Williamson's Lake report

download Williamson's Lake report

of 92

Transcript of Williamson's Lake report

  • 8/18/2019 Williamson's Lake report

    1/92

    PREPARED BY: JANUARY 26TH  , 2016

    WILLIAMSON’S LAKE COMMUNITY

    PARK & CAMPGROUNDCONCEPT PLAN

  • 8/18/2019 Williamson's Lake report

    2/92

  • 8/18/2019 Williamson's Lake report

    3/92

    WILLIAMSON’S LAKE COMMUNITY PARK & CAMPGROUND

    CONCEPT PLAN

    SELKIRK PLANNING & DESIGN| Community Planning | Urban Design |Box 1994Revelstoke, BC V0E 2S0(250) [email protected]

    LARCHLandscape + Authentic Mountain DesignBox 1738Golden, BC V0A [email protected]

    TAKE TO HEART CONTRACTING LTD.Box 2368776 Westside Rd.Revelstoke, BC V0E 2S0(250) 837-4482taketoheart.ca

    PREPARED FOR:

    THE CITY OF REVELSTOKE DEPARTMENT OF PARKS, RECREATION & CULTURE P.O. BOX 170600 CAMPBELL AVE.REVELSTOKE, BC V0E 2S0(250) 837-9351

    SUBMITTED ON JANUARY 26TH  BY:

  • 8/18/2019 Williamson's Lake report

    4/92

  • 8/18/2019 Williamson's Lake report

    5/92

    CONTENTS

    PART 01: PROJECT INTRODUCTION 1

    01.01 PROJECT BACKGROUND 1

    01.02 PROJECT PURPOSE 1

    PART 02: PROJECT PROCESS 202.01 REVIEWING PREVIOUS PLAN PRIORITIES 2

    02.02 HISTORICAL/PRECEDENT RESEARCH 2

    02.03 SITE ASSESSMENT – IDENTIFY MAIN ISSUES 2

    02.04 OPPORTUNITIES 4

    02.05 DESIGN CONCEPTS 6

    02.06 PUBLIC OPEN HOUSE 7

    02.07 FEEDBACK ON CONCEPT PLANS 7

    PART 03: RECOMMENDATIONS 8

    03.01 COMMUNITY INPUT ON PRIORITIZED RECOMMENDATIONS 8

    03.02 PRIORITIZED RECOMMENDATIONS 8

    03.03 IMPROVEMENTS & CONSIDERATIONS 24

    PART 04: IMPLEMENTATION 26

    04.01 PHASING 26

    APPENDICES 29

  • 8/18/2019 Williamson's Lake report

    6/92

  • 8/18/2019 Williamson's Lake report

    7/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT1

     

    PART 01: PROJECT INTRODUCTION

    01.01 PROJECT BACKGROUND

    In September 2015 consultants Selkirk Planning & Design (SPD), in partnership with Larch Landscape + Authentic Moun-tain Design (LLAMD) and Take To Heart Contracting (TTHC) undertook site analysis and conceptual design for the William-son’s Lake Campground and Day Use Area. The 2015 site plan is an update to a previous site plan completed in 2011 The2011 Plan can be viewed in Appendix A.

    The project was to focus on three main areas:

    • Plan for the long-term replacement of the aging existing day use and campground buildings;

    • Improving the day use area of the park; and

    • Improving the campground to bring it up the standards of a municipal park in a BC Resort community.

    01.02 PROJECT PURPOSE

    Prior to beginning the project, SPD met with City staff to clarify the project purpose. The priorities for the project are to:

    • Improve and enhance Williamson’s Lake;

    • Make it feel like a community park rather than a private campground; and

    • Create a great public space and increase resident and tourist visits.

    Photos of existing park and campground 

  • 8/18/2019 Williamson's Lake report

    8/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT2

     

    PART 02: PROJECT PROCESS

    02.01 REVIEWING PREVIOUS PLAN PRIORITIES

    Before beginning the project, the previous site plan, developed in 2011, was reviewed and updated. The Key Priorities thatwere completed were acknowledged and incomplete priorities were forwarded to the 2016 plan. The 2011 priorities weresent out to community stakeholders involved with the previous plan to review and conrm their inclusion in the 2015 plan.

    02.02 HISTORICAL/PRECEDENT RESEARCH

    Historical research of Williamson’s Lake was done at the Revelstoke Museum & Archives before beginning any design oranalysis work. The nal design was inuenced by images of the old park with a central stairway down to the water as a formalprocession down to the water. See Appendix B. Precedents were studied to help brainstorm ideas and adapt other improve-ments and enhancements for Williamson’s Lake.

    02.03 SITE ASSESSMENT – IDENTIFY MAIN ISSUES

    The design process began with a site assessment. SPD, LLMAD & TTHC walked the site, took photos and notes of the day usearea, the campground and the buildings. During the site visit, the team interviewed the Campground Manager to betterunderstand the issues and opportunities for the day use area and campground. A map was developed to identify all issues,and locate and describe them.

    From the issues a map of opportunities was developed to describe how each issue could be addressed. The opportunitiesmap focussed on all the recommendations big and small. These recommendations fell under three main focus areas iden-tied in section 01.01 on page 1.

    The Issues Map & Boards can be reviewed in Appendix C.

    Photos courtesy of Revelstoke Museum & Archives

  • 8/18/2019 Williamson's Lake report

    9/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT3

     

    Campsite Markers

    Existing campground showers & washrooms

    Existing pathway to the beach

    RV sites

    Campsite signage

    Upslope erosion

    Undefned parking spaces

    Beach condition

    Existing food service

    Road and campsites along the waterfront 

    Signage

    Existing day use building

  • 8/18/2019 Williamson's Lake report

    10/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT4

     

    02.04 OPPORTUNITIES

    The recommendations focused on the following 3 main areas:

    • Plan for the long-term replacement of the aging existing day use and campground buildings;

     ◦ This includes:

     g cleaning up clutter to improve the day use experience;

     g providing a better food service experience;

     g providing a better campground reception experience;

    • Improving the day use area of the park;

     ◦ This includes:

     g providing better access to the beach;

     g improving and expanding the public beach;

     g successional landscape planning;

     g proposing activity areas, and better placemaking; and

    • Improving the campground to bring it up the standards of a municipal park in a BC Resort community;

     ◦ This includes:

     g leveling and formalizing camping sites;

     g improving privacy, signage and layout.

       I   S   S   U   E

       0   9 .   0   8 .   2   0   1   5

       R   E  -   I   S   S   U   E

       C   L   I   E   N   T

       C   i   t  y   o   f   R   e  v   e   l   s   t   o   k   e  -   P   a   r   k   s ,   R   e   c   r   e   a   t   i   o   n   &   C  u   l   t  u   r   e   D   e   p   t .

       6   0   0   C   a   m   p   b   e   l   l   A  v   e .

       P .   O .   B   o  x   1   7   0

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   8   3   7  -   9   3   5   1

       S   E   L   K   I   R   K   P   L   A   N   N   I   N   G   &   D   E   S   I   G   N

       B   o  x   1   9   9   4

       1   0   1   S   e   c   o   n   d   S   t .   E

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   2   0   0  -   0   6   8   0

       E  :   s   e   l   k   i   r   k   p   l   a   n   n   i   n   g   @   g   m   a   i   l .   c   o   m

       P   R   O   J   E   C   T   N   O .

       2   0   1   5  -   C   O   P  -   W   L

       P   R   O   J   E   C   T

       W   i   l   l   i   a   m   s   o   n   ’   s   L   a   k   e   D   a  y   U   s   e   A   r   e   a   &

       C   a   m   p   g   r   o  u   n   d   C   o   n   c   e   p   t   P   l   a   n

       D   R   A   W   N   B   Y

       F   B ,   J   J

       D   E   S   C   R   I   P   T   I   O   N

    a

    05

    OPPORTUNITIES

    01 Improved Signage @ Airport Way 

    02 Overflow Day Use Parking w/ Improvements

    03 Entry Sign @ Important Wayfinding View 

    04 Narrow Road for One Way 

    05 Campground Registration Parking

    06 Vehicular Wayfinding Signage

    07 Plaza & Pedestrian Wayfinding Signage

    08 Day Use Parking - Defined Spaces

    09 New Day Use & Office Building(s)

    09.1 Change rooms (3M, 3F)

    09.2 Washrooms (3M, 3F)

    09.3 Wheelchair accessible washroom & change room

    09.4 Campground office

    09.5 Food service kitchen

    09.6 Outdoor covered dining area & viewing deck

    09.7 Laundry 

    09.8 Outdoor wood storage

    09.9 Potential caretaker residence

    09.10Rinse showers for day use patrons

    09.11Garbage & recycling storage

    09.12 Indoor lockable storage for paddleboards, paddles, etc.

    09.13Outdoor cooking shelter & fish-washing station (stand alone build-

    ing - open air, stove, sink, bear-aware garbage)

