2009 1 Wind farm Baku 50 Megawatts renewable energy in co-operation of

Transcript of Wind farm Baku

Page 1: Wind farm Baku

2009 1

Wind farm Baku

50 Megawatts renewable energy

in co-operation of

Page 2: Wind farm Baku

2009 2

Project scope

• Turn key delivery of 50 MW Wind farm – 20x 2,5 MW Wind energy converter (WEC) up to 80m hub height

– Project will involve:

• Finance structuring

• Design

• Procurement

• Construction

• Commissioning

• Training of customers employees

• Logistics / DDU

• Management (Project, Quality, Construction)

– Project duration: 16 months (Sept. 09 – Dec.10; dependent of L/C)

Page 3: Wind farm Baku

2009 3

Project stakeholders

Turn key delivery of 50 MW Wind farm

The project will involve

– financing by two European banks with the support and warranty of

International Bank of Azerbaijan

– an innovative financing structure developed by Mitaki project GmbH

Hamburg (Germany) with great support of the federal Republic of

Germany which grants an export credit insurance through its state-owned

insurance agency Euler Hermes Kreditversicherung

– approximately 15 German and European companies for engineering,

design, logistics and manufacturing of equipment as well as 10 Azeri

companies for construction works, local logistics and management under

the leadership of the general supplier airwerk GmbH, Essen (Germany)

Page 4: Wind farm Baku

2009 4

Organizational structure

Financing

Consulting

Legal advice

Airwerk: System responsible

engineering

logistics

Key partner

WECTrans-former

Tower Construction others

Customer: Caspian Management System & Aztorq

Owner Operation Maintenance Energy supply

Page 5: Wind farm Baku

2009 5

General information

Location of pilot

Wind farm

Wind energy potential in the Absheron economical region about 1000 Megawatts

Page 6: Wind farm Baku

2009 6

Location „Yeni Yashma“

Highway

Sumgayit

WEC

Co ordinates of land boundary

1

2

3

Page 7: Wind farm Baku

2009 7

Scope & Interfaces pilot wind farm “Yeni

Yashma”

transformer

transformer

transformer

transformer

public

Electrical network

Main Power line: 110 kV

Connection cabling

Approx. 200 m

690 V

Low voltage

20 kV medium voltage level

Redundant 31,5 MVA

Transformer station

Hand over / Connection to

public electrical network

provision

by purchaser

deliverables

supplier

Internal park communication

ISDN

Public telephone

network

Modem

50MW: 20x 2,5 MW WEC

Page 8: Wind farm Baku

2009 8

Page 9: Wind farm Baku

2009 9

Turbine production

Page 10: Wind farm Baku

2009 10

Transport of blades

Page 11: Wind farm Baku

2009 11

Hub with blades

Page 12: Wind farm Baku

2009 12

Hub with blades

Page 13: Wind farm Baku

2009 13

Future view “Yeni Yashma”

Page 14: Wind farm Baku

2009 14

Future view “Yeni Yashma”

Page 15: Wind farm Baku

2009 15

Thank you

Page 16: Wind farm Baku

2009 16

1:Location „Yeni Yashma“ North View

Page 17: Wind farm Baku

2009 17

2: Location „Yeni Yashma“ canal

Page 18: Wind farm Baku

2009 18

3:Location „Yeni Yashma“ East View