Sentinel Lake Assessment Report Cedar Lake (49-0140) Morrison
Williamson's Lake report
-
Upload
alexcooperrtr -
Category
Documents
-
view
216 -
download
0
Transcript of Williamson's Lake report
-
8/18/2019 Williamson's Lake report
1/92
PREPARED BY: JANUARY 26TH , 2016
WILLIAMSON’S LAKE COMMUNITY
PARK & CAMPGROUNDCONCEPT PLAN
-
8/18/2019 Williamson's Lake report
2/92
-
8/18/2019 Williamson's Lake report
3/92
WILLIAMSON’S LAKE COMMUNITY PARK & CAMPGROUND
CONCEPT PLAN
SELKIRK PLANNING & DESIGN| Community Planning | Urban Design |Box 1994Revelstoke, BC V0E 2S0(250) [email protected]
LARCHLandscape + Authentic Mountain DesignBox 1738Golden, BC V0A [email protected]
TAKE TO HEART CONTRACTING LTD.Box 2368776 Westside Rd.Revelstoke, BC V0E 2S0(250) 837-4482taketoheart.ca
PREPARED FOR:
THE CITY OF REVELSTOKE DEPARTMENT OF PARKS, RECREATION & CULTURE P.O. BOX 170600 CAMPBELL AVE.REVELSTOKE, BC V0E 2S0(250) 837-9351
SUBMITTED ON JANUARY 26TH BY:
-
8/18/2019 Williamson's Lake report
4/92
-
8/18/2019 Williamson's Lake report
5/92
CONTENTS
PART 01: PROJECT INTRODUCTION 1
01.01 PROJECT BACKGROUND 1
01.02 PROJECT PURPOSE 1
PART 02: PROJECT PROCESS 202.01 REVIEWING PREVIOUS PLAN PRIORITIES 2
02.02 HISTORICAL/PRECEDENT RESEARCH 2
02.03 SITE ASSESSMENT – IDENTIFY MAIN ISSUES 2
02.04 OPPORTUNITIES 4
02.05 DESIGN CONCEPTS 6
02.06 PUBLIC OPEN HOUSE 7
02.07 FEEDBACK ON CONCEPT PLANS 7
PART 03: RECOMMENDATIONS 8
03.01 COMMUNITY INPUT ON PRIORITIZED RECOMMENDATIONS 8
03.02 PRIORITIZED RECOMMENDATIONS 8
03.03 IMPROVEMENTS & CONSIDERATIONS 24
PART 04: IMPLEMENTATION 26
04.01 PHASING 26
APPENDICES 29
-
8/18/2019 Williamson's Lake report
6/92
-
8/18/2019 Williamson's Lake report
7/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT1
PART 01: PROJECT INTRODUCTION
01.01 PROJECT BACKGROUND
In September 2015 consultants Selkirk Planning & Design (SPD), in partnership with Larch Landscape + Authentic Moun-tain Design (LLAMD) and Take To Heart Contracting (TTHC) undertook site analysis and conceptual design for the William-son’s Lake Campground and Day Use Area. The 2015 site plan is an update to a previous site plan completed in 2011 The2011 Plan can be viewed in Appendix A.
The project was to focus on three main areas:
• Plan for the long-term replacement of the aging existing day use and campground buildings;
• Improving the day use area of the park; and
• Improving the campground to bring it up the standards of a municipal park in a BC Resort community.
01.02 PROJECT PURPOSE
Prior to beginning the project, SPD met with City staff to clarify the project purpose. The priorities for the project are to:
• Improve and enhance Williamson’s Lake;
• Make it feel like a community park rather than a private campground; and
• Create a great public space and increase resident and tourist visits.
Photos of existing park and campground
-
8/18/2019 Williamson's Lake report
8/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT2
PART 02: PROJECT PROCESS
02.01 REVIEWING PREVIOUS PLAN PRIORITIES
Before beginning the project, the previous site plan, developed in 2011, was reviewed and updated. The Key Priorities thatwere completed were acknowledged and incomplete priorities were forwarded to the 2016 plan. The 2011 priorities weresent out to community stakeholders involved with the previous plan to review and conrm their inclusion in the 2015 plan.
02.02 HISTORICAL/PRECEDENT RESEARCH
Historical research of Williamson’s Lake was done at the Revelstoke Museum & Archives before beginning any design oranalysis work. The nal design was inuenced by images of the old park with a central stairway down to the water as a formalprocession down to the water. See Appendix B. Precedents were studied to help brainstorm ideas and adapt other improve-ments and enhancements for Williamson’s Lake.
02.03 SITE ASSESSMENT – IDENTIFY MAIN ISSUES
The design process began with a site assessment. SPD, LLMAD & TTHC walked the site, took photos and notes of the day usearea, the campground and the buildings. During the site visit, the team interviewed the Campground Manager to betterunderstand the issues and opportunities for the day use area and campground. A map was developed to identify all issues,and locate and describe them.
From the issues a map of opportunities was developed to describe how each issue could be addressed. The opportunitiesmap focussed on all the recommendations big and small. These recommendations fell under three main focus areas iden-tied in section 01.01 on page 1.
The Issues Map & Boards can be reviewed in Appendix C.
Photos courtesy of Revelstoke Museum & Archives
-
8/18/2019 Williamson's Lake report
9/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT3
Campsite Markers
Existing campground showers & washrooms
Existing pathway to the beach
RV sites
Campsite signage
Upslope erosion
Undefned parking spaces
Beach condition
Existing food service
Road and campsites along the waterfront
Signage
Existing day use building
-
8/18/2019 Williamson's Lake report
10/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT4
02.04 OPPORTUNITIES
The recommendations focused on the following 3 main areas:
• Plan for the long-term replacement of the aging existing day use and campground buildings;
◦ This includes:
g cleaning up clutter to improve the day use experience;
g providing a better food service experience;
g providing a better campground reception experience;
• Improving the day use area of the park;
◦ This includes:
g providing better access to the beach;
g improving and expanding the public beach;
g successional landscape planning;
g proposing activity areas, and better placemaking; and
• Improving the campground to bring it up the standards of a municipal park in a BC Resort community;
◦ This includes:
g leveling and formalizing camping sites;
g improving privacy, signage and layout.
I S S U E
0 9 . 0 8 . 2 0 1 5
R E - I S S U E
C L I E N T
C i t y o f R e v e l s t o k e - P a r k s , R e c r e a t i o n & C u l t u r e D e p t .
6 0 0 C a m p b e l l A v e .
P . O . B o x 1 7 0
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 8 3 7 - 9 3 5 1
S E L K I R K P L A N N I N G & D E S I G N
B o x 1 9 9 4
1 0 1 S e c o n d S t . E
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 2 0 0 - 0 6 8 0
E : s e l k i r k p l a n n i n g @ g m a i l . c o m
P R O J E C T N O .
