Wi d PWind Power INTERNATIONALINTERNATIONAL
DEVELOPMENTS & STATUS IN PAKISTAN WITH CASE STUDY OF
DHA CITY KARACHI (DCK)DHA CITY KARACHI (DCK)FENG WEIJIANG
HUADONG ENGINEERING
BRIG DR NASIM A. KHAN
OSMANI & COMPANY (PVT) LTDPOWER CHINA
OSMANI & COMPANY (PVT) LTD KARACHI
ENERGY MASTER PLAN FOR DCKENERGY MASTER PLAN FOR DCK
WindWindWindWindWIND10%
BIOMASS8%
SolarSolarSOLAR
12%
10%
BiomassBiomassTHERMAL
12%
THERMAL70%
DCK Energy Master Plan
Wind Resource AssessmentWind Resource AssessmentM Wi d S d
Month Mean Wind Speed(Sep 2013 – Aug 2014)
Mean Wind Speed (Sep 2014 to
Onwards)
Mean Of Months
September 6.64 8.64 7.64October 5.77 5.82 5.79November 5 93 6 06 5 95November 5.93 6.06 5.95December 6.09January 7.23February 6.19March 6.25April 6 75April 6.75May 7.95June 9.77July 9.93August 8.48
Annual Average 7.44Note: The maximum wind speed recorded at DCK was 26.88 m/s at 80m on 1st Jan 2015
14%
World Ranking 2013 on Wind Market Share
10%
12%
%
6%
8%
et S
hare
%
4%
6%
Mar
ke
0%
2%
Wind Turine Supplier
WIND TURBINES OPERATIONAL IN PAKISTANWIND TURBINES OPERATIONAL IN PAKISTAN
VESTASVESTASVESTASVESTAS
GOLDWINDGOLDWIND
GENERAL ELECTRICGENERAL ELECTRIC
NORDEXNORDEXOO
Item Zorlu Enerji Pakistan Limited FFC Energy Limited
Foundation Wind Energy - I (Private)
LimitedCapacity 56.4 49.5MW 50MW
Project Location Jhimpir Jhimpir GharoLand Area 1,148 Acres 1,283 Acres 1,210 AcresEnergy Production Estimate/annum 167.6 GWh (P50) 144.137 GWh (P50) 129.1 GWh (P75)
Total Project Cost (USD Thousands) 161,880 133,557 128,703
Funding Plan Debt 70% : Equity 30% Debt 80% : Equity 20% Debt 75% : Equity 25%
Levelized Tariff US(Cent) 12.7743 Per KWh
US(Cent) 17.8951 Per KWh
US(Cent) 16.2972 Per KWhKWh KWh KWh
Total EPC Cost (USD Thousands) 138,801 112,979 111,939
Wind Turbines5 X VENSYS62 each of 1.2MW & 28 X Vestas V90 each of 1.8MW
Nordex S77, 1.5MW HCV x 33 WTG's
20 x Nordex N90 each of 2.5MW
EPC Contractors Zorlu O&M Pakistan Limited
Consortium Of Nordex & Descon, with Nordex as the Lead Contractor.
Consortium Of Nordex(Lead)Descon
ItemFoundation Wind
Energy - II (Private) Limited
Three Gorges Wind Farm
Tenaga Genarasi Limited
Capacity 50MW 49.5MW 49.5MWProject Location Gharo Jhimpir KhuttikunLand Area 1 656 Acres 1 210 Acres 4 881 AcresLand Area 1,656 Acres 1,210 Acres 4,881 AcresEnergy Production Estimate/annum 129.6 GWh (P75) 138.7 GWh (P50) 147.031 GWh (P50)
Total Project CostTotal Project Cost (USD Thousands) 127,693 134,748 129,674
Funding Plan Debt 75% : Equity 25% Debt 80% : Equity 20% Debt 75% : Equity 25%
Levelized Tariff US(Cent) 16.1240 Per KWh
US(Cent) 14.72 Per KWh
US(Cent) 14.2116 Per KWh
Total EPC Cost 111 022 110 315 109 940(USD Thousands) 111,022 110,315 109,940
Wind Turbines 20 x Nordex N90 each of 2.5MW
33 x GoldwindGW1500/77
33 X GEMW XLE each of 1.5MW
Consortium Of Nordex
China Huashui Hydropower Development as Off-
China Machinery Engineering
EPC Contractors (Lead)Descon
Shore ContractorChina Int. Water & Electric Corp as On-
Corporation; and China East Resource Import & Export Corporation.
Item Younus Energy Limited Sapphire Wind Power Company Limited
Master Wind Energy Limited Metro Power Company Ltd
Capacity 50MW 49.5MW 49.5MW 50MWProject Location Jhimpir Jhimpir Jhimpir JhimpirLand Area 696 Acres 1,372 Acres 1,408 Acres 1,553Energy Production Estimate/annum
138.9 GWH (P50) 140.9 GWh (P50) 142.1 GWh (P50) 142.3 GWh (P50)
Total Project Cost (USD Thousands) 132,529 128,872 133,677 133,446
Funding Plan Debt 80% : Equity Debt 75% : Equity Debt 75% : Equity Debt 75%:Equity Funding Plan 20% 25% 25% 25%
Levelized Tariff US(Cent) 18.14 Per KWh
US(Cent) 14.2116 Per KWh
US(Cent) 15.9561 Per KWh US(Cents)16
T t l EPC C tTotal EPC Cost (USD Thousands) 110,200 108,601 109,328 108,842
Wi d T bi20 X Nordex
N100/2500 h f 33 X GEMW XLE 33 X GEMW XLE 20 x Nordex N100 Wind Turbines N100/2500 each of 2.5MW each of 1.5MW each of 1.5MW each of 2.5MW
Consortium of Nordex Descon China Machinery China Machinery
E i i C Consortium Of EPC Contractors Engineeering, with
Nordex as Lead Contractor.
yEngineering Corporation.
Engineering CorpChina East Resource Import Export Corp
Nordex (Lead)Descon
Wind Power Project Cost Breakdown
Interest during Contruction, 5.6%
Working C it l 0 7%
Insurance during Construction, 1.2% Other Project
Cost, 7.1%
O i Fi d
Pre‐COD Insurance
Financial Charges, 2.6%
Capital, 0.7% Operation Fixed Assets, 0.3%
Taxes & Custom Duty, 0.6%
Cost, 1.1%
Project
Land Cost, 0.1%
Non EPC
Development Cost, 2.7%
EPC Cost, 84.4%
LC Confirmation
Cost, 0.9%
LC Confirmation, 0.6%
SHARE OF RENEWABLE ENERGY IN ALL NEW POWER (GW) IN EUROPE DURING THE YEAR 2009
10
12
ATT
S
6
8
R G
IGA
WA
0
2
4
POW
ER
0
WIN
D
GAS
SOLA
RPV CO
AL
BIO
MAS
S
OIL
WAS
TE
UC
LEAR
HYD
RO
SOLA
RC
SP
B N
ENERGY SOURCE
NEW POWER GENERATION CAPACITIES ADDED IN EU 28 IN 2013 (MW)