    09.14Formal day use entry/gateway 

    09.15 Incorporate historical/interpretive information (heritage panels)

    10 Re-vegetate Slope

    11 Formal Path/Stairs Down to Beach

    12 Private Property (or Trail) Signage

    13 Formalize Beach Area & Canoe Launch

    14 Permanent Wheelchair Accessible Dock

    15 Improved Beach Signage

    16 Pathway Defines/Protects Beach & Seating Area

    17 Wheelchair Accessible Pathway to Beach

    18 Mini Putt Moved Around Playground

    19 Successive Planting Area

    19.1 Plantspeciestoreplaceexistingtreesastheynearthe endoftheirlifespan

    20 Wheelchair Accessible Viewing Dock

    21 Campsites Removed From Beach - Public Beach

    22 Slip n’ Slide Route (Special Event Only)

    23 Beach Volleyball Court on Beach

    24 Walk-In Tent Sites Replace Beach Sites

    24.1 ~10 tenting sites

    24.2 Opens up the beach to more public use

    25 Expanded Yurt Camping Area

    25.1 4-6 Yurts + parking area - Walk-in only 

    26 Parking Area for Walk-In Sites & Re-vegetation

    27 Fishing/Wildlife Viewing Dock28 Level Tent Sites & Improve Parking Pad Access

    28.1 Level sites with wood berms & fill

    28.2 Change vehicle back-in angle where possible

    28.3 Improved site marking

    29 Private Property Signage

    30 Improved “No RV Access” Sign

    31 New Campground Shower/Washroom

    31.1 Move existing campsite & place building closer to the road

    31.2 Showers (3M, 3F)

    31.3 Washrooms (3M, 3F)

    31.4 Wheelchair accessible washroom & shower

    31.5 Roof extension for covered cooking area (2 cooking areas)

    31.6 Dish washing station

    31.7 Screened outdoor materials / gas tank storage

    32 Formalized RV Sites

    32.1 Formal RV pads

    32.2 Permanent picnic table & fire location

    32.3 Improved site marking

    33 Flexible Open Space Area

    34 Vegetation to Create Privacy Screening

    35 Trees to Provide Shade for Playground

    36 Remove Dangerous Trees

    37 Formalized Small Campground Sites

    37.1 Vegetation buffers

    37.2 Permanent picnic table & fire location

    37.3 Improved site marking

    38 Narrow Road for One Way 

    39 Improved Signage for RV Empty Station

    40 Formalized Day Use Parking Stalls

    41 Overflow/Winter Camping Area

    41.1 Suitable for RVs or tents

    41.2 Potential winter yurt area - Move yurts from summer location

    42 Reverse Traffic Direction

    42.1 Improves visual access to day use & office building - wayfinding

    42.2  Access to “preferred” day use parking first

    42.3 Improves ability for RVs to back into camping sites

    42.4 Reduces RVs driving down “tent only” road

    01 03 04 05 07 08 12 13 1409 1106 1002

    23

    27

    21

    24

    29

    28

    26

    25

    20

    22

    15

    16

    17

    18

    19

    32

    33

    41

    40

    38

    42

    39

    30

    31

    36

    34

    37

    35

  • 8/18/2019 Williamson's Lake report

    11/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT5

     

    Hammock area was explored 

    Yurt camping was explored 

    Fishing dock 

    Expanded dock with new fnishing

     An amphitheater was explored 

    Succession planting with appropriate native species

    Proposed sitting docks were explored 

    Simple, modern building design proposed 

    Formalizing campgrounds & walk-in sites

    Improved campsite markers

    Wheelchair accessible pathway 

    Proposed buildings would have food service

  • 8/18/2019 Williamson's Lake report

    12/92

  • 8/18/2019 Williamson's Lake report

    13/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT7

     

    02.05.02 Building Concepts

    Each of the three concepts had slightly different building layouts that helped illustrate each concept. The differing buildinglayout concepts are interchangeable and could work in any of the three concepts. Up to 5 building concepts are presentedon p. 4 with a breakdown of costs for each concept.

    02.06 PUBLIC OPEN HOUSE

    All three concept plans and building concepts were presented to the public at an open house at the Revelstoke Commu-nity Centre on November 23rd, 2015. There were 18 attendees who provided comments about the concepts. Commentswere submitted via a short survey. The survey and its results are summarized in Appendix D. The panels and surveys weremounted in the main foyer of the community centre until Monday November 30th, 2015. The full package of Open HouseMaterials can be found in Appendix E.

    02.07 FEEDBACK ON CONCEPT PLANS

    The comments from the open house were summarized and reviewed with the Director or Parks, Recreation and Culture.The feedback revealed that there was very little support for the expansion of the campground (Option 2). There was littledifference in support for the Community Park (Option 1) or Balanced Option (Option 3). A list of proposed improvementswas voted on by community members. The survey results led to the proposed recommendations in this plan.

    Several Building Concepts were explored 

  • 8/18/2019 Williamson's Lake report

    14/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT8

     

    PART 03: RECOMMENDATIONS

    03.01 COMMUNITY INPUT ON PRIORITIZED RECOMMENDATIONS

    The survey results were reviewed with the Director of Parks, Recreation and Culture to prioritize the highest priority rec-ommendations. The highest priority recommendations were chosen based on the survey results and an assessment of theissues and potential benets of some of the proposed recommendations.

    The top three improvements as voted on by the community were:

    1. Improved Buildings

    2. Accessible Pathway

    3. Landscape Improvements and succession planting

    The proposed dock improvements to make them accessible was the fourth highest improvement, but support was notice-ably lower than for the top 3.

    While the campsite improvements were low on the list of preferred options, both SPD and the Director of Parks, Recreationand Culture felt that there would be very little community support for this, but that it was important to include campgroundimprovements in the list of recommendations. There was little to no support for campground expansion and yurt camping.

    Note: Pathways and docks within 30m of the high water mark are subject to RAR approval by the Government of BC.

    The prioritized recommendations are described below.

    03.02 PRIORITIZED RECOMMENDATIONS

    03.02.01 New Buildings

    The plan recommends the replacement of the campground washroom & shower building, and the change room andwashroom. The recommendations are proposed to address issues with the aging infrastructure. The major benets of thenew building locations are that they house all the various activities needed for this site to function as both a park andcampground, and they act as a landmark to help people navigate the site. They become the physical anchors and identityfor Williamson’s Lake.

    The Building concepts focus on 2 or 3 main buildings. The highest priority improvement is to replace the campgroundwashroom & shower building which has reached the end of its lifespan. The second-highest priority is to remove thetrailers and outdoor storage used for day use food service and campground registration. The third building priority is toreplace the existing day use change room & washroom building, which is nearing the end of its lifespan. The day use &campground reception building and existing change room and washroom building replacement has been presented asve separate options. Options 1 to 3 examine a two-phased process that replaces the trailers and outdoor storage in the

    near future (3-5 years), while replacing the existing change room & washroom once it has reached the end of its lifespan(6-10 years). Options 4 to 5 examine a single-phased process that builds the day use building, campground reception andchange room & washroom at the same time once the existing building has reached the end of its lifespan.

    The campground washroom/shower building and building options 1 to 3 were presented at the Public Open House. Build-ing Options 4 and 5 were created afterwards. No building plans or visualizations were prepared for Options 4 and 5.

    The summary of recommendations identies the benets, challenges and cost estimates of constructing a new building.

  • 8/18/2019 Williamson's Lake report

    15/92

  • 8/18/2019 Williamson's Lake report

    16/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT10

     

    A) Campground Washroom & Shower Building

    The campground washroom & shower buildingis a simple rectangular structure. It would beconstructed to be wheelchair accessible. Thebuilding would have 3 showers, and 3 toilets

    with an additional wheelchair accessible wash-room and shower. Extra space within the build-ing is planned to act as storage for water heat-ers, cleaning equipment, and other equipmentrelated to the building function.

    A single-pitch roof extends over the building toprovide a covered picnic area and dish-washingstation.

    The backside of the building could includesome screened storage of rewood for sale to

    campground users, creating a more secure lo-cation.

    The building shape will be replicated for usewith the proposed day use change room &washroom (options 1 to 3).

    TABLE 1. CAMPGROUND WASHROOM/SHOWER BUILDING ASSESSMENT & COSTS

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Campground Washroom /

    Shower

    • Makes showers and

    washrooms wheelchair

    accessible

    • Upgrades building and

    addresses water damage

    issues

    • Adds covered outdoor

    cooking and dish cleaning

    area

    • Provides screened storage

    area for equipment

    • Provides firewood storage

    • Cost

    • Construction on existing

    location means timeline may

    overlap with campground

    service season

     ◦ no campground shower

    service

     ◦ washroom could beaccommodated at day

    use area change room

    $164,000-$188,000

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

     

    02 New Campground Shower/Washroom

    02.1 Multiple location options

    02.2 Showers (3M, 3F)

    02.3 Washrooms (3M, 3F)

    02.4 Wheelchair accessible washroom & shower

    02.5 Roof extension for covered cooking area (2 cooking areas)

    02.6 Dish washing station

    02.7 Screened materials / gas tank storage

    02.8 Outdoor wood storage

     

    02.2M02.2F 02.3F 02.3M

    02.4

    02.5

    02.6

    02.7

    02.8

  • 8/18/2019 Williamson's Lake report

    17/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT11

     

    B) Day Use & Campground Reception Buildings - Summary

    The table below summarizes the benets and challenges of the two day use & campground reception building options. De-tailed break-down of the benets and challenges along with a preliminary cost estimate is provided for each building option.