2 0 1 5 - C O P - W L
P R O J E C T
W i l l i a m s o n ’ s L a k e D a y U s e A r e a &
C a m p g r o u n d C o n c e p t P l a n
D R A W N B Y
F B , J J
D E S C R I P T I O N
a
05
OPPORTUNITIES
01 Improved Signage @ Airport Way
02 Overflow Day Use Parking w/ Improvements
03 Entry Sign @ Important Wayfinding View
04 Narrow Road for One Way
05 Campground Registration Parking
06 Vehicular Wayfinding Signage
07 Plaza & Pedestrian Wayfinding Signage
08 Day Use Parking - Defined Spaces
09 New Day Use & Office Building(s)
09.1 Change rooms (3M, 3F)
09.2 Washrooms (3M, 3F)
09.3 Wheelchair accessible washroom & change room
09.4 Campground office
09.5 Food service kitchen
09.6 Outdoor covered dining area & viewing deck
09.7 Laundry
09.8 Outdoor wood storage
09.9 Potential caretaker residence
09.10Rinse showers for day use patrons
09.11Garbage & recycling storage
09.12 Indoor lockable storage for paddleboards, paddles, etc.
09.13Outdoor cooking shelter & fish-washing station (stand alone build-
ing - open air, stove, sink, bear-aware garbage)
09.14Formal day use entry/gateway
09.15 Incorporate historical/interpretive information (heritage panels)
10 Re-vegetate Slope
11 Formal Path/Stairs Down to Beach
12 Private Property (or Trail) Signage
13 Formalize Beach Area & Canoe Launch
14 Permanent Wheelchair Accessible Dock
15 Improved Beach Signage
16 Pathway Defines/Protects Beach & Seating Area
17 Wheelchair Accessible Pathway to Beach
18 Mini Putt Moved Around Playground
19 Successive Planting Area
19.1 Plantspeciestoreplaceexistingtreesastheynearthe endoftheirlifespan
20 Wheelchair Accessible Viewing Dock
21 Campsites Removed From Beach - Public Beach
22 Slip n’ Slide Route (Special Event Only)
23 Beach Volleyball Court on Beach
24 Walk-In Tent Sites Replace Beach Sites
24.1 ~10 tenting sites
24.2 Opens up the beach to more public use
25 Expanded Yurt Camping Area
25.1 4-6 Yurts + parking area - Walk-in only
26 Parking Area for Walk-In Sites & Re-vegetation
27 Fishing/Wildlife Viewing Dock28 Level Tent Sites & Improve Parking Pad Access
28.1 Level sites with wood berms & fill
28.2 Change vehicle back-in angle where possible
28.3 Improved site marking
29 Private Property Signage
30 Improved “No RV Access” Sign
31 New Campground Shower/Washroom
31.1 Move existing campsite & place building closer to the road
31.2 Showers (3M, 3F)
31.3 Washrooms (3M, 3F)
31.4 Wheelchair accessible washroom & shower
31.5 Roof extension for covered cooking area (2 cooking areas)
31.6 Dish washing station
31.7 Screened outdoor materials / gas tank storage
32 Formalized RV Sites
32.1 Formal RV pads
32.2 Permanent picnic table & fire location
32.3 Improved site marking
33 Flexible Open Space Area
34 Vegetation to Create Privacy Screening
35 Trees to Provide Shade for Playground
36 Remove Dangerous Trees
37 Formalized Small Campground Sites
37.1 Vegetation buffers
37.2 Permanent picnic table & fire location
37.3 Improved site marking
38 Narrow Road for One Way
39 Improved Signage for RV Empty Station
40 Formalized Day Use Parking Stalls
41 Overflow/Winter Camping Area
41.1 Suitable for RVs or tents
41.2 Potential winter yurt area - Move yurts from summer location
42 Reverse Traffic Direction
42.1 Improves visual access to day use & office building - wayfinding
42.2 Access to “preferred” day use parking first
42.3 Improves ability for RVs to back into camping sites
42.4 Reduces RVs driving down “tent only” road
01 03 04 05 07 08 12 13 1409 1106 1002
23
27
21
24
29
28
26
25
20
22
15
16
17
18
19
32
33
41
40
38
42
39
30
31
36
34
37
35
-
8/18/2019 Williamson's Lake report
11/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT5
Hammock area was explored
Yurt camping was explored
Fishing dock
Expanded dock with new fnishing
An amphitheater was explored
Succession planting with appropriate native species
Proposed sitting docks were explored
Simple, modern building design proposed
Formalizing campgrounds & walk-in sites
Improved campsite markers
Wheelchair accessible pathway
Proposed buildings would have food service
-
8/18/2019 Williamson's Lake report
12/92
-
8/18/2019 Williamson's Lake report
13/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT7
02.05.02 Building Concepts
Each of the three concepts had slightly different building layouts that helped illustrate each concept. The differing buildinglayout concepts are interchangeable and could work in any of the three concepts. Up to 5 building concepts are presentedon p. 4 with a breakdown of costs for each concept.
02.06 PUBLIC OPEN HOUSE
All three concept plans and building concepts were presented to the public at an open house at the Revelstoke Commu-nity Centre on November 23rd, 2015. There were 18 attendees who provided comments about the concepts. Commentswere submitted via a short survey. The survey and its results are summarized in Appendix D. The panels and surveys weremounted in the main foyer of the community centre until Monday November 30th, 2015. The full package of Open HouseMaterials can be found in Appendix E.
02.07 FEEDBACK ON CONCEPT PLANS
The comments from the open house were summarized and reviewed with the Director or Parks, Recreation and Culture.The feedback revealed that there was very little support for the expansion of the campground (Option 2). There was littledifference in support for the Community Park (Option 1) or Balanced Option (Option 3). A list of proposed improvementswas voted on by community members. The survey results led to the proposed recommendations in this plan.
Several Building Concepts were explored
-
8/18/2019 Williamson's Lake report
14/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT8
PART 03: RECOMMENDATIONS
03.01 COMMUNITY INPUT ON PRIORITIZED RECOMMENDATIONS
The survey results were reviewed with the Director of Parks, Recreation and Culture to prioritize the highest priority rec-ommendations. The highest priority recommendations were chosen based on the survey results and an assessment of theissues and potential benets of some of the proposed recommendations.
The top three improvements as voted on by the community were:
1. Improved Buildings
2. Accessible Pathway
3. Landscape Improvements and succession planting
The proposed dock improvements to make them accessible was the fourth highest improvement, but support was notice-ably lower than for the top 3.
While the campsite improvements were low on the list of preferred options, both SPD and the Director of Parks, Recreationand Culture felt that there would be very little community support for this, but that it was important to include campgroundimprovements in the list of recommendations. There was little to no support for campground expansion and yurt camping.
Note: Pathways and docks within 30m of the high water mark are subject to RAR approval by the Government of BC.
The prioritized recommendations are described below.
03.02 PRIORITIZED RECOMMENDATIONS
03.02.01 New Buildings
The plan recommends the replacement of the campground washroom & shower building, and the change room andwashroom. The recommendations are proposed to address issues with the aging infrastructure. The major benets of thenew building locations are that they house all the various activities needed for this site to function as both a park andcampground, and they act as a landmark to help people navigate the site. They become the physical anchors and identityfor Williamson’s Lake.
The Building concepts focus on 2 or 3 main buildings. The highest priority improvement is to replace the campgroundwashroom & shower building which has reached the end of its lifespan. The second-highest priority is to remove thetrailers and outdoor storage used for day use food service and campground registration. The third building priority is toreplace the existing day use change room & washroom building, which is nearing the end of its lifespan. The day use &campground reception building and existing change room and washroom building replacement has been presented asve separate options. Options 1 to 3 examine a two-phased process that replaces the trailers and outdoor storage in the
near future (3-5 years), while replacing the existing change room & washroom once it has reached the end of its lifespan(6-10 years). Options 4 to 5 examine a single-phased process that builds the day use building, campground reception andchange room & washroom at the same time once the existing building has reached the end of its lifespan.
The campground washroom/shower building and building options 1 to 3 were presented at the Public Open House. Build-ing Options 4 and 5 were created afterwards. No building plans or visualizations were prepared for Options 4 and 5.
The summary of recommendations identies the benets, challenges and cost estimates of constructing a new building.
-
8/18/2019 Williamson's Lake report
15/92
-
8/18/2019 Williamson's Lake report
16/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT10
A) Campground Washroom & Shower Building
The campground washroom & shower buildingis a simple rectangular structure. It would beconstructed to be wheelchair accessible. Thebuilding would have 3 showers, and 3 toilets
with an additional wheelchair accessible wash-room and shower. Extra space within the build-ing is planned to act as storage for water heat-ers, cleaning equipment, and other equipmentrelated to the building function.
A single-pitch roof extends over the building toprovide a covered picnic area and dish-washingstation.
The backside of the building could includesome screened storage of rewood for sale to
campground users, creating a more secure lo-cation.
The building shape will be replicated for usewith the proposed day use change room &washroom (options 1 to 3).
TABLE 1. CAMPGROUND WASHROOM/SHOWER BUILDING ASSESSMENT & COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Campground Washroom /
Shower
• Makes showers and
washrooms wheelchair
accessible
• Upgrades building and
addresses water damage
issues
• Adds covered outdoor
cooking and dish cleaning
area
• Provides screened storage
area for equipment
• Provides firewood storage
• Cost
• Construction on existing
location means timeline may
overlap with campground
service season
◦ no campground shower
service
◦ washroom could beaccommodated at day
use area change room
$164,000-$188,000
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
02 New Campground Shower/Washroom
02.1 Multiple location options
02.2 Showers (3M, 3F)
02.3 Washrooms (3M, 3F)
02.4 Wheelchair accessible washroom & shower
02.5 Roof extension for covered cooking area (2 cooking areas)
02.6 Dish washing station
02.7 Screened materials / gas tank storage
02.8 Outdoor wood storage
02.2M02.2F 02.3F 02.3M
02.4
02.5
02.6
02.7
02.8
-
8/18/2019 Williamson's Lake report
17/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT11
B) Day Use & Campground Reception Buildings - Summary
The table below summarizes the benets and challenges of the two day use & campground reception building options. De-tailed break-down of the benets and challenges along with a preliminary cost estimate is provided for each building option.
