacturer, and will consist of compacted stone structure. A number of track designs may

    be utilised on site which will be determined during detailed design dependent on the ground

    conditions encountered on site. Examples of the track designs that may be used can be found

    in Drawing 02341D2221-02 in Annex 2 and include:

    cut track from suitable load bearing strata;

    cut track from ground improved strata;

    floating track; and

    another appropriate method identified by the civil works contractor appointed to

    undertake the works.

    Track drainage will be incorporated within the design as set out in Drawings MCL115-

    54_DWG_101_5 to MCL115-54_DWG_105_5 in Annex 5.

    5.3.2 Cut Track

    Cut track construction may be used in areas identified where the thickness of soft soils is low,

    and the underlying layer has adequate load bearing properties. This cut track system will

    likely consist of a suitable capping layer and then a suitable running layer, but may be

    optimised if a stiffer bearing stratum is encountered.

    5.3.3 Floating Track

    Floating track construction may be adopted where the ground conditions require. This system

    involves installing geo-grid directly onto the organic or exposed soil layer and placing layers of

    suitable stone and geo-grid (as required) above.

    5.3.4 Ground Stabilisation

    Where the load bearing properties of the underlying soils are determined to be insufficient,

    ground stabilisation may be carried out to provide adequate bearing capacity of the formation

    level. A variety of methods may be required due to the variable nature of the ground at

    Woolley Hill but are likely to comprise in-situ soil mixing with lime and/or cement. Specific

    construction methods shall be selected at detailed design stage in consultation with specialist

    contractors. Any track design based on ground improvement techniques will be performed in

    accordance with a project specific Specification for Ground Improvement Works.

    5.3.5 Watercourse buffers

    A buffer zone will be maintained around all watercourses on site. The exception to these

    buffer zones is where there are crossing points or where the existing track is located within

    the buffer zone. Site personnel will be made aware of the buffer zones through the site

    induction and specific tool box talks. Buffer zones and mitigation measures to prevent

    contamination of watercourse by silts will be in accordance with the SuDS Design Statement

    provided by McCloy Consulting in Annex 5.

    5.3.6 General Construction Methodology

    The following general methodology will apply to construction operations for both upgraded

    tracks and new tracks:

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.14

    establish alignment of the site tracks from the construction drawings and mark out the

    centrelines with ranging rods or timber posts, track corridors shall be pegged out in

    advance of operations;

    a cut off ditch may be installed on the slope above the earthworks footprint where

    achievable given the sloping topography;

    topsoil will be removed and stored carefully for use in reinstatement works (not

    applicable to floated tracks);

    any remaining subsoil will be excavated down to a suitable bearing stratum and set

    aside along each side of the road, for later use in landscaping, backfilling around

    structures and verge reinstatement (not applicable for floated tracks);

    design buffer zones will be adhered to and as construction is progressed the

    effectiveness of the buffer zones will be reviewed and if necessary increased;

    depending on depth and type of material, embankment slopes are anticipated to be

    between 1:1 to 1:3;

    the stone track pavement material shall then be either spread by a dozer or placed by

    excavator and compacted in layers, typically using vibratory rollers. The thickness of

    layers and amount of compaction required will be determined based on the design,

    which will take account of the characteristics of the material and the compaction

    plant to be used;

    track drainage will be excavated adjacent to the tracks where required. The running

    surfaces of the site tracks will be finished to encourage drainage and reduce ponding.

    Surface water runoff will not be allowed to discharge directly into existing

    watercourses but will be routed through the drainage system;

    where the road alignment crosses existing drainage channels, crossings appropriate to

    the location will be designed in accordance with the relevant guidelines; and

    reinstatement of the road verges, drainage swales and embankments will be ongoing

    as the roads are constructed. The intention will be to minimise the amount of time in

    which any material will be stockpiled.

    5.4 Bridge

    A bridge across Ellington Brook is required to provide access to the site for the delivery of

    turbine components. The construction of the bridge will require permanent Flood Defence

    Consent from the Environment Agency under the Flood and Water Management Act.

    The Abnormal Load Access Bridge General Arrangement is shown on Drawing

    CIV_SA_03_100_A03 in Annex 2.The proposed bridge will be a single span bridge so that there

    is no support within the existing channel and will have an overall length of approximately 10.5

    metres between faces of abutments. The bridge deck will be supported on reinforced concrete

    abutments and have steel containment parapets.

    5.4.1 Method Statement

    A Flood Defence Consent for temporary works will be obtained from the Environment Agency,

    prior to the works commencing. The temporary works Flood Defence Consent will include a

    method statement developed with reference to Works and maintenance in or near water:

    PPG5 and will details how elements of the bridge will be built including addressing the

    following:

    excavation for abutments and managing the risk of silt pollution;

    disposal of contaminated water;

    managing concrete and cement used in the works; and

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.15

    use of oils and chemicals in the works.

    5.5 Crane Hardstandings

    5.5.1 Design Philosophy

    All crane hardstandings will be designed taking account of the loadings provided by turbine

    manufacturers, and will consist of one or a combination of the following:

    a compacted stone structure bearing directly on a suitable formation strata;

    a compacted stone structure bearing on a formation strata improved through ground

    stabilisation techniques;

    a compacted stone structure bearing on a strengthened soil mass created by the

    installation of multiple stone or concrete columns; or

    another appropriate method identified by the civil works contractor appointed to

    undertake the works.

    Floated construction is not deemed to be acceptable for crane hardstandings due to the

    flexibility of such structures and the inevitable settlement.

    5.5.2 General Method

    The main crane hardstandings are anticipated to be 40m x 30m and have a maximum cross and

    longitudinal fall tolerance of 1% (1:100). The temporary hardstanding elements as shown in

    Drawing 02341D2226-04 in Annex 2 will be reinstated post construction. The main crane

    hardstanding area will be left uncovered for the operational lifetime of the wind farm in line

    with good practice outlined in the Scottish National Heritage guidance Good Practice during

    Windfarm Construction.

