Wood Group - NORWEP · Wood Group Design Methodology for Modifying a MODU into a FPU Anders M Moe...
Transcript of Wood Group - NORWEP · Wood Group Design Methodology for Modifying a MODU into a FPU Anders M Moe...
Wood Group
Design Methodology for Modifying a MODU into a FPU Anders M Moe
1st March 2017
• Wood Group Introduction
• Background
• Design Differences MODU vs FPU
• Main Design Changes Required for Converting MODU
• Design Case – A5000E to FPU
• Feasibility Evaluation
Agenda
2
To be recognised as the best
technical services company
to work with, work for and
invest in, with a relentless
focus on excellence.
Our vision
We provide smart technical
solutions which create and sustain
value for our customers.
Our purpose
$5bn revenue
About 30,000 people
40 countries
We are experienced
We are where you need us
6
With around 30,000 people
working in more than 40 countries
we have a strong network of
capability and expertise built over
30 years of successful operations
to help you wherever you need it.
We have a proven track record
7
Lightweight topside design
WORLD LEADER IN
In-house software development
Offshore decommissioning
Hook-up & commissioning
O&G brownfield contractor
Standard designs
Full offshore asset
management
Industry specifications for
flexible pipelines
Deepest TLP, SPAR and
platform
Longest and deepest
pipelines
Largest semi-submersible
Offshore wind
projects assessed
WORLD’S LEADING
PIONEER IN
Over 90 countries
PROJECTS IN 11.4GW
DESIGNED THE
WROTE THE
Semi-submersible units
1977 2014
1978197919801981198219831984198519861987198819891990199119921993199419951996199719981999200020012002200320042005200620072008200920102011201220132014
1986
Nortrym""Ross Rig
1997
C. Kirk Rhein Jr.
1999
Bideford Dolphin 2006
Blackford Dolphin1993
Borgny Dolphin
1980
Treasure Finder""Nordraug
1998
Borgland Dolphin1981
2001
GVA 4000MBingo9000-3
Transocean Searcher
1983
T. Swan
2011
COSLProspector
1977
Nordraug
1984
Sedco Phillips SS""T. Finder"
"Byford Dolphin
2002
Borgholm DolphinEirik Raude
1978
Polymariner2009
COSLPioneerCOSLInnovatorCOSLPromoter
1982
Nortrym""T. Hunter""T. Finder 2013
HYSY982Island Innovator
1996
Byford Dolphin
1995
Drillmar""Borgsten Dolphin
1979
Nortrym
1985
Dyvi Stena""Safe Holmia
2013
Safe Caledonia2000
Leiv Erikson
2014
Safe Scandinavia
More than 35 years experience with semi-submersibles
8
• For FPSOs conversion of tankers typically account for close to 2/3rds
• Conversion economically attractive for FPSOs
• Conversion of MODU (drillships, semis or jack-ups) are rare in the last 15 years
• Industry downturn resulting in a dramatic reduction in fleet utilization for MODUs
• Approx. 70% floater utilization per Q4 2016
• Projects are delayed, postponed or cancelled:
– Focus on increased confidence in reservoir and production profiles
– Large investments postponed if possible
– Early production facilities more interesting to some
• Continued strong focus on reducing CAPEX
– Standardization
– Simplification
Background
DEMAND DAYRATES STACKED RIGS
Market Analysis
Source Clarksons Research and IHS
• Drivers for MODU to FPU semi-submersible
conversion:
– Early production facility
– Minimum processing facility
– Full production facility
• May not be feasible for harsh environment areas
Drivers for Conversion
Differences between MODU and FPU
Parameter MODU FPU
Class/Flag Yes Typically designed to Class requirements.