TABLE 2. DAY USE BUILDING OPTIONS SUMMARY
BUILDING OPTION BENEFITS CHALLENGES
Building Opons 1, 2, & 3
Two-Building Concept
• Allows for quicker remedy of issues
around temporary buildings for food
service and campground reception
• Allows for easier, phased replacement
strategy
• Lower individual building costs may
make fundraising easier by separating
into different years
• Two buildings create central gateway /
walkway as a formal entrance to the dayuse area
• Highest cost option over the long term
Building Opons 4 & 5
One-Building Concept
• Lower cost option
• Single construction phase
• Larger Building, less conducive to
open, accessible building
PUBLIC SPACECommon to All Concepts
01 Approachable Entrance
02 New Day Use Building with food service
03 Covered & open dining patio
04 Stairs down to beach & permanent dock
05 Viewing/seating area
06 Wheelchair accessible ramp to beach
07 Open air picnic shelter with wood stove + BBQs
08 New day use change room, washroom + shower
09 Gateway entrance to park w/ building rooflines
10 Vehicle pick up area w/ seating
11 Bike parking out front of change room
12 Additional bike parking
02
01
03
04
09
05
08
11
10
12
0706
The two-building concept (options 1 to 3) create a great public space
-
8/18/2019 Williamson's Lake report
18/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT12
i. Day Use Change Room / Washroom Building(Options 1, 2, & 3 only)
The day use change room / washroom buildingis a proposed stand alone building that wouldreplace the existing change room / washroom
building at the end of its lifespan. The buildingwould have 3 change rooms and washrooms forboth men and women. A single, self-containedwheelchair accessible washroom and changeroom is also proposed. Outdoor and indoorstorage would house day use maintenanceequipment and building infrastructure andcleaning supplies.
The building side overlooking Williamson’sLake would also include 3 rinse showers wherebeach users can rinse off after swimming.
TABLE 3. CAMPGROUND WASHROOM/SHOWER BUILDING ASSESSMENT & COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COSTESTIMATE
Campground Washroom /
Shower
• Upgrades building to make it
wheelchair accessible
• Can be phased and built as
needed
• Creates second side of
gateway entrance to the
park
• Adds outdoor rinse shower
for day use area
• Provides screened storage
area for equipment• Back side of building creates
large area capable of
housing bike racks / storage
• Not needed until current
building reaches the end of
its lifespan
• Would need to extend
services or move new septic
system (2015)
$151,000-$174,000
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
01 Day Use Change Room & Washroom
01.1 Washrooms & change rooms (3M, 3F)
01.2 Wheelchair accessible washroom & change room
01.3 Rinse showers for day use patrons
01.4 Storage for cleaning supplies, boiler, etc.
01.5 Option to be insulated for winter use in part or whole building
01.1M01.1F
01.2
01.3
01.4
01.4
-
8/18/2019 Williamson's Lake report
19/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT13
ii. Day Use Building Option 1
Day Use Building Option 1 is a two-storey building that contains a food service kitchen and service window, campground
reception and laundry, equipment storage, and caretaker suite on the upper oor.
TABLE 4. DAY USE BUILDING OPTION 1 BUILDING ASSESSMENT AND COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Change Room / Washroom
Building
• see Table 3 for day use change
room / washroom benefits
• see Table 3 for day use change
room / washroom challenges$151,000-$174,000
Two-Storey Recepon, Food
Service, Storage, Suite
• Two-storey option takes up
less ground space, allowing
for more public space
• Two-storey option provides
the best visibility and best
wayfinding to direct peoplethrough the site
• Two-storey options creates
the most defined “gateway
feature” to the lake
• Highest cost option
• Caretaker suite only used in
summer months – empty the
rest of the year
$180,000-$215,000
Building Option 1 Total $331,000 - $389,000
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
01.4
01.5
01.6
01.7
01.8 01.9
01 Day Use & Office Building
01.1 Forms day use entry/gateway with change room building
01.2 Park & Heritage Information boards
01.3 Option to be insulated for winter & year-round use
First Floor
01.4 Campground registration office
01.5 Campground laundry - lockable and able to be monitored
01.6 Food service kitchen
01.7 Outdoor covered dining area & viewing deck
01.8 Indoor lockable storage for rental paddleboards, canoes, etc.
Second Floor
01.9 Caretaker suite eliminates need for trailer and non-permanent office
-
8/18/2019 Williamson's Lake report
20/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT14
iii. Day Use Building Option 2
Day Use Building Option 2 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, and caretaker suite all on a single oor.
TABLE 5. DAY USE BUILDING OPTION 2 BUILDING ASSESSMENT AND COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Change Room / Washroom
Building
• see Table 3 for day use change
room / washroom benefits
• see Table 3 for day use change
room / washroom challenges$151,000-$174,000
One-Storey Recepon, Food
Service, Storage, Suite
• Simple building footprint
and roofline saves on
construction costs
• Creates large covered patio
area
• Creates attractive entrance to
the day use area
• Higher cost option
• Less of a landmark at onestorey
• Caretaker suite only used in
summer months – empty the
rest of the year
$165,000-$197,000
Building Option 2 Total $316,000 - $371,000
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
01.101.2
01.3
01.4
01.5
01.6
01.7
01 Day Use & Office Building
01.1 Campground registration office
01.2 Caretaker suite eliminates need for trailer and non-permanent office
01.3 Campground laundry - lockable and able to be monitored
01.4 Food service kitchen
01.5 Kitchen storage
01.6 Outdoor covered dining area & viewing deck
01.7 Indoor lockable storage for rental paddleboards, canoes, etc.
01.8 Option to be insulated for winter & year-round use
01.9 Forms day use entry/gateway with change room building
01.10Park & Heritage Information boards
-
8/18/2019 Williamson's Lake report
21/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT15
iv. Day Use Building Option 3
Day Use Building Option 3 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, but no caretaker suite.
No oorplans were created for this option. The images show an approximately-sized building that does not contain thecampground reception.
TABLE 6. DAY USE BUILDING OPTION 3 BUILDING ASSESSMENT AND COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Change Room / Washroom
Building
• see Table 3 for day use change
room / washroom benefits
• see Table 3 for day use change
room / washroom challenges$151,000-$174,000
One-Storey Reception, Food
Service, Storage
• Simple building footprint
and roofline saves onconstruction costs
• Creates large covered patio
area
• Creates attractive entrance to
the day use area
• Lowest cost option of two-building concepts (1-3)*
• Less of a landmark at one
storey
• Caretaker suite needs to be
provided - likely as a trailer
$146,000 -$168,000
Building Option 3 Total $297,000 - $342,000
*Cost does not include facilities needed for campground caretaker suite and related storage
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
-
8/18/2019 Williamson's Lake report
22/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT16
v. Day Use Building Option 4
Day Use Building Option 4 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, caretaker suite, day use change room and washroom all in a single building.
This option was explored after the open house. No oorplans or graphics were created for this option.
TABLE 7. DAY USE BUILDING OPTION 4 BUILDING ASSESSMENT AND COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Change Room, Washroom, Food
Service, Recepon, Caretaker
Suite
• Simple building footprint
and roofline saves on
construction costs
• Easier construction schedule
• Lowest cost option that
houses all services
• Caretaker suite only used in
summer months – empty the
rest of the year
• Larger building means less
space for outdoor seating
area and public space
• Replace change room /
washroom before end of
lifespan or delay replacing
trailer and outdoor storage
until change room / washroom
reach the end of its lifespan
$315,000 - $375,000
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
vi. Day Use Building Option 5
Day Use Building Option 5 is a one-storey building that contains a food service kitchen and service window, campgroundreception and laundry, equipment storage, day use change room and washroom all in a single building.
This option was explored after the open house. No oorplans or graphics were created for this option.
TABLE 8. DAY USE BUILDING OPTION 5 BUILDING ASSESSMENT AND COSTS
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Change Room, Washroom, Food
Service, Recepon
• Simple building footprint
and roofline saves on
construction costs• Easier construction schedule
• Lowest cost option*
• Larger building means less
space for outdoor seating
area and public space
• Replace change room /
washroom before end of
lifespan or delay replacingtrailer and outdoor storage
until change room / washroom
reach the end of its lifespan
• Caretaker suite needs to be
provided - likely as a trailer
$276,000-$328,000*
*Cost does not include facilities needed for campground caretaker suite and related storage
Detailed Preliminary Cost Estimates for buildings can be found in Appendix 08
-
8/18/2019 Williamson's Lake report
23/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT17
03.02.02 Accessible Pathway
At present there is no accessible route to the waterfront at Williamson’s Lake Campground and Day Use Area. Pedestrianaccess is limited to concrete stairs with a handrail and a gravel path installed with concrete jersey barriers retaining thetrail mix. The existing topography to the lakefront is a series of steep turf slopes broken up with level benched areas, whichmakes access challenging for those in wheelchairs or with limited mobility.