    Where competent soils exist close to the existing ground surface, the hardstanding area shall

    typically be constructed using the following methods:

    a cut off ditch may be installed on the slope above the earthworks footprint where

    required given the sloping topography;

    topsoil will be removed and stored carefully for use in reinstatement works;

    any remaining subsoil will be excavated down to a suitable bearing stratum and set

    aside for later use in landscaping, backfilling around structures and verge

    reinstatement;

    where excavation is required to extend below the water table or in material which

    does not drain freely, appropriate pumping will be employed to keep the excavation

    dry. Water pumped from an excavation shall not be discharged directly to any

    watercourse, and shall be treated according to the principles of the SuDS Design

    Statement, refer Annex 5.

    temporary & permanent drainage shall be installed;

    temporary and permanent drainage will be excavated adjacent to the crane

    hardstanding where required. The surfaces of the crane hardstanding will be finished

    to a cross fall of no greater than 1% to encourage drainage and reduce ponding.

    Surface water runoff will not be allowed to discharge directly into existing

    watercourses but will be routed through the drainage system;

    the crane hardstanding material shall then be either spread by a dozer or placed by

    excavator and compacted in layers, typically using vibratory rollers. The thickness of

    layers and amount of compaction required will be determined based on the design,

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.16

    which will take account of the characteristics of the material and the compaction

    plant to be used.

    Where the load bearing properties of the underlying soils are determined to be insufficient,

    ground stabilisation may be carried out to provide adequate bearing capacity of the formation

    level. Due to the variable nature of the ground at Woolley Hill Wind Farm, specific

    construction methods shall be selected at detailed design stage in consultation with specialist

    contractors. Such methods may consist of:

    Compaction of the existing in situ soils;

    Lime/cement stabilisation of the existing in situ soils; or

    Installation of stone or concrete columns to provide adequate support.

    Any crane hardstanding design based on ground improvement techniques will be performed in

    accordance with a project specific Specification for Ground Improvement Works.

    In all cases, the completed hardstanding platform shall consist of a compacted stone layer

    from the improved formation level to design level.

    5.6 Turbine Foundations

    5.6.1 Design Philosophy

    Foundations will be designed in accordance with the RES Basis of Design - Wind Turbine

    Gravity Base Foundations, taking account of the specific foundation techniques to be

    employed at Woolley Hill. Due account will be taken of guidance provided in appropriate

    codes and standards such as Eurocodes, British Standards and other specialist design

    documents.

    Due to the anticipated load bearing capacity of the near surface soils, gravity base turbine

    foundations are expected to be used to support the wind turbine superstructure. The wind

    turbine foundation is characterised by having to resist very high overturning moments. Gravity

    foundations are designed to have sufficient weight to maintain stability under all loading

    conditions and be of appropriate size and stiffness to distribute load in accordance with the

    geotechnical conditions encountered at each turbine location.

    The foundations will be designed as a reinforced concrete structural slab. The foundation

    geotechnical design will be based on the information contained in the site investigation

    reports produced by RSK Environment Ltd and factors of safety will be incorporated in

    accordance with European design standards. The site specific designs will typically be of the

    dimensions detailed on Drawing 02341D2225-02 in Annex 2.

    An earth mat will be buried around the turbine to provide protection to personnel in the event

    of an electrical fault during operation of the wind farm.

    The foundations will been designed and constructed in accordance with relevant UK safety

    legislation and design regulations. Design risk assessments will be carried out and risk

    mitigation measures incorporated into the design.

    5.6.2 General Construction Method

    Details of the foundation works are detailed in the sections below:

    the extent of the excavation will be marked out, including an allowance for trimming

    the sides of the excavation to provide a safe working area;

    the topsoil will be excavated and stored to one side for reuse during the landscaping

    around the finished turbine;

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.17

    where excavation is required to extend below the water table or in material which

    does not drain freely, appropriate pumping will be employed to keep the excavation

    dry. Water pumped from an excavation shall not be discharged directly to any

    watercourse, and shall be treated according to the principles of the SuDS Design

    Statement, refer Annex 5.

    temporary & permanent drainage shall be installed;

    excavation will be undertaken to competent material. Excavated material may be

    stockpiled temporarily adjacent to the excavation for later use as backfill or stored

    elsewhere on site;

    a layer of concrete blinding will be laid directly on top of the newly exposed

    formation, finished to ensure a flat and level working surface;

    steel reinforcement, the turbine anchorage system and cable ducts will be fixed in

    accordance with the designers drawings and schedules. Formwork will be erected

    around the steel cage;

    concrete will be placed using a crane, pump or other suitable lifting device and

    compacted using vibrating pokers to the levels and profile indicated on the drawings

    and in accordance with best working practices;

    upon completion of the concreting works the foundation will be covered and allowed

    to cure;

    following the curing period any formwork around the foundation will be stripped and

    stored for reuse;

    the foundation will be backfilled with suitable material, where possible using the

    material arising during the excavation, and landscaped using the vegetated soil layer

    set aside during the initial excavation;

    a gravel footpath will be built leading from the access track or crane hardstanding to

    the turbine door or access steps and around the turbine for maintenance.

    In the case where competent material is lower than the required formation level the

    foundation will likely be over-excavated to competent material and compacted engineering

    fill used to provide suitable bearing capacity.

    5.7 Turbine and Turbine Transformer Erection

    5.7.1 Turbines

    In reference to Planning Condition 8, Planning Condition 9 and Planning Condition 10, the

    turbine will be supplied with a semi matt finish and be pale grey colour (RAL 7035) and

    installed with a height not exceeding 130.5 m measured from ground levels to the blade tip in

    the vertical position. The wind turbine blades will rotate in the same direction.

    The turbines will not carry any symbols, logos or other lettering except where required under

    other legislation. However, RES propose to add turbine numbers to the base of each tower to

    aid service engineers during the operational phase of the wind farm. A typical detail for a

    completed turbine is shown in Drawing 02341D2227-02 in Annex 2.

    In line with health and safety best practice, turbine manufacturers have indicated a

    preference to locate a passive infra-red (PIR) detector and light above each turbine door. It

    should be noted that this lamp will not be permanently lit and would only be switched by the

    PIR when personnel approach a particular turbine.

    Specific locations for the turbines are as per Drawing 02341D0001-09 in Annex 2.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.18

    5.7.2 Turbine Transformers

    Depending on the model of turbine finally chosen for the site, turbine transformers will be

    placed externally to the main turbine.

    The transformers are delivered by the manufacturer. If the oil cooled type, they will be

    supplied full of oil and will not require topping up or filtering on site. The transformers will be

    of the sealed type and will be inspected for any damage prior to offloading.