    TABLE 2. DAY USE BUILDING OPTIONS SUMMARY 

    BUILDING OPTION BENEFITS CHALLENGES

    Building Opons 1, 2, & 3

    Two-Building Concept

    • Allows for quicker remedy of issues

    around temporary buildings for food

    service and campground reception

    • Allows for easier, phased replacement

    strategy

    • Lower individual building costs may

    make fundraising easier by separating

    into different years

    • Two buildings create central gateway /

    walkway as a formal entrance to the dayuse area

    • Highest cost option over the long term

    Building Opons 4 & 5

    One-Building Concept

    • Lower cost option

    • Single construction phase

    • Larger Building, less conducive to

    open, accessible building

     

    PUBLIC SPACECommon to All Concepts

    01  Approachable Entrance

    02 New Day Use Building with food service

    03 Covered & open dining patio

    04 Stairs down to beach & permanent dock

    05 Viewing/seating area

    06 Wheelchair accessible ramp to beach

    07 Open air picnic shelter with wood stove + BBQs

    08 New day use change room, washroom + shower

    09 Gateway entrance to park w/ building rooflines

    10 Vehicle pick up area w/ seating

    11 Bike parking out front of change room

    12  Additional bike parking

    02

    01

    03

    04

    09

    05

    08

    11

    10

    12

    0706

    The two-building concept (options 1 to 3) create a great public space

  • 8/18/2019 Williamson's Lake report

    18/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT12

     

    i. Day Use Change Room / Washroom Building(Options 1, 2, & 3 only)

    The day use change room / washroom buildingis a proposed stand alone building that wouldreplace the existing change room / washroom

    building at the end of its lifespan. The buildingwould have 3 change rooms and washrooms forboth men and women. A single, self-containedwheelchair accessible washroom and changeroom is also proposed. Outdoor and indoorstorage would house day use maintenanceequipment and building infrastructure andcleaning supplies.

    The building side overlooking Williamson’sLake would also include 3 rinse showers wherebeach users can rinse off after swimming.

    TABLE 3. CAMPGROUND WASHROOM/SHOWER BUILDING ASSESSMENT & COSTS

    BUILDING OPTION BENEFITS CHALLENGES   PRELIMINARY COSTESTIMATE

    Campground Washroom /

    Shower

    • Upgrades building to make it

    wheelchair accessible

    • Can be phased and built as

    needed

    • Creates second side of

    gateway entrance to the

    park 

    • Adds outdoor rinse shower

    for day use area

    • Provides screened storage

    area for equipment• Back side of building creates

    large area capable of

    housing bike racks / storage

    • Not needed until current

    building reaches the end of

    its lifespan

    • Would need to extend

    services or move new septic

    system (2015)

    $151,000-$174,000

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

     

    01 Day Use Change Room & Washroom

    01.1 Washrooms & change rooms (3M, 3F)

    01.2 Wheelchair accessible washroom & change room

    01.3 Rinse showers for day use patrons

    01.4 Storage for cleaning supplies, boiler, etc.

    01.5 Option to be insulated for winter use in part or whole building

    01.1M01.1F

    01.2

    01.3

    01.4

    01.4

  • 8/18/2019 Williamson's Lake report

    19/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT13

     

    ii. Day Use Building Option 1

    Day Use Building Option 1 is a two-storey building that contains a food service kitchen and service window, campground

    reception and laundry, equipment storage, and caretaker suite on the upper oor.

    TABLE 4. DAY USE BUILDING OPTION 1 BUILDING ASSESSMENT AND COSTS

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Change Room / Washroom

    Building

    • see Table 3 for day use change

    room / washroom benefits

    • see Table 3 for day use change

    room / washroom challenges$151,000-$174,000

    Two-Storey Recepon, Food

    Service, Storage, Suite

    • Two-storey option takes up

    less ground space, allowing

    for more public space

    • Two-storey option provides

    the best visibility and best

    wayfinding to direct peoplethrough the site

    • Two-storey options creates

    the most defined “gateway

    feature” to the lake

    • Highest cost option

    • Caretaker suite only used in

    summer months – empty the

    rest of the year

    $180,000-$215,000

    Building Option 1 Total $331,000 - $389,000

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

     

    01.4

    01.5

    01.6

    01.7

    01.8 01.9

    01 Day Use & Office Building

    01.1 Forms day use entry/gateway with change room building

    01.2 Park & Heritage Information boards

    01.3 Option to be insulated for winter & year-round use

      First Floor

    01.4 Campground registration office

    01.5 Campground laundry - lockable and able to be monitored

    01.6 Food service kitchen

    01.7 Outdoor covered dining area & viewing deck

    01.8 Indoor lockable storage for rental paddleboards, canoes, etc.

      Second Floor

    01.9 Caretaker suite eliminates need for trailer and non-permanent office

  • 8/18/2019 Williamson's Lake report

    20/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT14

     

    iii. Day Use Building Option 2

    Day Use Building Option 2 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, and caretaker suite all on a single oor.

    TABLE 5. DAY USE BUILDING OPTION 2 BUILDING ASSESSMENT AND COSTS

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Change Room / Washroom

    Building

    • see Table 3 for day use change

    room / washroom benefits

    • see Table 3 for day use change

    room / washroom challenges$151,000-$174,000

    One-Storey Recepon, Food

    Service, Storage, Suite

    • Simple building footprint

    and roofline saves on

    construction costs

    • Creates large covered patio

    area

    • Creates attractive entrance to

    the day use area

    • Higher cost option

    • Less of a landmark at onestorey

    • Caretaker suite only used in

    summer months – empty the

    rest of the year

    $165,000-$197,000

    Building Option 2 Total $316,000 - $371,000

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

     

    01.101.2

    01.3

    01.4

    01.5

    01.6

    01.7

    01 Day Use & Office Building

    01.1 Campground registration office

    01.2 Caretaker suite eliminates need for trailer and non-permanent office

    01.3 Campground laundry - lockable and able to be monitored

    01.4 Food service kitchen

    01.5 Kitchen storage

    01.6 Outdoor covered dining area & viewing deck

    01.7 Indoor lockable storage for rental paddleboards, canoes, etc.

    01.8 Option to be insulated for winter & year-round use

    01.9 Forms day use entry/gateway with change room building

    01.10Park & Heritage Information boards

  • 8/18/2019 Williamson's Lake report

    21/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT15

     

    iv. Day Use Building Option 3

    Day Use Building Option 3 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, but no caretaker suite.

    No oorplans were created for this option. The images show an approximately-sized building that does not contain thecampground reception.

    TABLE 6. DAY USE BUILDING OPTION 3 BUILDING ASSESSMENT AND COSTS

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Change Room / Washroom

    Building

    • see Table 3 for day use change

    room / washroom benefits

    • see Table 3 for day use change

    room / washroom challenges$151,000-$174,000

    One-Storey Reception, Food

    Service, Storage

    • Simple building footprint

    and roofline saves onconstruction costs

    • Creates large covered patio

    area

    • Creates attractive entrance to

    the day use area

    • Lowest cost option of two-building concepts (1-3)*

    • Less of a landmark at one

    storey

    • Caretaker suite needs to be

    provided - likely as a trailer

    $146,000 -$168,000

    Building Option 3 Total $297,000 - $342,000

    *Cost does not include facilities needed for campground caretaker suite and related storage

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

  • 8/18/2019 Williamson's Lake report

    22/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT16

     

    v. Day Use Building Option 4

    Day Use Building Option 4 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, caretaker suite, day use change room and washroom all in a single building.

    This option was explored after the open house. No oorplans or graphics were created for this option.

    TABLE 7. DAY USE BUILDING OPTION 4 BUILDING ASSESSMENT AND COSTS

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Change Room, Washroom, Food

    Service, Recepon, Caretaker

    Suite

    • Simple building footprint

    and roofline saves on

    construction costs

    • Easier construction schedule

    • Lowest cost option that

    houses all services

    • Caretaker suite only used in

    summer months – empty the

    rest of the year

    • Larger building means less

    space for outdoor seating

    area and public space

    • Replace change room /

    washroom before end of

    lifespan or delay replacing

    trailer and outdoor storage

    until change room / washroom

    reach the end of its lifespan

    $315,000 - $375,000

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

    vi. Day Use Building Option 5

    Day Use Building Option 5 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, day use change room and washroom all in a single building.

    This option was explored after the open house. No oorplans or graphics were created for this option.

    TABLE 8. DAY USE BUILDING OPTION 5 BUILDING ASSESSMENT AND COSTS

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Change Room, Washroom, Food

    Service, Recepon

    • Simple building footprint

    and roofline saves on

    construction costs• Easier construction schedule

    • Lowest cost option*

    • Larger building means less

    space for outdoor seating

    area and public space

    • Replace change room /

    washroom before end of

    lifespan or delay replacingtrailer and outdoor storage

    until change room / washroom

    reach the end of its lifespan

    • Caretaker suite needs to be

    provided - likely as a trailer

    $276,000-$328,000*

    *Cost does not include facilities needed for campground caretaker suite and related storage

    Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08

  • 8/18/2019 Williamson's Lake report

    23/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT17

     

    03.02.02 Accessible Pathway

    At present there is no accessible route to the waterfront at Williamson’s Lake Campground and Day Use Area. Pedestrianaccess is limited to concrete stairs with a handrail and a gravel path installed with concrete jersey barriers retaining thetrail mix. The existing topography to the lakefront is a series of steep turf slopes broken up with level benched areas, whichmakes access challenging for those in wheelchairs or with limited mobility.