Feedback gathered through the public engagement process indicates that establishing a formalized accessible route tothe beach and lakefront is the second highest priority behind only the building improvements.
Moving forward, a 2.5m width asphalt pathway with a maximum grade of 8% will be designed and constructed with a hand-rail on the downslope side. Small retaining walls may be required to achieve the 2.5m width, however, it is anticipated thatthe majority of the pathway can be achieved with backsloping and balanced cut and ll.
The estimated costs for construction of the accessible pathway is: $41,875 including a 15% contingency and detailed design.
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
TABLE 9. ACCESSIBLE PATHWAY CONSTRUCTION OPTIONS
OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE*
Accessible Pathway Sloped
• Creates wheelchair accessible
access to the water
• High priority, low cost
• Cost
• Slope assessment by a geotechnical
engineer needed to be done first
• Engineering costs not included in
preliminary cost estimate
$22,500
Accessible Beach Pathway to
connect both Accessible Docks
• Connects viewing dock with fishing
and swimming dock • Additional costs $11,000
Accessible Pathway Total* $41,875
*Cost includes contingency (15%) and Estimated Design Fees (10%)
Wheelchair Accessible pathway down slope to the water would be paved
-
8/18/2019 Williamson's Lake report
24/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT18
03.02.03 Docks
The existing dock at Williamson’s Lake Day Use Area consists of a modular oating dock system (Jet Float - http://www.jetoat.com/index_new.shtml). Upon site inspection it was observed that some of the modular plastic components have become damaged andpose a safety hazard to users in bare feet. This oating dock system typically carries a 10 year warranty and the owner should explorehaving damaged modules replaced as soon as possible.
While modular oating docks have appeal in regards to ease of install, lack of maintenance, and expandability, this dock system doesnot allow for accessible design and lacks a natural aesthetic and tactile appeal.
A) Options
Options for the proposed accessible dock include a combination of wood decking with aluminum frame and polyethylene oats.Recommendations for decking material include western red cedar due to the resistance to rot, decay, and insects without having tobe pre-treated. Maintenance requirements for western red cedar include power washing annually. Application of a natural environ-mentally friendly stain may be considered every three to ve years.
Composite decking may also be considered as an appropriate option for dock surfacing. Compos-
ite decking does not need to be sanded, stained, or renished. It does still require power washingand requires extensive structure beneath, as composite decking cannot achieve the span require-ments of traditional wood decking.
Another consideration for deck surfacing for the accessible dock includes a slip resistant perforat-ed metal decking although it should be noted that this doesn’t provide for a very natural aesthetic.Moving forward the following options for accessible dock construction and refurbishment include:
i. Option 1
Construct new shing and swimming dock with timber or steel/aluminum substructure andinstall wood or composite decking surface. Construct new accessible dock with timber orsteel/aluminum substructure and wood or composite decking material.
ii. Option 2
Expand the existing modular oating dock system to include the shing and swimming ex-tensions and install wood or composite decking surface structure on top of oating modularcomponents. This option will require further engineering design to retrot the oating mod-ular dock system with a deck structure on top. Construct new low prole jetoat or approvedequivalent accessible dock with wood or composite decking and access ramp.
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
TABLE 10. DOCK CONSTRUCTION OPTIONS
OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE*
Option 1 - Viewing Dock + New
Swimming Dock
• Longer term solution
• Better aesthetics & stability• Highest cost option $124,975
Option 2 - Viewing Dock + Add
on to existing jetfloat dock • Lower cost option • Voids Jetfloat warranty $90,050
*Cost includes contingency (15%), Estimated Design Fees (10%) and Estimated Cost for obtaining Regulatory (riparian) Approvals (if required) ($7,500)
Option 2: Modular oating dock
Option 1: New wood & steel/aluminum dock
-
8/18/2019 Williamson's Lake report
25/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT19
03.02.04 Landscape Plan
A) Natural Landscaping for Slope & Environmental Protection & Enhancement
Heavy foot trafc has led to signicant degradation of vegetation in specic areas within the Williamson’s Lake Campgroundand Day use area. A combination of planting, formalizing popular pedestrian thoroughfares through paved and gravel trails,
and public education should be implemented in combination to restore strategic areas of the site and to promote healthyvegetation growth for succession planting and screening. To avoid newly planted vegetation from becoming damaged,signage and low barriers may be implemented to educate the public about the landscape restoration work occurring for therst two growing seasons until the vegetation becomes established.
The following plant communities (groupings of primarily native trees and shrubs with a grass seed mix) will be developedin the detailed design phase to re-vegetate strategic sites within Williamson’s Lake Campground and Day Use Area:
• Cedar succession planting community
• Cedar understory shrub and grass planting community
• Slope naturalization grass and forb plant community
• Riparian enhancement planting community• Campground screening planting community
The estimated costs for construction of the soft landscape plan is: $145,000
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
TABLE 11. SOFT LANDSCAPE PLAN PRELIMINARY COST ESTIMATES
OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE
Cedar succession plant
community• Strategic replacement of aging
trees
• Beach protection and enhancement
• Aesthetic landscape enhancement
• Slope stabilization
• Better privacy between
campground and beach
• Clear messaging and regulatory
information allows the operator
and bylaw the ability to enforce
rules and regulations
• Cost
$22,500
Cedar understory shrub and
grass planting community$15,000
Slope naturalization grass and
forb plant community$4,500
Riparian enhancement planting
community$5,500
Campground screening plant
community$50,000
Construct vegetated swale at
base of slope$18,500
Landscape Plan Total* $145,000
*Total includes contingency (15%) and Estimated Design Fees (10%)
-
8/18/2019 Williamson's Lake report
26/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT20
B) Hard Landscaping Around Buildings
Hard landscaping around the new buildings will help protect the surrounding natural environment by creating a formalwalkway and access to the beach, and reducing pedestrian trafc on surrounding landscaping. Combining the hard land-scaping with the new buildings will compliment the design and help enhance the day use area and create a sense of place,dened by walkways, trees, benches and formal landscaping.
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
TABLE 12. HARD LANDSCAPE PLAN (AROUND NEW BUILDINGS)
OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE*
Timber stairs to dock
• Creates formal walkway down to
the water
• Reduces traffic on slopes,
protecting roots and slope stability
• Additional cost $50,000
Paving, trees and landscaping
• Compliments new buildingshelping to create a sense of place
• Trees provide shade, reducing heat
island effect
• Additional Cost $55,000
Hard Landscaping Total* $131,250
*Cost includes contingency (15%), and Estimated Design Fees (10%)
Hard landscaping with paving, trees, shrubs and grasses, benches and bike racks compliments the new buildings and protects the surrounding environment
-
8/18/2019 Williamson's Lake report
27/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT21
03.02.05 Signage
Signage was identied in the 2011 plan as a high, short-term priority. Despite it not being a high community priority, theplan identies signage as an important proposed improvement. Creating a signage strategy for the park would help differ-entiate the day use area from the campground, and make waynding and directions easier to understand.
Aesthetically, a signage strategy creates a coordinated image for Williamson’s Lake. Rather than having a variety of sign types, generallyshowing too much information, the strategy helps “brand” the park with simple, easy to understand, and coordinated signage.
A signage strategy includes a hierarchy of sign types that directs park and campground users from their cars to where they want to go.