    The units will be tested, commissioned and energised by suitably trained and authorised

    persons. The transformers will be located within enclosures which shall be locked, accessible

    by trained and authorised personnel only, and displaying appropriate warning signs.

    5.7.3 General Turbine Erection Method

    The following steps will be undertaken in order to erect the turbines on site:

    turbine components are delivered in sections to the site;

    the sections are lifted by adequately sized cranes (1 main crane and smaller tail

    crane) and positioned on the foundations / other turbine sections until the entire

    turbine is erected;

    wind turbine erection is subject to a maximum wind speed and for safety and

    structural reasons if the upper tower section is in place it must have the nacelle

    section in place too, or other means to ensure the structural integrity of the tower in

    its partly constructed state;

    upon completion of the erection all fasteners will be tightened to the correct torque

    and the internal fit out of the turbine undertaken. Finally the mains power will be

    connected to the turbine controller; and

    when the controller is booted up the turbine commissioning will commence, and

    following the successful execution of the tests on completion the turbines will be

    handed over as complete.

    5.8 Cable Trenching Works

    5.8.1 Design Philosophy

    In accordance with Planning Condition 13, all electricity and other service cables between

    the turbines and the substation/control building will be placed underground.

    The detailed construction and trenching specifications will depend on the ground conditions

    encountered but typically cables will be directly buried inside a trench, except at road

    crossings where cables will be ducted.

    5.8.2 General Method

    The approximate layout of onsite cables can be found in Drawing 02341D4301-01 in Annex 2.

    The cable trench cross sectional size is dependent on the number and size of the cables

    required at each location. Typical details of a cable trench are shown in Drawing 02341D4304-

    02 in Annex 2.

    The following construction method will typically be used when cable trenching is on flat

    terrain:

    trenches will be excavated and a suitable bedding material placed for which to lay the

    cables upon. The ground is trenched typically using a mechanical digging machine;

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.19

    the cables shall be laid directly onto the bedding material;

    the trench will then be backfilled and compacted with a suitably competent material

    up to the required level and finished with a layer of topsoil to aid in the trench

    reinstatement.

    a suitable marking tape is installed between the cables and the surface; and

    the cables are terminated on the switchgear at each turbine and the substation.

    5.9 Substation Compound and RES Control Building

    5.9.1 Design Philosophy

    MV cables will export power from the wind turbine generators to the RES substation compound

    and control building before being transferred to the local distribution network. The location of

    the control building is shown on Drawing 02341D1001-06 in Annex 2.

    The control building has been designed, sized and positioned to be sympathetic with the

    surroundings. To ensure a high level of design will be carried out in the development of the

    control building and substation, Mott Macdonald has been commissioned to provide specialist

    input to the design process.

    The layout shown on Drawing 02341D2222-02 in Annex 2 and elevations shown in Drawing

    02341D2223-03 in Annex 2 represent the probable building configurations but are dependent

    on a final choice of turbine and detailed electrical design. The control building contains a

    control room, RES switch room, utility switch room, SCADA room, storage rooms and welfare

    facilities.

    The foundations for the building will be designed based on the investigation reports produced

    by RSK Environment Ltd. The substructure will likely consist of mass concrete foundations, in

    the form of part raft and part strip footing, insulated and tanked in accordance with best

    practice and Local Authority Building Control requirements. Trenches or a floor void would be

    provided between the foundation and ground floor to accommodate services via a raised floor

    system.

    The superstructure will likely consist of external and internal walls built off the foundation

    and would support the roof. The ground level raised floor system would be supported by either

    the walls or directly by the foundations. The walls would be constructed of precast reinforced

    concrete, masonry, blockwork or similar.

    The control building roof covering will be dark grey tiles or similar, while the external walls

    will be finished with a textured grey render. In accordance with Planning Condition 12,

    construction of the control building and substation compound will not commence until details

    of the exact finishes of the control building have been submitted to and approved by the Local

    Planning Authority.

    The roof will be a traditional pitch roof construction that complies with relevant design

    standards. All doors and window frames will be made of steel or timber, prefabricated to fit

    structural openings. All door openings will be sized to comply with the current mechanical and

    electrical requirements.

    The substation control building will have a domestic electrical system including lights, sockets,

    fire alarm and intruder alarm. This will be designed, installed and commissioned by specialist

    electrical contractors.

    Surface water drainage from the substation and control building will be connected to the wind

    farm drainage network, refer Annex 5. Foul water drainage will be provided in the form of a

    sealed cess pit at the location as shown in Drawing 02341D2222-02 in Annex 2.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.20

    5.9.2 General Method

    The control building and substation compound will be constructed generally in accordance

    with the following:

    the plan area of the control building and substation compound will be set out and the

    soil stripped and removed to a temporary stockpile. Storage areas will be stripped of

    vegetation prior to stockpiling in line with best working practises;

    the dimensions of the control building and substation compound area will be set out to

    meet the layout shown on Drawing 02341D2222-02 in Annex 2. Since the overall

    footprint cannot be determined until a turbine has been selected, all details present a

    worst-case in terms of overall footprint to satisfy the requirements of the Grid

    Operator and the necessary equipment and accommodation to safely and efficiently

    operate the wind farm;

    the building foundations will be excavated down to the level indicated by the

    designer. Reinforcement, waterproofing systems and formwork will be installed and

    the foundation concrete will be poured;

    internal and external walls will be installed/constructed by mobile crane or by hand as

    appropriate, services or ducts will be incorporated, and the raised floor system will be

    put in place;

    the 33kV switchgear is typically installed using a mobile crane or HIAB, the indoor

    equipment is then connected, wired, tested and commissioned typically by engineers

    supplied by the switchgear manufacturer;

    the roof trusses will be lifted into position using an adequately sized mobile crane,

    felted, battened, tiled and sealed against the weather;

    the doors will be fitted and the external & internal finishing applied including any

    fitted furniture. If precast wall are used, doors may be installed prior to erection;

    internal and external fittings, finishes and hardware will be installed in the Control

    Building. Finishes are to be agreed with the local authority:

    o Walls to be finished with render or cladding on all sides.

    o Roof tiles to be fibre slating or similar.

    o Doors to be made or framed by steel or timber with steel sheeting for

    security. The compound area will be re-graded, the electrical equipment

    plinths constructed and an over site carpet of single size clean granular

    material will be laid.