    Feedback gathered through the public engagement process indicates that establishing a formalized accessible route tothe beach and lakefront is the second highest priority behind only the building improvements.

    Moving forward, a 2.5m width asphalt pathway with a maximum grade of 8% will be designed and constructed with a hand-rail on the downslope side. Small retaining walls may be required to achieve the 2.5m width, however, it is anticipated thatthe majority of the pathway can be achieved with backsloping and balanced cut and ll.

    The estimated costs for construction of the accessible pathway is: $41,875 including a 15% contingency and detailed design.

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

    TABLE 9. ACCESSIBLE PATHWAY CONSTRUCTION OPTIONS

    OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE*

    Accessible Pathway Sloped

    • Creates wheelchair accessible

    access to the water

    • High priority, low cost

    • Cost

    • Slope assessment by a geotechnical

    engineer needed to be done first

    • Engineering costs not included in

    preliminary cost estimate

    $22,500

    Accessible Beach Pathway to

    connect both Accessible Docks

    • Connects viewing dock with fishing

    and swimming dock • Additional costs $11,000

     Accessible Pathway Total* $41,875

    *Cost includes contingency (15%) and Estimated Design Fees (10%)

    Wheelchair Accessible pathway down slope to the water would be paved 

  • 8/18/2019 Williamson's Lake report

    24/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT18

     

    03.02.03 Docks

    The existing dock at Williamson’s Lake Day Use Area consists of a modular oating dock system (Jet Float - http://www.jetoat.com/index_new.shtml). Upon site inspection it was observed that some of the modular plastic components have become damaged andpose a safety hazard to users in bare feet. This oating dock system typically carries a 10 year warranty and the owner should explorehaving damaged modules replaced as soon as possible.

    While modular oating docks have appeal in regards to ease of install, lack of maintenance, and expandability, this dock system doesnot allow for accessible design and lacks a natural aesthetic and tactile appeal.

    A) Options

    Options for the proposed accessible dock include a combination of wood decking with aluminum frame and polyethylene oats.Recommendations for decking material include western red cedar due to the resistance to rot, decay, and insects without having tobe pre-treated. Maintenance requirements for western red cedar include power washing annually. Application of a natural environ-mentally friendly stain may be considered every three to ve years.

    Composite decking may also be considered as an appropriate option for dock surfacing. Compos-

    ite decking does not need to be sanded, stained, or renished. It does still require power washingand requires extensive structure beneath, as composite decking cannot achieve the span require-ments of traditional wood decking.

    Another consideration for deck surfacing for the accessible dock includes a slip resistant perforat-ed metal decking although it should be noted that this doesn’t provide for a very natural aesthetic.Moving forward the following options for accessible dock construction and refurbishment include:

    i. Option 1

    Construct new shing and swimming dock with timber or steel/aluminum substructure andinstall wood or composite decking surface. Construct new accessible dock with timber orsteel/aluminum substructure and wood or composite decking material.

    ii. Option 2

    Expand the existing modular oating dock system to include the shing and swimming ex-tensions and install wood or composite decking surface structure on top of oating modularcomponents. This option will require further engineering design to retrot the oating mod-ular dock system with a deck structure on top. Construct new low prole jetoat or approvedequivalent accessible dock with wood or composite decking and access ramp.

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

    TABLE 10. DOCK CONSTRUCTION OPTIONS

    OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE*

    Option 1 - Viewing Dock + New

    Swimming Dock 

    • Longer term solution

    • Better aesthetics & stability• Highest cost option $124,975

    Option 2 - Viewing Dock + Add

    on to existing jetfloat dock • Lower cost option • Voids Jetfloat warranty $90,050

    *Cost includes contingency (15%), Estimated Design Fees (10%) and Estimated Cost for obtaining Regulatory (riparian) Approvals (if required) ($7,500)

    Option 2: Modular oating dock 

    Option 1: New wood & steel/aluminum dock 

  • 8/18/2019 Williamson's Lake report

    25/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT19

     

    03.02.04 Landscape Plan

    A) Natural Landscaping for Slope & Environmental Protection & Enhancement

    Heavy foot trafc has led to signicant degradation of vegetation in specic areas within the Williamson’s Lake Campgroundand Day use area. A combination of planting, formalizing popular pedestrian thoroughfares through paved and gravel trails,

    and public education should be implemented in combination to restore strategic areas of the site and to promote healthyvegetation growth for succession planting and screening. To avoid newly planted vegetation from becoming damaged,signage and low barriers may be implemented to educate the public about the landscape restoration work occurring for therst two growing seasons until the vegetation becomes established.

    The following plant communities (groupings of primarily native trees and shrubs with a grass seed mix) will be developedin the detailed design phase to re-vegetate strategic sites within Williamson’s Lake Campground and Day Use Area:

    • Cedar succession planting community

    • Cedar understory shrub and grass planting community

    • Slope naturalization grass and forb plant community

    • Riparian enhancement planting community• Campground screening planting community

    The estimated costs for construction of the soft landscape plan is: $145,000

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

    TABLE 11. SOFT LANDSCAPE PLAN PRELIMINARY COST ESTIMATES

    OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE

    Cedar succession plant

    community• Strategic replacement of aging

    trees

    • Beach protection and enhancement

    • Aesthetic landscape enhancement

    • Slope stabilization

    • Better privacy between

    campground and beach

    • Clear messaging and regulatory

    information allows the operator

    and bylaw the ability to enforce

    rules and regulations

    • Cost

    $22,500

    Cedar understory shrub and

    grass planting community$15,000

    Slope naturalization grass and

    forb plant community$4,500

    Riparian enhancement planting

    community$5,500

    Campground screening plant

    community$50,000

    Construct vegetated swale at

    base of slope$18,500

    Landscape Plan Total* $145,000

    *Total includes contingency (15%) and Estimated Design Fees (10%)

  • 8/18/2019 Williamson's Lake report

    26/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT20

     

    B) Hard Landscaping Around Buildings

    Hard landscaping around the new buildings will help protect the surrounding natural environment by creating a formalwalkway and access to the beach, and reducing pedestrian trafc on surrounding landscaping. Combining the hard land-scaping with the new buildings will compliment the design and help enhance the day use area and create a sense of place,dened by walkways, trees, benches and formal landscaping.

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

    TABLE 12. HARD LANDSCAPE PLAN (AROUND NEW BUILDINGS)

    OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE*

    Timber stairs to dock 

    • Creates formal walkway down to

    the water

    • Reduces traffic on slopes,

    protecting roots and slope stability

    • Additional cost $50,000

    Paving, trees and landscaping

    • Compliments new buildingshelping to create a sense of place

    • Trees provide shade, reducing heat

    island effect

    • Additional Cost $55,000

    Hard Landscaping Total* $131,250

    *Cost includes contingency (15%), and Estimated Design Fees (10%)

    Hard landscaping with paving, trees, shrubs and grasses, benches and bike racks compliments the new buildings and protects the surrounding environment 

  • 8/18/2019 Williamson's Lake report

    27/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT21

     

    03.02.05 Signage

    Signage was identied in the 2011 plan as a high, short-term priority. Despite it not being a high community priority, theplan identies signage as an important proposed improvement. Creating a signage strategy for the park would help differ-entiate the day use area from the campground, and make waynding and directions easier to understand.

    Aesthetically, a signage strategy creates a coordinated image for Williamson’s Lake. Rather than having a variety of sign types, generallyshowing too much information, the strategy helps “brand” the park with simple, easy to understand, and coordinated signage.

    A signage strategy includes a hierarchy of sign types that directs park and campground users from their cars to where they want to go.

    A) Options

    i. Proposed Sign Hierarchy

    The following proposed signage hierarchy represents a method of creating a recognizable and consistent brand for Wil-liamson’s Lake while presenting the user with appropriate levels of information at key decision points. Consideration forlongevity, maintenance, and material selection will be explored with the client during the design development and detaileddesign phases of this project. The proposed signage hierarchy for Williamson’s Lake includes:

    ii. Directional Signage

    a. Purpose

    • Direct users to Williamson’s Lake Campground

    • Establish a graphic identity that is distinct from other signage enabling the user to distinguish the sign type from a distance

    b. Location(s):

    • Strategic locations along Fourth St E and Airport Way

    • A large directional sign will be located at the intersection of Airport Way and Williamson’s Lake Road

    iii. Entry Arrival Signage

    a. Purpose

    • Create a sense of arrival

    • Welcome visitors and residents to Williamson’s Lake

    • Establish the visual identity of the Williamson’s Lake Community Park

    b. Location

    • At the entry to the site along Williamson’s Lake Road

    iv. Day Use Information Signage

    a. Purpose• Provide pedestrian scale orientation and directional information to Williamson’s

    Lake day use facilities and amenities

    • Provide rules and regulations i.e. no lifeguards on duty

    • Provide local information i.e. wildlife warnings, community events

    • May be tailored to specic locations i.e. rules and regulations for beach and ac -cessible docks, walking trail

    Example: Day Use Information Signage

    Example: Simple Entry Arrival Signage

  • 8/18/2019 Williamson's Lake report

    28/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT22

     