Leased units often have class and flag
Inspection regime Typical 5 years SPS at quayside or dry-
dock
Typically inspection in lieu of dry docking
regimes
Location Worldwide mobile operations and
design for typ. 20 yrs
Remains at location for the
production/lease time (up to 20 yrs)
Mooring & station
keeping
Pre-laid or self mooring
Thrusters and DP
High spec long term pre-laid mooring and
no DP
Fit to purpose
equipment
Drilling eq. and utilities often integrated
in hull structure. (ship-style)
Topside process and utilities normally not
integrated in the hull. (offshore-style)
Transit and speed Transit speed generally a design
requirement
Transit is not relevant
Operational loads VDL (part of deadweight) is the main
design parameter
Topsides weight, footprint and riser loads
are main design drivers
Major evaluation and changes - hull
Hull
• Check and verification of global structure
• Check fatigue life
• Verify payload limitations and stability
• Assess hydrodynamic characteristics
• Assess mooring system arrangement
• Assess riser interface on hull
• Check major tank capacity
• For major buoyancy upgrades, evaluate installation of transverse pontoons
and removal of bracings
• Establish inspection regime in lieu of typical SPS class renewal
Major evaluation and changes – topsides & utilities
Topsides Utilities
• Introduce new process
topsides
• FPU with drilling capabilities
• Complete layout
redesign
• Typical minimum
processing facility
• FPU without drilling
capabilities
• Removal of drilling
equipment
• Design and installation
of new processing
modules
• Review and upgrade utilities
• Cooling water
• Fire system
• Fuel and lub systems
• Power generation
• HVAC
• Safety systems – F&G and ESD
• LQ and working spaces
Weight distribution
Semi submersible MODU Semi submersible FPU
Example MODU FPU
MODU main particulars
Square Column Width 15.50 m
Number of Columns 4
Pontoon Width 16.50 m
Pontoon Height 10.05 m
Operational Draught 17.50 m
Elevation Underside Deck Box 29.55 m
Overall Width 70.50 m
Overall Length 104.50 m
Deck Box Height 8 m
Deck Area 5 812 m²
Displacement (approx.) 40 800 t
Lightship weight 25 500 t
Variable Deck Load 5 000 t
• Base case is to use the same hull and upgrade/modify where necessary to increase
the topside weight
• Particulars are the same but weight budget is changed:
FPU main particulars
Item Weight VCG
Hull Weight (Including Riser and
Mooring Forces)
20 100 t 11 m
Topsides Dry Weight 10 000 t 44 m
Riser & Mooring Loads 3 000 t 2 m
Fluids & Consumables (ex. Ballast) 4 000 t 17 m
Margin 2 000 t 29 m
Ballast 5 700 t 6 m
Total 44 800 t 19.8 m
Potential hull modifications:
1. Blisters and sponsons
• Offers improved stability and additional topsides payload
• Will influence motion characteristics
• Relatively minor modification
2. Replace bracings with transverse pontoon
• Requires modifications to areas subject to high stresses
• Offers significantly increased topsides payload (order of magnitude 5000 tonnes)
• May be positive with regards to service life compared to bracings
3. Transverse pontoon + blisters and sponsons
• Relatively large modification
• Offers significantly improved stability and additional topsides payload
Potential modifications
Potential modifications
1 2 3
Opportunities
• Upgrade and life extension well known to the industry (I.e. Aker H3 rigs from the 1970s still operating, some as deepwater units)
• Steel replacement/renewal also well known in the industry
× Challenges/threats
• Lifetime extension and fatigue sensitive areas
– Pontoon/bracing configuration
• Payload capacity for integrated production and drilling, and for full production facilities
• Riser interface and hang-off
• Mooring arrangement
• Air gap can limit the operational areas
Technical Feasibility Evaluation
Opportunities
• Lease and operate models
• Reduced CAPEX
– Low hull cost
– High number of laid-up rigs
– Reduced topsides cost?
× Challenges/threats
• Cost of upgrade and limitation to the renewal scope
• Topside facility integration
• Suitable fields
– Infrastructure
– Environmental conditions (e.g. wind and wave loading)
– Reservoir characteristics
Commercial Feasibility
• Drilling market situation is pushing many drilling rigs to be laid-up or scrapped
• This gives availability of reusing relatively modern units for other purposes
• Owners and Investors need to be creative in order to reduce the risk of big financial losses
• Modifying a semi-submersible from drilling to production is technically feasible and could be commercially attractive
Conclusion