    A palisade fence will be erected around the compound and the area surrounding the

    building landscaped as required, returning it as far as practicable to near original

    condition;

    PIR (Passive Infrared) operated external lighting will be installed on the building and

    substation compound to enable safe access and egress during periods of reduced light.

    5.10 Grid Connection

    Connection to the grid shall be made at Perry Primary Substation. UK Power Networks will

    facilitate the connection by installing an underground power line from the onsite substation to

    the grid connection point. UK Power Networks will design and construct the connection in

    accordance with their recognised standards, planning conditions and any relevant landowner

    agreements.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.21

    All necessary consents for the underground power line shall be obtained by UK Power

    Networks, and constitute separate consents.

    5.11 Anemometry & Communication masts

    Two types of mast have permission to be erected at Woolley Hill Wind Farm, permanent

    lattice and temporary guyed tubular masts. In total four different masts are required for the

    development as follows:

    one permanent anemometry mast;

    two temporary site calibration and power performance masts; and

    one permanent communication mast.

    The locations of permanent and temporary masts are identified in Drawing 02341D1001-06 in

    Annex 2. Typical details of the masts can be found in Drawing 02341D2224-04 in Annex 2.

    5.11.1 Permanent Anemometry Mast

    The mast will require its own reinforced concrete foundation and crane pad to allow for

    erection, plus associated electrical and communication plant that service the mast. The

    foundation construction and mast erection will follow a similar approach to that of the

    turbines.

    5.11.2 Temporary Site Calibration & Power Performance Masts

    Two masts are to be installed within the development boundary.

    Temporary site calibration & power performance masts have planning permission to be

    erected during construction and will continue to be in place for a period during operation of

    the wind farm while accurate wind speed measurements are taken.

    5.11.3 Communication Mast

    The mast will require its own reinforced concrete foundation and crane pad to allow for

    erection, plus associated electrical and communication plant that service the mast. The

    foundation construction and mast erection will follow a similar approach to that of the

    turbines.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.22

    6.0 DECOMMISSIONING METHOD

    In conformance with Planning Condition 4, within 24 months of the end of the 25 year period

    pursuant to Planning Condition 3, decommissioning of the wind farm will be carried out in

    accordance with Planning Condition 4.

    Planning Condition 4 requires that a site restoration scheme will be provided to the Local

    Planning Authority no later than 12 months before the expiry of the planning permission for

    written approval and will detail measures covering the removal of all ground elements of the

    development. The site restoration scheme will include:

    the management and timing of works;

    the environmental management provisions; and

    a traffic management plan.

    The works described below are indicative of the decommissioning method which would be

    undertaken.

    6.1 Site Access Tracks & Temporary Hardstanding Areas

    The new site tracks and temporary hardstanding areas would be reinstated to the approximate

    pre-wind farm condition, unless otherwise agreed with the Local Planning Authority. Areas to

    be reinstated would likely be treated in the following way:

    the material used to construct the tracks would be taken up and removed to areas

    identified and agreed in the site restoration scheme;

    the areas would be backfilled with material generated local to the access tracks and

    hardstanding areas, covered with topsoil and reseeded as required;

    backfilling of access tracks would be carefully planned in advance to avoid having to

    unnecessarily move plant and equipment on freshly reinstated land.

    Upgraded tracks would be left unchanged from the conditions used during the operation phase

    of the wind farm.

    6.2 Wind turbines

    The decommissioning of the wind turbines would be the reverse of the erection process

    involving similar lifting plant and equipment;

    It is anticipated that the turbine nacelle would be taken down and loaded straight

    onto the back of transport vehicles and removed from site for reconditioning or scrap;

    and

    The turbine towers and blades would be broken down into smaller component parts

    than during the initial delivery and erection process, into more manageable sections

    prior to removal from site.

    6.3 Turbine Foundations

    Following the removal of the wind turbine the concrete foundation would be removed

    to 1.5 m below existing ground level;

    The steel foundation insert or bolt ring and any exposed reinforcement would also be

    cut back to 1.5 m below existing ground level and treated with a proprietary corrosion

    protection system;

  • Document Reference: 02341-003667 Issue: 01 - Approved

    p.23

    Upon completion of the corrosion protection the foundation would be backfilled with

    material generated local to the foundation, covered with topsoil and reseeded as

    required; and

    It is widely accepted within the construction industry that there is no appreciable

    effect on the local environment from buried reinforced concrete structures left in-situ

    due to the inert state and classification of concrete.

    6.4 Electrical Equipment

    The electrical equipment will be decommissioned in the reverse of the installation method

    described above to a depth of 1.5m or as agreed with the Local Planning Authority. The

    equipment would be dismantled, removed from site and disposed of in an appropriate manner.

    Cables may be left in the ground if recovery is not reasonably practicable.

    6.4.1 Substation and RES Control Building

    The substation and RES control building would be decommissioned by disconnecting and

    dismantling all the surface plant. Solid structures such as the building and equipment plinths

    will also be dismantled and foundations removed to a depth of 1.5 m. Ducting and cabling that

    is practical to remove will be removed to a depth of 1.5 m.

    The fence surrounding the compound would be removed and the area landscaped back to its

    original state.

    6.4.2 Turbine Transformers

    The units would be decommissioned in the same manner as they were installed, removed from

    site and either disposed of or refurbished by a company certified to handle such materials.

    This specialist company will also dispose of any oil or residual waste products in line with

    applicable COSHH Regulations.

    7.0 RECORDS

    Records, as-built drawings, specifications, operational maintenance manuals and residual risks

    will be collated and filed in the Project Health & Safety file based upon the requirements of

    the Construction (Design & Management) Regulations 2007 or applicable legislation at the time

    of decommissioning.