    • Reinforce the visual identity of the Williamson’s Lake signage style so that users know where to seek information

    b. Locations

    • Main entry to day use area, access points to beach area

    v. Interpretive Signs

    a. Purpose

    • Provide interpretive information: Historic, Educational, Environmental

    • Tie into existing Revelstoke Interpretive Signage program

    b. Location

    • Adjacent to the main pedestrian thoroughfare overlooking Williamson’s Lakefrom the deck structure

    vi. Campground Registration Signage

    a. Purpose

    • Provide detailed campground information including layout, location of campsites, and location of amenities• Provide self check-in box

    • Provide rules and regulations

    • Provide local information i.e. wildlife warnings, community events

    • Reinforce the visual identity of the Williamson’s Lake signage style so that users know where to seek information

    b. Location

    • North and South ends of the campground, walk-in sites

    vii. Campsite Markers

    a. Purpose

    • Provide distinct identication to each formalized campsite

    • Allow reserved campsites to be clearly distinguished

    b. Locations

    • At each campsite

    viii. Advisory Signage

    a. Purpose

    • Provide text based regulatory or advisory information

    • Note that overall number of vehicular advisory signs may be reduced through pavement markings

    b. Locations

    • As required by the client or campground operator

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

    Example: Campsite Markers

    Example: Interpretive Signage already built in Revelstoke

  • 8/18/2019 Williamson's Lake report

    29/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT23

     

    TABLE 13. SIGNAGE PRELIMINARY COST ESTIMATES

    OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE

    Directional Signage • Vastly improves wayfinding and

    communication

    • Provides coordinated aesthetic

    upgrade to the park “brand”

    • Reduces illegal dumping

    • Reduces trailers getting stuck on

    steep road

    • Enhances campground and

    compliments campsite definition

    • Can be implemented over a

    number of years in small steps

    • Cost

    • Would benefit from a City-wide

    signage strategy to direct people

    to the park 

    $3,848

    Entry Arrival Signage $17,500

    Day Use Information Signage $,8,100

    Interpretive Sign $6,250

    Campground Registration

    Signage$6,750

    Campsite Markers (45) $16,875

    Advisory Signage $2,625

     Signage Total* $61,948

    *Total includes contingency (15%) and Estimated Design Fees (10%)

    03.02.06 Campground and Campsite Improvements

    A) Description

    Campsites within the Williamson’s Lake Campground t into three categories:

    • RV full service campsites

    • Vehicular access tent sites

    • Walk-in sites

    Primary considerations for campsite improvements include:• Safety considerations focused on reducing potential conict between animals and campers.

    • Providing a high level of visitor experience

    • Clearly marking each campsite with consistent campsite markers

    • Creating privacy and screening between campsites

    • Creating level, free draining campsites

    • Designated areas for vehicular parking (non walk-in)

    • Designated or obvious tent sites

    • Fixed picnic table locations

    • Fixed re pit locations• Walk in sites may require a food storage locker

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

  • 8/18/2019 Williamson's Lake report

    30/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT24

     

    TABLE 14. CAMPSITE IMPROVEMENTS PRELIMINARY COST ESTIMATES

    OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE

    Construct new full service RV

    sites• Improves campsite aesthetics

    making it a more attractive

    accommodation

    • Addresses poorly constructed

    tenting sites on steep slopes

    • Environmental enhancement by

    removing lakefront sites and road

    • Better site layout to maximize sites

    while improving privacy

    • Walk-in sites create a different

    camping option

    • Implements bear-safe practices

    • Cost

    • Implementation of improvements

    would need to be scheduled

    around camping season

    • Walk-in sites within 30m RAR Buffer

    would need RAR approval

    $80,000

    Removal of existing sites $7,500

    Construct walk-in campsites $15,000

    Construct gravel or natural

    surface walking trail to walk-in

    campsites

    $3,000

    Install bear proof food locker $3,500

    Install campsite markers N/A

    Install fixed picnic tables $90,000

    Install fixed fire pits $15,750

    Campsite Improvements Total* $268,438

    *Total includes contingency (15%) and Estimated Design Fees (10%)

    03.03 IMPROVEMENTS & CONSIDERATIONS

    03.03.01 Mini Putt

    Early in the process it was clear that the best location for the new day use buildings is in the current mini-putt location. Dueto the condition of the mini-putt course, it was left out of the three site plan options presented to the public at the openhouse. Feedback from the open house both verbally and written was that the mini-putt was a desired amenity. In the nalsite plan it has been relocated around the existing playground, based on that feedback. The mini-putt would be rebuilt new,and incorporate more natural landscaping and trees to create the course.

    Refer to Appendix 09 for Preliminary Opinions of Probable cost.

    TABLE 15. MINI PUTT REDESIGN AND RELOCATION

    BUILDING OPTION BENEFITS CHALLENGES  PRELIMINARY COST

    ESTIMATE

    Removed, redesign and

    construct mini putt course in

    new locations

    • Mini putt is a popular amenity

    • Upgrade the mini putt course

    to make it more aesthetically

    pleasing

    • Allows for the placement ofthe best building location

    • Cost $62,500

    *Total includes contingency (15%) and Estimated Design Fees (10%)

  • 8/18/2019 Williamson's Lake report

    31/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT25

     

    03.03.02 Other Proposed Amenities

    Several amenities were explored through the open house. Though they didn’t rank high on the community priorities, theyare presented below for reference. These options may wish to be revisited once the recommendations from this plan havebeen completed.

    These improvements include:

    • Seating Docks (medium community support)

    • Hammock Area (medium community support)

    • Amphitheater (medium community support)

    • Exercise Area (low community support)

    • Climbing Blocks (unknown community support)

    • Yurt Camping (very low community support)

    New mini-putt course should be more natural and could include rocks, trees & plants as features of the course, similar to a natural playground 

  • 8/18/2019 Williamson's Lake report

    32/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT26

     

    PART 04: IMPLEMENTATION

    04.01 PHASING

    TABLE 16. WILLIAMSON’S LAKE IMPROVEMENTS IMPLEMENTATION PLAN

    IMPROVEMENT   COMMUNITY

    PRIORITY   LEAD TIMELINE

      COST /FUNDING

    BUILDINGS HIGHEST  

    Campground Washroom / Showers Highest  

    Fundraising / Budgeting PRC, CED, CF Spring 2016

    Construction Drawings CSLT, PRC, DEDS Summer 2016 $3,000

    Existing Building Demolition PRC, PW Fall 2016 T.B.D.

    Services Assessment & Connection Fees CSLT, PRC, PW Fall 2016 T.B.D.

    Building ConstructionPRC, DEDS, PW,

    CSLTSpring 2017

    $164,000-$188,000

    Day Use Food Service / Campground Reception Building Very High

    Fundraising / Budgeting PRC, CED, CF 2016 - 2017

    Construction Drawings CSLT, PRC, DEDS 2017 $2,600

    Mini Putt Removal & Relocation PRC, PW Spring 2018 $62,500

    Services Assessment & Connection Fees CSLT, PRC, PW Spring 2018 T.B.D.

    Building ConstructionPRC, DEDS, PW,

    CSLTSpring 2018

    $146,000-$215,000

    Day Use Change Room / Washroom Medium

    Building Assessment Fundraising / Budgeting PRC, CED, CF 2016

    Building Assessment - Determine LifespanPRC, PW, DEDS,

    CSLT2016 or 2017 T.B.D.

    Construction Fundraising / Budgeting PRC, CED, CF2 yrs before end

    of life

    Construction Drawings CSLT, PRC, DEDSSpring beforeconstruction

    $1,500*

    Services Assessment & Connection Fees CSLT, PRC, PWSpring beforeconstruction

    T.B.D.

    Existing Building Demolition PRC, PWFall before

    constructionT.B.D.

    Building Construction PRC, DEDS, PW,CSLT

    Fall before& spring ofconstruction

    151,000-$174,000

    * 2015 Rate - If using the same building design & layout as campground washroom / shower building

  • 8/18/2019 Williamson's Lake report

    33/92

    WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN

    SUMMARY REPORT27

     

    TABLE 16. WILLIAMSON’S LAKE IMPROVEMENTS IMPLEMENTATION PLAN

    IMPROVEMENT   COMMUNITY

    PRIORITY   LEAD TIMELINE

      COST /FUNDING

     ACCESSIBLE PATHWAY VERY HIGH

    Geotechnical Engineer Assessment Fundraising / Budgeting PRC, CED, CF 2016

    Geotechnical Engineer Assessment PRC, DEDS, CSLT 2016 or 2017 T.B.D.