A) Options
i. Proposed Sign Hierarchy
The following proposed signage hierarchy represents a method of creating a recognizable and consistent brand for Wil-liamson’s Lake while presenting the user with appropriate levels of information at key decision points. Consideration forlongevity, maintenance, and material selection will be explored with the client during the design development and detaileddesign phases of this project. The proposed signage hierarchy for Williamson’s Lake includes:
ii. Directional Signage
a. Purpose
• Direct users to Williamson’s Lake Campground
• Establish a graphic identity that is distinct from other signage enabling the user to distinguish the sign type from a distance
b. Location(s):
• Strategic locations along Fourth St E and Airport Way
• A large directional sign will be located at the intersection of Airport Way and Williamson’s Lake Road
iii. Entry Arrival Signage
a. Purpose
• Create a sense of arrival
• Welcome visitors and residents to Williamson’s Lake
• Establish the visual identity of the Williamson’s Lake Community Park
b. Location
• At the entry to the site along Williamson’s Lake Road
iv. Day Use Information Signage
a. Purpose• Provide pedestrian scale orientation and directional information to Williamson’s
Lake day use facilities and amenities
• Provide rules and regulations i.e. no lifeguards on duty
• Provide local information i.e. wildlife warnings, community events
• May be tailored to specic locations i.e. rules and regulations for beach and ac -cessible docks, walking trail
Example: Day Use Information Signage
Example: Simple Entry Arrival Signage
-
8/18/2019 Williamson's Lake report
28/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT22
• Reinforce the visual identity of the Williamson’s Lake signage style so that users know where to seek information
b. Locations
• Main entry to day use area, access points to beach area
v. Interpretive Signs
a. Purpose
• Provide interpretive information: Historic, Educational, Environmental
• Tie into existing Revelstoke Interpretive Signage program
b. Location
• Adjacent to the main pedestrian thoroughfare overlooking Williamson’s Lakefrom the deck structure
vi. Campground Registration Signage
a. Purpose
• Provide detailed campground information including layout, location of campsites, and location of amenities• Provide self check-in box
• Provide rules and regulations
• Provide local information i.e. wildlife warnings, community events
• Reinforce the visual identity of the Williamson’s Lake signage style so that users know where to seek information
b. Location
• North and South ends of the campground, walk-in sites
vii. Campsite Markers
a. Purpose
• Provide distinct identication to each formalized campsite
• Allow reserved campsites to be clearly distinguished
b. Locations
• At each campsite
viii. Advisory Signage
a. Purpose
• Provide text based regulatory or advisory information
• Note that overall number of vehicular advisory signs may be reduced through pavement markings
b. Locations
• As required by the client or campground operator
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
Example: Campsite Markers
Example: Interpretive Signage already built in Revelstoke
-
8/18/2019 Williamson's Lake report
29/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT23
TABLE 13. SIGNAGE PRELIMINARY COST ESTIMATES
OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE
Directional Signage • Vastly improves wayfinding and
communication
• Provides coordinated aesthetic
upgrade to the park “brand”
• Reduces illegal dumping
• Reduces trailers getting stuck on
steep road
• Enhances campground and
compliments campsite definition
• Can be implemented over a
number of years in small steps
• Cost
• Would benefit from a City-wide
signage strategy to direct people
to the park
$3,848
Entry Arrival Signage $17,500
Day Use Information Signage $,8,100
Interpretive Sign $6,250
Campground Registration
Signage$6,750
Campsite Markers (45) $16,875
Advisory Signage $2,625
Signage Total* $61,948
*Total includes contingency (15%) and Estimated Design Fees (10%)
03.02.06 Campground and Campsite Improvements
A) Description
Campsites within the Williamson’s Lake Campground t into three categories:
• RV full service campsites
• Vehicular access tent sites
• Walk-in sites
Primary considerations for campsite improvements include:• Safety considerations focused on reducing potential conict between animals and campers.
• Providing a high level of visitor experience
• Clearly marking each campsite with consistent campsite markers
• Creating privacy and screening between campsites
• Creating level, free draining campsites
• Designated areas for vehicular parking (non walk-in)
• Designated or obvious tent sites
• Fixed picnic table locations
• Fixed re pit locations• Walk in sites may require a food storage locker
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
-
8/18/2019 Williamson's Lake report
30/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT24
TABLE 14. CAMPSITE IMPROVEMENTS PRELIMINARY COST ESTIMATES
OPTION BENEFITS CHALLENGESPRELIMINARYCOSTESTIMATE
Construct new full service RV
sites• Improves campsite aesthetics
making it a more attractive
accommodation
• Addresses poorly constructed
tenting sites on steep slopes
• Environmental enhancement by
removing lakefront sites and road
• Better site layout to maximize sites
while improving privacy
• Walk-in sites create a different
camping option
• Implements bear-safe practices
• Cost
• Implementation of improvements
would need to be scheduled
around camping season
• Walk-in sites within 30m RAR Buffer
would need RAR approval
$80,000
Removal of existing sites $7,500
Construct walk-in campsites $15,000
Construct gravel or natural
surface walking trail to walk-in
campsites
$3,000
Install bear proof food locker $3,500
Install campsite markers N/A
Install fixed picnic tables $90,000
Install fixed fire pits $15,750
Campsite Improvements Total* $268,438
*Total includes contingency (15%) and Estimated Design Fees (10%)
03.03 IMPROVEMENTS & CONSIDERATIONS
03.03.01 Mini Putt
Early in the process it was clear that the best location for the new day use buildings is in the current mini-putt location. Dueto the condition of the mini-putt course, it was left out of the three site plan options presented to the public at the openhouse. Feedback from the open house both verbally and written was that the mini-putt was a desired amenity. In the nalsite plan it has been relocated around the existing playground, based on that feedback. The mini-putt would be rebuilt new,and incorporate more natural landscaping and trees to create the course.
Refer to Appendix 09 for Preliminary Opinions of Probable cost.
TABLE 15. MINI PUTT REDESIGN AND RELOCATION
BUILDING OPTION BENEFITS CHALLENGES PRELIMINARY COST
ESTIMATE
Removed, redesign and
construct mini putt course in
new locations
• Mini putt is a popular amenity
• Upgrade the mini putt course
to make it more aesthetically
pleasing
• Allows for the placement ofthe best building location
• Cost $62,500
*Total includes contingency (15%) and Estimated Design Fees (10%)
-
8/18/2019 Williamson's Lake report
31/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT25
03.03.02 Other Proposed Amenities
Several amenities were explored through the open house. Though they didn’t rank high on the community priorities, theyare presented below for reference. These options may wish to be revisited once the recommendations from this plan havebeen completed.
These improvements include:
• Seating Docks (medium community support)
• Hammock Area (medium community support)
• Amphitheater (medium community support)
• Exercise Area (low community support)
• Climbing Blocks (unknown community support)
• Yurt Camping (very low community support)
New mini-putt course should be more natural and could include rocks, trees & plants as features of the course, similar to a natural playground
-
8/18/2019 Williamson's Lake report
32/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT26
PART 04: IMPLEMENTATION
04.01 PHASING
TABLE 16. WILLIAMSON’S LAKE IMPROVEMENTS IMPLEMENTATION PLAN
IMPROVEMENT COMMUNITY
PRIORITY LEAD TIMELINE
COST /FUNDING
BUILDINGS HIGHEST
Campground Washroom / Showers Highest
Fundraising / Budgeting PRC, CED, CF Spring 2016
Construction Drawings CSLT, PRC, DEDS Summer 2016 $3,000
Existing Building Demolition PRC, PW Fall 2016 T.B.D.
Services Assessment & Connection Fees CSLT, PRC, PW Fall 2016 T.B.D.
Building ConstructionPRC, DEDS, PW,
CSLTSpring 2017
$164,000-$188,000
Day Use Food Service / Campground Reception Building Very High
Fundraising / Budgeting PRC, CED, CF 2016 - 2017
Construction Drawings CSLT, PRC, DEDS 2017 $2,600
Mini Putt Removal & Relocation PRC, PW Spring 2018 $62,500
Services Assessment & Connection Fees CSLT, PRC, PW Spring 2018 T.B.D.
Building ConstructionPRC, DEDS, PW,
CSLTSpring 2018
$146,000-$215,000
Day Use Change Room / Washroom Medium
Building Assessment Fundraising / Budgeting PRC, CED, CF 2016
Building Assessment - Determine LifespanPRC, PW, DEDS,
CSLT2016 or 2017 T.B.D.
Construction Fundraising / Budgeting PRC, CED, CF2 yrs before end
of life
Construction Drawings CSLT, PRC, DEDSSpring beforeconstruction
$1,500*
Services Assessment & Connection Fees CSLT, PRC, PWSpring beforeconstruction
T.B.D.
Existing Building Demolition PRC, PWFall before
constructionT.B.D.
Building Construction PRC, DEDS, PW,CSLT
Fall before& spring ofconstruction
151,000-$174,000
* 2015 Rate - If using the same building design & layout as campground washroom / shower building
-
8/18/2019 Williamson's Lake report
33/92
WILLIAMSON’S LAKE PARK & CAMPGROUND CONCEPT PLAN
SUMMARY REPORT27
TABLE 16. WILLIAMSON’S LAKE IMPROVEMENTS IMPLEMENTATION PLAN
IMPROVEMENT COMMUNITY
PRIORITY LEAD TIMELINE
COST /FUNDING
ACCESSIBLE PATHWAY VERY HIGH
Geotechnical Engineer Assessment Fundraising / Budgeting PRC, CED, CF 2016
Geotechnical Engineer Assessment PRC, DEDS, CSLT 2016 or 2017 T.B.D.