  • Document Reference: 02341-003667 Issue: 01 - Approved

    Annexes

    ANNEX 1 NON-MATERIAL AMENDMENT CONFIRMATION

    ANNEX 2 DRAWINGS

    ANNEX 3 ENVIRONMENTAL REQUIREMENTS OF CONTRACTORS

    ANNEX 4 PROCEDURE IN THE EVENT OF A CONTAMINANT SPILL

    ANNEX 5 SUDS DESIGN STATEMENT

    ANNEX 6 WATER QUALITY MONITORING PROCEDURE

    ANNEX 7 COMMUNITY LIAISON GROUP INITIATION LETTER AND TERMS OF REFERENCE

  • Document Reference: 02341-003667 Issue: 01 - Approved

    ANNEX 1 NON-MATERIAL AMENDMENT CONFIRMATION

  • RIECIE~VIED, 1 FEB,2013

    ~ ...... ~

    ,. .. ~./Huntingdo~nshireDISTRICT COUNCIL

    Pathfinder House, St Mary's StreetHuntingdon. PE29 3TNmail~huntsdc.gov.ukDX 140316 HuntingdonSC

    Tel: 01480 388388Fax: 01480 388099

    ww.huntingdonshire.gov.uk

    RES UK And Ireland Ltd (FAO Mr J Knight)Beaufort CourtEgg Farm LaneKings LangleyHertordshireWD4 8LR

    Our Ref: 1300045NMAYour Ref:

    7th February 2013

    Oear Sir/Madam

    Application for Non-Material Amendment following a grant of Planning ~ermissionAmendment to Planning Permission 1001741FUL (allowed at appeal) to alter position of trackleading to turbine 4 and associated infrastructure. Additional temporary constrUction areas.Redesign of bridge crossing Ellngton Brook. Redesign of substation compound and controlbuilding layoutLand East Of Whitleather Lodge Woolley Hil Ellngton

    I refer to the above submission received on the 11 th January 2013 and accompanying drawingsreferenced below.

    '(4

    Plan Type Reference Version Date ReceivedGeneral 0234102226-04 11.01.2013PlanninQ Layout 0234102222-02 11.01.2013Elevations 02341 02223-03 11.01.2013Planning Layout 02341 02220-02 11.01.2013Elevations 02341 02239-02 11.01.2013General 0234102414-01 11.01.2013General 0234101301-01 11.01.2013PlanninQ Layout 0234101001-06 11.01.2013

    I would confirm that the non-material amendment(s) as described is (are) considered acceptablesubject to the additional conditions identified below (the development remains subject to theconditions attached to the original planning permission) ;1. Note to applicant. No conditions

    Should you wish to discuss the matter further please contact Jennie Parsonson 01480 388409.

    ufm4.rt

  • -(( I1 ,\ '/I!! i ,t~ ....~ ~

    ~ .... ~.,/HuntingdonshireDISTRICT COUNCIL

    Pathfinder House, St Mary's StreetHuntingdon. PE29 3TNmail~huntsdc.gov.ukDX140316 Huntingdon se

    Tel: 01480 388388Fax: 01480 388099

    ww.huntingdonshire.gov.uk

    Yours faithfully

    A;tvft'Andy MoffatPlanning Service Manager(Development Management) ~

    ufm4.rt

  • Document Reference: 02341-003667 Issue: 01 - Approved

    ANNEX 2 DRAWINGS

  • Document Reference: 02341-003667 Issue: 01 - Approved

    Schedule of Drawings

    Layouts

    Turbine Layout 02341D0001-09

    Infrastructure Layout 02341D1001-06

    Civil Works

    Abnormal Load Access Bridge General Arrangement CIV_SA_03_100_A03

    Crane Hardstanding General Arrangement 02341D2226-04

    Typical Access Track Design 02341D2221-02

    Typical Construction Compound Layout 02341D2220-02

    Typical Construction Compound Layout Elevations 02341D2239-02

    Typical Enabling Works Construction Compound 02341D2229-02

    Control Building and Substation Layout 02341D2222-02

    Control Building and Substation Elevations 02341D2223-03

    Wind Turbine Foundation 02341D2225-02

    Met Masts 02341D2224-04

    Drainage Design (Refer SuDS Design Statement - Annex6)

    Drainage Management (SuDS) Site General Arrangement Sheet 1 of 5 MCL115-54_DWG_101_5

    Drainage Management (SuDS) Site General Arrangement Sheet 2 of 5 MCL115-54_DWG_102_5

    Drainage Management (SuDS) Site General Arrangement Sheet 3 of 5 MCL115-54_DWG_103_5

    Drainage Management (SuDS) Site General Arrangement Sheet 4 of 5 MCL115-54_DWG_104_5

    Drainage Management (SuDS) Site General Arrangement Sheet 5 of 5 MCL115-54_DWG_105_5

    Drainage Management (SuDS) Typical Details Surface Water

    Detention Basin

    MCL115-54_DWG_201_2

    Drainage Management (SuDS) Typical Details Trackside Drainage MCL115-54_DWG_202_2

    Drainage Management (SuDS) Typical Details Silt Fence MCL115-54_DWG_203_2

    Drainage Management (SuDS) Permanent & Temporary Track

    Drainage Grip / Waterbar

    MCL115-54_DWG_204_2

    Spoil Placement

    Permanent Landscaping Areas 02341D3503-01

    Wind Turbine Generator

    Typical Front and Side Elevations of Typical Wind Turbine 02341D2227-02

    Electrical Works

    MV Cable Layout 02341D4301-02

    Cable Trench Profile 02341D4304-02

  • Project scoping turbine shortlist:ECM memo 01456-000067

    Some turbines are closer than 10D tohouses. This has been approved bythe DPM.

    Some of the turbines spacing is < 4D.

  • GENERAL NOTES

    Amendments

    DescriptionDateRev

    Title

    Client

    Publisher Revision

    Designed by

    Drawn by

    Checked by

    Date

    Scales @ A1

    work to figured dimensions only

    By

    Project

    Drawing Status

    Project No

    Computer File No

    Zone Category Number

    his drawing should not be scaled. Dimensions to be verified on site.Any discrepancies should be referred to the Engineer prior to work being put in hand.

    This drawing is the property of Waterman Transport & Development Limited, and thedrawing is issued on the condition that it is not copied reproduced, retained or disclosed toany unauthorised person, either wholly or in part without the consent in writing ofWaterman Transport & Development LimitedPickfords Wharf, Clink Street, London SE1 9DG t 020 7928 7888 f 020 7902 0992

    &

    www.watermangroup.com

    File

    Pat

    h

    [email protected]

    Civic House 156 Great Charles Street Birmingham B3 3HNt 0121 212 7700 f 03333 444 501

    PRELIMINARY

  • CONFIGURATION 1 CONFIGURATION 2

    BEAUFORT COURT, EGG FARM LANE,KINGS LANGLEY, HERTS WD4 8LR.