    Regulatory Approvals (if needed)CSLT, PRC, DEDS,

    GovBC, CSRD2016 or 2017   $7,500†

    Pathway Design & Permits CSLT, PRC, DEDS 2016 or 2017 $2,250

    Pathway ConstructionPRC, DEDS, PW,

    CSLT2016 or 2017 $22,500

    Wheelchair Accessible Path between docks Med-High

    Fundraising / Budgeting PRC, CED, CF 2020

    Regulatory Approvals (if needed)CSLT, PRC, DEDS,

    GovBC, CSRD2020   $7,500†

    Pathway DesignPRC, PW, GovBC,

    CSRD2020 $1,100

    Pathway ConstructionPRC, DEDS, PW,

    CSLTSpring 2021 $11,000

    DOCKS HIGH

    Jet Float Warranty Repairs of existing dock (if still covered) PRC, PW Spring 2016 $0

     Main Dock Construction or E xpansion High

    Dock Fundraising / Budgeting PRC, CED, CF 2017-2018

    Regulatory Approvals (if needed)CSLT, PRC, DEDS,

    GovBC, CSRD2017   $7,500†

    Dock Design & Permits PRC, PW, GovBC,CSRD 2018 $5,000-$7,000

    Dock ConstructionPRC, DEDS, PW,

    CSLTSpring 2018 $50,000-$70,000

    Viewing Dock Med-High

    Dock Fundraising / Budgeting PRC, CED, CF 2020

    Regulatory Approvals (if needed)CSLT, PRC, DEDS,

    GovBC, CSRD2020   $7,500†

    Dock Design & PermitsPRC, PW, GovBC,

    CSRD2020 $1,500-$2,250

    Dock ConstructionPRC, DEDS, PW,

    CSLTSpring 2021 $15,000-$22,500

    LANDSCAPING HIGH

     Soft Landscaping: Successional Planti ng High

    Fundraising / Budgeting PRC, CED, CF 2018-2020

    Landscape Plan & Construction Drawings CSLT, PRC, DEDS 2020 $11,600

    Landscape Planting PRC, PW 2021 $116,000

  • 8/18/2019 Williamson's Lake report

    34/92

    TABLE 16. WILLIAMSON’S LAKE IMPROVEMENTS IMPLEMENTATION PLAN

    IMPROVEMENT   COMMUNITY

    PRIORITY   LEAD TIMELINE

      COST /FUNDING

    H ar d Lan dsca ping: S ta ir s, Pa ving, Trees, S hr ubs, Gr asses & Benc hes M ed 

    Fundraising / Budgeting PRC, CED, CF 2020

    Hard Landscaping Construction Drawings CSLT, PRC, DEDS 2020 $10,500

    Hard Landscaping Construction PRC, PW Spring 2021 $105,000

    SIGNAGE MED-HIGH

    Fundraising / Budgeting PRC, CED, CF 2018-2020

    Signage Strategy & Construction Drawings CSLT, PRC, DEDS 2020 $6,200

    Signage Installation PRC, PW 2021-2026 $61,948

    CAMPGROUND IMPROVEMENTS MED

    Fundraising / BudgetingPRC, CED, CF,

    WLCM2018-2020

    Campground Improvements & Construction DrawingsCSLT, PRC, DEDS,

    WLCM2020 $21,475

    Campground Improvements PRC, PW, WLCM 2021-2026 $214,750

    † Regulatory costs may be shared if plans are submitted together 

    Detailed Cost Estimates can be found in Appendix 08 (Buildings) and Appendix 09 (Landscape)

    ABBREVIATIONS

    Priority Timelines

    Very High 1-2 YearsHigh 3-5 YearsMedium 6-15 Years

    Lead Abbreviations

    CBT Columbia Basin TrustCF City of Revelstoke Finance DepartmentCSLT External ConsultantCED City of Revelstoke Community Economic Development DepartmentCoC Revelstoke Chamber of CommerceCSRD Columbia Shuswap Regional DistrictDEDS City of Revelstoke Department of Engineering & Development ServicesGovBC Government of BCPRC City of Revelstoke Department of Parks, Recreation and CulturePW City of Revelstoke Public Works DepartmentWLCM Williamson’s Lake Campground Manager

    Cost Categories

    $0 - $999 Lowest$1,000 - $9,999 Low$10,000- $49,999 Medium$50,000 – $99,999 High> $100,000 Highest

  • 8/18/2019 Williamson's Lake report

    35/92

  • 8/18/2019 Williamson's Lake report

    36/92

    APPENDIX 01 PREVIOUS SITE PLAN AND PRIORITIES

  • 8/18/2019 Williamson's Lake report

    37/92

  • 8/18/2019 Williamson's Lake report

    38/92

  • 8/18/2019 Williamson's Lake report

    39/92

  • 8/18/2019 Williamson's Lake report

    40/92

  • 8/18/2019 Williamson's Lake report

    41/92

  • 8/18/2019 Williamson's Lake report

    42/92

  • 8/18/2019 Williamson's Lake report

    43/92

  • 8/18/2019 Williamson's Lake report

    44/92

  • 8/18/2019 Williamson's Lake report

    45/92

  • 8/18/2019 Williamson's Lake report

    46/92

    APPENDIX 02 WILLIAMSON’S LAKE HISTORICALPHOTOS

  • 8/18/2019 Williamson's Lake report

    47/92

    Historical Photos of Williamson’s Lake courtesy of Revelstoke Museum & Archives

  • 8/18/2019 Williamson's Lake report

    48/92

    Historical Photos of Williamson’s Lake courtesy of Revelstoke Museum & Archives

  • 8/18/2019 Williamson's Lake report

    49/92

    Historical Photos of Williamson’s Lake courtesy of Revelstoke Museum & Archives

  • 8/18/2019 Williamson's Lake report

    50/92

    APPENDIX 03 SITE ISSUES MAP

  • 8/18/2019 Williamson's Lake report

    51/92

       I   S   S   U   E

       0   9 .   0   8 .   2   0   1   5

       R   E  -   I   S   S   U   E

       C   L   I   E   N   T

       C   i   t  y   o   f   R   e  v   e   l   s   t   o   k   e  -   P   a   r   k

       s ,   R   e   c   r   e   a   t   i   o   n   &   C  u   l   t  u   r   e   D   e   p   t .

       6   0   0   C   a   m   p   b   e   l   l   A  v   e .

       P .   O .   B   o  x   1   7   0

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   8   3   7  -   9   3   5   1

       S   E   L   K   I   R   K   P   L   A   N   N   I   N   G   &   D   E   S   I   G   N

       B   o  x   1   9   9   4

       1   0   1   S   e   c   o   n   d   S   t .   E

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   2   0   0  -   0   6   8   0

       E  :   s   e   l   k   i   r   k   p   l   a   n   n   i   n   g   @   g   m   a   i   l .   c   o   m

       P   R   O   J   E   C   T   N   O .

       2   0   1   5  -   C   O   P  -   W   L

       P   R   O   J   E   C   T

       W   i   l   l   i   a   m   s   o   n   ’   s   L   a   k   e   D   a  y   U   s   e   A   r   e   a   &

       C   a   m   p   g   r   o  u   n   d   C   o   n   c   e   p   t   P   l   a   n

       D   R   A   W   N   B   Y

       F   B ,   J   J

       D   E   S   C   R   I   P   T   I   O   N

    a

    04

    OBSERVED ISSUES01 Poor Quality Signage at Intersection01.1 Too much information and not directional - No sense of entry to

    the site

    02 Road Condition & Parking02.1 Road is in poor condition

    02.2 Overflow parking along the street is not well defined

    03 Poor Quality Signage03.1 Too much information and not directional

    04 Outdoor Storage of Materials04.1 Mulch and wood stored outside uncovered indicates the need for

    formal materials storage

    05 Day Use Parking Area05.1 Day Use Parking Area not well defined

    06 Parking Barriers06.1 Tall parking barriers create an unwelcoming feeling of privacy 

    07 Mini Golf Area Placement07.1 Poor quality fencing creates a feeling of privacy 

    07.2 Mini golf area is first visual upon entering the site - makes it feel pri-

    vate

    08 Severe Erosion08.1 Severe erosion at the top of the bank showing roots makes the

    area unusable

    09 Dangerous Leaning Tree09.1 Tree Leaning over the day use area - potential to injure

    10 Beach Erosion10.1 Beach area is showing signs of erosion

    11 Floating Dock11.1 Dock is broken and deteriorating and feels temporary 

    12 Bear-Proof Garbage12.1 Open Garbage cans create risk for bear conflicts - currently emp-

    tied nightly 

    13 Change Rooms & Washroom Building13.1 Cracks in structural walls showing signs of deterioration and need

    for replacement

    14 Food Service Area14.1 Very cluttered and unorganized - freezers and fridges kept outside

    all summer

    15 Pathway Down to Lake15.1 Pathway is steep, unpaved and is not suitable for handicapped ac-

    cess

    15.2 Corner switchback is not able to accommodate wheelchair turn-

    around in the future

    16 Trailer & Caretaker Private Yard16.1 Trailer is not designed or oriented well for public/private interface

    16.2 Trailer is not big enough to function properly - outdoor storage

    needed, small office, etc.

    16.3 Fence along parking area creates a strong feeling of private space

    17 Unscreened storage of garbage/recycling17.1 Unsightly and is near the main access to the beach - highly visible

    18 Privacy Fences Between Campsites18.1 Fencing creates and awkward interface between public and pri-

    vate space

    18.2  A stop-gap solution rather than properly defining public and pri-

    vate space

    19 Aging Trees19.1 No succession plan for existing trees that will all reach the end of

    their life at the same time

    20 Playground Shading20.1 No shade for playground, making it hot with severe sun exposure

    21 Unlevel Tent Sites21.1 Tent pads are not level with several tents placed on a sloped hill

    22 Beach Volleyball Court22.1 Volleyball court is set up in the open field and is to be played on

    grass, rather than sand

    23 Beach front Road23.1 Prime riparian habitat and beach front is occupied by the road. It

    creates a feeling of a private rather than public beach

    24 Underutilized Green Space24.1 Undefined open space is underutilized and a lack of trees makes

    the area hot and exposed

    25 Difficult Back In Sites25.1 The steep road is difficult to back in

    26 Temporary Fence26.1 Temporary fence erected at the southwest corner to keep people

    from accessing the property to the south

    27 Short Camping Sites27.1 Camping sites are small and push tents and small campers towards

    the road. These sites lack privacy.

