ID: ST/P/BLDG/QFM/SPC/APPX0710.DOC WLD N7 C34 (Feb 13) APPENDIX TO PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS REF DESCRIPTION CLAUSE DETAILS (i) Option Modules : 1.1(c) a. Bills of Quantities Not Applicable b. Unused Materials or Goods Not Delivered to Site Applicable c. Nominated Subcontractors Not Applicable (ii) Defects Liability Period (12 months if none stated) 1.1(k) See ref (xii) of this Appendix (iii) Superintending Officer’s Representative 1.1(ac) The Managing Directors, deputy Managing Directors, Project Directors, Vice Presidents or Qualified Persons of Surbana International Consultants Pte. Ltd.. The powers vested in the Superintending Officer under Clause 31 of the Conditions of Contract shall only be exercised by the Managing Directors of Surbana International Consultants Pte. Ltd.. (iv) Limitations on The Authority of the Superintending Officer 2.1 Nil (v) Security Deposit : a. Number of days to deposit after Letter of Acceptance (14 days if none stated) b. Quantum 4.5(1) 14 days 5% (vi) Time for Completion 14.1 See ref (xii) of this Appendix (vii) Rate of Liquidated Damages 16.1 See ref (xii) of this Appendix The cumulative amount of liquidated damages payable by the contractor for all occasions of delay under the contract shall not exceed $50 million or the Contract Sum, whichever is lower.

Transcript of Wol n7c34 Appendix to Psscoc

ID: ST/P/BLDG/QFM/SPC/APPX0710.DOC WLD N7 C34 (Feb 13)

APPENDIX TO PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

REF DESCRIPTION CLAUSE DETAILS

(i) Option Modules : 1.1(c) a. Bills of Quantities Not Applicable

b. Unused Materials or Goods Not Delivered to Site

Applicable

c. Nominated Subcontractors Not Applicable

(ii) Defects Liability Period (12 months if none stated)

1.1(k) See ref (xii) of this Appendix

(iii) Superintending Officer’s Representative

1.1(ac) The Managing Directors, deputy Managing Directors, Project Directors, Vice Presidents or Qualified Persons of Surbana International Consultants Pte. Ltd.. The powers vested in the Superintending Officer under Clause 31 of the Conditions of Contract shall only be exercised by the Managing Directors of Surbana International Consultants Pte. Ltd..

(iv) Limitations on The Authority of the Superintending Officer

2.1 Nil

(v) Security Deposit : a. Number of days to deposit after

Letter of Acceptance (14 days if none stated)

b. Quantum

4.5(1)

14 days

5%

(vi) Time for Completion 14.1 See ref (xii) of this Appendix

(vii) Rate of Liquidated Damages 16.1 See ref (xii) of this Appendix The cumulative amount of liquidated damages payable by the contractor for all occasions of delay under the contract shall not exceed $50 million or the Contract Sum, whichever is lower.

ID: ST/P/BLDG/QFM/SPC/APPX0710.DOC WLD N7 C34 (Feb 13)

APPENDIX TO PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

REF DESCRIPTION CLAUSE DETAILS

(viii) Insurance

a. Limitation on extent of Insurer's liability

27.1 $2 million for any one accident and unlimited for the period of insurance.

b. Percentage for Professional Fees 28.1 Nil

(ix) Period for Honouring Certificate (21 days if none stated)

32.6 21 days

(x) Rate of Interest upon Unpaid Sums (5 percent if none stated)

32.6 7 percent

(xi)

Fluctuations

33

Not Applicable Refer to Specification Clause No. 1.2.12 and 72.1

ID: ST/P/BLDG/QFM/SPC/APPX0710.DOC WLD N7 C34 (Feb 13)

APPENDIX TO PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

Ref (xii) PART A: BUILDING WORKS AND OTHER INSTALLATIONS AT WOODLANDS N7 C34 (TOTAL 194

DWELLING UNITS) PHASE/PART

OF THE WORKS TIME FOR

COMPLETION RATE OF

LIQUIDATED DAMAGES DEFECTS LIABILITY

PERIOD

Phase 1 ESS near to Block 717B

Within twenty (20) months and fifteen (15) days

Dollars One Thousand Eight Hundred only ($1,800) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) months from Date of Substantial Completion of this Phase

Phase 2 Minor Sewer

Within twenty-five (25) months and fifteen (15) days

Dollars Five Hundred only ($500) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) months from Date of Substantial Completion of this Phase

Phase 3 Podium Car Park Block 717C

Within twenty-six (26) months and fifteen (15) days

Dollars Six Hundred and Thirty only ($ 630 ) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) months from Date of Substantial Completion of this Phase

Phase 4 Block 717B

Within twenty-seven (27) months and fifteen (15) days

Dollars Two Thousand and Nine Hundred only ($2,900) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) monthsfrom Date of Substantial Completion of this Phase

Phase 5 Block 717A

Within twenty-eight (28) months and zero (0) days

Dollars Three Thousand and Thirty only ($3,030) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) months from Date of Substantial Completion of this Phase

Phase 6 Driveway, Service Road and CE Drain

Within thirty (30) months and zero (0) days

Dollars Five Hundred only ($ 500) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) months from Date of Substantial Completion of this Phase

Phase 7 Remaining Site Structures, Site works, Precinct Pavilion Block 717, E-Deck including Plaza, Adult Fitness Corner, Elderly Fitness Corner, Playground, Shelters

Within thirty (30) months and zero (0) days

Dollars Three Hundred and Sixty only ($360) per day for every day the Works in this Phase remain incomplete

Twelve ( 12 ) months from Date of Substantial Completion of this Phase

PART B: CONTINGENCY WORKS

PHASE/PART OF THE WORKS

TIME FOR COMPLETION

RATE OF LIQUIDATED DAMAGES

DEFECTS LIABILITY PERIOD

Contingency Works As stated in Works Order(s)

Refer to Section 76 of the Specifications, Clause 76.8