    TEL +44 (0) 1923 299200FAX +44 (0) 1923 299299

    G

    1 2

    F

    E

    D

    3 4 5

    C

    B

    A

    DRAWING NUMBER

    1 2 3 4 5

    DRAWN

    DRAWING TITLE

    PROJECT TITLE

    DRAWING NUMBER

    LAYOUT DWG

    6 7 8 9

    SCALE

    PURPOSE

    COORDS

    ISSUE

    10

    G

    ORIGINAL PLOT SIZE

    DATEDATE APPD REVISION NOTES

    T-LAYOUT NO.

    A3

    F

    E

    D

    6 7 8 9

    C

    B

    10

    A

    THIS DRAWING IS THE PROPERTY OF RENEWABLE ENERGY SYSTEMSLIMITED AND NO REPRODUCTION MAY BE MADE IN WHOLE OR IN PART

    WITHOUT PERMISSION

    TJS 060710 FIRST ISSUE050710SB01

    NTS

    PLANNING

    N/A

    N/AN/A

    GENERAL ARRANGEMENTCRANE HARDSTANDING

    WIND FARMWOOLLEY HILL

    02341D2226-04

    02341D2226-04

    09071002 SB ROTOR DIAMETER AMENDED090710TJS

    07091003 DJK MINOR AMENDMENTS070910MPW

    17121204 MP MINOR AMENDMENTS070113GE

  • TYPICAL RUNNING WIDTH 4.5-5.0m

    CUT TRACK SECTION

    0.25m SHOULDER0.25m SHOULDER

    EXISTING GROUND LEVEL

    DRAINAGE SWALESHOWN INDICATIVELY

    FILL TRACK SECTION

    (SEE NOTE 5)

    FLOATED TRACK SECTION

    SLOPING GROUND SECTION

    EXISTING GROUND LEVEL

    DRAINAGE SWALESHOWN INDICATIVELY

    TYPICAL RUNNING WIDTH 4.5-5.0m 0.25m SHOULDER0.25m SHOULDER

    TYPICAL RUNNING WIDTH 4.5-5.0m 0.25m SHOULDER0.25m SHOULDER

    EXISTING GROUND LEVEL

    EXISTING GROUND LEVEL

    TYPICAL RUNNING WIDTH 4.5-5.0m

    0.25m SHOULDER0.25m SHOULDER

    DRAINAGE SWALESHOWN INDICATIVELY

    DEPTH VARIES GEOSYNTHETIC MESH REINFORCEMENT.NUMBER OF LAYERS REQUIRED TO BEDETERMINED DURING DETAILED DESIGN.

    GEOTEXTILE SEPARATOR LAID DIRECTLYONTO VEGETATION MAT

    DRAINAGE SWALESHOWN INDICATIVELY

    BENCHING TYPICALLY300-500mm

    DEPTH VARIES(SEE NOTE 5)

    TYPICALLY 250-450mm DRAINAGE SWALESHOWN INDICATIVELY

    DEPTH VARIES

    BEAUFORT COURT, EGG FARM LANE,KINGS LANGLEY, HERTS WD4 8LR.

    TEL +44 (0) 1923 299200FAX +44 (0) 1923 299299

    G

    1 2

    F

    E

    D

    3 4 5

    C

    B

    A

    1 2 3 4 5

    DRAWN

    DRAWING TITLE

    PROJECT TITLE

    DRAWING NUMBER

    LAYOUT DWG

    6 7 8 9

    SCALE

    PURPOSE

    COORDS

    ISSUE

    10

    G

    ORIGINAL PLOT SIZE

    DATECHKD APPD REVISION NOTES

    T-LAYOUT NO.

    A3

    F

    E

    D

    6 7 8 9

    C

    B

    10

    A

    THIS DRAWING IS THE PROPERTY OF RENEWABLE ENERGY SYSTEMSLIMITED AND NO REPRODUCTION MAY BE MADE IN WHOLE OR IN PART

    WITHOUT PERMISSION

    TJS 060710 FIRST ISSUESB01

    1:100

    PLANNING

    N/A

    N/AN/A

    TRACK DESIGNTYPICAL ACCESS

    WIND FARMWOOLLEY HILL

    02341D2221-02

    PB02 DJK CMS ISSUE110313GE

    1. EFFECTIVE WIDTH OF TRACK TO BE4.5-5.0m ON STRAIGHT SECTIONS WITHWIDENING ON BENDS AND PASSINGPLACES.

    2. ALL EMBANKMENT SLOPES TO BEPROVIDED AT A STABLE ANGLE BASED ONTHE PROPERTIES OF THE MATERIALENCOUNTERED ON SITE.

    3. MATERIALS ARISING FROM TRACKCONSTRUCTION TO BE SEGREGATEDAND PLACED IN AGREED LOCATIONSADJACENT TO THE WORKING AREA.REINSTATEMENT AND/OR SPOILMANAGEMENT PLANS WILL BEDEVELOPED DURING THE DETAILEDDESIGN OF SITE INFRASTRUCTURE ANDWILL IDENTIFY AREAS OF RE-USE ANDPERMANENT STORAGE OF EXCAVATEDMATERIALS IN LINE WITH CURRENT BESTPRACTICE.

    4. RUNNING SURFACE, CAPPING LAYER ANDENGINEERED FILL TO BE FORMED FROMSUITABLE MATERIALS COMPACTED INLAYERS.

    5. GEOSYNTHETIC REINFORCEMENT MAY BEUSED TO REDUCE THE DEPTH OF TRACKCONSTRUCTION. REQUIREMENT TO BEDETERMINED DURING DETAILED DESIGN.

    6. A GEOTEXTILE SEPARATOR MAY BEINSTALLED BENEATH THECAPPING/ENGINEERED FILL LAYER FORALL TRACK CONSTRUCTION TYPESDEPENDING ON GROUND CONDITIONSENCOUNTERED ON SITE.