    28 Poor Signage for RVs28.1 RVs constantly miss the sign to not drive down the road, meaning

    they have to reverse up the steep, narrow road

    29 Isolated Camping Site29.1 The single site is on the opposite end of the washroom/shower

    making for an awkward and uncomfortable site

    30 Unscreened Materials & Infrastructure30.1 Propane tanks and various building materials are piled outside the

    building making it look cluttered and messy 

    31 Shower/Washroom Facility 31.1 Upgrades needed as the building is in disrepair

    32 Open, unshaded camping sites32.1 Lack of vegetation makes for a lack of shade and privacy for RV

    sites

    33 Sharp Angle of RV Sites33.1 The direction of traffic through the campground and angle of the

    RV sites mean backing in requires a 135 degree turn

    34 Dangerous Trees on Adjacent Property 34.1 Dead and leaning trees on adjacent property could fall on camp-

    sites causing injury and damage to RVs, electrical wires and other

    infrastructure

    35 RV Empty Station is Not Signed35.1 There is no signage indicating that this is the location for the RV

    empty station

    05 06 07 08 09 10

    11

    12131415

    161718

    19

    2021

    22

    23

    24

    25

    26

    2728

    293031

    32

    33

    34

    35

    04030201

    MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPSMAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS

  • 8/18/2019 Williamson's Lake report

    52/92

    APPENDIX 04 SITE OPPORTUNITIES MAP

  • 8/18/2019 Williamson's Lake report

    53/92

       I   S   S   U   E

       0   9 .   0   8 .   2   0   1   5

       R   E  -   I   S   S   U   E

       C   L   I   E   N   T

       C   i   t  y   o   f   R   e  v   e   l   s   t   o   k   e  -   P   a   r   k

       s ,   R   e   c   r   e   a   t   i   o   n   &   C  u   l   t  u   r   e   D   e   p   t .

       6   0   0   C   a   m   p   b   e   l   l   A  v   e .

       P .   O .   B   o  x   1   7   0

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   8   3   7  -   9   3   5   1

       S   E   L   K   I   R   K   P   L   A   N   N   I   N   G   &   D   E   S   I   G   N

       B   o  x   1   9   9   4

       1   0   1   S   e   c   o   n   d   S   t .   E

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   2   0   0  -   0   6   8   0

       E  :   s   e   l   k   i   r   k   p   l   a   n   n   i   n   g   @   g   m   a   i   l .   c   o   m

       P   R   O   J   E   C   T   N   O .

       2   0   1   5  -   C   O   P  -   W   L

       P   R   O   J   E   C   T

       W   i   l   l   i   a   m   s   o   n   ’   s   L   a   k   e   D   a  y   U   s   e   A   r   e   a   &

       C   a   m   p   g   r   o  u   n   d   C   o   n   c   e   p   t   P   l   a   n

       D   R   A   W   N   B   Y

       F   B ,   J   J

       D   E   S   C   R   I   P   T   I   O   N

    a

    05

    OPPORTUNITIES

    01 Improved Signage @ Airport Way 

    02 Overflow Day Use Parking w/ Improvements

    03 Entry Sign @ Important Wayfinding View 

    04 Narrow Road for One Way 

    05 Campground Registration Parking

    06 Vehicular Wayfinding Signage

    07 Plaza & Pedestrian Wayfinding Signage

    08 Day Use Parking - Defined Spaces

    09 New Day Use & Office Building(s)

    09.1 Change rooms (3M, 3F)

    09.2 Washrooms (3M, 3F)09.3 Wheelchair accessible washroom & change room

    09.4 Campground office

    09.5 Food service kitchen

    09.6 Outdoor covered dining area & viewing deck

    09.7 Laundry 

    09.8 Outdoor wood storage

    09.9 Potential caretaker residence

    09.10Rinse showers for day use patrons

    09.11Garbage & recycling storage

    09.12Indoor lockable storage for paddleboards, paddles, etc.

    09.13Outdoor cooking shelter & fish-washing station (stand alone build-

    ing - open air, stove, sink, bear-aware garbage)

    09.14Formal day use entry/gateway 

    09.15Incorporate historical/interpretive information (heritage panels)

    10 Re-vegetate Slope

    11 Formal Path/Stairs Down to Beach

    12 Private Property (or Trail) Signage

    13 Formalize Beach Area & Canoe Launch

    14 Permanent Wheelchair Accessible Dock

    15 Improved Beach Signage

    16 Pathway Defines/Protects Beach & Seating Area

    17 Wheelchair Accessible Pathway to Beach

    18 Mini Putt Moved Around Playground

    19 Successive Planting Area

    19.1 Plant species to replace existing trees as they near the end of their

    lifespan

    20 Wheelchair Accessible Viewing Dock

    21 Campsites Removed From Beach - Public Beach

    22 Slip n’ Slide Route (Special Event Only)

    23 Beach Volleyball Court on Beach

    24 Walk-In Tent Sites Replace Beach Sites

    24.1 ~10 tenting sites

    24.2 Opens up the beach to more public use

    25 Expanded Yurt Camping Area

    25.1 4-6 Yurts + parking area - Walk-in only 

    26 Parking Area for Walk-In Sites & Re-vegetation

    27 Fishing/Wildlife Viewing Dock

    28 Level Tent Sites & Improve Parking Pad Access

    28.1 Level sites with wood berms & fill

    28.2 Change vehicle back-in angle where possible

    28.3 Improved site marking

    29 Private Property Signage

    30 Improved “No RV Access” Sign

    31 New Campground Shower/Washroom

    31.1 Move existing campsite & place building closer to the road

    31.2 Showers (3M, 3F)

    31.3 Washrooms (3M, 3F)

    31.4 Wheelchair accessible washroom & shower

    31.5 Roof extension for covered cooking area (2 cooking areas)

    31.6 Dish washing station

    31.7 Screened outdoor materials / gas tank storage

    32 Formalized RV Sites

    32.1 Formal RV pads

    32.2 Permanent picnic table & fire location

    32.3 Improved site marking

    33 Flexible Open Space Area

    34 Vegetation to Create Privacy Screening

    35 Trees to Provide Shade for Playground

    36 Remove Dangerous Trees

    37 Formalized Small Campground Sites

    37.1 Vegetation buffers

    37.2 Permanent picnic table & fire location

    37.3 Improved site marking

    38 Narrow Road for One Way 

    39 Improved Signage for RV Empty Station

    40 Formalized Day Use Parking Stalls

    41 Overflow/Winter Camping Area

    41.1 Suitable for RVs or tents

    41.2 Potential winter yurt area - Move yurts from summer location

    42 Reverse Traffic Direction

    42.1 Improves visual access to day use & office building - wayfinding

    42.2  Access to “preferred” day use parking first

    42.3 Improves ability for RVs to back into camping sites

    42.4 Reduces RVs driving down “tent only” road

    01 03 04 05 07 08 12 13 1409 1106 1002

    23

    27

    21

    24

    29

    28

    26

    25

    20

    22

    15

    16

    17

    18

    19

    32

    33

    41

    40

    38

    42

    39

    30

    31

    36

    34

    37

    35

    MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS

  • 8/18/2019 Williamson's Lake report

    54/92

    APPENDIX 05 SURVEY RESULTS SUMMARY 

  • 8/18/2019 Williamson's Lake report

    55/92

  • 8/18/2019 Williamson's Lake report

    56/92

  • 8/18/2019 Williamson's Lake report

    57/92

    Williamson’s Lake Concept Preferences

    Weight Concept 1 - Community Park Concept 2 - Campground Campground 3 - Balanced

    Votes Weighted

    Score

    Votes Weighted

    Score

    Votes Weighted

    Score

    Not Appropriate -2 2 -4 8 -16 1 -2

    Not very appropriate -1 1 -1 3 -3 3 -3

    Unsure 0 3 0 4 0 4 0

    Appropriate 1 4 4 1 1 4 4

    Very Appropriate 2 5 10 0 0 6 12

    Total 15 9 16 -18 18 11

    Average Total per # of Votes 0.60 -1.13 0.61

    Preferred Improvements - Vote for your top 3

    No. of Votes

    Improved buildings 13

    Accessible pathway 10

    Landscape improvements andsuccession planting

    8

    Proposed docks 5

    Hammock area 4

    Amphitheatre 4

    Improved campsites 3

    Exercise nodes / circuit 3

    Improved signage & wayfinding 2

    Improved site markers 0

    Expanded yurt camping 0

    Other suggested improvements

    Comment Needs reviewwith L.

    Donato?

    Proposed Resolution / Action

    Maintain size of beach Yes Planned expansion of public beach area

    Keep mini golf Yes Not in current plan

    Camping should be limited Yes Consistent with Concept Plan 1, but not 2 or 3

    Keep the park the way it is Yes No proposed improvements address this

    Secure bike parking Yes Proposed racks only, no storage lockers etc.

    Canoe/kayak launch Yes Potential to have at proposed fishing dock location with potential small parking lot

    Make it a more local swimming hole/area Yes Consistent with Concept Plan 1 & 3

    Dog-friendly area of the beach Yes Nothing proposed right now - Potential to have this area, but how to manage?