Regulatory Approvals (if needed)CSLT, PRC, DEDS,
GovBC, CSRD2016 or 2017 $7,500†
Pathway Design & Permits CSLT, PRC, DEDS 2016 or 2017 $2,250
Pathway ConstructionPRC, DEDS, PW,
CSLT2016 or 2017 $22,500
Wheelchair Accessible Path between docks Med-High
Fundraising / Budgeting PRC, CED, CF 2020
Regulatory Approvals (if needed)CSLT, PRC, DEDS,
GovBC, CSRD2020 $7,500†
Pathway DesignPRC, PW, GovBC,
CSRD2020 $1,100
Pathway ConstructionPRC, DEDS, PW,
CSLTSpring 2021 $11,000
DOCKS HIGH
Jet Float Warranty Repairs of existing dock (if still covered) PRC, PW Spring 2016 $0
Main Dock Construction or E xpansion High
Dock Fundraising / Budgeting PRC, CED, CF 2017-2018
Regulatory Approvals (if needed)CSLT, PRC, DEDS,
GovBC, CSRD2017 $7,500†
Dock Design & Permits PRC, PW, GovBC,CSRD 2018 $5,000-$7,000
Dock ConstructionPRC, DEDS, PW,
CSLTSpring 2018 $50,000-$70,000
Viewing Dock Med-High
Dock Fundraising / Budgeting PRC, CED, CF 2020
Regulatory Approvals (if needed)CSLT, PRC, DEDS,
GovBC, CSRD2020 $7,500†
Dock Design & PermitsPRC, PW, GovBC,
CSRD2020 $1,500-$2,250
Dock ConstructionPRC, DEDS, PW,
CSLTSpring 2021 $15,000-$22,500
LANDSCAPING HIGH
Soft Landscaping: Successional Planti ng High
Fundraising / Budgeting PRC, CED, CF 2018-2020
Landscape Plan & Construction Drawings CSLT, PRC, DEDS 2020 $11,600
Landscape Planting PRC, PW 2021 $116,000
-
8/18/2019 Williamson's Lake report
34/92
TABLE 16. WILLIAMSON’S LAKE IMPROVEMENTS IMPLEMENTATION PLAN
IMPROVEMENT COMMUNITY
PRIORITY LEAD TIMELINE
COST /FUNDING
H ar d Lan dsca ping: S ta ir s, Pa ving, Trees, S hr ubs, Gr asses & Benc hes M ed
Fundraising / Budgeting PRC, CED, CF 2020
Hard Landscaping Construction Drawings CSLT, PRC, DEDS 2020 $10,500
Hard Landscaping Construction PRC, PW Spring 2021 $105,000
SIGNAGE MED-HIGH
Fundraising / Budgeting PRC, CED, CF 2018-2020
Signage Strategy & Construction Drawings CSLT, PRC, DEDS 2020 $6,200
Signage Installation PRC, PW 2021-2026 $61,948
CAMPGROUND IMPROVEMENTS MED
Fundraising / BudgetingPRC, CED, CF,
WLCM2018-2020
Campground Improvements & Construction DrawingsCSLT, PRC, DEDS,
WLCM2020 $21,475
Campground Improvements PRC, PW, WLCM 2021-2026 $214,750
† Regulatory costs may be shared if plans are submitted together
Detailed Cost Estimates can be found in Appendix 08 (Buildings) and Appendix 09 (Landscape)
ABBREVIATIONS
Priority Timelines
Very High 1-2 YearsHigh 3-5 YearsMedium 6-15 Years
Lead Abbreviations
CBT Columbia Basin TrustCF City of Revelstoke Finance DepartmentCSLT External ConsultantCED City of Revelstoke Community Economic Development DepartmentCoC Revelstoke Chamber of CommerceCSRD Columbia Shuswap Regional DistrictDEDS City of Revelstoke Department of Engineering & Development ServicesGovBC Government of BCPRC City of Revelstoke Department of Parks, Recreation and CulturePW City of Revelstoke Public Works DepartmentWLCM Williamson’s Lake Campground Manager
Cost Categories
$0 - $999 Lowest$1,000 - $9,999 Low$10,000- $49,999 Medium$50,000 – $99,999 High> $100,000 Highest
-
8/18/2019 Williamson's Lake report
35/92
-
8/18/2019 Williamson's Lake report
36/92
APPENDIX 01 PREVIOUS SITE PLAN AND PRIORITIES
-
8/18/2019 Williamson's Lake report
37/92
-
8/18/2019 Williamson's Lake report
38/92
-
8/18/2019 Williamson's Lake report
39/92
-
8/18/2019 Williamson's Lake report
40/92
-
8/18/2019 Williamson's Lake report
41/92
-
8/18/2019 Williamson's Lake report
42/92
-
8/18/2019 Williamson's Lake report
43/92
-
8/18/2019 Williamson's Lake report
44/92
-
8/18/2019 Williamson's Lake report
45/92
-
8/18/2019 Williamson's Lake report
46/92
APPENDIX 02 WILLIAMSON’S LAKE HISTORICALPHOTOS
-
8/18/2019 Williamson's Lake report
47/92
Historical Photos of Williamson’s Lake courtesy of Revelstoke Museum & Archives
-
8/18/2019 Williamson's Lake report
48/92
Historical Photos of Williamson’s Lake courtesy of Revelstoke Museum & Archives
-
8/18/2019 Williamson's Lake report
49/92
Historical Photos of Williamson’s Lake courtesy of Revelstoke Museum & Archives
-
8/18/2019 Williamson's Lake report
50/92
APPENDIX 03 SITE ISSUES MAP
-
8/18/2019 Williamson's Lake report
51/92
I S S U E
0 9 . 0 8 . 2 0 1 5
R E - I S S U E
C L I E N T
C i t y o f R e v e l s t o k e - P a r k
s , R e c r e a t i o n & C u l t u r e D e p t .
6 0 0 C a m p b e l l A v e .
P . O . B o x 1 7 0
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 8 3 7 - 9 3 5 1
S E L K I R K P L A N N I N G & D E S I G N
B o x 1 9 9 4
1 0 1 S e c o n d S t . E
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 2 0 0 - 0 6 8 0
E : s e l k i r k p l a n n i n g @ g m a i l . c o m
P R O J E C T N O .
2 0 1 5 - C O P - W L
P R O J E C T
W i l l i a m s o n ’ s L a k e D a y U s e A r e a &
C a m p g r o u n d C o n c e p t P l a n
D R A W N B Y
F B , J J
D E S C R I P T I O N
a
04
OBSERVED ISSUES01 Poor Quality Signage at Intersection01.1 Too much information and not directional - No sense of entry to
the site
02 Road Condition & Parking02.1 Road is in poor condition
02.2 Overflow parking along the street is not well defined
03 Poor Quality Signage03.1 Too much information and not directional
04 Outdoor Storage of Materials04.1 Mulch and wood stored outside uncovered indicates the need for
formal materials storage
05 Day Use Parking Area05.1 Day Use Parking Area not well defined
06 Parking Barriers06.1 Tall parking barriers create an unwelcoming feeling of privacy
07 Mini Golf Area Placement07.1 Poor quality fencing creates a feeling of privacy
07.2 Mini golf area is first visual upon entering the site - makes it feel pri-
vate
08 Severe Erosion08.1 Severe erosion at the top of the bank showing roots makes the
area unusable
09 Dangerous Leaning Tree09.1 Tree Leaning over the day use area - potential to injure
10 Beach Erosion10.1 Beach area is showing signs of erosion
11 Floating Dock11.1 Dock is broken and deteriorating and feels temporary
12 Bear-Proof Garbage12.1 Open Garbage cans create risk for bear conflicts - currently emp-
tied nightly
13 Change Rooms & Washroom Building13.1 Cracks in structural walls showing signs of deterioration and need
for replacement
14 Food Service Area14.1 Very cluttered and unorganized - freezers and fridges kept outside
all summer
15 Pathway Down to Lake15.1 Pathway is steep, unpaved and is not suitable for handicapped ac-
cess
15.2 Corner switchback is not able to accommodate wheelchair turn-
around in the future
16 Trailer & Caretaker Private Yard16.1 Trailer is not designed or oriented well for public/private interface
16.2 Trailer is not big enough to function properly - outdoor storage
needed, small office, etc.