    RUNNING SURFACE

    CAPPING LAYER/ENGINEERED FILL

    TOPSOIL/PEAT LAYER

    LOAD BEARING STRATA TBC VIA IN-SITUTESTING

    SNOW POLES TO DELINEATE SITE TRACKS AT NOMINAL 50m INTERVALS

  • Storagearea

    RES office &meeting room

    Sub contractoroffices, drying room

    & canteen

    Laydown area

    Parking

    Site

    Roa

    d

    Chain link fence

    6m wide gateUnder roaddrainage

    Turning area

    Soak away(See note 4)

    Pedestrianaccess gate

    40m Septic tank(See note 3)

    Generator fortemporary compoundelectrics

    Fence 1.2m highbetween pedestrian and

    vehicular areas

    Skips with windshield and lid

    Hardstanding to compoundconsisting of compacted

    stone over a layer ofgoetextile to provide a cleanand firm surface suitable for

    cabins / heavy traffic

    Containers forRES use.

    Containers as required andsupplied by subcontractors

    80m

    Temporary passingplace allows fortemporary lorryparking

    6m wide gate

    Parking

    Toilets

    Oil separator(See note 4)

    Bundedrefueling

    area

    Storagearea

    Parking

    TemporaryStorage

    area

    20m

    Pedestrian access gate

    Soak away(See note 3)

    TYPICAL FENCE PANEL1:75 SCALE

    2.5m

    KERB EDGING FINISH

    NOTES

    1. NUMBER AND LOCATION OFCOMPOUND EQUIPMENT ANDFACILITIES ARE INDICATIVE ONLY

    2. STRUCTURE TO BE TEMPORARYAND TO BE REMOVED AFTERCONSTRUCTION.

    3. SEWAGE DISPOSAL TO BE INACCORDANCE WITH THE RELEVANTAGENCY REQUIREMENTS, TO SUIT THEGROUND CONDITIONS. A CESS PIT ORPACKAGE TREATMENT PLANT MAY BESUBSTITUTED FOR THE PROPOSEDSEPTIC TANK AND SOAKAWAY.

    4. THE USE OF AN OIL INTERCEPTORAND SOAKAWAY FOR THE BUNDEDREFUELLING AREA SHALL BE AGREEDWITH THE RELEVANT AGENCY TO SUITGROUND CONDITIONS. USE OF AFULLY COVERED BUNDED AREA MAYBE SUBSTITUTED FOR THE PROPOSEDOIL INTERCEPTOR AND SOAKAWAY.

    5. INTERNAL LAYOUT OF THECONSTRUCTION COMPOUND MAY BEREVISED TO SUIT THE CONTRACTORSWORKING REQUIREMENTS.

    BEAUFORT COURT, EGG FARM LANE,KINGS LANGLEY, HERTS WD4 8LR.

    TEL +44 (0) 1923 299200FAX +44 (0) 1923 299299

    G

    1 2

    F

    E

    D

    3 4 5

    C

    B

    A

    DRAWING NUMBER

    1 2 3 4 5

    DRAWN

    DRAWING TITLE

    PROJECT TITLE

    DRAWING NUMBER

    LAYOUT DWG

    6 7 8 9

    SCALE

    PURPOSE

    COORDS

    ISSUE

    10

    G

    ORIGINAL PLOT SIZE

    DATEDATE APPD REVISION NOTES

    T-LAYOUT NO.

    A3

    F

    E

    D

    6 7 8 9

    C

    B

    10

    A

    THIS DRAWING IS THE PROPERTY OF RENEWABLE ENERGY SYSTEMSLIMITED AND NO REPRODUCTION MAY BE MADE IN WHOLE OR IN PART

    WITHOUT PERMISSION

    TJS 060710 FIRST ISSUE050710SB01

    1:350@A1

    PLANNING

    N/A

    N/AN/A

    COMPOUND LAYOUTTYPICAL CONSTRUCTION

    WIND FARMWOOLLEY HILL

    02341D2220-02

    02341D2220-02

    17121202 MP UPDATED TO SUIT THE TOPOGRAPHY070113GE

  • 80m

    Containers as required andsupplied by subcontractors

    Skips with windshield and lidGenerator for temporary compound

    electrics

    SCALE : 1:300

    SOUTH ELEVATION

    SCALE : 1:300

    RES office &meeting room

    Sub contractoroffices, drying room

    & canteen

    RES office & Sub contractor offices, drying

    2.5m

    Generator for temporarycompound electrics

    Containers as required andsupplied by subcontractors

    Containers as required andsupplied by subcontractors

    Skips with windshield and lid

    Sub contractoroffices, drying room

    & canteen

    80m

    Toilets

    Containers as required and

    NORTH ELEVATIONSCALE : 1:300

    6m 6m 6m1m

    2.5m

    40m 20m6m

    Generator for temporary compound electrics

    2.5m2

    .5m

    WEST ELEVATION

    SCALE : 1:250

    40m

    ToiletsRES office &meeting room

    Sub contractor offices, dryingroom & canteen

    EAST ELEVATIONSCALE : 1:250

    20m

    2.5m

    2.5m

    NOTES

    1. NUMBER AND LOCATION OFCOMPOUND EQUIPMENT ANDFACILITIES ARE INDICATIVE ONLY

    2. STRUCTURE TO BE TEMPORARYAND TO BE REMOVED AFTERCONSTRUCTION.

    3. ALL DIMENSIONS ARE INDICATIVEAND SUBJECT TO CHANGE.CONTRACTOR MUST COMPLETE THEIROWN SURVEY BEFORE COMMENCINGDETAILED DESIGN.

    G

    1 2

    F

    E

    D

    3 4 5

    C

    B

    A

    DRAWING NUMBER

    1 2 3 4 5

    DRAWN

    DRAWING TITLE

    PROJECT TITLE

    DRAWING NUMBER

    LAYOUT DWG

    6 7 8 9

    SCALE

    PURPOSE

    COORDS

    ISSUE

    10

    G

    ORIGINAL PLOT SIZE

    DATEDATE APPD REVISION NOTES

    T-LAYOUT NO.