    Remove parking from some campsites and make them walk-in sites Yes Consistent with Concept Plan 1 & 3

    Improve parking area No In current plans to define parking areas

    Remove campsites from the beach No Consistent with Concept Plan 1 & 3

    Work with RMR to develop trails No Not in scope of project

    Reduce speed on airport way or add sidewalk No Not in scope of project

    Keep the natural look No Consistent with landscaping improvements and succession planting

    Wheelchair accessible No Consistent with all plans

    Bigger park No Not in scope of project

    Improve swim quality of water by removing weeds from water No Not in scope of project

    Move fishing dock No Will create expanded dock for fishing off main swimming dock

    More sand on beach No Beach remediation and planting suggestions will keep sand from washing into the lake

     

    1

  • 8/18/2019 Williamson's Lake report

    58/92

    APPENDIX 06 OPEN HOUSE MATERIALS

  • 8/18/2019 Williamson's Lake report

    59/92

    Campground and Day Use Area CONCEPT PLANSOPEN HOUSENovember 23rd , 2015

    City of Revelstoke - Parks, Recreation & Culture Dept.

    600 Campbell Ave.

    P.O. Box 170

    Revelstok e, BC V0E 2S0

    T: (250) 837-9351

    WILLIAMSON’S LAKE

    MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS

  • 8/18/2019 Williamson's Lake report

    60/92

       I   S   S   U   E

       0   9 .   0   8 .   2   0   1   5

       R   E  -   I   S   S   U   E

       1   1 .   0   1 .   2   0   1   5

       C   L   I   E   N   T

       C   i   t  y   o   f   R   e  v   e   l   s   t   o   k   e  -   P   a   r   k

       s ,   R   e   c   r   e   a   t   i   o   n   &   C  u   l   t  u   r   e   D   e   p   t .

       6   0   0   C   a   m   p   b   e   l   l   A  v   e .

       P .   O .   B   o  x   1   7   0

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   8   3   7  -   9   3   5   1

       S   E   L   K   I   R   K   P   L   A   N   N   I   N   G   &   D   E   S   I   G   N

       B   o  x   1   9   9   4

       1   0   1   S   e   c   o   n   d   S   t .   E

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   2   0   0  -   0   6   8   0

       E  :   s   e   l   k   i   r   k   p   l   a   n   n   i   n   g   @   g   m   a   i   l .   c   o   m

       P   R   O   J   E   C   T   N   O .

       2   0   1   5  -   C   O   P  -   W   L

       P   R   O   J   E   C   T

       W   i   l   l   i   a   m   s   o   n   ’   s   L   a   k   e   D   a  y   U   s   e   A   r   e   a   &

       C   a   m   p   g   r   o  u   n   d   C   o   n   c   e   p   t   P   l   a   n

       D   R   A   W   N   B   Y

       F   B ,   J   J

       D   E   S   C   R   I   P   T   I   O   N

    a

    02

    PROPOSED SITE IMPROVEMENTSCommon to All Concepts

    01 03 04 05 07 11 12 1308 1006 0902

    01 Improved Signage @ Airport Way 

    02 Overflow Day Use Parking w/ Improvements

    03 Entry Sign @ Important Wayfinding View 

    04 Narrow Road for One Way Traffic

    05 Campground Registration Parking

    05.1 Potential campground office & caretaker residence

    06 Vehicular Wayfinding Signage

    07 Public Space @ Entrance

    07.1 Includes Pedestrian Wayfinding Signage

    08 Construct New Day Use & Office Building(s)

    08.1 Change rooms & Washrooms (3M, 3F)

    08.2 Wheelchair accessible washroom & change room08.3 Campground office

    08.4 Food service kitchen

    08.5 Outdoor covered dining area & viewing deck

    08.6 Campground Laundry 

    08.7 Outdoor wood storage

    08.8 Potential caretaker residence

    08.9 Rinse showers for day use patrons

    08.10Indoor lockable storage for paddleboards, paddles, etc.

    08.11Formal day use entry/gateway 

    08.12Incorporate historical/interpretive information (heritage panels)

    09 Re-vegetate Slope

    10 Formal Path/Stairs Down to Beach

    11 Private Property (or Trail) Signage

    12 Formalize/Protect Beach Area & Canoe Launch

    13 Permanent Wheelchair Accessible Dock

    14 Improved Beach Signage

    15 Beach Protection - from erosion, etc.

    16 Rotary Outdoor Cooking Shelter

    16.1 Wood oven + BBQs

    16.2 Covered seating area with picnic tables

    16.3 Fish-washing station

    17 Proposed Recreation/Improvement Area

    17.1 Hammocks, climbing cubes, slack lines, etc.

    18  Activity Area

    18.1 Horseshoes, volleyball, etc.

    19 Wheelchair Accessible Pathway to Beach

    20 Mini Putt Removed

    21 Succession Planting

    21.1 Plant tree and species to revegetate degraded areas and replace

    existing trees as they near the end of their lifespan

    22 Beach Improvements and Potential New Dock

    23 Campsites Removed From Beach - Public Beach

    24  Address Awkward Small Campground Sites

    25 Provide Shade for Playground

    26 Flexible Open Space Area

    27 Potential Walk-In Tent Sites

    27.1 ~10 tenting sites

    27.2 Opens up the beach to more public use

    28 Potential Yurt Camping Area Expansion

    28.1 Potential for approx. 4-6 Yurts + parking area - Walk-in only 

    29 Parking Area for Walk-In Sites Beach Area

    30 Potential Fishing/Wildlife Viewing Dock

    31 Level Tent Sites & Improve Parking Pad Access

    31.1 Level sites with wood berms & fill or retaining walls

    31.2 Change vehicle back-in angle where possible

    31.3 Improved site marking

    32 Private Property Signage

    33 Improved “No RV Access” Sign

    34 Potential New Shower/Washroom Location

    34.1 Construct campground shower/washroom in new location

    34.2 Showers & Washrooms (3M, 3F)

    34.3 Wheelchair accessible washroom & shower

    34.4 Roof extension for covered cooking area (2 cooking areas)

    34.5 Dish washing station

    34.6 Screened outdoor materials / gas tank storage

    35 Campsite Improvements

    35.1 Defined campsite pads

    35.2 Permanent picnic table & fire location

    35.3 Improved site marking

    36 Vegetation to Create Privacy Screening

    37 Remove Dangerous Trees

    38 Narrow Road for One Way 

    39 Improved Signage for RV Empty Station40 Garbage & Recycling Pick Up Area

    41 Formalized Day Use Parking Stalls

    42 Overflow/Winter Camping Area OR Picnic Area

    42.1 Suitable for RVs or tents

    42.2 Potential winter yurt area - Move yurts from summer location

    43 Reverse Traffic Direction

    43.1 Improves visual access to day use & office building - wayfinding

    43.2  Access to “preferred” day use parking first

    30

    23

    24

    25

    26

    27

    32

    31

    29

    28

    22

    14

    15

    18

    16

    17

    19

    21

    35

    42

    38

    43

    39

    40

    33

    34a

    34b

    36

    37

    41

    20

    MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS

  • 8/18/2019 Williamson's Lake report

    61/92

       I   S   S   U   E

       0   9 .   0   8 .   2   0   1   5

       R   E  -   I   S   S   U   E

       1   1 .   0   1 .   2   0   1   5

       C   L   I   E   N   T

       C   i   t  y   o   f   R   e  v   e   l   s   t   o   k   e  -   P   a   r   k

       s ,   R   e   c   r   e   a   t   i   o   n   &   C  u   l   t  u   r   e   D   e   p   t .

       6   0   0   C   a   m   p   b   e   l   l   A  v   e .

       P .   O .   B   o  x   1   7   0

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   8   3   7  -   9   3   5   1

       S   E   L   K   I   R   K   P   L   A   N   N   I   N   G   &   D   E   S   I   G   N

       B   o  x   1   9   9   4

       1   0   1   S   e   c   o   n   d   S   t .   E

       R   e  v   e   l   s   t   o   k   e ,   B   C   V   0   E   2   S   0

       T  :   (   2   5   0   )   2   0   0  -   0   6   8   0

       E  :   s   e   l   k   i   r   k   p   l   a   n   n   i   n   g   @   g   m   a   i   l .   c   o   m

       P   R   O   J   E   C   T   N   O .

       2   0   1   5  -   C   O   P  -   W   L

       P   R   O   J   E   C   T

       W   i   l   l   i   a   m   s   o   n   ’   s   L   a   k   e   D   a  y   U   s   e   A   r   e   a   &

       C   a   m   p   g   r   o  u   n   d   C   o   n   c   e   p   t   P   l   a   n

       D   R   A   W   N   B   Y

       F   B ,   J   J

       D   E   S   C   R   I   P   T   I   O   N

    a

    03

    PUBLIC SPACECommon to All Concepts

    01  Approachable Entrance

    02 New Day Use Building with food service

    03 Covered & open dining patio

    04 Stairs down to beach & permanent dock

    05 Viewing/seating area

    06 Wheelchair accessible ramp to beach

    07 Open air picnic shelter with wood stove + BBQs

    08 New day use change room, washroom + shower

    09 Gateway entrance to park w/ building rooflines

    10 Vehicle pick up are