16.3 Fence along parking area creates a strong feeling of private space
17 Unscreened storage of garbage/recycling17.1 Unsightly and is near the main access to the beach - highly visible
18 Privacy Fences Between Campsites18.1 Fencing creates and awkward interface between public and pri-
vate space
18.2 A stop-gap solution rather than properly defining public and pri-
vate space
19 Aging Trees19.1 No succession plan for existing trees that will all reach the end of
their life at the same time
20 Playground Shading20.1 No shade for playground, making it hot with severe sun exposure
21 Unlevel Tent Sites21.1 Tent pads are not level with several tents placed on a sloped hill
22 Beach Volleyball Court22.1 Volleyball court is set up in the open field and is to be played on
grass, rather than sand
23 Beach front Road23.1 Prime riparian habitat and beach front is occupied by the road. It
creates a feeling of a private rather than public beach
24 Underutilized Green Space24.1 Undefined open space is underutilized and a lack of trees makes
the area hot and exposed
25 Difficult Back In Sites25.1 The steep road is difficult to back in
26 Temporary Fence26.1 Temporary fence erected at the southwest corner to keep people
from accessing the property to the south
27 Short Camping Sites27.1 Camping sites are small and push tents and small campers towards
the road. These sites lack privacy.
28 Poor Signage for RVs28.1 RVs constantly miss the sign to not drive down the road, meaning
they have to reverse up the steep, narrow road
29 Isolated Camping Site29.1 The single site is on the opposite end of the washroom/shower
making for an awkward and uncomfortable site
30 Unscreened Materials & Infrastructure30.1 Propane tanks and various building materials are piled outside the
building making it look cluttered and messy
31 Shower/Washroom Facility 31.1 Upgrades needed as the building is in disrepair
32 Open, unshaded camping sites32.1 Lack of vegetation makes for a lack of shade and privacy for RV
sites
33 Sharp Angle of RV Sites33.1 The direction of traffic through the campground and angle of the
RV sites mean backing in requires a 135 degree turn
34 Dangerous Trees on Adjacent Property 34.1 Dead and leaning trees on adjacent property could fall on camp-
sites causing injury and damage to RVs, electrical wires and other
infrastructure
35 RV Empty Station is Not Signed35.1 There is no signage indicating that this is the location for the RV
empty station
05 06 07 08 09 10
11
12131415
161718
19
2021
22
23
24
25
26
2728
293031
32
33
34
35
04030201
MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPSMAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS
-
8/18/2019 Williamson's Lake report
52/92
APPENDIX 04 SITE OPPORTUNITIES MAP
-
8/18/2019 Williamson's Lake report
53/92
I S S U E
0 9 . 0 8 . 2 0 1 5
R E - I S S U E
C L I E N T
C i t y o f R e v e l s t o k e - P a r k
s , R e c r e a t i o n & C u l t u r e D e p t .
6 0 0 C a m p b e l l A v e .
P . O . B o x 1 7 0
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 8 3 7 - 9 3 5 1
S E L K I R K P L A N N I N G & D E S I G N
B o x 1 9 9 4
1 0 1 S e c o n d S t . E
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 2 0 0 - 0 6 8 0
E : s e l k i r k p l a n n i n g @ g m a i l . c o m
P R O J E C T N O .
2 0 1 5 - C O P - W L
P R O J E C T
W i l l i a m s o n ’ s L a k e D a y U s e A r e a &
C a m p g r o u n d C o n c e p t P l a n
D R A W N B Y
F B , J J
D E S C R I P T I O N
a
05
OPPORTUNITIES
01 Improved Signage @ Airport Way
02 Overflow Day Use Parking w/ Improvements
03 Entry Sign @ Important Wayfinding View
04 Narrow Road for One Way
05 Campground Registration Parking
06 Vehicular Wayfinding Signage
07 Plaza & Pedestrian Wayfinding Signage
08 Day Use Parking - Defined Spaces
09 New Day Use & Office Building(s)
09.1 Change rooms (3M, 3F)
09.2 Washrooms (3M, 3F)09.3 Wheelchair accessible washroom & change room
09.4 Campground office
09.5 Food service kitchen
09.6 Outdoor covered dining area & viewing deck
09.7 Laundry
09.8 Outdoor wood storage
09.9 Potential caretaker residence
09.10Rinse showers for day use patrons
09.11Garbage & recycling storage
09.12Indoor lockable storage for paddleboards, paddles, etc.
09.13Outdoor cooking shelter & fish-washing station (stand alone build-
ing - open air, stove, sink, bear-aware garbage)
09.14Formal day use entry/gateway
09.15Incorporate historical/interpretive information (heritage panels)
10 Re-vegetate Slope
11 Formal Path/Stairs Down to Beach
12 Private Property (or Trail) Signage
13 Formalize Beach Area & Canoe Launch
14 Permanent Wheelchair Accessible Dock
15 Improved Beach Signage
16 Pathway Defines/Protects Beach & Seating Area
17 Wheelchair Accessible Pathway to Beach
18 Mini Putt Moved Around Playground
19 Successive Planting Area
19.1 Plant species to replace existing trees as they near the end of their
lifespan
20 Wheelchair Accessible Viewing Dock
21 Campsites Removed From Beach - Public Beach
22 Slip n’ Slide Route (Special Event Only)
23 Beach Volleyball Court on Beach
24 Walk-In Tent Sites Replace Beach Sites
24.1 ~10 tenting sites
24.2 Opens up the beach to more public use
25 Expanded Yurt Camping Area
25.1 4-6 Yurts + parking area - Walk-in only
26 Parking Area for Walk-In Sites & Re-vegetation
27 Fishing/Wildlife Viewing Dock
28 Level Tent Sites & Improve Parking Pad Access
28.1 Level sites with wood berms & fill
28.2 Change vehicle back-in angle where possible
28.3 Improved site marking
29 Private Property Signage
30 Improved “No RV Access” Sign
31 New Campground Shower/Washroom
31.1 Move existing campsite & place building closer to the road
31.2 Showers (3M, 3F)
31.3 Washrooms (3M, 3F)
31.4 Wheelchair accessible washroom & shower
31.5 Roof extension for covered cooking area (2 cooking areas)
31.6 Dish washing station
31.7 Screened outdoor materials / gas tank storage
32 Formalized RV Sites
32.1 Formal RV pads
32.2 Permanent picnic table & fire location
32.3 Improved site marking
33 Flexible Open Space Area
34 Vegetation to Create Privacy Screening
35 Trees to Provide Shade for Playground
36 Remove Dangerous Trees
37 Formalized Small Campground Sites
37.1 Vegetation buffers
37.2 Permanent picnic table & fire location
37.3 Improved site marking
38 Narrow Road for One Way
39 Improved Signage for RV Empty Station
40 Formalized Day Use Parking Stalls
41 Overflow/Winter Camping Area
41.1 Suitable for RVs or tents
41.2 Potential winter yurt area - Move yurts from summer location
42 Reverse Traffic Direction
42.1 Improves visual access to day use & office building - wayfinding
42.2 Access to “preferred” day use parking first
42.3 Improves ability for RVs to back into camping sites
42.4 Reduces RVs driving down “tent only” road
01 03 04 05 07 08 12 13 1409 1106 1002
23
27
21
24
29
28
26
25
20
22
15
16
17
18
19
32
33
41
40
38
42
39
30
31
36
34
37
35
MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS
-
8/18/2019 Williamson's Lake report
54/92
APPENDIX 05 SURVEY RESULTS SUMMARY
-
8/18/2019 Williamson's Lake report
55/92
-
8/18/2019 Williamson's Lake report
56/92
-
8/18/2019 Williamson's Lake report
57/92
Williamson’s Lake Concept Preferences
Weight Concept 1 - Community Park Concept 2 - Campground Campground 3 - Balanced
Votes Weighted
Score
Votes Weighted
Score
Votes Weighted
Score
Not Appropriate -2 2 -4 8 -16 1 -2
Not very appropriate -1 1 -1 3 -3 3 -3
Unsure 0 3 0 4 0 4 0
Appropriate 1 4 4 1 1 4 4
Very Appropriate 2 5 10 0 0 6 12
Total 15 9 16 -18 18 11
Average Total per # of Votes 0.60 -1.13 0.61
Preferred Improvements - Vote for your top 3
No. of Votes
Improved buildings 13
Accessible pathway 10
Landscape improvements andsuccession planting
8
Proposed docks 5
Hammock area 4
Amphitheatre 4
Improved campsites 3
Exercise nodes / circuit 3
Improved signage & wayfinding 2
Improved site markers 0
Expanded yurt camping 0
Other suggested improvements
Comment Needs reviewwith L.
