Wireless Service Projectat Qualcomm Stadium
Haruhisa Kamiyama
July 14, 2004
GBA 573 IT Project Management
Haruhisa Kamiyama 27/14/2004
Introduction
Qualcomm Stadium Profile
built in 1967 owned and operated by the City of San Diego the naming rights obtained in 1997 until 2017 used by Chargers and Aztec for football Under renovation
seat arrangement will become for football trolley extension
Problems Padres has gone to Petco Park Chargers may leave after 2008
Haruhisa Kamiyama 37/14/2004
Project Analysis
Problem Statement Qualcomm Stadium is facing the biggest problem after Padres has
gone. need to implement new service to patrons.
revisit the stadium get new customers
Project Objectives Providing the system that allows patrons to do:
Instant messaging to other patrons Online Voting Snack bar ordering Access to statistics regarding other athletic events Ability to view instant replays
Increasing attractiveness to get Chargers stay in Qualcomm Stadium
Haruhisa Kamiyama 47/14/2004
Project Scope
Project Justification This service will provide new stadium experience to patrons
Product Characteristics Hard-wired consoles are to be installed on only Club and Press seats
(about 10,000) for free Other patrons can use their own PDAs or PCs with wireless access or
rental PDA will be provided with charge Project Deliverables
Consoles that are installed on designated seat. Servers Software Web Contents Manuals (store users guide, patrons users guide, administration guide)
Haruhisa Kamiyama 57/14/2004
Cost Analysis
Revenue Increase sales of season ticket (2,000 x $1000) Increase number of guests (3,000 x $50) Increase sales of food service (10,000 x $5) PDA rental (700/game x 10 games x $5)
Setup Cost Consoles (10,500 x $900) PDA (1,000 x $700) Servers ($300,000) Software ($1,000,000)
Maintenance Cost Upgrade web contents ($300,000/year) Hardware maintenance (5% of purchasing price)
Haruhisa Kamiyama 67/14/2004
ROI AnalysisProject Assumptions
Your company
What are the setup costs for your
project? $11,450,000
What are the annual maintenance
costs? $822,500
What are the annual benefits? $4,035,000
Enter your discount factor* 3%
Timeframe for calculating return (in
years)** 3
Year 1 net benefits $3,212,500
Year 2 net benefits $3,212,500
Year 3 net benefits $3,212,500
The ReturnCumulati
veDiscounted
Example 150% 124%
Your company 84% 79%
Haruhisa Kamiyama 77/14/2004
Breakeven Analysis
0
5000000
10000000
15000000
20000000
1 2 3 4 5
Setup cost
Accumulatedbenefit
Haruhisa Kamiyama 87/14/2004
Measures of success
Increasing sales of season tickets by 5% Increasing sales of food and drink service
by 5% 10% of patrons use this system Chargers stays in Qualcomm Stadium
after 2008
Haruhisa Kamiyama 97/14/2004
Feasibility
Technical Only use existing technologies
Economic Cost will pay with in four years
Operational Many people can use computer and the Internet. Staffs use computerized system day-to-day-basis
Haruhisa Kamiyama 107/14/2004
Risk analysisincrease revenue
don’t increase revenue
Chargers leave Qualcomm
decrease revenue
Chargers leave Qualcomm
New Wireless Service
with free console
No
without free consoleincrease revenue
don’t increase revenue
don’t increase revenue
probability x benefit
70% x -$1.8M
30% x -$11.5M
50% x $1.1M
40% x $2.7M
10%
10% x $0
70% x -$3M
20%
-$4.7M
Total Risk
-$0.7M or Chargers
go
-$2.1M or Chargers
go
Haruhisa Kamiyama 117/14/2004
Tasks and ScheduleID Task Name Duration Start Finish
1 Develop Specification 10 days Mon 1/3/05 Fri 1/14/05
2 Web site requirement 10 days Mon 1/3/05 Fri 1/14/05
3 Software requirement 10 days Mon 1/3/05 Fri 1/14/05
4 hardware specs 3 days Mon 1/3/05 Wed 1/5/05
5 Implement Software 40 days Mon 1/17/05 Fri 3/11/05
6 Web contents 30 days Mon 1/17/05 Fri 2/25/05
7 monitor test 5 days Mon 2/28/05 Fri 3/4/05
8 Ordering system 2 mons Mon 1/17/05 Fri 3/11/05
9 Instant messaging 1 mon Mon 1/17/05 Fri 2/11/05
10 Install hardware 57 days Thu 1/6/05 Fri 3/25/05
11 select hardwares 10 days Thu 1/6/05 Wed 1/19/05
12 install wireless base station 5 days Thu 1/20/05 Wed 1/26/05
13 Install software to the terminals 10 days Mon 3/14/05 Fri 3/25/05
14 install terminals 10 days Tue 2/1/05 Mon 2/14/05
15 install servers 15 days Thu 1/20/05 Wed 2/9/05
16 System test 30 days Mon 3/28/05 Fri 5/6/05
1/3 1/14
1/3 1/14
1/3 1/5
1/17 2/25
2/28 3/4
1/17 3/11
1/17 2/11
1/6 1/19
1/20 1/26
3/14 3/25
2/1 2/14
1/20 2/9
3/28 5/6
12/19 1/2 1/16 1/30 2/13 2/27 3/13 3/27 4/10 4/24 5/8 5/22December January February March April May
Haruhisa Kamiyama 127/14/2004
Final Analysis/Method of Evaluation
Final analysis Implementation cost is highBut we must get Chargers stay in Qualcomm
Stadium Method of Evaluation
Increasing patronsHigh usage of the system Increase sales of food services.