    A3

    F

    E

    D

    6 7 8 9

    C

    B

    10

    A

    PF 101110 FIRST ISSUE031110BC01

    AS SHOWN@A3

    PLANNING

    N/A

    N/AN/A

    COMPOUND LAYOUT ELEVATIONSTYPICAL CONSTRUCTION

    WIND FARMWOOLLEY HILL

    02341D2239-02

    02341D2239-02

    17121202 MP AMENDED TO SUIT THE REVISED LAYOUT070113GE

  • Laydown area

    Hardstanding to compoundconsisting of compacted stone

    over a layer of goetextile toprovide a clean and firm surface

    suitable for heavy traffic

    29.5

    m

    43.5m

    50.5m

    36.0

    m

    TemporaryStorage

    Area

    TemporaryStorage

    Area

    TemporaryStorage

    Area

    TemporaryStorage

    Area

    BEAUFORT COURT, EGG FARM LANE,KINGS LANGLEY, HERTS WD4 8LR.

    TEL +44 (0) 1923 299200FAX +44 (0) 1923 299299

    G

    1 2

    F

    E

    D

    3 4 5

    C

    B

    A

    DRAWING NUMBER

    1 2 3 4 5

    DRAWN

    DRAWING TITLE

    PROJECT TITLE

    DRAWING NUMBER

    LAYOUT DWG

    6 7 8 9

    SCALE

    PURPOSE

    COORDS

    ISSUE

    10

    G

    ORIGINAL PLOT SIZE

    DATECHKD APPD REVISION NOTES

    T-LAYOUT NO.

    A3

    F

    E

    D

    6 7 8 9

    C

    B

    10

    A

    THIS DRAWING IS THE PROPERTY OF RENEWABLE ENERGY SYSTEMSLIMITED AND NO REPRODUCTION MAY BE MADE IN WHOLE OR IN PART

    WITHOUT PERMISSION

    MPW 080910 FIRST ISSUE070910DJK01

    1 : 250 @ A3

    PLANNING

    BRITISH NATIONAL GRID 1936

    N/AN/A

    CONSTRUCTION COMPOUNDTEMPORARY ENABLING WORKS

    WIND FARMWOOLLEY HILL

    02341D2229-02

    02341D2229-02

    13021302 BC INTERNAL LAYOUT REVISED150213GE

    KEY

    NEW SITE TRACK

    EXISTING TRACK

    NOTES

    ENABLING WORKS COMPOUND TO BEUSED SOLELY FOR THE SHORT TERMSTORAGE OF MATERIALS DURINGCONSTRUCTION

    MATERIALS STORED WITHIN THEENABLING WORKS COMPOUND TO BEPLACED ALIGNED PARALLEL TOELLINGTON BROOK

    HARD STANDING AREAS TO BEREMOVED FOLLOWINGCONSTRUCTION

    NO FENCE TO BE ERECTED AROUNDENABLING WORKS COMPOUND

  • WF CONTROLROOM

    TURBINE SCADAROOM

    BUNDEDSTOREROOM

    DRYINGROOM

    WC

    STORE ROOM

    LIVING AREA

    OFFICE

    WF HVROOM

    TARIFFMETERROOM

    DNO HV ROOM

    TEMPGENERATORHARD STAND

    13m

    30m

    1.5m

    1.5m1.5m

    SEWAGE DISPOSAL TO BE INACCORDANCE WITH RELEVANTAGENCY REQUIREMENTS AND INACCORDANCE WITH BUILDINGREGULATIONS

    CONCRETE AREA TO FACILITATEPALLET LOADING EQUIPMENT

    47m1.5m 1.5m

    19m

    3m1.

    5m

    1.5m

    1.5m

    3m

    20m

    27m

    50m

    13m

    17m 1.5m1.5m

    PATH LEVEL TO TIE IN WITHADJACENT TRACK

    APPROXIMATELOCATION OFSOLAR TUBE

    NOTES

    1. ROOM DESCRIPTIONS AND POSITIONS OF DOORS,GATES, INTERNAL WALLS AND EXTERNAL EQUIPMENTARE INDICATIVE ONLY AND ARE SUBJECT TOREQUIREMENTS OF THE TURBINE SUPPLIER AND GRIDCOMPANY.

    2. LIGHTING & VENTILATION LEVELS WITHIN OFFICE TOBE DESIGNED FOR OCCASIONAL USE.

    3. POSITION OF DOORS AND GATES, ARE INDICATIVEONLY AND ARE SUBJECT TO REQUIREMENTS OF THETURBINE SUPPLIER AND GRID COMPANY

    4. LOCAL BUILDING MATERIALS AND FINISHES AREPROPOSED TO ENSURE THAT THE BUILDING IS INKEEPING WITH OTHERS IN THE AREA

    ?????????????????????????????????

    BEAUFORT COURT, EGG FARM LANE,KINGS LANGLEY, HERTS WD4 8LR.

    TEL +44 (0) 1923 299200FAX +44 (0) 1923 299299

    G

    1 2

    F

    E

    D

    3 4 5

    C

    B

    A

    DRAWING NUMBER

    1 2 3 4 5

    DRAWN

    DRAWING TITLE

    PROJECT TITLE

    DRAWING NUMBER

    LAYOUT DWG

    6 7 8 9

    SCALE

    PURPOSE

    COORDS

    ISSUE

    10

    G

    ORIGINAL PLOT SIZE

    DATEDATE APPD REVISION NOTES

    T-LAYOUT NO.

    A3

    F

    E

    D

    6 7 8 9

    C

    B

    10

    A

    THIS DRAWING IS THE PROPERTY OF RENEWABLE ENERGY SYSTEMSLIMITED AND NO REPRODUCTION MAY BE MADE IN WHOLE OR IN PART

    WITHOUT PERMISSION

    TJS 060710 FIRST ISSUE050710SB01

    1:200@A3

    PRELIMINARY

    N/A

    N/AN/A

    SUBSTATION LAYOUTCONTROL BUILDING AND

    WIND FARMWOOLLEY HILL

    02341D2222-02

    02341D2222-02

    17121202 MP UPDATED TO SUIT THE TOPOGRAPHY 070113GE

    SINGLE SIZED GRAVEL SURROUNDFOR EARTHING PROTECTION

  • VIEW 'B'

    13m

    VIEW B

    REAR ELEVATION OF BUILDING

    5.5m

    FRONT ELEVATION

    27m

    VIEW 'A'

    AIR CONDITIONINGUNIT.

    3m

    3m

    17m

    1.5m

    VIEW A

    VIEW B

    VIEW