Donato?
Proposed Resolution / Action
Maintain size of beach Yes Planned expansion of public beach area
Keep mini golf Yes Not in current plan
Camping should be limited Yes Consistent with Concept Plan 1, but not 2 or 3
Keep the park the way it is Yes No proposed improvements address this
Secure bike parking Yes Proposed racks only, no storage lockers etc.
Canoe/kayak launch Yes Potential to have at proposed fishing dock location with potential small parking lot
Make it a more local swimming hole/area Yes Consistent with Concept Plan 1 & 3
Dog-friendly area of the beach Yes Nothing proposed right now - Potential to have this area, but how to manage?
Remove parking from some campsites and make them walk-in sites Yes Consistent with Concept Plan 1 & 3
Improve parking area No In current plans to define parking areas
Remove campsites from the beach No Consistent with Concept Plan 1 & 3
Work with RMR to develop trails No Not in scope of project
Reduce speed on airport way or add sidewalk No Not in scope of project
Keep the natural look No Consistent with landscaping improvements and succession planting
Wheelchair accessible No Consistent with all plans
Bigger park No Not in scope of project
Improve swim quality of water by removing weeds from water No Not in scope of project
Move fishing dock No Will create expanded dock for fishing off main swimming dock
More sand on beach No Beach remediation and planting suggestions will keep sand from washing into the lake
1
-
8/18/2019 Williamson's Lake report
58/92
APPENDIX 06 OPEN HOUSE MATERIALS
-
8/18/2019 Williamson's Lake report
59/92
Campground and Day Use Area CONCEPT PLANSOPEN HOUSENovember 23rd , 2015
City of Revelstoke - Parks, Recreation & Culture Dept.
600 Campbell Ave.
P.O. Box 170
Revelstok e, BC V0E 2S0
T: (250) 837-9351
WILLIAMSON’S LAKE
MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS
-
8/18/2019 Williamson's Lake report
60/92
I S S U E
0 9 . 0 8 . 2 0 1 5
R E - I S S U E
1 1 . 0 1 . 2 0 1 5
C L I E N T
C i t y o f R e v e l s t o k e - P a r k
s , R e c r e a t i o n & C u l t u r e D e p t .
6 0 0 C a m p b e l l A v e .
P . O . B o x 1 7 0
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 8 3 7 - 9 3 5 1
S E L K I R K P L A N N I N G & D E S I G N
B o x 1 9 9 4
1 0 1 S e c o n d S t . E
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 2 0 0 - 0 6 8 0
E : s e l k i r k p l a n n i n g @ g m a i l . c o m
P R O J E C T N O .
2 0 1 5 - C O P - W L
P R O J E C T
W i l l i a m s o n ’ s L a k e D a y U s e A r e a &
C a m p g r o u n d C o n c e p t P l a n
D R A W N B Y
F B , J J
D E S C R I P T I O N
a
02
PROPOSED SITE IMPROVEMENTSCommon to All Concepts
01 03 04 05 07 11 12 1308 1006 0902
01 Improved Signage @ Airport Way
02 Overflow Day Use Parking w/ Improvements
03 Entry Sign @ Important Wayfinding View
04 Narrow Road for One Way Traffic
05 Campground Registration Parking
05.1 Potential campground office & caretaker residence
06 Vehicular Wayfinding Signage
07 Public Space @ Entrance
07.1 Includes Pedestrian Wayfinding Signage
08 Construct New Day Use & Office Building(s)
08.1 Change rooms & Washrooms (3M, 3F)
08.2 Wheelchair accessible washroom & change room08.3 Campground office
08.4 Food service kitchen
08.5 Outdoor covered dining area & viewing deck
08.6 Campground Laundry
08.7 Outdoor wood storage
08.8 Potential caretaker residence
08.9 Rinse showers for day use patrons
08.10Indoor lockable storage for paddleboards, paddles, etc.
08.11Formal day use entry/gateway
08.12Incorporate historical/interpretive information (heritage panels)
09 Re-vegetate Slope
10 Formal Path/Stairs Down to Beach
11 Private Property (or Trail) Signage
12 Formalize/Protect Beach Area & Canoe Launch
13 Permanent Wheelchair Accessible Dock
14 Improved Beach Signage
15 Beach Protection - from erosion, etc.
16 Rotary Outdoor Cooking Shelter
16.1 Wood oven + BBQs
16.2 Covered seating area with picnic tables
16.3 Fish-washing station
17 Proposed Recreation/Improvement Area
17.1 Hammocks, climbing cubes, slack lines, etc.
18 Activity Area
18.1 Horseshoes, volleyball, etc.
19 Wheelchair Accessible Pathway to Beach
20 Mini Putt Removed
21 Succession Planting
21.1 Plant tree and species to revegetate degraded areas and replace
existing trees as they near the end of their lifespan
22 Beach Improvements and Potential New Dock
23 Campsites Removed From Beach - Public Beach
24 Address Awkward Small Campground Sites
25 Provide Shade for Playground
26 Flexible Open Space Area
27 Potential Walk-In Tent Sites
27.1 ~10 tenting sites
27.2 Opens up the beach to more public use
28 Potential Yurt Camping Area Expansion
28.1 Potential for approx. 4-6 Yurts + parking area - Walk-in only
29 Parking Area for Walk-In Sites Beach Area
30 Potential Fishing/Wildlife Viewing Dock
31 Level Tent Sites & Improve Parking Pad Access
31.1 Level sites with wood berms & fill or retaining walls
31.2 Change vehicle back-in angle where possible
31.3 Improved site marking
32 Private Property Signage
33 Improved “No RV Access” Sign
34 Potential New Shower/Washroom Location
34.1 Construct campground shower/washroom in new location
34.2 Showers & Washrooms (3M, 3F)
34.3 Wheelchair accessible washroom & shower
34.4 Roof extension for covered cooking area (2 cooking areas)
34.5 Dish washing station
34.6 Screened outdoor materials / gas tank storage
35 Campsite Improvements
35.1 Defined campsite pads
35.2 Permanent picnic table & fire location
35.3 Improved site marking
36 Vegetation to Create Privacy Screening
37 Remove Dangerous Trees
38 Narrow Road for One Way
39 Improved Signage for RV Empty Station40 Garbage & Recycling Pick Up Area
41 Formalized Day Use Parking Stalls
42 Overflow/Winter Camping Area OR Picnic Area
42.1 Suitable for RVs or tents
42.2 Potential winter yurt area - Move yurts from summer location
43 Reverse Traffic Direction
43.1 Improves visual access to day use & office building - wayfinding
43.2 Access to “preferred” day use parking first
30
23
24
25
26
27
32
31
29
28
22
14
15
18
16
17
19
21
35
42
38
43
39
40
33
34a
34b
36
37
41
20
MAP NOT TO SCALE. SEE FULL SIZED 24X36” BOARDS FOR SCALED MAPS
-
8/18/2019 Williamson's Lake report
61/92
I S S U E
0 9 . 0 8 . 2 0 1 5
R E - I S S U E
1 1 . 0 1 . 2 0 1 5
C L I E N T
C i t y o f R e v e l s t o k e - P a r k
s , R e c r e a t i o n & C u l t u r e D e p t .
6 0 0 C a m p b e l l A v e .
P . O . B o x 1 7 0
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 8 3 7 - 9 3 5 1
S E L K I R K P L A N N I N G & D E S I G N
B o x 1 9 9 4
1 0 1 S e c o n d S t . E
R e v e l s t o k e , B C V 0 E 2 S 0
T : ( 2 5 0 ) 2 0 0 - 0 6 8 0
E : s e l k i r k p l a n n i n g @ g m a i l . c o m
P R O J E C T N O .
2 0 1 5 - C O P - W L
P R O J E C T
W i l l i a m s o n ’ s L a k e D a y U s e A r e a &
C a m p g r o u n d C o n c e p t P l a n
D R A W N B Y
F B , J J
D E S C R I P T I O N
a
03
PUBLIC SPACECommon to All Concepts
01 Approachable Entrance
02 New Day Use Building with food service
03 Covered & open dining patio
04 Stairs down to beach & permanent dock
05 Viewing/seating area
06 Wheelchair accessible ramp to beach
07 Open air picnic shelter with wood stove + BBQs
08 New day use change room, washroom + shower
09 Gateway entrance to park w/ building rooflines
10 Vehicle pick up are